Method Statement For Installation, Monitoring and Maintenance of Geotechnical Instrumentation
Method Statement For Installation, Monitoring and Maintenance of Geotechnical Instrumentation
Method Statement For Installation, Monitoring and Maintenance of Geotechnical Instrumentation
: Page 1 of 10
Revision : 0
Issued : September 2002
UE Construction Sdn Bhd UEC/MS/GIE/
IMPORTANT:
The information contained herein is the proprietary property of UE CONSTRUCTION SDN BHD.
CONTENTS
METHOD STATEMENT Page No. : Page 2 of 10
Revision : 0
Issued : September 2002
UE Construction Sdn Bhd UEC/MS/GIE/
1.0 SCOPE
2.0 MATERIALS
4.0 METHOD
9.0 DOCUMENTATION
METHOD STATEMENT Page No. : Page 3 of 10
Revision : 0
Issued : September 2002
UE Construction Sdn Bhd UEC/MS/GIE/
1.0 SCOPE
2.0 MATERIALS
a) Not applicable.
c) A 100 mm diameter Class “O” PVC pipe which will act as a sleeve over the
steel pipe to prevent contact between the steel pipe and the file surcharge
and to ensure freedom of movement of the steel pipe when displacement
of the base plate occurs.
METHOD STATEMENT Page No. : Page 4 of 10
Revision : 0
Issued : September 2002
UE Construction Sdn Bhd UEC/MS/GIE/
d) Dumpy Level
3.2 Manpower
Manpower involved :
a) 1 Supervisor
b) 1 Surveyor
c) 2 Chainman
4.0 METHOD
4.1 Installation
4.1.1 During the installation period, a short section, typically 1.00m to 1.5m of the
steel pipe welded and secured to the steel base plate.
4.1.2 Once completed, these so called ‘primary’ sections or elements are placed in
specially prepared compacted granular platform, arranged according to the
layout of location of settlement.
4.1.3 The above procedure is to facilitate the placement and construction of the
required 1.0 m thick sand blankets.
4.1.4 Once the sand blankets has been put in place, the stage loading in the form
of increment surcharging according the Engineer’s design load required will
begin.
4.1.5 Prior to procedure above however, the extension of steel pipe has to be
carried out by means of coupling the joints. The steel pipes are extended to
the required height to enable future monitoring to perform.
Correspondingly, the 100mm diameter PVC pipe will be placed over the steel
pipe along its entire length within the fill surcharge during this period of
reasons as outlined in paragraph 4.1.1 above.
METHOD STATEMENT Page No. : Page 5 of 10
Revision : 0
Issued : September 2002
UE Construction Sdn Bhd UEC/MS/GIE/
4.2 Monitoring
Frequency of Monitoring
Type
Construction Period Defect Liability Period
1. Settlement 1. Immediately before and right Once a month (if required
plate after each layer of fill then to be monitored)
everyday during filling works.
2. Thereafter, trice weekly for
two weeks.
3. Followed twice weekly for
next two weeks
4. Thereafter, once a week until
end of construction or until as
instructed by the SE.
4.2.7 Each weekly report shall include complete information about the work not
limited to the following :
4.2.8 The format for the monthly report is the same as the weekly report except
that the required details reported are for a month instead of a week.
4.3 Procedure
4.3.2 Take the reduce level (RL) from TBM by using levelling staff (record
down).
4.3.3 Take the settlement point reduce level (RL) by placing the levelling staff
on the settlement point.
4.3.4 By shooting the precise level equipment to levelling staff, adjust the focus
knob until the center cross hair coincides with the staff reading. The height
of the staff is hence recorded. Then the reduced level (RL) of the settlement
point can be calculated as follows :
4.3.5 By comparing the initial reading with subsequent reading, the settlement
at individual location can be calculated.
4.3.6 A graph of Settlement Vs Time will be presented in the report through out
the period of monitoring during excavation and construction stages.
On site quality control shall be carried out in accordance with the inspection
and test plan.
6.1 Work will be carried out according to the Project Safety Plan.
6.2 Tool box meeting will be carried out on construction area at regular
interval to ensure compliance with the Safety Plan and familiarity with
accident and emergency procedures.
6.6 Safety officer will carry out frequent surveillance checks to ensure that
safety, health and environment is maintained.
6.7 Safety officer will check that all workers use the required PPE during
works.
Not applicable.
9.0 DOCUMENTATION
APPENDIX A
METHOD STATEMENT Page No. : Page 10 of 10
Revision : 0
Issued : September 2002
UE Construction Sdn Bhd UEC/MS/GIE/
APPENDIX B
METHOD STATEMENT Page No. : Page 11 of 10
Revision : 0
Issued : September 2002
UE Construction Sdn Bhd UEC/MS/GIE/