Pile Driving Analyser Test-Rev 1
Pile Driving Analyser Test-Rev 1
Pile Driving Analyser Test-Rev 1
: 1 of 6
METHOD STATEMENT Revision : 1
Issued : Mar 2002
UE Construction Sdn Bhd UEC/MS/PDA/001
IMPORTANT:
CONTENTS
1.0 SCOPE
2.0 MATERIALS
4.0 METHOD
1.0 SCOPE
Dynamic pile testing on bored piles is normally performed using the Pile
Driving Analyser (PDA) to enable field estimation of the static
Geotechnical carrying capacity of the pile installed. This method of testing
is served to obtain field data for computer signal matching using
commercially established computer software such as the TNOWAVE and
CAPWAP to assess the Geotechnical capacity.
2.0 MATERIALS
Not required.
Two pairs of transducers attached below the pile head are used to
measure the dynamic forces and velocity wave during a hammer strike on
the pile head. These transducers are connected to the PDA via a
transducer cable.
Field data is digitized and stored in a random file in the computer hard
disk. The random files are automatically generated according to the
hammer blow numbers detected by the computer software. The digitized
dynamic forces or velocity or time information recorded are operated on
by TNOWAVE or CAPWAP software to a number of pile resistance,
maximum compression stress, maximum tensile stress and energy
transmitted past the transducers.
accelerometers are bolted onto the pile using plugs or anchor bolts.
The transducers and accelerometers are then connected to the PDA
via a cable.
4.1.3 The pile head will be protected to resist the dynamic impact
force by means of steel casing and normally is done while casting
the pile. As such test pile shall be pre-selected prior to the
installation of pile so as pile will be casted to the platform level to
facilitate the testing.
4.1.4 A steel guide shaft or frame is then positioned onto the pile.
The guide shaft or frame is used to guide the drop weight.
4.2.2 The analysis involves applying the measured pile top force or time
recorded to the model pile. The model consists of lumped mass,
spring, dampers and surrounding soil. The TNOWAVE or CAPWAP
software computes the resultant force and velocity/time for the
model pile and then compared with the actual measured force and
velocity/time during the test.
Page No. : 5 of 6
METHOD STATEMENT Revision : 1
Issued : Mar 2002
UE Construction Sdn Bhd UEC/MS/PDA/001
4.2.3 The pile model and soil models are then adjusted in an interactive
manner until a good match is obtained. The signal matching could
be between the measured and computed velocity or/and between
the measured and computed displacement. Once a matched is
achieved, good dynamic model of the pile/soil system at the time of
testing could be obtained.
After the completion of the PDA, a full report will be submitted which
contain the following information:
Dynamic load testing will be conducted on bored piles with the following
preliminary control parameters. Control parameters to be adjusted upon
maximum test load is confirmed:
Pile Size Working Load Test Load Hammer Weight Drop Height
(mm) (tonnes) (tonnes) (tonnes) (m)
900 WL 1.5WL 10.0 ~ 15.0 1.0 ~ 2.0
1200 WL 1.5WL 10.0 ~ 15.0 1.0 ~ 2.0
1500 WL 1.5WL 10.0 ~ 15.0 1.0 ~ 2.0
Subject to the respond of the test pile after first blow and when necessary,
the hammer weight and drop height may be adjusted at the site.
Not required.
Not required.
Page No. : 6 of 6
METHOD STATEMENT Revision : 1
Issued : Mar 2002
UE Construction Sdn Bhd UEC/MS/PDA/001
Not required.