Method Statement For Cable Laying & Termination

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 18

SITE : MEP,INTERIOR WORK

METHOD OF STATEMENT FOR CABLE LAYING &


TERMINATION
 <PROJECT NAME> - <Sub-system, Product or Component Name>
<dd-mm-yy>
Unit Software Requirements – Specification document

CONTENTS
1 INTRODUCTION................................................................................................................................................................................. 3
1.1 Purpose.........................................................................................................................................................................................................................3
1.2 Scope.............................................................................................................................................................................................................................3
1.3 Abbreviations and definitions....................................................................................................................................................................................3

2 SEQUENCE OF ACTIVITY................................................................................................................................................................3
3 PREPARATION.................................................................................................................................................................................... 3
3.1 General installation Procedures................................................................................................................................................................................3
3.2 Installation ..................................................................................................................................................................................................................5
3.3 Safety............................................................................................................................................................................................................................5

4 TRAINING MATRIX......................................................................................................................................................................... 14
5 CONTIGENCY PLAN........................................................................................................................................................................ 16
6 REQUIRED QUALIFICATION........................................................................................................................................................16
7 TOOLS REQUIRED........................................................................................................................................................................... 17
8 LOGISTIC, TRANSPORT AND MATERIALS HANDLING.......................................................................................................18

CONFIDENTIAL. All rights reserved. ALSTOM. Passing on and copying of this document,
Reference Issue Page
use and communication of its content are not permitted without prior written authority. <reference number> <rev> 18
MODAL BCI 61 202 IND A
1 INTRODUCTION

1.1 Purpose
This document describes the Method Statement for installation of Cable Laying & Termination Works.

1.2 Scope
Supply and Installation of cables.

1.3 Abbreviations and definitions


Abbreviation Definition
EHS Environmental Health and safety
SIG Signalling

2 SEQUENCE OF ACTIVITY

Cable laying & TerminationMarking and


Cable pulling/ drill the gland
Checking area laying on cable plate
and visual in- trays and lad-
spection be- ders.
fore starting
work

1 2 3 4 5 6

Excavation &
Support Instal-
lation Cable dressing
Gladding, joint-
ing and termi-
nation

3 PREPARATION

3.1 General Installation Procedure:


- Ensure that the proper clearance is available from civil side before commencement of works
- Ensure that the work area is clean and safe for carrying out the activities
- Prior to start of works, it shall be ensured that the relevant shop drawings and coordination drawings are approved
and issued for construction.
- It shall be ensured that no contraction with other previously installed services, and if there is any shall be cleared.

Page 3 / 18
- It shall be ensured that the material issued is as per the approval material submittal.
- Check proper supports for the erection is available (if applicable).

3.2 Installation:-

3.2.1 Laying Procedures For Underground HT Cable :- .


- Size & Length of the cable to be checked by engineer In charge & Supervisor before cutting high tension cables
- Cable drums are to be positioned on cable Jockeys and cable end to be left from the top
- Rollers are to be provided at regular intervals according to cable route while pulling the cable on ground shall be
avoided to protect cable insulation
- Insulation resistance of HT cable should be checked by 5KV megger after installation and before termination of
cables
- The width of the cable trench shall be maintained minimum 450mm and 1200m depth according to number of
cables buried
- Soft sand shall be spread 150mm below the cable and 100mm above the cable. Over this a layer of 300mm clean
earth soil shall be filled
- Laying protective RCC/Bricks over the cable properly with regular arrangements
- CI markings to be provided at every 20m span with cable routing identification

3.2.2 Laying Procedures For HT Cable On Tray:-


- The tray shall be curved enough to allow the cable with correct bending radius
- Cable shall be dressed properly and using clamps where vertical cable is laid and the cable tray surface is
horizontal without any overlapping
- Cable identification to be provided to both the ends of cable as per approved cable schedule
- Cable ends should be earthed and sealed properly
- Earth conductor should be laid parallel along with cables
- Mobilizing & Positioning Of Boom/scissor lift In Work Location
- Cable laying work Process by Mechanized equipment by Boom/scissor lifts
- Ensure that proper colour coding is followed for phase ,neutral ,earth as per the standard
- The colour coding of cable shall be followed till the termination within Panels

3.2.3 Terminations Of HT Cables :-


- Termination shall be done by using approved termination materials that include glands ,lugs and other
accessories part of termination kit
- Gland the cables in the panels using the suitable size / type of cable gland
- Cable Lugs shall be heavy duty copper type lugs
- Terminate the cables / wires in the panels using suitable size of cable lugs crimped by proper crimping tool
- Termination bolt nuts to be tightened properly and lugs crimping to be done properly
- Gland Earthling connected to the Panel body earth

3.2.4 Cables Identification :-


- Install the tags/ labels as per project specification and as per approved material submittals
- Identification of cable by proper tag of the cable drum at both end of the cables
- Warning Identification labels to provide with height of 50mm and the background of identification to be yellow
and with black letters.

Page 4 / 18
3.3 Safety
- Head Protection: - Hard hats or helmets should be worn where there is the possibility of injury from falling
objects. All time mandatory.
- Foot Protection: - Safety shoes should be worn if there are hazards from falling objects or when handling heavy
crates or equipment. All time mandatory.
- Hand Protection: - Gloves should be used while handling Earth flat to avoid cutting. All time mandatory.
- Eye and Face protection: - Eye glasses, nose mask, or face shields should be worn.
- Ear Protection:-It may be necessary to wear ear plugs or muffs when noise levels surpass 85 decibels.
- Shoulder protection: - Shoulder pads should be worn, if in case of manual straddling.
- Height work area shall be hard barricaded and only authorized persons will enter inside the earthing works
- Proper housekeeping should be done daily after finishing of works in the evening.
- As we are all aware regarding the COVID-19, we should take our own precautions to control the spreading rate
while activities going at site, so compulsory masks & sanitizers should be used at workplace.

4.Risk Assessment:

Page 5 / 18
5 0 5 10 15 20 25
4 0 4 8 12 16 20 Likelihood 4 SEVERITY
3 0 3 6 9 12 15
Rating 0 = Zero to very low
Severity

2 0 2 4 6 8 10 Rating 1 = Very unlikely Rating 0 = No injury or illness


1 0 1 2 3 4 5 Rating 2 = Unlikely Rating 1 = First aid injury or illness
0 0 0 0 0 0 0 Rating 3 = Likely Rating 2 = Minor injury or illness
0 1 2 3 4 5 Rating 4 = Very likely Rating 3 = “3 day” injury or illness
Likelihood Rating 5 = Almost certain Rating 4 = Major injury or illness
Rating 5 = Fatality, disabling injury, etc

4.1.1 Risk = Likelihood x Severity

4.1.2
Acceptable Further Unacceptable Risk
review

Page 6 / 18
1 2 3 4 5 6 7 8
Factors of Harm Control
measures
Residual
implemented by
ACTIVITY HAZARD Risk Likelihoo Severit risk
CONTROLMEASURES Multiple of
Multiple d y columns 5
of Seenote1 Seenote1
Likelihoo Severit columns 6
d y 12

Checking area and Slip, Trip & Fall 5 5 25 1. Proper housekeeping shall be 4 1 4 Site
engineer,HSE
visual inspection maintained in the work area.
officer
before starting work 2. Appropriate type of PPE such as eye
protection shall be worn along with
hand and foot protection.
3. Adequate access to the work location
be provided or should be available.

Excavation & 5 5 25 1. Before commencing excavation 4 1 4 Site


Support Installation work, the Site Engineer shall look for engineer,Site
supervisor
the presence of underground utilities
using detectors and checking for the
presence of markers & other suitable
methods.
2. Trial pits shall be excavated
manually before using the equipment
to identify the underground utilities (if
any).
3. Workmen involved shall
essentially use safety shoes,
electrical safety hand gloves and
insulated crowbars & other tools.
4. Work permit shall be taken & the

Page 7 / 18
utility shall be de-energized/emptied
and all the safety requirements
mentioned in the permit shall be
complied with.
5. In case of underground electrical
cables, the cable shall be de-
energized and if the excavation is to
be done manually, the tools like
crowbar, spade, etc. shall be well
insulated to prevent electrical shock.
6 All the exposed underground
utilities shall be supported when
excavation is open.

Undiscovered buried 5 5 25 1. Excavated material shall be 4 1 4 Site


obstructions and kept away from the edge of the engineer,Site
supervisor
existing piles excavation to provide a clear
berm of a width of not less than
one-third the final depth of
excavation.
2. In special cases, where the
disposal area is limited or where the
application of this requirement is
impracticable, the Site Engineer may
adopt a berm of reduced width in
any case not less than 1 m., provided
the material being excavated is
sufficiently stable and shoring is
provided to carry the additional load.
3. Excavation walls shall be

Page 8 / 18
dressed to remove loose materials
and boulders, which can fall
inside.

Collapse of soil 5 5 25 1. Excavated material shall be 4 1 4 Site


kept away from the edge of the engineer,Site
supervisor
excavation to provide a clear
berm of a width of not less than
one-third the final depth of
excavation.
2. In special cases, where the
disposal area is limited or where the
application of this requirement is
impracticable, the Site Engineer may
adopt a berm of reduced width in
any case not less than 1 m., provided
the material being excavated is
sufficiently stable and shoring is
provided to carry the additional load.
3. Excavation walls shall be
dressed to remove loose materials
and boulders, which can fall
inside.

No hard barricading 5 5 24 1. Hard barriers/earthen bund, 3 1 3 Site


provided warning signs and warning lights / engineer,Site
supervisor
light reflectors shall be provided to
prevent fall of persons/vehicles
inside.
2. Ladders shall be used to enter or

Page 9 / 18
leave the excavation. The ladder shall
extend at least 1m above the ground
level.
3. The sides of the excavation shall
be provided with benching to avoid
rollover of materials.
4. Materials shall not be stored or
moved so closely to the edge of the
excavation that they could fall down.

Cable pulling/laying on Sharp edges from 3 2 6 1. Extra care to be taken while pulling the 2 1 2 Site
cable trays and ladders. existing cable cable on cable trays/ladders, use hard hand engineer,Site
gloves. supervisor
tray/ladders.
2. Conduct training and gives information,
instructions about the tasks. Explain their
hazards and their control measures in that
job.
3. Ensure competent persons are allowed
to do the job.
Damaged existing 3 2 6 1. Extra care to be taken while pulling cable 2 1 1 Site engineer,
cable. to the existing cable tray/ ladders, if Site supervisor
necessary protects the existing cable with
polyethylene sheet.

Page 10 / 18
Slips, trips and fall at 3 2 6 1. Maintain housekeeping around the 2 1 1 Site
the same level. working area. engineer,Site
2. Conduct the program about the safety supervisor
and housekeeping techniques and create
the awareness of housekeeping.

Fall from height or 3 3 9 1. Use only wooden or GRP ladder. 2 2 1 Site


from ladder. 2. Don’t leave cut cable inside the building engineer,Site
and top of panels. supervisor
3. Inspect ladder before use, assign one
man to hold the ladder on the ground while
in used.
4. Always climb up and down facing the
ladder.
5. Don’t carry tools or materials in your
hand while climbing up and down ladder.
6. All workers involve in working at height
must wear their full body harness and 100%
tie off.
Fall of objects 3 3 9 1. Cordon the work area to avoid 1 2 1 Site
unauthorized entry. engineer,Site
2. Provide applicable safety warning supervisor
signboards.
3. Do not keep unwanted materials on top
of the ladder.
4. Materials to be removed should be in
safe manner one by one ensure no
materials to be dropped.

Page 11 / 18
Communication 3 2 6 Good communication measures or devices 2 1 1 Site
barriers among shall be used. engineer,Site
supervisor
workers.

Manual handling 3 2 6 Supervisor to give toolbox talk regarding 2 1 1 Site


hazards proper manual handling. engineer,Site
supervisor

MARKING AND DRILL Use of damaged Hand 3 3 9 1. Obtain LOTO permit. 2 2 Low Site
THE GLAND PLATE. tools. Using of drill 2.Strictly follow EMAL LOTOV procedure engineer,Site
3. Supervisor to ensure approved PTW is supervisor
1.Remove the gland machine. Dust from
available on site prior to commencement
plate from DB 2.Mark drill machine the task.
the gland location Electrocution Sprains& 4. Toolbox talks to be held at site and
3. Drill the marked area strains to hands and documented. 5. Inspect hand tools before
according to the gland arms. use.
size. 5. Inspect drill machine before use and
ensure dead man switch.
6. Ensure proper grounding.
7. Ensure area to be drill is clear from any
services.
8. Only competent and authorized worker
for the using contractor supervisor of power
tools.
9. Provide dust mask 3M 8210or 3M

Page 12 / 18
respiratory mask. . (where ever required)
10. Only 110 V to be used at site.
11. Use of cutting fluid when drilling to
avoid burns, damage to equipment’s.
12. Close unused holes in gland plate by
grommets or PVC plug.
GLANDING, JOINTING 1. Use of sharp hand 3 4 12 1. Obtain LOTOV permit. 2 2 Low Site
AND TERMINATION: tools. 2. Strictly follow EMAL LOTOV procedure engineer,Site
3. When doing the termination in existing supervisor
1. Opening of insulation 2. Competency of
system ensure that power is isolated and no
and cut the cable for electrician/cable current in the working place.
jointing/termination. jointer. 4. All hand tools must be in good condition
2. Crimp the lugs/ferrules 3. Using damaged with valid color code, no homemade hand
to the cable. hand tools/ 4.Torque tools to be used at site, supervisor to check.
3. Remove the bolt from wrench. 5. Torque wrench must be in good condition
with calibrated sticker on it. Supervisor to
the breaker and tight the 5. Use of Heat gun (hot
check
cable lugs with bolts to blower), electrocution/ 6. Supervisor to ensure the competency of
the breaker burns. electrician/cable jointer.
6.Using damaged 7. Inspect heat gun before use; ensure that
hydraulic crimping tool heat gun is in good contractor supervisor
condition with valid colour coded.
8. Only 110 V to be used at site.

5 TRAINING MATRIX
-
TRAINING MATRIX

Total
Management Supervisor Specific

Page 13 / 18
Electricians

Security Staff
Project Manager

Warehouse Manager
PMRC Representative

Sr. OHS&E Managers


Chief OHS& E Manager

Sub-contractor Personnel
OHS&E Induction

OHS&E Leadership

OHS&E Plan

Alstom EHS Passport

High Risk Activity


Management
Applicable Statutes &
Regulations
OHS&E Audit & Inspection

Day to Day Risk Management

First Aid & CPR

OHS&E Emergency Response


& Preparedness
Safety Training Observation
Programme (STOP)
Power Tools and Equipment
Inspection
Housekeeping and waste
management
Incident / Accident
Investigation & Reporting
Page 14 / 18
Co-Current Permit to Work
System
Confined Space Working

Working at Height

Working Near adjacent railway


or Live Electrical atmosphere

Heavy Lifting Operation

Electrical Safety & Power


operated Portable tools
Manual Material Handling

Scaffold Erection/ Dismantling

Hours
6 CONTINGENCY PLAN
- For any unforeseen situations or uncertainties which could lead to unsafe situation, the supervisor should consider
the followings:
 Stop work and remove all tools and materials from location.
 Report to Engineers or raise any concern during meeting etc.

7 REQUIRED QUALIFICATION
- Work Authorization
 Permit to work on site need to be obtained before start of the installation activities and cancelled after completion
of the work. Permit to work system must be in accordance with employer requirements and ALSTOM EHS
policies/Procedures.
 Permit Issuer and Permit Receiver shall comply the guideline of PTW procedure.
 Competency assessment and work authorization is mandatory from Project Director and nominated Ones

- Manpower
 Operational Construction Supervisor (ALSTOM)
 Project manager ( Mr.sachin pmc pune) ELEMENTS
 Site Engineer (Sub-contractor)
 Quality Engineer (Sub-Contractor)
 Site Supervisor (Sub-Contractor)
 Electrician (Sub-Contractor)
 Safety Engineer (Alstom)
 Safety Supervisor (Sub-contractor)
 Workforce (15 No’s) for shifting and lifting Material as Required (Sub-Contractor)
The above listed team is a theoretical team, according to safety plan and working conditions.

Page 15 / 18
8 TOOLS
Standard Tools
Tools Short Description Picture (For Illustration Purpose only)

Measuring Tape To do linear measurement


5m (1) markings

Spirit Level (1) To level the foundations, or beds


of machines to ensure the machine
can output work pieces to the
accuracy pre-built in the machine.

Hammer (1) To deliver an impact to a small


area of an object

Electrical It is used as a Multi – plugger.


Extension Leads Only Industrial type Electrical
(1) distribution board used for power
distribution and contain ELCB
/RCCB. Sensitivity of
RCCB/ELCB should not more
than 30mA and temporary
distribution board must be in
accordance with IP44 standard or
above
Steel Rule To measure short distance
150mm (1)

Knife (as per For cable stripping and termination


requirement) purpose

Insulated Step To work at height


Ladder (1)

Page 16 / 18
Drilling / Cutting For cutting / drilling the surfaces
machine

Megger (as per For IR Testing


requirement)

Crimping Tool Used to conjoin two pieces

Cable Roller For Cable Pulling

Page 17 / 18
Cable Jack For Lifting, unrolling the cable

9 LOGISTIC, TRANSPORT AND MATERIALS HANDLING


- Equipment should be delivered to the work area from the stores by trolley on rail or road or any other suitable
means.
- Following inspection shall be carried out when collecting mounting stands/ bases:
 Shifting of material by trolley or manually to the exact location depending site conditions. (Weight less
than 40 Kg).
 Finish of Stand is in good condition.
 Fixing bolts and ladders (where applicable) are shipped together with stand.
 No visible damage
 Deliveries are consistent with drawings and associated drawings and documentation.
 Stored materials on site shall be properly secured well marked and covered

Page 18 / 18