Method Statement For Earthworks at VBC Kg. Titi Besi (CH 232.457)
Method Statement For Earthworks at VBC Kg. Titi Besi (CH 232.457)
Method Statement For Earthworks at VBC Kg. Titi Besi (CH 232.457)
: Page 1 of 6
Revision : 1
Issued : Dec 2002
UE Construction Sdn Bhd UEC/MS/KGTB/EW/004
IMPORTANT:
The information contained herein is the proprietary property of UE CONSTRUCTION SDN. BHD.
CONTENTS
1.0 SCOPE
2.0 MATERIALS
3.0 EQUIPMENT & RESOURCES
4.0 METHOD
5.0 QUALITY CONTROL PROCEDURE
6.0 HEALTH, SAFETY AND ENVIRONMENT
7.0 TRACK POSSESSION
8.0 SUMMARY OF FORMS
9.0 DOCUMENTATION
METHOD STATEMENT Page No. : Page 3 of 6
Revision : 1
Issued : Dec 2002
UE Construction Sdn Bhd UEC/MS/KGTB/EW/004
1.0 SCOPE
This method statement covers all necessary works to be carried out such
as identifying source, filling methods, equipment, machineries, slope
stability, compaction methods and test until earth filling is completed at
Vehicular Box Culvert near Kg. Titi Besi. This is to ensure that the
earthworks are carried out in accordance with specification and safety
requirements.
The scope of works shall include:
g) Construct and maintain all temporary and permanent drains, silt trap,
turfing, etc.
2.0 MATERIALS
a) Excavator
b) Dump Truck/Licence Lorry
c) Soil Test Equipment
d) Survey Equipment
e) Back pusher
f) Compactor/Roller
METHOD STATEMENT Page No. : Page 4 of 6
Revision : 1
Issued : Dec 2002
UE Construction Sdn Bhd UEC/MS/KGTB/EW/004
4.0 METHOD
4.4 Silt trap and wash trough will be constructed as and when
necessary, depending on site conditions.
4.6 One sample will be taken for every 20,000 cu.m of original soil or
borrow pit to be tested at Geolab laboratory at Tapah for the following
tests:
a) Sieve analysis (Form: DRB-F-E004)
b) Particle size distribution (Form: DRB-F-E015)
c) Plastic and liquid limit (Form: DRB-F-E010)
d) Soil compaction test (Form: DRB-F-E007)
e) CBR test (Form: DRB-F-E016)
4.7 Material cut from ROW that is found to be unsuitable for use shall be
spread out evenly within the ROW but outside the permanent works area
subject to approval of SE.
4.8 The Surveyor will peg the top of the cut, toe line for embankment
filling and center line of embankment at 20m intervals for checking the
thickness of filling.
4.10 Suitable fill shall be laid in layers of loose thickness not exceeding
300mm and compacted with vibratory roller up to subgrade level or
required level.
6.1 Work will be carried out according to the Project Safety Plan Particular
activities requiring attention are highlighted in the Appendix B.
6.2 Tool box meeting will be carried out on construction area at regular
interval to ensure compliance with the Safety Plan and familiarity with
accident and emergency procedures.
6.4 Provide PPE to all workers including safety helmet, safety shoe, vest, etc.
6.5 Provide signboards to warn workers and public of dangers associated with
construction works.
6.6 Advanced traffic warning signs will be positioned in place along and at
entrance of access roads and designated flagman will be used when
working in the vicinity of existing road if required.
6.9 Inspect all machinery at site and ensure that it has competent certificate
and is safe to operate.
METHOD STATEMENT Page No. : Page 6 of 6
Revision : 1
Issued : Dec 2002
UE Construction Sdn Bhd UEC/MS/KGTB/EW/004
Not applicable.
9.0 DOCUMENTATION