Method Statement For Construction of Access Road To BR 570 (Sg. Batang Padang)

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 7

Page No.

: 1 of 6
METHOD STATEMENT Revision : 1
Issued : Aug 2001
UE Construction Sdn Bhd UEC/MS/BR570/AR/011

Electrified Double Track Project Between Ipoh and Rawang

CONTROLLED COPY NO:

METHOD STATEMENT FOR CONSTRUCTION OF


ACCESS ROAD TO
BR 570 (SG. BATANG PADANG)

(PACKAGE KAMPAR TO BIDOR)

Prepared by Date Reviewed by Date Approved by Date

Mohd Faizal Mohd Fauzi B.T Tee


Page No. : 6 of 6
METHOD STATEMENT Revision : 1
Issued : Aug 2001
UE Construction Sdn Bhd UEC/MS/BR570/AR/011

Electrified Double Track Project Between Ipoh and Rawang

IMPORTANT:

The information contained herein is the proprietary property of UE CONSTRUCTION SDN


BHD.

The holder agrees to the following:


1. Not to reproduce; copy; reveal; publish; or, distribute it in whole or any portion of in
without authorisation; and,
2. To maintain this document in confidence.

METHOD STATEMENT FOR CONSTRUCTION OF


ACCESS ROAD TO
BR 570 (SG. BATANG PADANG)

(PACKAGE KAMPAR TO BIDOR)

Submitted by Date Reviewed/Approved by Date Verified by Date

Subcontractor Consultant PMC


HSSI-KMQR
Page No. : 6 of 6
METHOD STATEMENT Revision : 1
Issued : Aug 2001
UE Construction Sdn Bhd UEC/MS/BR570/AR/011

Electrified Double Track Project Between Ipoh and Rawang

CONTENTS

1.0 SCOPE

2.0 MATERIALS

3.0 EQUIPMENT & RESOURCES

4.0 METHOD

5.0 QUALITY CONTROL PROCEDURE

6.0 HEALTH, SAFETY AND ENVIRONMENT

7.0 TRACK POSSESSION

8.0 SUMMARY OF FORMS

9.0 DOCUMENTATION
Page No. : 6 of 6
METHOD STATEMENT Revision : 1
Issued : Aug 2001
UE Construction Sdn Bhd UEC/MS/BR570/AR/011

Electrified Double Track Project Between Ipoh and Rawang

1.0 SCOPE

This method statement outlines and describes the scope of work,


construction sequence, safety and other related items generally
applicable for the construction of the proposed access road to
Abutment A2 RB 570 – Sg Batang Padang. The proposed access is via
Lot 2142 (new lot no : 6784) privately own by Messr. Goodwood
Valley Sdn. Bhd. as alternate route through Kg. Changkat Dermawan
has received objection from the Ketua Kampung. The scope of works
shall include:

a) Construction of a new 6.0m wide access road.

b) Widening existing tracks to achieve 6.0m width.

c) Provide temporary earth drain where appropriate.

d) Provide new pipe culvert to replace existing bridges where


required.

e) Lengthening existing pipe culvertS where required.


f) Maintaining drain within access boundary

g) Construction of wash trough if necessary.

h) Construction of silt trap if necessary.

i) Provide necessary traffic management scheme if necessary.

j) Obtaining all necessary approvals from local authorities.

2.0 MATERIALS

Materials to be used will be :

a) Suitable materials (Sand or Earth)

b) Pipe culverts

c) Crusher run

d) Barriers and signages where appropriate.


Page No. : 6 of 6
METHOD STATEMENT Revision : 1
Issued : Aug 2001
UE Construction Sdn Bhd UEC/MS/BR570/AR/011

Electrified Double Track Project Between Ipoh and Rawang

3.0 EQUIPMENT & RESOURCES

3.1 The following is a list of equipment to be used. However, the actual


number of units would depend on the area involved.

a) Survey equipment

b) Licensed lorry/dump truck

c) Excavator/backhoe

d) Compactor

e) Back pusher

f) Water bowser to control dust when necessary

3.2 All plants and machinery will be with valid documents or licences.

4.0 METHOD

4.1 Project Engineer (PE) to carry out joint inspection with Project
Management Consultant (PMC) or Supervising Engineer (SE) or both at
the proposed route for approval and to confirm the requirements and
identify any obstacles.

4.2 Obtain wayleave from the Messr Goodwood Valley Sdn. Bhd. who own Lot
2142 (6784)

4.3 Land owner to sign agreement letter and forward to PMC.

4.4 Identify biomass disposal site


4.5 Inform Jabatan Kerja Raya (JKR) and Majlis Daerah Tapah (MDT)
regarding construction of the access road.

4.6 Install appropriate warning and traffic controlling signs such as


“Awas”, “Kurangkan Laju”, and “Kenderaan Berat Keluar/Masuk” as per
JKR’s Arahan Teknik.

4.7 To provide flagmen at the entrance of the access (if necessary).

4.8 To provide 25mm steel plate at the entrance of Jalan Tapah Road –
Goodwood Valley as protection for Lembaga Air Perak (LAP) water
main. The methodology for installation of the steel plate is as per
Appendix C.

4.9 Carry out site clearance as per Method Statement for Site Clearing
inclusive of felling and prunning existing palm trees, stripping
topsoil and dispose surplus material to approved dumping area.
(Ref : UEC/MS/GEN/M/002)

4.10 Excavate and remove unsuitable material where instructed by SE and


dispose to approved dumping area.

4.11 Lengthening culvert no. 1 with 600  pipe culvert.


Page No. : 6 of 6
METHOD STATEMENT Revision : 1
Issued : Aug 2001
UE Construction Sdn Bhd UEC/MS/BR570/AR/011

Electrified Double Track Project Between Ipoh and Rawang

4.12 Lengthening culvert no. 2 and 3 with 900  pipe culvert.

4.13 Replace bridge no. 1 with 1200  pipe culvert.

4.14 Replace bridge no. 2 with twin 900  pipe culvert.

4.15 Provide temporary drainage alongside the proposed access road where
required.

4.16 Supply, spread, level and compact suitable material to a maximum of


500mm thick.

4.17 Supply, spread, level and compact 300mm thick crusher run for the
running surface.

4.18 However, changes may be made to the above method of construction and
alignment of the proposed access road to suit existing ground
condition and local requirements subject to PMC/SE approval.

5.0 QUALITY CONTROL PROCEDURE

Not applicable.

6.0 HEALTH, SAFETY AND ENVIRONMENT

6.1 Work will be carried out in accordance with the Project Safety Plan.

6.2 Toolbox meeting will be carried out on construction area at regular


intervals to ensure compliance with the Safety Plan and familiarity
with accident and emergency procedures.
6.3 Conduct safety induction course to workers before commencement of
work.

6.4 Provide PPE to all workers including safety helmet, safety shoe,
vest, ear protector, etc.

6.5 Provide signboards to warn workers and public of dangers associated


with construction works.

6.6 Advanced traffic warning signs will be positioned in place along and
at entrance of access roads and designated flagmen will be used when
working in the vicinity of existing roads if required.

6.7 Ensure all affected utilities are relocated or protected prior to


commencement of work.

6.8 Water bowser will be used to control dust when necessary.

6.9 Inspect all machinery at site and ensure that it has competent
certificate and is safe to operate.

7.0 TRACK POSSESSION


Page No. : 6 of 6
METHOD STATEMENT Revision : 1
Issued : Aug 2001
UE Construction Sdn Bhd UEC/MS/BR570/AR/011

Electrified Double Track Project Between Ipoh and Rawang

Not applicable.

8.0 SUMMARY OF FORMS

Not applicable.

9.0 DOCUMENTATION

9.1 Appendix A - Proposed access road (Plan and cross section).

9.2 Appendix B - Proposed traffic management at access entrance.

9.3 Appendix C – Installation of 25mm thick steel plate.

9.4 Appendix D – Construction of temporary culvert.

9.5 Appendix E – Bill of Quantities.

9.6 Appendix F – Letter from Goodwood Valley Sdn. Bhd.

9.7 Appendix G – Letter from Ketua Kampung Changkat Dermawan.