Method Statement For Bored Pile at Proposed Pedestrian/Motorcycle Bridge Near Kg. Changkat Melintang (CH 230.900)
Method Statement For Bored Pile at Proposed Pedestrian/Motorcycle Bridge Near Kg. Changkat Melintang (CH 230.900)
Method Statement For Bored Pile at Proposed Pedestrian/Motorcycle Bridge Near Kg. Changkat Melintang (CH 230.900)
: 1 of 11
METHOD STATEMENT Revision : 0
Issued : Dec 01
UE Construction Sdn Bhd UEC/MS/MPKCM/BP/006
IMPORTANT:
CONTENTS
1.0 SCOPE
2.0 MATERIALS
4.0 METHOD
9.0 DOCUMENTATION
1.0 SCOPE
d) Carry out sonic logging test, load test and cavity treatment.
2.0 MATERIALS
2.1 Water
Potable water shall be used in preparing the slurry suspension and
concrete.
2.3 Concrete
The ready mixed concrete (G40 Tremmie mix T2) for piling will be supplied
by the approved supplier, Supermix Concrete Sdn. Bhd./Classic Best Sdn
Bhd. The concrete shall be in accordance with the Specification.
3.1 Machinery/Equipment
3.1.1 The basic configuration required for the construction of 900mm diameter
bored piles are:-
b) Service crane
1 no. crawler crane (45t, 50t or 60t)
3.2 Manpower
Each rig will have a foreman and crew allocated. The crew will consist of rig
operator, crane operator, banksman, welder and general workers. The
foreman will be responsible for all piling supervision, who will generally
supervise the rig machine.
There is also a gang for steel reinforcement work and a gang for pile load
testing.
4.1.1 Joint survey to check the setting out of pile position from control
point by the surveyor will be carried out before commencement of
the drilling work.
4.1.2 Setting out of the first pile point and subsequent selected pile
points shall be confirmed by DRB appointed surveyor.
4.1.3 Drilling rig shall be stationed on stable ground. Steel plate shall be
provided if required.
4.1.4 The pile position set by the surveyor shall be offset in two
perpendicular directions.
(a) The boring plant will be moved to the pile point intended for
excavation. The kelly bar mounted with an auger is placed
just above the pile point.
(d) Reasonable care should be taken so that the pile position and
vertically are constructed within the specified tolerance i.e.
75mm and 1 in 75 respectively. Plumb bob shall be used to
check the verticality as boring is in progress.
4.1.5 During the course of boring, the following checks shall be made:-
4.1.7 The drop chisel will be used if it is found that the coring cannot be
continued due to hard strata.
4.1.8 Boring will stop when the required depth is reached. Soil sample to
be taken whenever soil strata changes during the course of drilling
and shall be properly labelled.
4.1.10 After reaching the required depth, a cleaning bucket will be used to
clean up the bottom of the borehole and the cleanliness of the toe is
checked by the weigh tie to the measuring tape. A joint
measurement of the depth should be made before lowering of
reinforcement and concreting.
4.1.11 For dry borehole, each hole shall be inspected by S.E prior to the
placing of concrete in it. The inspection shall be carried out from
the ground surface in the case where the borehole diameter is less
than 750 mm. Torches or other approved means of lighting,
measuring tapes and a means of measuring verticality shall be
provided. Where the borehole diameter exceeds 750mm, adequate
equipment conforming to BS 5573 shall be provided to enable
descending into the borehole for inspection.
4.1.12 For wet boreholes, i.e holes filled with drilling fluid water, a suitable
probe shall be provided to ascertain the evenness and cleanliness
of the pile base. The water or drilling fluid in the bored hole shall be
checked for its specific gravity and sand content.
4.1.13 Soil sample shall be taken whenever soil strata changes during the
course of drilling, and shall be properly labelled.
4.2.2 After fabrication by the bar benders, the helical links will be tack
welded to the main reinforcement. Laps (50D or 1.25m) are also to
be welded sufficiently so that they are intact during transportation.
4.3 Concreting
4.3.1.1 When the hole is practically dry, ready mix concrete shall
be discharged directly into the hole through a 1.5m length
funnel hopper.
4.3.1.3 The concrete level shall be cast at least 0.5m above the
cut-off level.
4.3.1.5 Concrete slump for dry hole method shall be between 100 –
200mm.
4.3.2.1 In bore hole where water is less than 500mm and without
substantial water seepage from the side of borehole, 2
(two) bags of cement shall be dumped into the hole and
concrete shall be discharged immediately into the hole
through a funnel hopper.
4.3.3.1 In bore hole with more than 1.0 m of water and continuous
seepage to such an extent that the borehole cannot be
dewatered, tremie method shall be applied.
4.3.3.5 As the trimmie pipe extends to the base of the bore hole,
a sliding plug on barrier shall be placed in the pipe to
prevent direct contact between the first change of
concrete in the trimie and the water on the drilling fluid.
4.3.3.6 The concrete level shall be cast at least 1m above the cut-
off level.
Upon acceptance of sonic test results, the sonic tubes shall be backfilled
with a cement water mix of appropriate composition, through the following
steps :
c) Cement mix shall be grouted from the bottom to the top until
uncontaminated grout mix comes out from other circuit.
Three test cubes will be taken for each set of sonic tubes.
The test of the bored pile shall consist of either sonic coring, integrity test,
static load test or other load tests instructed or approved by S.E. Detail for
the sonic coring and integrity testing are as detailed below :
The sonic tubes shall be capped during concreting. The sonic tubes
shall be flushed prior to the coring and filled with clean water.
Sonic measurement shall be conducted between each of the sonic
tubes. The sonic coring tests shall be carried out by lowering the
ultrasonic data acquisition and transmitting units to the base of
adjacent sonic tubes and raising them simultaneously, maintaining
the probes in the horizontal plane. The test data is recorded on a
data logger. Refer to Appendix B for Sonic Coring Details
For load testing, maintained load test or other method of testing instructed
or approved by S.E will be carried out. Separate method statement will be
submitted for method of load testing instructed or approved by S.E.
6.1 The work to be carried out in accordance with the Project Safety plan.
Particular activities requiring attention are highlighted in the Appendix E.
6.2 All machinery engaged are subject to the standard colour coding system
as required in the Site Safety Manual and all other relevant requirements.
6.3 All the works shall comply with DRB-HICOM Environmental management
Plan.
6.6 Provide PPE to all workers including safety helmet, safety shoe, vest, ear
protector, etc.
6.7 Provide signboards to warn workers and public of dangers associated with
construction works.
6.8 Inspect all machinery at site and ensure that it has competent certificate
and is safe to operate.
Page No. : 11 of 11
METHOD STATEMENT Revision : 0
Issued : Dec 01
UE Construction Sdn Bhd UEC/MS/MPKCM/BP/006
7.1 A line block will be applied during piling work at abutment A1, pier P1, pier
P2 and pier P3 as the location of the abutment and piers is very near to
the track and might pose a danger to trains as well as to the track. All
KTM regulations regarding line blocks will be adhered to.
9.0 DOCUMENTATION