Method Statement For Earthworks at BR 570 - Sg. Batang Padang
Method Statement For Earthworks at BR 570 - Sg. Batang Padang
Method Statement For Earthworks at BR 570 - Sg. Batang Padang
: Page 1 of 6
Revision : 0
Issued : Nov 2001
UE Construction Sdn Bhd UEC/MS/BR570/EW/008
IMPORTANT:
The information contained herein is the proprietary property of UE CONSTRUCTION SDN. BHD.
CONTENTS
1.0 SCOPE
2.0 MATERIALS
3.0 EQUIPMENT & RESOURCES
4.0 METHOD
5.0 QUALITY CONTROL PROCEDURE
6.0 HEALTH, SAFETY AND ENVIRONMENT
7.0 TRACK POSSESSION
8.0 SUMMARY OF FORMS
8.1 APPENDIX A : Inspection and Test Plan
8.2 APPENDIX B : Safety Health and Environment
METHOD STATEMENT Page No. : Page 3 of 6
Revision : 0
Issued : Nov 2001
UE Construction Sdn Bhd UEC/MS/BR570/EW/008
1.0 SCOPE
This method statement covers all necessary works to be carried out such as
identifying source, filling methods, equipment, machineries, slope stability,
compaction methods and test until earth filling is completed at BR 570 – Sg.
Batang Padang. This is to ensure that the earthworks are carried out in
accordance with specification and safety requirements.
The scope of works shall include:
g) Construct and maintain all temporary and permanent drains, silt trap, turfing,
etc.
2.0 MATERIALS
a) Excavator
b) Dump Truck/Licence Lorry
c) Soil Test Equipment
d) Survey Equipment
e) Back pusher
f) Compactor/Roller
METHOD STATEMENT Page No. : Page 4 of 6
Revision : 0
Issued : Nov 2001
UE Construction Sdn Bhd UEC/MS/BR570/EW/008
4.0 METHOD
4.4 Silt trap and wash trough will be constructed as and when necessary,
depending on site conditions.
4.6 1 sample will be taken for every 20,000m 2 of original soil or borrow pit to
be tested at Geolab laboratory at Tapah for the following tests:
a) Sieve analysis (Form: DRB-F-E004)
b) Particle size distribution (Form: DRB-F-E015)
c) Plastic and liquid limit (Form: DRB-F-E010)
d) Soil compaction test (Form: DRB-F-E007)
e) CBR test (Form: DRB-F-E016)
4.8 Material cut from ROW that is found to be unsuitable for use shall be
spread out evenly within the ROW but outside the permanent works area subject
to approval of SE.
4.9 The Surveyor will peg the top of the cut, toe line for embankment filling
and center line of embankment at 20m intervals for checking the thickness of
filling.
4.10 Suitable fill shall be laid in layers of loose thickness not exceeding 300mm
and compacted with vibratory roller up to subgrade level or required level.
4.11 Field density test will be conducted with a minimum of 3 samples per
2000m2 either by Sand Replacement Method (Form: DRB-F-E009) or Core Cutter
Method (DRB-F-E017) after compaction. The sample shall be taken every layer of
filling by the Geolab laboratory personnel and sent for testing to ensure the soil
compaction achieved the required density (Dry density of not less than 90% for
general embankment and 95% for near formation). The Soil Compaction Test will
be carried out as and when instructed by the SE. If the results indicate that the
required density has not been achieved, the soil will be re-compacted and another
sample taken for testing. However, if the test failed marginally, the soil will be
re-compacted a few more passes as instructed by SE without further testing.
METHOD STATEMENT Page No. : Page 5 of 6
Revision : 0
Issued : Nov 2001
UE Construction Sdn Bhd UEC/MS/BR570/EW/008
4.14 A joint survey shall be carried out for completed earthworks together with
SE representative and the earthwork As-built drawing will be submitted to SE for
approval.
On site quality control shall be carried out in accordance with the Inspection and
Test Plan as attached in the Appendix A to ensure that the job is carried out to
the client satisfaction. Materials test must be conducted to ensure their
conformance with the specification requirement.
The work to be carried out in accordance with the Project Safety Plan. Particular
activities requiring attention are highlighted in the Appendix B.
The tool box meeting will be carried out on construction area at regular intervals
to ensure compliance with the Safety Plan and familiarity with accident and
emergency procedures.
Not applicable.