BILL OF QUANTITY FOR TEMPORARY COMMUNAL TOILET AND

CLASS ROOM MAINTENACE

at Dire dawa Compressive school & at Dire dawa Resource center

1. Excavation & Earth Work. 14,014.00

2. Concrete work 22,260.00

3. Block Work 58,800.00

4. Glazing work 32,000.00

5. Roofing 15,500.00

6. Metal Work 6,880.00

7. Electrical Installation 99,000.00

8. SANITARY WORKS 97,200.00

Total 345,654.00

vat 15% 51,848.10

Grand total 397,502.10

For . Mayer office

1
ITEM UNIT QTY. PRICE PRICE

1. Excavation & Earth Work.


Clearing of the building area and removal of all dirt and
1.10
expansive soil to an average depthof 20cm m2 52.00 20.00 1,040.00
1.20 Bulk excavation to reduce level to a depth not exceeding 50cm m3 39.00 70.00 2,730.00
-
Back fill around stone masonry foundation wall with selected
1.30
material from quarry well compacted in layers of 20cm m3 39.00 20.00 780.00
-
Cart away surplus ecxavated material and deposit at a
1.40
distance not exceeding 2km from the site. m3 10.40 10.00 104.00
-
15cm thick basaltic or equivalent stone hard core well rolled,
1.50 consolidated and blinded with crushed stone. For Typical
Guard House m2 39.00 240.00 9,360.00
Total carried to summary 14,014.00
-
2. Concrete work -
Reinforced concrete in class C-20, with minimum cement content
of 360kg/m3 filled in into form work and vibrated around
reinforcement bar (steel and formwork measured separately). -
2.10 In 10cm thick ground floor slab. m2 42.00 350.00 14,700.00
-
2.20 cement screed floor finish with desire slope m2 42.00 180.00 7,560.00
Total Carried to Summary 22,260.00
-
3. Block Work -
GIS 34 Sheet wall including the partition of Toilet m2 80.00 240.00 19,200.00
3.10 Ø 10cm woodn Post For GIS 34 Sheet Wall
ml 90.00 110.00 9,900.00
3.20 Ø 8cm woodn Diagonal Member For GIS 34 Sheet Wall
ml 270.00 110.00 29,700.00
Total Carried to 58,800.00
Summary.
4. Glazing work -
Replace 1oo pcs of louver despaired windows glass louver pcs
4.10 with full fixture to the existing hall to use temporary restaurant
for guest. ( at Dire dawa Compressive school ) pcs 100.00 320.00 32,000.00
Total carried to Summary. 32,000.00
5. Roofing -
5.10 GIS-34 roof cover with Full Compelet Work m² 50.00 310.00 15,500.00
-
Total carried to Summary. 15,500.00
-

2
ITEM UNIT QTY. PRICE PRICE

6. Metal Work -
GIS-34 Metal Sheet cover Door with Full Compelet Work -
6.10 Doors -
a) size 70 x200cm NO 16.00 430.00 6,880.00
-
Total carrid to summary 6,880.00
-
7. Electrical Installation -
-
Light point repair and maintain with full Fixture and flush
7.10 mounted switch (32 class room at Dire dawa Compressive
school for A purpose of Gust room ) No 80.00 600.00 48,000.00
Flush mounted socket outlets repair and maintain with full
Fixture(32 class room at Dire dawa Compressive school for A
7.20
purpose of Gust room ) & (two class room at Dire dawa
Resource center school compound) No 86.00 500.00 43,000.00
Light point installing with full Fixture and flush mounted
7.30 switch of temporary shower and toilet. (at Dire dawa
Resource center school compound) No 16.00 500.00 8,000.00
Total Carried to Summary 99,000.00
8. SANITARY WORKS -
-
INSTALING FLOOR SET WATER TANK (ROTO) -
Installing three 10,000 liters roto at floor set at four steps hcb
set two around toilet and one at restaurant around with full
8.10 fixture and accessory installation with complete work.(ONE at
Dire dawa Resource center school compound TWO at Dire dawa
Compressive secondary school compound ) No 3.00 25,000.00 75,000.00
-
HAND WASH BASINS -
Maintain the existing 8 pcs hand wash maintenance with full
8.20 accessory and necessary material (at Dire dawa Compressive
secondary school compound ) No 10.00 1,000.00 10,000.00
-
Red made one hand wash at restaurant place with hcb with full
8.30 accessory and necessary material (at Dire dawa Compressive
secondary school compound ) No 1.00 1,400.00 1,400.00
-
HCB WATER CLOSET -
Installing hcb set water closet with full installation of Di 50mm
8.40 pvc pipe with connect with existing septic tank.(at Dire dawa
Resource center school compound ) No 8.00 400.00 3,200.00
-
SHOWER -
Installing Shower Floor Drain with full installation of Di 25mm
8.50 pvc pipe with connect with existing septic tank. By Di 50mm pvc
pipe.(at Dire dawa Resource center school compound ) No 8.00 250.00 2,000.00
-
Installing Shower Floor Drain with full installation of Di 25mm
pvc pipe connect from the existing shower room with with
8.60
existing septic tank. By Di 50mm pvc pipe..(at Dire dawa
Resource center school compound ) No 8.00 700.00 5,600.00
-
Total Carried to Summary 97,200.00