Method Statement For Cable Laying & Termination
Method Statement For Cable Laying & Termination
Method Statement For Cable Laying & Termination
CONTENTS
1 INTRODUCTION................................................................................................................................................................................. 3
1.1 Purpose.........................................................................................................................................................................................................................3
1.2 Scope.............................................................................................................................................................................................................................3
1.3 Abbreviations and definitions....................................................................................................................................................................................3
2 SEQUENCE OF ACTIVITY................................................................................................................................................................3
3 PREPARATION.................................................................................................................................................................................... 3
3.1 General installation Procedures................................................................................................................................................................................3
3.2 Installation ..................................................................................................................................................................................................................5
3.3 Safety............................................................................................................................................................................................................................5
4 TRAINING MATRIX......................................................................................................................................................................... 14
5 CONTIGENCY PLAN........................................................................................................................................................................ 16
6 REQUIRED QUALIFICATION........................................................................................................................................................16
7 TOOLS REQUIRED........................................................................................................................................................................... 17
8 LOGISTIC, TRANSPORT AND MATERIALS HANDLING.......................................................................................................18
CONFIDENTIAL. All rights reserved. ALSTOM. Passing on and copying of this document,
Reference Issue Page
use and communication of its content are not permitted without prior written authority. <reference number> <rev> 18
MODAL BCI 61 202 IND A
1 INTRODUCTION
1.1 Purpose
This document describes the Method Statement for installation of Cable Laying & Termination Works.
1.2 Scope
Supply and Installation of cables.
2 SEQUENCE OF ACTIVITY
1 2 3 4 5 6
Excavation &
Support Instal-
lation Cable dressing
Gladding, joint-
ing and termi-
nation
3 PREPARATION
Page 3 / 18
- It shall be ensured that the material issued is as per the approval material submittal.
- Check proper supports for the erection is available (if applicable).
3.2 Installation:-
Page 4 / 18
3.3 Safety
- Head Protection: - Hard hats or helmets should be worn where there is the possibility of injury from falling
objects. All time mandatory.
- Foot Protection: - Safety shoes should be worn if there are hazards from falling objects or when handling heavy
crates or equipment. All time mandatory.
- Hand Protection: - Gloves should be used while handling Earth flat to avoid cutting. All time mandatory.
- Eye and Face protection: - Eye glasses, nose mask, or face shields should be worn.
- Ear Protection:-It may be necessary to wear ear plugs or muffs when noise levels surpass 85 decibels.
- Shoulder protection: - Shoulder pads should be worn, if in case of manual straddling.
- Height work area shall be hard barricaded and only authorized persons will enter inside the earthing works
- Proper housekeeping should be done daily after finishing of works in the evening.
- As we are all aware regarding the COVID-19, we should take our own precautions to control the spreading rate
while activities going at site, so compulsory masks & sanitizers should be used at workplace.
4.Risk Assessment:
Page 5 / 18
5 0 5 10 15 20 25
4 0 4 8 12 16 20 Likelihood 4 SEVERITY
3 0 3 6 9 12 15
Rating 0 = Zero to very low
Severity
4.1.2
Acceptable Further Unacceptable Risk
review
Page 6 / 18
1 2 3 4 5 6 7 8
Factors of Harm Control
measures
Residual
implemented by
ACTIVITY HAZARD Risk Likelihoo Severit risk
CONTROLMEASURES Multiple of
Multiple d y columns 5
of Seenote1 Seenote1
Likelihoo Severit columns 6
d y 12
Checking area and Slip, Trip & Fall 5 5 25 1. Proper housekeeping shall be 4 1 4 Site
engineer,HSE
visual inspection maintained in the work area.
officer
before starting work 2. Appropriate type of PPE such as eye
protection shall be worn along with
hand and foot protection.
3. Adequate access to the work location
be provided or should be available.
Page 7 / 18
utility shall be de-energized/emptied
and all the safety requirements
mentioned in the permit shall be
complied with.
5. In case of underground electrical
cables, the cable shall be de-
energized and if the excavation is to
be done manually, the tools like
crowbar, spade, etc. shall be well
insulated to prevent electrical shock.
6 All the exposed underground
utilities shall be supported when
excavation is open.
Page 8 / 18
dressed to remove loose materials
and boulders, which can fall
inside.
Page 9 / 18
leave the excavation. The ladder shall
extend at least 1m above the ground
level.
3. The sides of the excavation shall
be provided with benching to avoid
rollover of materials.
4. Materials shall not be stored or
moved so closely to the edge of the
excavation that they could fall down.
Cable pulling/laying on Sharp edges from 3 2 6 1. Extra care to be taken while pulling the 2 1 2 Site
cable trays and ladders. existing cable cable on cable trays/ladders, use hard hand engineer,Site
gloves. supervisor
tray/ladders.
2. Conduct training and gives information,
instructions about the tasks. Explain their
hazards and their control measures in that
job.
3. Ensure competent persons are allowed
to do the job.
Damaged existing 3 2 6 1. Extra care to be taken while pulling cable 2 1 1 Site engineer,
cable. to the existing cable tray/ ladders, if Site supervisor
necessary protects the existing cable with
polyethylene sheet.
Page 10 / 18
Slips, trips and fall at 3 2 6 1. Maintain housekeeping around the 2 1 1 Site
the same level. working area. engineer,Site
2. Conduct the program about the safety supervisor
and housekeeping techniques and create
the awareness of housekeeping.
Page 11 / 18
Communication 3 2 6 Good communication measures or devices 2 1 1 Site
barriers among shall be used. engineer,Site
supervisor
workers.
MARKING AND DRILL Use of damaged Hand 3 3 9 1. Obtain LOTO permit. 2 2 Low Site
THE GLAND PLATE. tools. Using of drill 2.Strictly follow EMAL LOTOV procedure engineer,Site
3. Supervisor to ensure approved PTW is supervisor
1.Remove the gland machine. Dust from
available on site prior to commencement
plate from DB 2.Mark drill machine the task.
the gland location Electrocution Sprains& 4. Toolbox talks to be held at site and
3. Drill the marked area strains to hands and documented. 5. Inspect hand tools before
according to the gland arms. use.
size. 5. Inspect drill machine before use and
ensure dead man switch.
6. Ensure proper grounding.
7. Ensure area to be drill is clear from any
services.
8. Only competent and authorized worker
for the using contractor supervisor of power
tools.
9. Provide dust mask 3M 8210or 3M
Page 12 / 18
respiratory mask. . (where ever required)
10. Only 110 V to be used at site.
11. Use of cutting fluid when drilling to
avoid burns, damage to equipment’s.
12. Close unused holes in gland plate by
grommets or PVC plug.
GLANDING, JOINTING 1. Use of sharp hand 3 4 12 1. Obtain LOTOV permit. 2 2 Low Site
AND TERMINATION: tools. 2. Strictly follow EMAL LOTOV procedure engineer,Site
3. When doing the termination in existing supervisor
1. Opening of insulation 2. Competency of
system ensure that power is isolated and no
and cut the cable for electrician/cable current in the working place.
jointing/termination. jointer. 4. All hand tools must be in good condition
2. Crimp the lugs/ferrules 3. Using damaged with valid color code, no homemade hand
to the cable. hand tools/ 4.Torque tools to be used at site, supervisor to check.
3. Remove the bolt from wrench. 5. Torque wrench must be in good condition
with calibrated sticker on it. Supervisor to
the breaker and tight the 5. Use of Heat gun (hot
check
cable lugs with bolts to blower), electrocution/ 6. Supervisor to ensure the competency of
the breaker burns. electrician/cable jointer.
6.Using damaged 7. Inspect heat gun before use; ensure that
hydraulic crimping tool heat gun is in good contractor supervisor
condition with valid colour coded.
8. Only 110 V to be used at site.
5 TRAINING MATRIX
-
TRAINING MATRIX
Total
Management Supervisor Specific
Page 13 / 18
Electricians
Security Staff
Project Manager
Warehouse Manager
PMRC Representative
Sub-contractor Personnel
OHS&E Induction
OHS&E Leadership
OHS&E Plan
Working at Height
Hours
6 CONTINGENCY PLAN
- For any unforeseen situations or uncertainties which could lead to unsafe situation, the supervisor should consider
the followings:
Stop work and remove all tools and materials from location.
Report to Engineers or raise any concern during meeting etc.
7 REQUIRED QUALIFICATION
- Work Authorization
Permit to work on site need to be obtained before start of the installation activities and cancelled after completion
of the work. Permit to work system must be in accordance with employer requirements and ALSTOM EHS
policies/Procedures.
Permit Issuer and Permit Receiver shall comply the guideline of PTW procedure.
Competency assessment and work authorization is mandatory from Project Director and nominated Ones
- Manpower
Operational Construction Supervisor (ALSTOM)
Project manager ( Mr.sachin pmc pune) ELEMENTS
Site Engineer (Sub-contractor)
Quality Engineer (Sub-Contractor)
Site Supervisor (Sub-Contractor)
Electrician (Sub-Contractor)
Safety Engineer (Alstom)
Safety Supervisor (Sub-contractor)
Workforce (15 No’s) for shifting and lifting Material as Required (Sub-Contractor)
The above listed team is a theoretical team, according to safety plan and working conditions.
Page 15 / 18
8 TOOLS
Standard Tools
Tools Short Description Picture (For Illustration Purpose only)
Page 16 / 18
Drilling / Cutting For cutting / drilling the surfaces
machine
Page 17 / 18
Cable Jack For Lifting, unrolling the cable
Page 18 / 18