METHOD STATEMENT Page No.

: Page 1 of 6
Revision : 0
Issued : Feb 2002
UE Construction Sdn Bhd UEC/MS/EW/001

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

METHOD STATEMENT FOR EARTHWORKS AT :

1) RB011 – JALAN KAMPAR – TELUK INTAN (CH218.608)


- REF : UEC/MS/RB011/EW/008

2) RB012 – JALAN TEMOH – SG. LESONG (CH226.026)


- REF : UEC/MS/RB012/EW/011

3) RB013 – JALAN AIR KUNING – BANIR (CH229.424)


- REF : UEC/MS/RB013/EW/011

4) RB014 – JALAN TAPAH – TELUK INTAN (CH233.637)


- REF : UEC/MS/RB014/EW/009

5) BR562 – SG. CHENDERIANG (CH226.735)


- REF : UEC/MS/BR562/EW/013

6) BR583 – SG. CHIKUS (CH239.165)


- REF : UEC/MS/BR583/EW/013

7) MPKBP – PROPOSED PEDESTRIAN / MOTORCYCLE BRIDGE NEAR KG.


BAHARU PINJI (CH219.560)
- REF : UEC/MS/MPKBP/EW/010

8) MPKCM – PROPOSED PEDESTRIAN / MOTORCYCLE BRIDGE NEAR KG.


CHANGKAT MELINTANG (CH231.054)
- REF : UEC/MS/MPKCM/EW/010

9) MPKMK – PROPOSED PEDESTRIAN / MOTORCYCLE BRIDGE NEAR KG.


MERBAU / KG. KASSIM (CH238.572)
- REF : UEC/MS/MPKMK/EW/010

(BIDOR TO IPOH PACKAGE)


Prepared by Date Reviewed by Date Approved by Date

Sheikh Faizal 01/02/02 Mohd Fauzi 02/02/02 B.T Tee 02/02/02

IMPORTANT:

The information contained herein is the proprietary property of UE CONSTRUCTION SDN. BHD.

The holder agrees to the following:


1. Not to reproduce; copy; reveal; publish; or, distribute it in whole or any portion of in without
authorisation; and,
2. To maintain this document in confidence.
METHOD STATEMENT Page No. : Page 2 of 6
Revision : 0
Issued : Feb 2002
UE Construction Sdn Bhd UEC/MS/EW/001

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

CONTENTS

1.0 SCOPE
2.0 MATERIALS
3.0 EQUIPMENT & RESOURCES
4.0 METHOD
5.0 QUALITY CONTROL PROCEDURE
6.0 HEALTH, SAFETY AND ENVIRONMENT
7.0 TRACK POSSESSION
8.0 SUMMARY OF FORMS
8.1 APPENDIX A : Inspection and Test Plan
8.2 APPENDIX B : Safety Health and Environment
METHOD STATEMENT Page No. : Page 3 of 6
Revision : 0
Issued : Feb 2002
UE Construction Sdn Bhd UEC/MS/EW/001

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

1.0 SCOPE

This method statement covers all necessary works to be carried out such as
identifying source, filling methods, equipment, machineries, slope stability,
compaction methods and test until earth filling is completed at locations stated
below. This is to ensure that the earthworks are carried out in accordance with
specification and safety requirements.

a) RB011, Jalan Kampar – Teluk Intan

b) RB012, Jalan Temoh – Sg. Lesong

c) RB013, Jalan Air Kuning – Banir

d) RB014, Jalan Tapah – Teluk Intan

e) BR562 – Sg. Chenderiang

f) BR583 – Sg. Chikus

g) MPKBP – Near Kg. Baharu Pinji

h) MPKCM – Near Kg. Changkat Melintang

i) MPKMK – Near Kg. Merbau/Kg. Kassim

The scope of works shall include:

a) Check setting out and existing ground level.

b) Identifying borrow pit areas.

c) Excavation and disposal of unsuitable materials as directed by SE to dumping


area.

d) Ensure all relevant ground improvement is completed as per Construction


Drawings.

e) Cut and fill with suitable material up to formation level.

f) Conduct all necessary test as per relevant clauses in the specification.

g) Construct and maintain all temporary and permanent drains, silt trap, turfing,
etc.

h) Obtain approval from local authorities where applicable.


METHOD STATEMENT Page No. : Page 4 of 6
Revision : 0
Issued : Feb 2002
UE Construction Sdn Bhd UEC/MS/EW/001

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

2.0 MATERIALS

2.1 Suitable material (sand or earth)

2.2 V-shape drains/Culverts, where appropriate

2.3 Geotextile when required.

3.0 EQUIPMENT & RESOURCES

3.1 The basic equipment to be used is as follows:

a) Excavator
b) Dump Truck/Licence Lorry
c) Soil Test Equipment
d) Survey Equipment
e) Back pusher
f) Compactor/Roller

4.0 METHOD

4.1 Temporary Bench Mark (TBM) shall be established and maintained.

4.2 The Right-Of-Way (ROW) pegs installed by Client’s Surveyor shall be


located and checked to ensure that the permanent works is within the
ROW.

4.3 A joint survey will be arranged together with SE representative to check


the existing ground level and setting out.

4.4 Silt trap and wash trough will be constructed as and when necessary,
depending on site conditions.

4.5 Ground improvement works shall be completed before proceeding with the
filling of embankments. (Separate method statement will be submitted for
each type of ground improvement work)

4.6 One sample will be taken for every 20,000 cu.m of original soil or borrow
pit to be tested at Geolab laboratory at Tapah for the following tests:
a) Sieve analysis (Form: DRB-F-E004)
b) Particle size distribution (Form: DRB-F-E015)
c) Plastic and liquid limit (Form: DRB-F-E010)
d) Soil compaction test (Form: DRB-F-E007)
e) CBR test (Form: DRB-F-E016)
METHOD STATEMENT Page No. : Page 5 of 6
Revision : 0
Issued : Feb 2002
UE Construction Sdn Bhd UEC/MS/EW/001

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

4.7 Material cut from ROW that is found to be unsuitable for use shall be
spread out evenly within the ROW but outside the permanent works area
subject to approval of SE.

4.8 The Surveyor will peg the top of the cut, toe line for embankment filling
and center line of embankment at 20m intervals for checking the thickness
of filling.

4.9 Trial compaction if required by SE will be carried out.

4.10 Suitable fill shall be laid in layers of loose thickness not exceeding 300mm
and compacted with vibratory roller up to subgrade level or required level.

4.11 Density of embankment filling shall follow as per technical specification.

4.12 Berm drain shall be constructed if required to protect the embankment


slope from erosion and turfing works will commence after completion of
earth filling and slope trimming. The final finishing of the embankment
surface shall be 150mm above formation level for track carriage way while
the rest of embankment is finished to the formation level (subgrade level).

4.13 All necessary geotechnical instrumentation such as settlement plate,


surface marker, inclinometer standpipe and piezometer shall be installed
as directed by the SE.

4.14 A joint survey shall be carried out for completed earthworks together with
SE representative and the earthwork As-built drawing will be submitted to
SE for approval.

5.0 QUALITY CONTROL PROCEDURE

On site quality control shall be carried out in accordance with the Inspection and
Test Plan as attached in the Appendix A to ensure that the job is carried out to
the client satisfaction. Materials test must be conducted to ensure their
conformance with the specification requirement.

6.0 HEALTH, SAFETY AND ENVIRONMENT

The work to be carried out in accordance with the Project Safety Plan. Particular
activities requiring attention are highlighted in the Appendix B.
The tool box meeting will be carried out on construction area at regular intervals
to ensure compliance with the Safety Plan and familiarity with accident and
emergency procedures.
METHOD STATEMENT Page No. : Page 6 of 6
Revision : 0
Issued : Feb 2002
UE Construction Sdn Bhd UEC/MS/EW/001

ELECTRIFIED DOUBLE TRACK PROJECT BETWEEN RAWANG AND IPOH

7.0 TRACK POSSESSION

Not applicable.

8.0 SUMMARY OF FORMS

List of forms to be used for the works is as follows:


a) Sieve analysis [Form No: DRB-F-E004]
b) Soil compaction test [Form No: DRB-F-E007]
c) FDT sand replacement [Form No: DRB-F-E009]
d) Plastic and liquid limit [Form No: DRB-F-E010]
e) Particle size distribution [Form No: DRB-F-E015]
f) CBR test [Form No: DRB-F-E016]
g) FDT core cutter method [Form No: DRB-F-E017]