TemporaryToilet & Maintenance BOQ
TemporaryToilet & Maintenance BOQ
TemporaryToilet & Maintenance BOQ
5. Roofing 15,500.00
Total 345,654.00
1
ITEM UNIT QTY. PRICE PRICE
2
ITEM UNIT QTY. PRICE PRICE
6. Metal Work -
GIS-34 Metal Sheet cover Door with Full Compelet Work -
6.10 Doors -
a) size 70 x200cm NO 16.00 430.00 6,880.00
-
Total carrid to summary 6,880.00
-
7. Electrical Installation -
-
Light point repair and maintain with full Fixture and flush
7.10 mounted switch (32 class room at Dire dawa Compressive
school for A purpose of Gust room ) No 80.00 600.00 48,000.00
Flush mounted socket outlets repair and maintain with full
Fixture(32 class room at Dire dawa Compressive school for A
7.20
purpose of Gust room ) & (two class room at Dire dawa
Resource center school compound) No 86.00 500.00 43,000.00
Light point installing with full Fixture and flush mounted
7.30 switch of temporary shower and toilet. (at Dire dawa
Resource center school compound) No 16.00 500.00 8,000.00
Total Carried to Summary 99,000.00
8. SANITARY WORKS -
-
INSTALING FLOOR SET WATER TANK (ROTO) -
Installing three 10,000 liters roto at floor set at four steps hcb
set two around toilet and one at restaurant around with full
8.10 fixture and accessory installation with complete work.(ONE at
Dire dawa Resource center school compound TWO at Dire dawa
Compressive secondary school compound ) No 3.00 25,000.00 75,000.00
-
HAND WASH BASINS -
Maintain the existing 8 pcs hand wash maintenance with full
8.20 accessory and necessary material (at Dire dawa Compressive
secondary school compound ) No 10.00 1,000.00 10,000.00
-
Red made one hand wash at restaurant place with hcb with full
8.30 accessory and necessary material (at Dire dawa Compressive
secondary school compound ) No 1.00 1,400.00 1,400.00
-
HCB WATER CLOSET -
Installing hcb set water closet with full installation of Di 50mm
8.40 pvc pipe with connect with existing septic tank.(at Dire dawa
Resource center school compound ) No 8.00 400.00 3,200.00
-
SHOWER -
Installing Shower Floor Drain with full installation of Di 25mm
8.50 pvc pipe with connect with existing septic tank. By Di 50mm pvc
pipe.(at Dire dawa Resource center school compound ) No 8.00 250.00 2,000.00
-
Installing Shower Floor Drain with full installation of Di 25mm
pvc pipe connect from the existing shower room with with
8.60
existing septic tank. By Di 50mm pvc pipe..(at Dire dawa
Resource center school compound ) No 8.00 700.00 5,600.00
-
Total Carried to Summary 97,200.00