Bill of Quantity for Access Road to Property.

Road Length = 4219m. (Cross Section 1 = 7.8m) Lined drains at Specific Location on Site

ITEM DESCRIPTION UNIT QTY RATE AMOUNT NGN


Preliminaries , Setting out, Mobilization &
1 LS 1 lump sum 24,700,000.00
Demobilization and Project Supervision.
Mobilization of Earth moving Equipment (Grader,
a LS 2,000,000.00
Excavator, Roller, Low Bed etc)
ai Initial 1,200,000.00
aii Monthly Months 4 200,000 800,000.00
b Demoblization from Site LS 1,000,000.00
Setting out, Rental and use of Survey Equipment for the
c LS 1,500,000.00
entire project
ai Initial 900,000.00
aii Monthly Months 4 150,000 600,000.00
d Mobile Toilet and Convinience Months 4 75,000 300,000.00
Mobile Site Offices & Shed (Inclusive of AC, generator,
e Nos 2 1,250,000 2,500,000.00
office furniture and office staioneries)
Personal Protective Equipment (Helmet, safety boots,
f Nos 50 50,000 2,500,000.00
gloves etc) - for project team members
g Reflective Construction safety signs Nos 10 50,000 500,000.00
Projct Sign Post (inclusive of solar power lighting at
h Nos 2 200,000 400,000.00
night)
i Insurance for work and Personnel LS 2,000,000.00
j Provision of facilities and meal for site meetings Months 4 100,000 400,000.00
k Site Photographs Months 6 100,000 600,000.00
l Quality Control / Testing of Materials LS 5,000,000.00
m Diversion & Temporary Access road LS 1,000,000.00
n As-built drawing development LS 1,500,000.00

Grade, shape, and compact existing subgrade in


2 m2 32098.2 350 11,234,370.00
readiness to receive regulatory fill material

Provide regulatory fill on existing ground level to


3 achieve desired shape and slope, wet and compact to m3 19744.92 10,990 216,996,670.80
give formation level

Excavate for edge kerbs, Access culverts and Cross


4 m 7438 1,050 7,809,900.00
culverts

Install New edge kerbs 150mm x 450mm rate to


5 m 7438 3,000 22,314,000.00
include haunchng and concrete bed

Repair existing edge kerbs 150mm x 450mm rate to


6 m 1000 2,500 2,500,000.00
include haunchng and concrete bed
Provide and place G25 Reinforced Concrete covered
7 lined drain. ( 1.2m x 1.0m x 0.15m = 0.85m3/m) - at m 1000 95,000 95,000,000.00
specified locations by project Engineer

Provide and install guard rail with concrete base.


8 Refer to drawings for details. Locations at m 500 15,000 7,500,000.00
embankment above 2m.

Provide and Place thick Geotextile material


9 m2 32098.2 1,350 43,332,570.00
(120grams) to top of well compacted filling

Provide and compact 100mm sand bed to receive


10 m2 32,500 1,200 39,000,000.00
interlocking stones

Supply and install 100mm x 200mm x 80mm thick


11 road grade interlocking concrete stones with a strength m2 32,500 8,500 276,250,000.00
of 30N/mm2

Allow for Road Accessories & Furniture, Road Signs


12 LS 1 Lump Sum 5,500,000.00
and Road Marking

Reflective road signs Nos 6 150,000 900,000.00

reflective painting of guard rails m 1,000 500 500,000.00

Painting of Kerbs m 8,200 500 4,100,000.00

TOTAL 752,137,510.80