METHOD STATEMENT Revision : 1
Issued : OCT 2002
UE Construction Sdn Bhd UEC/MS/RB012/GEI/018
Electrified Double Track Project Between Rawang And Ipoh
METHOD STATEMENT
Sheikh Faizal OCT 2002 Mohd Fauzi OCT 2002 B.T Tee OCT 2002
IMPORTANT:
CONTENTS
1.0 SCOPE
2.0 MATERIALS
4.0 METHOD
9.0 DOCUMENTATION
1.0 SCOPE
Page No. : 3 of 12
METHOD STATEMENT Revision : 1
Issued : OCT 2002
UE Construction Sdn Bhd UEC/MS/RB012/GEI/018
Electrified Double Track Project Between Rawang And Ipoh
2.0 MATERIALS
Not applicable.
3.1 Machinery/Equipment
b) Dumpy level.
3.2 Manpower
Manpower involved :
a) 1 Supervisor
b) 1 Surveyor
c) 2 Chainman
4.1 Installation
4.1.1 During the installation period, a short section, typically 1.00m to 1.50m of
the steel pipe welded and secured to the steel base plate.
4.1.2 Once completed, these so called “primary” sections or elements are placed
in specially prepared compacted granular platform, arranged according to
the layout of location of settlement.
Page No. : 4 of 12
METHOD STATEMENT Revision : 1
Issued : OCT 2002
UE Construction Sdn Bhd UEC/MS/RB012/GEI/018
Electrified Double Track Project Between Rawang And Ipoh
4.1.3 The above procedure is to facilitate the placement and construction of the
required 1.0m thick sand blankets.
4.1.4 Once the sand blankets has been put in place, the stage loading in the
form of incremental surcharging according the Engineer’s design load
requirement will begin.
4.1.5 Prior to procedure above however, the extension of steel pipe has to be
carried out by means of coupling the joints. The steel pipes are extended
to the required height to enable future monitoring to perform.
Correspondingly, the 85mm diameter PVC pipe will be placed over the
steel pipe along its entire length within the fill surcharge during this period
of reasons as outlined in paragraph 4.1.1 above.
4.2 Monitoring
4.2.1 Once installed, these markers will be monitored using a Dumpy Level,
which accurately record the reduced up to an accuracy of +0.1mm.
4.2.2 A suitable location will be identified to station the survey instrument. The
chosen location would have to have an unobstructed line of sight to the
targets (settlement plates/markers and be reasonably distant from the
influence of settlement or ground deformation brought about the
consolidation of the clay soil beneath the fill surcharge.
4.2.3 A temporary benchmark (TBM) would be sited close to the area of the
project site during monitoring to provide reference record for the
settlement plates/markers readings.
4.2.4 The monitoring of settlement plate shall be done until the subgrade level
of embankment fill or as directed by S.E. The instrument shall form a part
of permanent works and shall remain operational after contract period.
4.2.5 On each occasion that readings are taken from an instrument or set of
instruments, the measured values shall be recorded on a record sheet.
Details of information and values to be stored on each record sheet in
addition to the general information required are given below :
Frequency of Monitoring
Type
Defect Liability
Construction Period
Period
4.2.7 Each weekly report shall include complete information about the work not
limited to the following :
i. A description of monitoring works which have been in operation during
the preceding week.
ii. Information on reading anomalies or corrections, and factors which
may influence measured data.
iii. Observations or remarks.
iv. Diagram showing installed location of instrument (taken from
installation report).
v. Data tabulations or plots of thickness of fill and settlement of gauge
plate vs. time.
4.2.8 The format for the monthly report is the same as the weekly report except
that the required details reported are for a month instead of a week.
4.3 Maintenance
4.4 Procedure
4.4.2 Take the reduce level (RL) from TBM by using levelling staff (record
down).
4.4.3 Take the settlement point reduce level (RL) by placing the levelling staff
on the settlement point.
4.4.4 By shooting the precise level equipment to levelling staff, adjust the focus
knob until the center cross hair coincides with the staff reading. The height
of the staff is hence recorded. Then the reduced level (RL) of the
settlement point can be calculate as follows :
4.4.5 By comparing the initial reading with subsequent reading, the settlement
at individual location can be calculated.
4.4.6 A graph of Settlement versus Time will be presented in the report through
out the period of monitoring during excavation and construction stages.
6.1 The work to be carried out in accordance with the Project Safety Plan.
6.2 All the works shall comply with DRB-HICOM Environmental management
Plan.
Page No. : 7 of 12
METHOD STATEMENT Revision : 1
Issued : OCT 2002
UE Construction Sdn Bhd UEC/MS/RB012/GEI/018
Electrified Double Track Project Between Rawang And Ipoh
6.5 Provide PPE to all workers including safety helmet, safety shoe, vest, ear
protector, etc.
6.6 Provide signboards to warn workers and public of dangers associated with
construction works.
6.7 Inspect all machinery at site and ensure that it has competent certificate
and is safe to operate.
Not applicable.
9.0 DOCUMENTATION
Calibration Certificate
Appendix A
Page No. : 9 of 12
METHOD STATEMENT Revision : 1
Issued : OCT 2002
UE Construction Sdn Bhd UEC/MS/RB012/GEI/018
Electrified Double Track Project Between Rawang And Ipoh
Appendix B
Page No. : 10 of 12
METHOD STATEMENT Revision : 1
Issued : OCT 2002
UE Construction Sdn Bhd UEC/MS/RB012/GEI/018
Electrified Double Track Project Between Rawang And Ipoh
Appendix C
Page No. : 11 of 12
METHOD STATEMENT Revision : 1
Issued : OCT 2002
UE Construction Sdn Bhd UEC/MS/RB012/GEI/018
Electrified Double Track Project Between Rawang And Ipoh
Appendix D
Page No. : 12 of 12
METHOD STATEMENT Revision : 1
Issued : OCT 2002
UE Construction Sdn Bhd UEC/MS/RB012/GEI/018
Electrified Double Track Project Between Rawang And Ipoh
Appendix E