Timeline Tamco 3001

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

TIMELINE FOR INTERIOR FITTING

No. Items JAN FEBRUARY Description


31 1 2 3 4 5 6 7 8 9 10
1. Reception area
Reception desk Placed at TAMCO's office
Waiting for approval of material and if the
material is approved the installation will
Marble for the reception area be done within 2 days
Glass partition behind the reception desk Waiting for approval of material
Waiting for approval of material and if the
material is approved the installation will
TAMCO logo be done within 7 days
Waiting for approval of material and if the
material is approved the installation will
L & T Logo be done within 7 days

2. Foyer
Wall treatment Installation
Ceiling treatment Installation

3. Staircase
Glass railing Installation
Wood partition Installation
Marble flooring Installation

4. Upper outer wall treatment


Waiting for approval and if it's approved
the process will take 5 days and 1 day for
Wood wall treatment installation

5. Signage
Main gate signage Installation
TAMCO and L & T Logo Installation

6. Lobby enterance
Granite Installation Installation