Method Statement For Earthworks at VBC Kg. Titi Besi (CH 232.457)

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 6

METHOD STATEMENT Page No.

: Page 1 of 6
Revision : 1
Issued : Dec 2002
UE Construction Sdn Bhd UEC/MS/KGTB/EW/004

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

METHOD STATEMENT FOR EARTHWORKS AT


VBC KG. TITI BESI
(CH 232.457)

(PACKAGE KAMPAR TO BIDOR)

Prepared by Date Reviewed by Date Approved by Date

Sheikh Faizal 18/12/02 Mohd Fauzi 18/12/02 B.T Tee 19/12/02

IMPORTANT:

The information contained herein is the proprietary property of UE CONSTRUCTION SDN. BHD.

The holder agrees to the following:


1. Not to reproduce; copy; reveal; publish; or, distribute it in whole or any portion of it without
authorisation; and,
2. To maintain this document in confidence.
METHOD STATEMENT Page No. : Page 2 of 6
Revision : 1
Issued : Dec 2002
UE Construction Sdn Bhd UEC/MS/KGTB/EW/004

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

CONTENTS

1.0 SCOPE
2.0 MATERIALS
3.0 EQUIPMENT & RESOURCES
4.0 METHOD
5.0 QUALITY CONTROL PROCEDURE
6.0 HEALTH, SAFETY AND ENVIRONMENT
7.0 TRACK POSSESSION
8.0 SUMMARY OF FORMS
9.0 DOCUMENTATION
METHOD STATEMENT Page No. : Page 3 of 6
Revision : 1
Issued : Dec 2002
UE Construction Sdn Bhd UEC/MS/KGTB/EW/004

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

1.0 SCOPE

This method statement covers all necessary works to be carried out such
as identifying source, filling methods, equipment, machineries, slope
stability, compaction methods and test until earth filling is completed at
Vehicular Box Culvert near Kg. Titi Besi. This is to ensure that the
earthworks are carried out in accordance with specification and safety
requirements.
The scope of works shall include:

a) Check setting out and existing ground level.

b) Identifying borrow pit areas.

c) Excavation and disposal of unsuitable materials as directed by SE to


dumping area.

d) Ensure all relevant ground improvement is completed as per


Construction Drawings.

e) Cut and fill with suitable material up to formation level.

f) Conduct all necessary test as per relevant clauses in the specification.

g) Construct and maintain all temporary and permanent drains, silt trap,
turfing, etc.

h) Obtain approval from local authorities where applicable.

2.0 MATERIALS

2.1 Suitable material (sand or earth)

2.2 V-shape drains/Culverts, where appropriate

2.3 Geotextile when required.

3.0 EQUIPMENT & RESOURCES

3.1 The basic equipment to be used is as follows:

a) Excavator
b) Dump Truck/Licence Lorry
c) Soil Test Equipment
d) Survey Equipment
e) Back pusher
f) Compactor/Roller
METHOD STATEMENT Page No. : Page 4 of 6
Revision : 1
Issued : Dec 2002
UE Construction Sdn Bhd UEC/MS/KGTB/EW/004

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

4.0 METHOD

4.1 Temporary Bench Mark (TBM) shall be established and maintained.

4.2 The Right-Of-Way (ROW) pegs installed by Client’s Surveyor shall


be located and checked to ensure that the permanent works is within the
ROW.

4.3 A joint survey will be arranged together with SE representative to


check the existing ground level and setting out.

4.4 Silt trap and wash trough will be constructed as and when
necessary, depending on site conditions.

4.5 Ground improvement works shall be completed before proceeding


with the filling of embankments. (Separate method statement will be
submitted for each type of ground improvement work)

4.6 One sample will be taken for every 20,000 cu.m of original soil or
borrow pit to be tested at Geolab laboratory at Tapah for the following
tests:
a) Sieve analysis (Form: DRB-F-E004)
b) Particle size distribution (Form: DRB-F-E015)
c) Plastic and liquid limit (Form: DRB-F-E010)
d) Soil compaction test (Form: DRB-F-E007)
e) CBR test (Form: DRB-F-E016)

4.7 Material cut from ROW that is found to be unsuitable for use shall be
spread out evenly within the ROW but outside the permanent works area
subject to approval of SE.

4.8 The Surveyor will peg the top of the cut, toe line for embankment
filling and center line of embankment at 20m intervals for checking the
thickness of filling.

4.9 Trial compaction if required by SE will be carried out.

4.10 Suitable fill shall be laid in layers of loose thickness not exceeding
300mm and compacted with vibratory roller up to subgrade level or
required level.

4.11 Density of embankment filling shall follow as per technical


specification.

4.12 Berm drain shall be constructed if required to protect the


embankment slope from erosion and turfing works will commence after
completion of earth filling and slope trimming. The final finishing of the
embankment surface shall be 150mm above formation level for track
METHOD STATEMENT Page No. : Page 5 of 6
Revision : 1
Issued : Dec 2002
UE Construction Sdn Bhd UEC/MS/KGTB/EW/004

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

carriage way while the rest of embankment is finished to the formation


level (subgrade level).

4.13 All necessary geotechnical instrumentation such as settlement plate,


surface marker, inclinometer standpipe and piezometer shall be installed
as directed by the SE.

4.14 A joint survey shall be carried out for completed earthworks


together with SE representative and the earthwork As-built drawing will be
submitted to SE for approval.

5.0 QUALITY CONTROL PROCEDURE

On site quality control shall be carried out in accordance with the


Inspection and Test Plan as attached in the Appendix A to ensure that
the job is carried out to the client satisfaction. Materials test must be
conducted to ensure their conformance with the specification requirement.

6.0 HEALTH, SAFETY AND ENVIRONMENT

6.1 Work will be carried out according to the Project Safety Plan Particular
activities requiring attention are highlighted in the Appendix B.

6.2 Tool box meeting will be carried out on construction area at regular
interval to ensure compliance with the Safety Plan and familiarity with
accident and emergency procedures.

6.3 Conduct safety induction course to workers before commencement of


work.

6.4 Provide PPE to all workers including safety helmet, safety shoe, vest, etc.

6.5 Provide signboards to warn workers and public of dangers associated with
construction works.

6.6 Advanced traffic warning signs will be positioned in place along and at
entrance of access roads and designated flagman will be used when
working in the vicinity of existing road if required.

6.7 Ensure affected utilities, if any are relocated or protected prior to


commencement of work.

6.8 Water browser will be used to control dust when necessary.

6.9 Inspect all machinery at site and ensure that it has competent certificate
and is safe to operate.
METHOD STATEMENT Page No. : Page 6 of 6
Revision : 1
Issued : Dec 2002
UE Construction Sdn Bhd UEC/MS/KGTB/EW/004

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

7.0 TRACK POSSESSION

Not applicable.

8.0 SUMMARY OF FORMS

List of forms to be used for the works is as follows:


a) Sieve analysis [Form No: DRB-F-E004]
b) Soil compaction test [Form No: DRB-F-E007]
c) FDT sand replacement [Form No: DRB-F-E009]
d) Plastic and liquid limit [Form No: DRB-F-E010]
e) Particle size distribution [Form No: DRB-F-E015]
f) CBR test [Form No: DRB-F-E016]
g) FDT core cutter method [Form No: DRB-F-E017]

9.0 DOCUMENTATION

9.1 Appendix A : Inspection and Test Plan


9.2 Appendix B : Safety, Health and Environment
9.3 Appendix C : Site Organisation
9.4 Appendix D : Ground Treatment

You might also like