Method Statement FOR Launching of Prestressed I Beams AT RB 014, Jalan Tapah - Teluk Intan (Pier 2 To Abutment 2)

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 14

METHOD STATEMENT Page No.

: Page 1 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

METHOD STATEMENT
FOR
LAUNCHING OF PRESTRESSED I BEAMS
AT
RB 014 ,JALAN TAPAH – TELUK INTAN
(Pier 2 to Abutment 2)

Prepared by: Date: Reviewed by: Date: Approved by: Date:


SFO Oct2003 MNS Oct 2003 TBT Oct 2003

IMPORTANT:

The information contained herein is the proprietary property of UE Construction Sdn Bhd

The holder agrees to the following:


1. Not to reproduce; copy; reveal; publish; or, distribute it in whole or any portion of it
without authorisation; and,
2. To maintain this document in confidence.
METHOD STATEMENT Page No. : Page 2 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

CONTENTS

1.0 INTRODUCTION

2.0 MATERIALS

3.0 MANPOWER & EQUIPMENT

3.1 MANPOWER
3.2 EQUIPMENT

4.0 METHOD

5.0 HEALTH, SAFETY AND ENVIRONMENT

6.0 APPENDICES
METHOD STATEMENT Page No. : Page 3 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

1.0 INTRODUCTION

This method statement describes the method and procedures for


launching the prestressed I beams at span 3 (Pier 2 to Abut 2) at RB
014 - (JALAN TAPAH – TELUK INTAN). Beams for launched and span 1
will be launched at a later stage.

The launching layout and other relevant information on machinery


and equipment used in this work are included.

2.0 MATERIALS

2.1 Prestressed “I” Beams

The prestressed “I” Beams must achieve the required design


strength prior to the launching activities. Test cube results should
be submitted to the Supervising Engineer prior to the launching
activities to ensure the 28 days required strength had been
achieved.

The permanent position of the I-beams sitting on the cross head


and abutment shall be marked before launching activities started.

3.0 MANPOWER & EQUIPMENT

3.1 MANPOWER

 1 Engineer
 1 Supervisor
 2 Operators
 4 Bar benders
 10 General Workers
 2 Welders
 1 Safety Officer
METHOD STATEMENT Page No. : Page 4 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

3.2 EQUIPMENT

 2 units of 45 tonne mobile crane


 Trailers
 2 units of launching truss c/w winch
 Welding set
 Timber wedges
 Steel bar bracing

4.0 METHOD

4.1 Work Access And Area

 The working access and platform shall be leveled and


compacted to form a firm ground. The pipe culvert installed
below the platform will not be subjected to crane and beam
loading as the outrigger of the crane will not be placed over
the culvert.

 Steel plate shall be provided if necessary wherever heavy


machine operating at the soft ground.

4.2 Launching Sequence And Methodology

 Audit survey shall be carried out to confirm the top level of


cross head and abutment prior to the launching works.

 The supporting structure including epoxy plinth shall have


reached the required strength and acceptable to the Resident
Engineer before beam launching.

 All relevant quality control records including beam hogging


and bowing report for the beams will be submitted before
launching

 Rubber bearing pads will be placed at the position marked by


surveyor prior to launching activities.
METHOD STATEMENT Page No. : Page 5 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

 Two general workers will be designated, one each on the pier


crossbeams to ensure the 'I' beams will be sitting in place
(centre of the bearing pad).

 For this launching, 2 units of 45 tonnes mobile crane will be


used to load the beam onto the trailers at the casting yard.

 2 units ‘A’ frame launching truss c/w motorised winch will be


placed on the steel girders fixed at the cross head and
pilecap of Pier 2 and Abutment A2 respectively. (This beam
launching method was used at Spans 2 and 3 of BR 570 Sg
Batang Padang earlier).

 Upon arrival at Abutment A2, the 'I' beams will be hoist up


by the winch and the beams will be moved by the winch to
the designated beam sitting position.

 Launching for Span 3 (P2-A2) will be carried out at this


stage. Sketch and photographs showing the beam launching
process are attached in Appendix 1.

5.0 HEALTH, SAFETY AND ENVIRONMENT

5.1 Working Hour


Line block is required for 10 days.

5.2 Regulations
All site activities shall comply strictly with KTM regulations and
requirements. Before commencement of works all relevant staff
will be briefed and trained to comply with KTMB regulations. All
staff will also be familiar with the Construction Crisis Team’s
Handbook.
METHOD STATEMENT Page No. : Page 6 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

5.3 Launching Safety Briefing


A safety briefing will be conducted by the launcher prior to
beam launching to ensure that all people involved are familiar
with the works (Designated Launcher will be fully in charge
during the launching activity). The safety officer with knowledge
of the launching works will supervise the safety aspect of the
whole launching activity. Before starting the works, this safety
officer will brief the workers on the general hazards of beam
launching activities.

5.4 Equipment Checks


The safety officer will check and ensure that all cranes are with
valid PMA and fully operational and that there are no
irregularities prior to the launching. The launching will be halted
if any irregularities are observed. Pre-Lift Checklist Crane
Operation is attached in Appendix 2.

5.5 Safety Pre-caution After Launching


All beams shall be braced immediately after launching works is
completed to avoid any accident while waiting for the
subsequent activities. Beams will be braced using extreme load
case as per calculation and sketch attached in Appendix 3.
Adequate timber wedges, temporary welding or other supports
shall also be provided to ensure the I beams remain stable on
bridge bearing pads.

Upon completion of beam launching, works on diaphragm


beams shall be completed within 7 days, with first beam
completed by 5th day.

5.6 General Safety


All workers are to wear High Visibility Vest (Orange colour),
safety helmet and safety shoes within KTMB Right Of Way
(ROW). All safety issues will be governed by the DRB-HICOM’s
Safety And Health Plan. DRB-HICOM procedure for heavy lifting
attached in Appendix 4 will be adhered to. The crane operator
must possess a valid certificate of competency on crane
operation.

The area shall be barricaded from construction equipment,


machinery and general public.
METHOD STATEMENT Page No. : Page 7 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

5.7 Environment Issues


The Environmental Management Plan will be adhered to strictly
on site.

6.0 APPENDICES

a) Appendix 1 - Sketch and photographs showing the launching


trusses/girders and positioning trailer for
launching beams.

b) Appendix 2 - Pre-lift Checklist Crane Operation &


Pre-commencement Checklist

c) Appendix 3 - Temporary Bracing Calculation and


Welding Details For Beams Launched

d) Appendix 4 - DRB-HICOM Heavy Lifting Operation

e) Appendix 5 - Welder Certificate & Sling Certificate

f) Appendix 6 - Location Plan.

g) Appendix 7 - Site Organisation Chart.


METHOD STATEMENT Page No. : Page 8 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

APPENDIX 1
METHOD STATEMENT Page No. : Page 9 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

APPENDIX 2
METHOD STATEMENT Page No. : Page 10 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

APPENDIX 3
METHOD STATEMENT Page No. : Page 11 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

APPENDIX 4
METHOD STATEMENT Page No. : Page 12 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

APPENDIX 5
METHOD STATEMENT Page No. : Page 13 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

APPENDIX 6
METHOD STATEMENT Page No. : Page 14 of 14
Revision : 0
Issued : Oct 2003
UE Construction Sdn Bhd UEC/MS/RB014/LB/018A

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

APPENDIX 7