UEC-MS-BR484-PV-016-Laying of ACWC, Rev (1) .1
UEC-MS-BR484-PV-016-Laying of ACWC, Rev (1) .1
UEC-MS-BR484-PV-016-Laying of ACWC, Rev (1) .1
: Page 1 of 6
METHOD STATEMENT Revision : 1
Issued : September 2002
UE Construction Sdn Bhd UEC-MS-BR484-PV-016 :
IMPORTANT:
CONTENTS
1.0 SCOPE
2.0 MATERIALS
3.0 EQUIPMENT & RESOURCES
4.0 METHOD
5.0 QUALITY CONTROL PROCEDURE
6.0 HEALTH, SAFETY AND ENVIRONMENT
7.0 TRACK POSSESSION
8.0 SUMMARY OF FORMS
Page No. : Page 3 of 6
METHOD STATEMENT Revision : 1
Issued : September 2002
UE Construction Sdn Bhd UEC-MS-BR484-PV-016 :
1.0 SCOPE
2.0 MATERIALS
i) Road paver
Brand : Mitsubishi
Model : MF 45W
Or equivalent
4.0 METHOD
4.2 Permanent works shall only be carried out on site upon the laying
materials been accepted by S.E.
4.3 Clean and make good of the surface of completed in-situ deck slab by
mean of sweeping or blowing using air compressor prior to receive the
primer coat.
4.4 Apply a layer of approved bituminous primer over the in-situ deck slab
and leave it for at least 2 hours.
4.5 Lay the approved water proofing membrane over the required area prior
to receive the ACWC layer. Tack coat shall be applied on the top surface
of water proofing membrane at a rate of 0.25 litre/m2.
4.6 The ACWC will be plant-mixed as per approved mix design and transport
to work site by mean of transporting lorries.
4.7 To prevent the lost of heat, the transporting lorries shall be covered by
tarpaulin.
4.8 Upon delivered to job site, ACWC shall be discharged directly into the
paver hoper from the transporting lorry. Care shall be taken in any
loading, hauling and unloading operations to prevent segregation of the
mix.
4.9 Before discharging into the paver hopper, the temperature for the ACWC
shall be checked to be not less than 125C.
4.10 Upon discharged into the paver hopper, the ACWC will be laid in single
layer and in single run.
4.11 Generally, the paving layer shall have a thickness of 20% more than the
required compacted thickness with hope that the required thickness can
be achieved after the compaction.
Page No. : Page 5 of 6
METHOD STATEMENT Revision : 1
Issued : September 2002
UE Construction Sdn Bhd UEC-MS-BR484-PV-016 :
4.12 The laying shall be commenced along the lower side and progress to the
higher side.
4.16 Rolling shall always commence from lower to the higher side of the laid
area. The minimum rolling temperature shall be kept as not less than
110C.
4.17 The surface of the ACWC shall be finished to the grade and line as
required by the S.E.
4.18 No coring is allowed but samples from plant need to be sent for testing
at Geolab.
4.19 Upon completion of the ACWC layer, joint survey shall be carried out to
check for compliance with the specified requirements.
All testing shall follow the procedure laid out in the Project Inspection &
Test Plan.
6.1 Work will be carried out in accordance with the Project Safety Plan.
6.2 Provide PPE to all workers including safety helmet, vest, etc.
6.3 Inspect all machinery at site and ensure that it has competent
certificate and is safe to operate.
Not required.