DR Oskar 191020-SocMyanmarCivilEng - 01

Download as pdf or txt
Download as pdf or txt
You are on page 1of 123

Society of Myanmar Civil Engineers

(Singapore)

Challenges of Underground Construction


in the Built-up environment

Dr. Oskar SIGL – Geoconsult


Singapore, 20.10.2019
1
Synopsis

 Underground Construction is more and more taking place in


urban environments

 Increased levels of complexity, difficulty and providing ever


greater challenges to us engineers

 Linkways and Underpasses are often “forgotten”

 Discuss some “Special Solutions” to such linkway challenges


= Rectangular Pipe Jacking
= Box jacking in very shallow cover
= Pipe pile box with steel frames
= Mined tunnel in very shallow cover

 Some thoughts to evaluation of monitoring results


2
1. Rectangular Pipe Jacking TBM

 Open cut excavation with sheet piles not possible

 Services & Utilities & Traffic disruption

 Overall duration required for completion

 RC concrete box jacking was chosen

 Faster and higher productivity

3
Pedestrian Underpass

 Connecting Entrances with Station

MRT Station

4
Pedestrian Underpass

 Services and Utilities

5
Pedestrian
Project Underpass

 Subsequent TBM tunneling below

 Clearance crown-to-soffit about 10m

Cast
In-situ
141 m of Precast Segments (94 Nos) 15 m

6
Pedestrian Underpass - Future

 3x Future Knock-Out Panels (FKOP) for future connections

 1x Future underpassing of major underground expressway


infrastructure (FUI)

FUI

FKOP

7
Functional Cross Section

 Segment width is 1.5m

Cutting Line for FKOP


4625 Clear Internal Dimension

3005 Clearance to ceiling


Thickness of Segment = 500 mm
6600 Clear internal dimension

Cast in Situ Slab (min 275 mm)


Cutting Line for FKOP

External Radius of Corner = 1000 mm


100 mm Recess for Fire H.
Type 3 Segments

8
Geotechnical Long Section

 About 60m of ground treatment (44 rings)

 Overburden varies between 5 m and 7 m

 Total Number of rings = 94

 Intermediate Jacking Station = 1


Base of Kallang Formation

FILL
E
M
F1
GVI

GV

Rock Head

9
Ground Treatment

Ground Treatment (Zone 4)

Ground Treatment (Zone 3)

Ground Treatment (Zones 2a & 2b)

Ground Treatment (Zone 1)

Underpass Tunnel

NB
SB MRT
MRT

10
Rectangular Pipe Jacking Machine

11
Rectangular Pipe Jacking Machine

 EPB Type of Excavation Machine


Intermediate Thrust Ring Back Support
Jacking System

Thrust System

12
Rectangular Pipe Jacking Machine

 Intermediate
Jacking Station

13
Rectangular Pipe Jacking Machine

 Bentonite injection system (Lubrication)

14
Lining Segment

 Pre-cast on site

15
Lining Segment

 Segment Turning and Lowering into the Shaft

16
Knock-out Panels

 One for this project & 3 for future connections


Side wall cut out of
Entrance D KOP 21 Segments (22%
Future KOP of 94 nos.)

Stronger Type 2
segments are used
Future KOP at KOP locations

Type 1b KOP not


possible to shift in
the future

Type 2 KOP could


FUI
be shifted to Type
1b location in the
future

17
Knockout Panels

 External Support provided to Roof and Base Slab

18
Future Connections

 Segments mainly supported from the outside

Macalloy tensioning
bars provided in the
top corners.

Temporary prop
across the drain
between corbel and
cast in situ slab.

Sufficient rebar is provided in


slab so that it is able to span
across the opening

19
Future Connections

 RC slab on top of linkway

20
Future Connections

 Slabs and Beams

FUTURE SLAB

FUTURE BEAMS

21
Tunnelling KPIs

 Target volume loss: <1% expected, 2% used for impact assessment

 Face pressure:
= Ground Treatment: Max. / Target / Min. = 105 / 85 / 75kPa
= Residual Soil: Max. / Target / Min. = 135 / 115 / 105kPa

 Lubricant pressure:
= Ground Treatment: Max. / Min. = 150 / 90kPa
= Residual Soil: Max. / Min. = 150 / 120kPa

 Backfill grout pressure Max. / Min. = 150 / 125kPa

 Thrust force 7,500 ~ 30,000 (Max. 50,000kN)

 Initial CHI air pressure: Treated Ground 75kPa


Residual Soil 95kPa

22
Construction

 Obstructions related to utility works in the past

 Left-in-place temporary retaining walls

23
Construction

 Obstructions

Steel recovered from screw conveyor

24
Obstructions

 Steel plate wrapped around cutter head

25
Tool Damage

 Damaged cutter bits, recovered from screw conveyor

26
Obstructions

 Granite boulders removed from cutterhead

27
Cutterhead Interventions

 CHI access only from the “middle”

28
Cutterhead
Intervention

29
Cutterhead Intervention

30
Excavation progress

Obstructions to Cutterhead

Very Soft Soils Residual Soils of Granite

31
Synopsis

 Underground Construction is more and more taking place in


urban environments

 Increased levels of complexity, difficulty and providing ever


greater challenges to us engineers

 Linkways and Underpasses are often “forgotten”

 Discuss some “Special Solutions” to such challenges


= Rectangular Pipe Jacking
= Box jacking in very shallow cover
= Pipe pile box with steel frames
= Mined tunnel in very shallow cover

 Some thoughts to evaluation of monitoring results


32
2. Box Jacking in very Shallow Cover

 Full scale underground expressway

 Stacked arrangement (2x3 lanes)

 Follows a major road

 Large number of utilities and services

 Crossing with existing MRT twin bored tunnels (above &


below)

 Practically no overburden for upper tunnel

 Lower tunnel crossing not presented here

33
Underground Expressway

 Top of final structure at ground level or higher

 Services & Utilities & Traffic

 Very wide structure (3 lanes expressway)

 Heave due to load reduction caused by excavation

 Maintain weight to eliminate uplift

 Safer, faster and higher productivity

34
Crossing Existing MRT Line

MRT
Crossing

35
Underground Expressway

 Crossing of
Existing MRT Fill
Southbound
Tunnel Sand (Fluvial)

Residual Soils NSL


Clay (Marine/Fluvial)

Northbound
Tunnel

Rock Head
Granite

36
Underground Expressway 2x 3-Lanes

 Major Road Junction

 Existing operational MRT Line

37
Underground Expressway 2x 3-Lanes

 Major Road Junction

 Existing operational MRT Line


Road on the surface Existing MRT bored tunnel Road on the surface

SB – Expressway 3 lanes

Future Development – Underpass Future Development - Underpass

NB – Expressway 3 lanes

38
Sequence

 Work shafts

39
Sequence

 Uplift of existing tunnels during excavation of Upper crossing

40
Reference Design

 Load path travels around many corners

41
Alternative – SFT Method

 Simple Faceless Tunneling Method (patented)

 Entire soil package is jacked out by jacking element

 Element is “pre-cast” in the shaft and then jacked into the


ground

 Maintain weight to eliminate uplift of existing MRT

 No open face

 All excavation is carried out in the shaft

 Once jacking is finished, the permanent structure is already


completed

42
SFT Box Jacking Method for the Upper
Tunnel
 Involves Patents Road level

SB Tunnel

1.5m

NSL Tunnel

43
Square Pile Box Installation

 Roof laid out on the ground Road level

NSL Tunnel

44
Square Pile Box Installation

 Installed from adjacent shaft

1.5m

NSL Tunnel

45
Square Pile Box Installation

46
Square Pile Box Installation

– Retractable cutterhead
– Removal of obstructions when encountered
– Bentonite can be injected for lubrication

47
Square Pile Box Installation

 Side from bottom up

Square pile box

1.5m

NSL Tunnel

48
Square Pile Box Installation

 xx

49
Closure of the Square Pile Box

50
Friction Cut Plates

 On soil sides of square box pipes

 Connected by welding at the front edge and will be


pulled into ground by box pile during jacking process

 Left in the ground

Jacking
Jacking
Direction
Direction

For 1st Box Pipe For Subsequent Box Pipes

51
SFT Method

Friction cut plates


Square pile box and soil

Square piles
1000×1000×3000
Source: Uemura Giken Co. Ltd

52
SFT Method

Segment cast in shaft

Friction cut plates are left in the ground


Source: Uemura Giken Co. Ltd

53
Jacking of Box Segment

 Jacking force need to be taken care of

54
Jacking Arrangements

 Work shaft designs need to consider very large jacking forces

 Large jacking forces at the reaction wall

= Ground Treatment behind reaction wall

= T-shape diaphragm wall panels behind reaction wall

= Combination of both

 OR

= Early installation of permanent structure behind the reaction


wall for a defined distance (65m)

= Take force with diaphragm walls (side walls) and the slabs

55
Jacking Arrangements

 Design for very large jacking forces

 3D analysis of entire structure

 65m of permanent structure – walls and slabs take the load

56
Sequence

 Work shafts

57
Sequence

 Work shafts

Receiving Shaft Launching Shaft

58
Sequence

 Square pile box and reaction structure

Receiving Shaft Launching Shaft Reaction Structure

59
Sequence

 SFT Method – Jacking

Receiving Shaft Launching Shaft Reaction Structure

60
Sequence

 Upper Tunnel (SFT) completed

61
Sequence for Lower Tunnel

 For information only

 Excavate work shafts deeper

62
Sequence for Lower Tunnel

 Lower tunnel installed by JF Method (Front Jacking)

 Pulling from both sides using other side as reaction

Upper Tunnel

Future Development Future Development

Lower Tunnel 3 1 2

63
Synopsis

 Underground Construction is more and more taking place in


urban environments

 Increased levels of complexity, difficulty and providing ever


greater challenges to us engineers

 Linkways and Underpasses are often “forgotten”

 Discuss some “Special Solutions” to such challenges


= Rectangular Pipe Jacking
= Box jacking in very shallow cover
= Pipe pile box with steel frames
= Mined tunnel in very shallow cover

 Some thoughts to evaluation of monitoring results


64
3. Pipe Pile Box with Steel Frames

 Mixed ground conditions with granite rock and residual soils

 Underpasses a major intersection

 Large number of utilities and services and major 13m wide


drainage culvert

 Connecting to existing MRT station

 Alternative proposal with large diameter pipes and omitting


intermediate shaft

65
Original Proposal

 Keep jacking length to a maximum of around 40

 Intermediate work shaft

 42 nos. dia. 813/16mm interlocking steel pipes

 Support frame spacing 1.5m

 Horizontal ground treatment

66
Original Proposal

Entrance Shaft
Pipe jacking tunnel 1
Shaft 1

Pipe Jacking tunnel 2

Shaft 4

Shaft 3

67
Alternative Proposal

 No intermediate large work shaft (only concreting chute)

 Jacking length increased to almost 100m

 42 nos. of pipe jackings reduced to 13 nos.

 13 nos. dia. 2,030/16mm interlocking steel pipes

 Support frame spacing 5m

 Temporary concrete slab at the base between the frames

 Ground treatment form within the large pipes and vertical

68
Alternative Proposal

 Revised Layout

Entrance C
Launching shaft

Link Bridge

Concreting access

Arrival shaft

Entrance A

69
Soil Profile

 Mixed ground conditions

Entrance A
Entrance C
Arrival
13m wide Canal Launching
FILL
GVI
F2

GIV GV

GIII

Proposed Pipe Jacking

FILL F1 F2 GVI GV GIV GIII

70
Alternative Proposal

71
Alternative

Launching seal

72
Pipe Jacking Machine

 Collapsible cutter head due to no space for retrieval at arrival


shaft

Jacking diameter Collapsed diameter


2,082mm 1,810mm
73
Pipe Connections

 All pipes are interconnected with T-clutch detail

74
Alternative Ground Treatment

 Jet grouting from within the pipes

75
Alternative Ground Treatment

JGP
Columns

Rockhead

76
77
Completed Pedestrian Linkway

78
Synopsis

 Underground Construction is more and more taking place in


urban environments

 Increased levels of complexity, difficulty and providing ever


greater challenges to us engineers

 Linkways and Underpasses are often “forgotten”

 Discuss some “Special Solutions” to such challenges


= Rectangular Pipe Jacking
= Box jacking in very shallow cover
= Pipe pile box with steel frames
= Mined tunnel in very shallow cover

 Some thoughts to evaluation of monitoring results


79
4. Mined Tunnel in Shallow Cover

 Connecting Entrance to MRT station

 Mixed ground conditions with cemented sand and soft clays

 Large number of utilities and traffic without possibility of


diversion

 Original proposal pipe pile box with steel frames

 Due to programming constraints only excavation from the


station side possible

 A mined option was only one which was able to meet the
program

80
Original Proposal

 Pipe piles box with steel frames

 24 nos. dia. 800/12mm interlocking steel pipes

 Support frame spacing 1.5m

 Horizontal ground treatment

81
Passenger Linkway

Jacking Shaft
Receiving Shaft 8mx17m
4mx15m

STATION

Mined Tunnel Layout


82
Reference Design
Pipe Roof Cross Section
Ground Level 109.43 (approx.)

103.03m Existing 1.2m Water Pipe

101.48 Supporting Steel Frame

SUBWAY STRUCTURE
PIPE
800mmx11mm thk

Soil Improvement

~ 94.00m

83
Reference Design

Water Main 1.2m

Jacking Shaft
Reaction Wall
84
Alternative Proposal

 Reverse excavation direction for programming reasons

 Remove all activities from the entrance side

Jacking Shaft Wall

85
Mined Tunnel – SCL

 Mixed Ground

FILL – N=10
Sand – N=20

Sand
Clayey Alluvium – N=15

Cemented Alluvium – N=50

Cemented Alluvium – N>80

86
Longitudinal Section - Sequencing

Double Pipe
roof

Double Single Pipe


Pipe roof roof

Top
Heading

Invert

87
Cross Section – Pipe Roof and Face
Grouting
Typical Pipe Roof
Arrangement

88
Typical Face Grouting Arrangement
Cross Section - Sequencing

89
Cross Section - Sequencing

90
Cross Section - Sequencing

91
Cross Section - Sequencing

Half of permanent
structure

Temp. props

92
Cross Section - Sequencing

93
Cross Section - Sequencing

94
Cross Section - Sequencing

95
Pipe Roof Drilling

96
Excavation

97
Excavation – Top Heading

98
Drilling of Face Grouting – 1st Drift

99
Excavation – 2nd Drift

100
2nd Drift Completed

101
Synopsis

 Underground Construction is more and more taking place in


urban environments

 Increased levels of complexity, difficulty and providing ever


greater challenges to us engineers

 Linkways and Underpasses are often “forgotten”

 Discuss some “Special Solutions” to such challenges

 Some thoughts to evaluation of monitoring results

102
5. Monitoring Considerations

 Control over construction risks

 Sometimes only settlement tables – not even time histories

 Time history graphs do not tell the entire story

 Assessment of TREND lines or INFLUENCE lines

103
Monitoring

 Trend Line
 Longitudinal Settlement profiles

 Connect settlement points above the face with a line at different dates

 Provides a means of tend analysis

 Trend line often shows changes well before changes are “visible” in
time history graphs

104
Trend Line

 Connect settlement points above the face


with a line at different dates

105
Trend Line

 Same increments  horizontal line

106
Trend Line

 Larger increments, the curve is dipping down

107
Trend Line

 Surface
settlement

 Crown
settlement
108
Mined Tunnel – From rock into soft ground

 xxxx

 xxxxxxx

109
Mined Tunnel – From rock into soft ground

 xxxx

 xxxxxxx

110
Mined tunnel - Monitoring

 Time history plots

111
Mined tunnel – Monitoring

112
Mined tunnel – Monitoring

113
Mined tunnel – Monitoring

114
Mined tunnel – Monitoring

115
Mined tunnel – Monitoring

116
Mined tunnel – Monitoring

117
Mined tunnel – Monitoring

118
Mined tunnel – Monitoring

119
Mined tunnel – Monitoring

120
Mined tunnel – Monitoring

 Trend Line

 Tool for analysis of monitoring results


 Helps with judgement

121
Mined tunnel - Monitoring

122
Thank
You

123

You might also like