Method Statement For Construction of Bridge RC Structure at BR 562-Sg. Chenderiang
Method Statement For Construction of Bridge RC Structure at BR 562-Sg. Chenderiang
Method Statement For Construction of Bridge RC Structure at BR 562-Sg. Chenderiang
: Page 1 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562
IMPORTANT:
The information contained herein is the proprietary property of UE CONSTRUCTION SDN BHD.
CONTENTS
1.0 SCOPE
2.0 MATERIALS
4.0 METHOD
9.0 DOCUMENTATION
METHOD STATEMENT Page No. : Page 3 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562
1.0 SCOPE
2.0 MATERIALS
3.1 The following is a list of equipment to be used. However, the actual number
of units would depend on the works involved.
a) Survey equipment
b) Excavator / backhoe
c) Cranes
d) Vibrator
e) Compressor / jack hammers
f) Welding set
g) Gas cutting set
h) Bar cutter
i) Bar bending machine
3.2 All plants and machinery will be with valid documents or license.
4.1.1 Piles shall be exposed to 75mm below cut off levels. The level shall
then be marked on exposed bored piles.
4.1.2 Bored piles shall then be hacked using pneumatic breaker up to the
pile cut-off level or up to required lap length whichever is greater.
4.4.2 Concreting shall be carried out using crane and bucket. The lift of
concreting shall be approximately 2.0m.
4.5.2 Bottom timber formwork shall be fixed first. Side formwork will
only be installed after reinforcement bars, fabricated according to
drawings, are put in place.
4.5.3 Holes for dowel bars shall be provided at required locations before
concreting.
4.5.5 The cross beam shall be concreted at one stretch using crane and
bucket.
4.5.6 The side formwork for cross beam shall be stripped after 12 hours
of concreting. Bottom formwork and staging shall be removed after
7-10 days provided concrete has attained 2/3 of 28-day strength.
4.6.1 As shown in the drawings, dowel bar and rubber strips shall be
provided at required location using approved materials.
METHOD STATEMENT Page No. : Page 6 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562
4.8.1 Precast slabs shall be transported from casting yard using trailers
and brought to the site at the time of launching.
4.9.2 The top levels of concrete shall be marked over the side formwork
and also on the 6mm dia. steel rods spaced suitably covering the
entire deck slab area.
4.9.4 Curing shall be done by providing wet gunny sacks for 7 days.
4.10.1 The works shall be taken up upon completion of deck slab of the
bridge.
4.10.4 Wooden formwork shall be used for casting of kerb and cable
trench.
4.11.2 The levelling of lean concrete shall be done manually using scoops /
shovels.
4.11.4 Concrete with required grade shall be laid using crane and bucket.
Testing shall follow the procedure laid out in the Project Inspection & Test
Plan.
METHOD STATEMENT Page No. : Page 8 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562
6.1 Work will be carried out according to the Project Safety Plan.
6.2 Tool box meeting will be carried out on construction area at regular interval
to ensure compliance with the Safety Plan and familiarity with accident and
emergency procedures.
6.4 Provide PPE to all workers including safety helmet, safety shoe, vest, ear
protector, etc.
6.5 Provide signboards to warn workers and public of dangers associated with
construction works.
6.6 Advanced traffic warning signs will be positioned in place along and at
entrance of access roads and designated flagman will be used when working
in the vicinity of existing road if required.
6.9 Inspect all machinery at site and ensure that it has competent certificate and
is safe to operate.
Not applicable.
9.0 DOCUMENTATION
APPENDIX A
METHOD STATEMENT Page No. : Page 11 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562
APPENDIX B
METHOD STATEMENT Page No. : Page 12 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562
APPENDIX C