DR Oskar 191020-SocMyanmarCivilEng - 01
DR Oskar 191020-SocMyanmarCivilEng - 01
DR Oskar 191020-SocMyanmarCivilEng - 01
(Singapore)
3
Pedestrian Underpass
MRT Station
4
Pedestrian Underpass
5
Pedestrian
Project Underpass
Cast
In-situ
141 m of Precast Segments (94 Nos) 15 m
6
Pedestrian Underpass - Future
FUI
FKOP
7
Functional Cross Section
8
Geotechnical Long Section
FILL
E
M
F1
GVI
GV
Rock Head
9
Ground Treatment
Underpass Tunnel
NB
SB MRT
MRT
10
Rectangular Pipe Jacking Machine
11
Rectangular Pipe Jacking Machine
Thrust System
12
Rectangular Pipe Jacking Machine
Intermediate
Jacking Station
13
Rectangular Pipe Jacking Machine
14
Lining Segment
Pre-cast on site
15
Lining Segment
16
Knock-out Panels
Stronger Type 2
segments are used
Future KOP at KOP locations
17
Knockout Panels
18
Future Connections
Macalloy tensioning
bars provided in the
top corners.
Temporary prop
across the drain
between corbel and
cast in situ slab.
19
Future Connections
20
Future Connections
FUTURE SLAB
FUTURE BEAMS
21
Tunnelling KPIs
Face pressure:
= Ground Treatment: Max. / Target / Min. = 105 / 85 / 75kPa
= Residual Soil: Max. / Target / Min. = 135 / 115 / 105kPa
Lubricant pressure:
= Ground Treatment: Max. / Min. = 150 / 90kPa
= Residual Soil: Max. / Min. = 150 / 120kPa
22
Construction
23
Construction
Obstructions
24
Obstructions
25
Tool Damage
26
Obstructions
27
Cutterhead Interventions
28
Cutterhead
Intervention
29
Cutterhead Intervention
30
Excavation progress
Obstructions to Cutterhead
31
Synopsis
33
Underground Expressway
34
Crossing Existing MRT Line
MRT
Crossing
35
Underground Expressway
Crossing of
Existing MRT Fill
Southbound
Tunnel Sand (Fluvial)
Northbound
Tunnel
Rock Head
Granite
36
Underground Expressway 2x 3-Lanes
37
Underground Expressway 2x 3-Lanes
SB – Expressway 3 lanes
NB – Expressway 3 lanes
38
Sequence
Work shafts
39
Sequence
40
Reference Design
41
Alternative – SFT Method
No open face
42
SFT Box Jacking Method for the Upper
Tunnel
Involves Patents Road level
SB Tunnel
1.5m
NSL Tunnel
43
Square Pile Box Installation
NSL Tunnel
44
Square Pile Box Installation
1.5m
NSL Tunnel
45
Square Pile Box Installation
46
Square Pile Box Installation
– Retractable cutterhead
– Removal of obstructions when encountered
– Bentonite can be injected for lubrication
47
Square Pile Box Installation
1.5m
NSL Tunnel
48
Square Pile Box Installation
xx
49
Closure of the Square Pile Box
50
Friction Cut Plates
Jacking
Jacking
Direction
Direction
51
SFT Method
Square piles
1000×1000×3000
Source: Uemura Giken Co. Ltd
52
SFT Method
53
Jacking of Box Segment
54
Jacking Arrangements
= Combination of both
OR
= Take force with diaphragm walls (side walls) and the slabs
55
Jacking Arrangements
56
Sequence
Work shafts
57
Sequence
Work shafts
58
Sequence
59
Sequence
60
Sequence
61
Sequence for Lower Tunnel
62
Sequence for Lower Tunnel
Upper Tunnel
Lower Tunnel 3 1 2
63
Synopsis
65
Original Proposal
66
Original Proposal
Entrance Shaft
Pipe jacking tunnel 1
Shaft 1
Shaft 4
Shaft 3
67
Alternative Proposal
68
Alternative Proposal
Revised Layout
Entrance C
Launching shaft
Link Bridge
Concreting access
Arrival shaft
Entrance A
69
Soil Profile
Entrance A
Entrance C
Arrival
13m wide Canal Launching
FILL
GVI
F2
GIV GV
GIII
70
Alternative Proposal
71
Alternative
Launching seal
72
Pipe Jacking Machine
74
Alternative Ground Treatment
75
Alternative Ground Treatment
JGP
Columns
Rockhead
76
77
Completed Pedestrian Linkway
78
Synopsis
A mined option was only one which was able to meet the
program
80
Original Proposal
81
Passenger Linkway
Jacking Shaft
Receiving Shaft 8mx17m
4mx15m
STATION
SUBWAY STRUCTURE
PIPE
800mmx11mm thk
Soil Improvement
~ 94.00m
83
Reference Design
Jacking Shaft
Reaction Wall
84
Alternative Proposal
85
Mined Tunnel – SCL
Mixed Ground
FILL – N=10
Sand – N=20
Sand
Clayey Alluvium – N=15
86
Longitudinal Section - Sequencing
Double Pipe
roof
Top
Heading
Invert
87
Cross Section – Pipe Roof and Face
Grouting
Typical Pipe Roof
Arrangement
88
Typical Face Grouting Arrangement
Cross Section - Sequencing
89
Cross Section - Sequencing
90
Cross Section - Sequencing
91
Cross Section - Sequencing
Half of permanent
structure
Temp. props
92
Cross Section - Sequencing
93
Cross Section - Sequencing
94
Cross Section - Sequencing
95
Pipe Roof Drilling
96
Excavation
97
Excavation – Top Heading
98
Drilling of Face Grouting – 1st Drift
99
Excavation – 2nd Drift
100
2nd Drift Completed
101
Synopsis
102
5. Monitoring Considerations
103
Monitoring
Trend Line
Longitudinal Settlement profiles
Connect settlement points above the face with a line at different dates
Trend line often shows changes well before changes are “visible” in
time history graphs
104
Trend Line
105
Trend Line
106
Trend Line
107
Trend Line
Surface
settlement
Crown
settlement
108
Mined Tunnel – From rock into soft ground
xxxx
xxxxxxx
109
Mined Tunnel – From rock into soft ground
xxxx
xxxxxxx
110
Mined tunnel - Monitoring
111
Mined tunnel – Monitoring
112
Mined tunnel – Monitoring
113
Mined tunnel – Monitoring
114
Mined tunnel – Monitoring
115
Mined tunnel – Monitoring
116
Mined tunnel – Monitoring
117
Mined tunnel – Monitoring
118
Mined tunnel – Monitoring
119
Mined tunnel – Monitoring
120
Mined tunnel – Monitoring
Trend Line
121
Mined tunnel - Monitoring
122
Thank
You
123