Method Statement For Construction of Bridge RC Structure at BR 562-Sg. Chenderiang

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 12

METHOD STATEMENT Page No.

: Page 1 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

METHOD STATEMENT FOR


CONSTRUCTION OF
BRIDGE RC STRUCTURE
AT BR 562-SG. CHENDERIANG

Prepared by: Date: Reviewed by: Date: Approved by: Date:

IMPORTANT:

The information contained herein is the proprietary property of UE CONSTRUCTION SDN BHD.

The holder agrees to the following:


1. Not to reproduce; copy; reveal; publish; or, distribute it in whole or any portion of it without
authorisation; and,
2. To maintain this document in confidence.
METHOD STATEMENT Page No. : Page 2 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

CONTENTS

1.0 SCOPE

2.0 MATERIALS

3.0 EQUIPMENT & RESOURCES

4.0 METHOD

5.0 QUALITY CONTROL PROCEDURE

6.0 HEALTH, SAFETY AND ENVIRONMENT

7.0 TRACK POSSESSION

8.0 SUMMARY OF FORMS

9.0 DOCUMENTATION
METHOD STATEMENT Page No. : Page 3 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

1.0 SCOPE

This method statement describes the procedures generally involved in


constructing RC structures of railway bridge BR562. While some procedures
requires specific method statements and dealt separately, this document will
address the following activities:

a) Hacking of bored piles


b) Construction of pier column / pile extentsion
c) Construction of bank seat / cross beam
d) Construction of in-situdeck slab
e) Construction of cable trench
f) Construction of parapet wall

2.0 MATERIALS

Exact materials to be used will vary according to component being


constructed, but mainly comprise of the following :

2.1 Reinforcement bars as per the drawings.

2.2 Concrete Grade 40/20

2.3 Steel mould and/or timber formwork

2.4 Scaffold (if required)

2.5 Curing compound

2.6 Precast slab

2.7 Rubber bearing strip

2.8 Stainless steel dowel bar

3.0 EQUIPMENT & RESOURCES


METHOD STATEMENT Page No. : Page 4 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

3.1 The following is a list of equipment to be used. However, the actual number
of units would depend on the works involved.

a) Survey equipment
b) Excavator / backhoe
c) Cranes
d) Vibrator
e) Compressor / jack hammers
f) Welding set
g) Gas cutting set
h) Bar cutter
i) Bar bending machine

3.2 All plants and machinery will be with valid documents or license.

4.0 METHOD & QUALITY CONTROL PROCEDURE

4.1 HACKING OFF BORED PILES

4.1.1 Piles shall be exposed to 75mm below cut off levels. The level shall
then be marked on exposed bored piles.

4.1.2 Bored piles shall then be hacked using pneumatic breaker up to the
pile cut-off level or up to required lap length whichever is greater.

4.1.3 Waste piles shall then be disposed.

4.1.4 As-built positions of piles shall be recorded by surveyor before


carrying out any further works.

4.2 CONSTRUCTION OF PILE EXTENSION / PIER COLUMN

4.2.1 The reinforcement of pile extension / pier columns shall be


extended vertically maintaining lap length of 50D with the starter
bar of pile.
4.2.2 Circular steel mould of 900mm and 1500mm dia. shall be used for
abutment and pier column respectively.
4.4.1 The position and verticality of the moulds shall be checked for
accuracy and tolerance before concreting.
METHOD STATEMENT Page No. : Page 5 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

4.4.2 Concreting shall be carried out using crane and bucket. The lift of
concreting shall be approximately 2.0m.

4.4.3 Where required, scaffolding with timber platform shall be erected


around the pile / pier location for the workers to pour concrete
above ground level.

4.4.4 The mould shall be removed after 12 hours of concreting. Curing


compound shall be sprayed on concrete surface for curing
purposes.

4.5 CONSTRUCTION OF CROSS BEAMS

4.5.1 Temporary staging for cross beams construction shall be erected.


The dimensions of staging at top shall be sized for adequate and
safe working area.

4.5.2 Bottom timber formwork shall be fixed first. Side formwork will
only be installed after reinforcement bars, fabricated according to
drawings, are put in place.

4.5.3 Holes for dowel bars shall be provided at required locations before
concreting.

4.5.4 Levels shall be marked on the formwork for concreting to maintain


the required top camber crosshead.

4.5.5 The cross beam shall be concreted at one stretch using crane and
bucket.

4.5.6 The side formwork for cross beam shall be stripped after 12 hours
of concreting. Bottom formwork and staging shall be removed after
7-10 days provided concrete has attained 2/3 of 28-day strength.

4.5.7 Curing of concrete shall be carried out by applying curing compound


on exposed concrete surface.

4.6 DOWEL BAR / RUBBER STRIPS

4.6.1 As shown in the drawings, dowel bar and rubber strips shall be
provided at required location using approved materials.
METHOD STATEMENT Page No. : Page 6 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

4.6.2 This shall be done before launching of precast slab.

4.7 CASTING OF PRECAST SLAB

4.7.1 Precast slab shall be manufactured in factory.

4.8 LAUNCING OF PRECAST SLABS

4.8.1 Precast slabs shall be transported from casting yard using trailers
and brought to the site at the time of launching.

4.8.2 Launching of precast slab shall be done by cranes.

4.9 CASTING OF DECK SLAB

4.9.1 Reinforcement shall be laid as shown in the drawings.

4.9.2 The top levels of concrete shall be marked over the side formwork
and also on the 6mm dia. steel rods spaced suitably covering the
entire deck slab area.

4.9.3 Concreting shall be done using crane and bucket.

4.9.4 Curing shall be done by providing wet gunny sacks for 7 days.

4.10 PARAPET, KERB AND CABLE TRENCH

4.10.1 The works shall be taken up upon completion of deck slab of the
bridge.

4.10.2 Precast parapet shall be manufactured in factory and transported


from the casting yard using trailers and brought to the site at the
time of launching.

4.10.3 Launching of precast parapet shall be done by cranes. However,


stitching of precast parapet with deck slab shall be done in-situ.
METHOD STATEMENT Page No. : Page 7 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

4.10.4 Wooden formwork shall be used for casting of kerb and cable
trench.

4.11 APPROACH SLABS

4.11.1 Lean concrete shall be laid using crane and bucket.

4.11.2 The levelling of lean concrete shall be done manually using scoops /
shovels.

4.11.3 Fixing of reinforcement shall be as per drawings.

4.11.4 Concrete with required grade shall be laid using crane and bucket.

5.0 QUALITY CONTROL PROCEDURE

Testing shall follow the procedure laid out in the Project Inspection & Test
Plan.
METHOD STATEMENT Page No. : Page 8 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

6.0 HEALTH, SAFETY AND ENVIRONMENT

6.1 Work will be carried out according to the Project Safety Plan.

6.2 Tool box meeting will be carried out on construction area at regular interval
to ensure compliance with the Safety Plan and familiarity with accident and
emergency procedures.

6.3 Conduct safety induction course to workers before commencement of work.

6.4 Provide PPE to all workers including safety helmet, safety shoe, vest, ear
protector, etc.

6.5 Provide signboards to warn workers and public of dangers associated with
construction works.

6.6 Advanced traffic warning signs will be positioned in place along and at
entrance of access roads and designated flagman will be used when working
in the vicinity of existing road if required.

6.7 Ensure affected utilities are relocated or protected prior to commencement of


work.

6.8 Water browser will be used to control dust when necessary.

6.9 Inspect all machinery at site and ensure that it has competent certificate and
is safe to operate.

6.10 Ensure proper staging is provided to the workers during concreting


operation.

7.0 TRACK POSSESSION & MONITORING

Not applicable.

8.0 SUMMARY OF FORMS

List of form to be used for the work is as follows :

a) Site Concreting Record (DRB-F-E018 Rev 1)


METHOD STATEMENT Page No. : Page 9 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

b) Pre Concrete Checklist (DRB-F-E003 Rev 1)

c) Post Concrete Checklist (DRB-F-E013 Rev 1)

9.0 DOCUMENTATION

9.1 Appendix A – Site Concreting Record

9.2 Appendix B – Pre Concrete Checklist

9.3 Appendix C – Post Concrete Checklist


METHOD STATEMENT Page No. : Page 10 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

APPENDIX A
METHOD STATEMENT Page No. : Page 11 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

APPENDIX B
METHOD STATEMENT Page No. : Page 12 of 14
Revision : 0
Issued : May 2002
UE Construction Sdn Bhd UEC/MS/BR562

ELECTRIFIED DOUBLE TRACK IPOH - RAWANG

APPENDIX C