Method Statement For Installation of Electrical DB, SMDB and MDB Panelboards

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

Method Statement For Installation Of

Electrical DB, SMDB And MDB


Panelboards
Method Statement For Installation of DB, SMDB and MDB.

1. Introduction and Scope


This statement is written for the purpose of establishing method and procedures for the
Installation of DB, SMDB and MDB.
2. Applicable Projects Specification
Section: SWITCHBOARD DISTRIBUTION PANELS AND MCCs.
Division: INSTALLATION
Sub Division: Subdivision

3. Location of Activity
Low Voltage Room and Electrical Rooms

4. Health and Safety Hazards


Specific safety measures have to follow as applicable, and all the safety measures are
covered separately in the project safety plan.

5. Operation
1. Materials: Materials used will be as per the material submittal approved by the
engineer and will be as per the approved drawings in coordination with other services.
2. Storage / Protection: DB, SMDB, and MDB and Accessories shall be unloaded
with care to avoid any damages. If they are shipped in packs or pallets, each pack of
pallet shall be lifted individually with suitable lifting equipment. Every precaution
shall be taken to preserve their cleanliness before installation. Store in accordance
with manufacturer’s instructions, Properly protected from construction activities and
weather conditions.
3. Installation:
a. To make sure that the entire installation is in conformance and in
accordance with the design intent of the project for the Electrical and Low Voltage
System in addition to the specification and as per approved shop drawings and
comply.
b. with local and International Standards.
c. All the switchboards shall be fabricated at the manufacturer’s works.
d. Before beginning installation in any area, examine all parts of the
adjoining works into which applicable work is to be placed. Should any condition be
found which will prevent the proper execution of the work, installation shall not
proceed in that area until such conditions are corrected by the contractor.
e. Fix all equipment independently of wiring system. Use cadmium of zinc
electroplated bolts, nuts, washers and screw.
f. Mount single DB at 1800mm from finish floor level to top of equipment,
unless shown otherwise on drawing / schedules.
g. Ensures that clearance in front of switchgear is not less than 1m, or as
indicated.
h. Number terminals, cables and component parts to correspond with
manufacturer have certified drawings.
i. Terminate PVC, SWA PVC and MICS cables inside enclosure by securing
cables to switchboards with gland bracket; and enclosure with glanding plates or
fabricated steel extension boxes.
j. For flush installation, DB’s all conductors shall terminate behind the board
in an adaptable box. For surface mounting, trunking shall be fixed between the
board and ceiling or floor level, or conduit run directly into Trunking which prevent
correct installation of the Trunking lid. Adequate earth continuity shall be made
between the various components.
6. Responsibilities
1. Project Manager
a. To ensure that all the preparation and application works are carried out
according to the Contract Specification.
b. To ensure that the progressing of works is carried out according to the
planned program and as per the approved method statement.
c. To ensure that all equipment and material required executing the work are
available according to the planned Construction Programme.
d. To co-ordinate with the Main Contractor, MEP co-coordinator, and Safety
Officer for a safe and proper execution of the works.
2. Site Engineer
a. To ensure that the works are carried out according to the Contract
Specifications approved method statement.
b. To provide all necessary information and distribute responsibilities to his
construction team.
c. To monitor the progress of work in relation with the work program and to
report to the Project Manager.
d. To co-ordinate with the safety officer and to ensure that the works are
carried out in safe practicing methods.
3. Foreman
a. The foreman will carry out his duties by maintaining continuous
coordination with the site engineer on daily basis, and ensure proper distribution of
the workforce in the required and planned locations.
b. To ensure that his assistant foreman/ charge hand are aware of the job
requirements and they have enough information to carry out their duties properly.
c. To ensure in consultation with the site engineer that the manpower
involved in the works are moving as agreed and planned for the work.
d. To ensure that the daily work is progressing as planned and advise the Site
Engineer for any requirement of the additional resources.
e. To control disposal of waste materials to the instructions received from the
site engineer.
f. To ensure full coordination with the safety officer to maintain safe working
and proper house keeping of the site, following the approved safety measures and
further ensure that all his working team are aware of the same to prevent accident
and losses.
g. After completion of works, Foreman shall inform the site engineer for
inspection of works.
h. Distribution and the control of materials shall be monitored by foreman
and storekeeper.
4. Safety Engineer
a. Ensure the implementation of all the safety measures in accordance with
the HSE plan and everybody aware of it for it’s proper implementation.
b. Ensure all the implemented safety measures are adequate to maintain safe
working on the site.
c. Inspect all the site activities and train the person to prevent accidents and
it’s proper implementation.
d. Ensure that the site is maintained clean and tidy.
7. Manpower Required
Charge hand and Experienced Technicians

8. Materials Requirements
DB, SMDB, MDB and accessories

9. Equipments Requirement
The equipment that will be engaged for Installation of DB, SMDB and MDB works will
be as follows:

1. Wire cutters
2. Measuring tape
3. Drill machine
4. Wooden hammer
5. Flat file
6. Screw drivers
7. Open and box spanners
8. Crimping tool
10. Health and Safety
Strictly follow as per the manufacturer’s Health and Safety recommendations for
handling and use of the materials. Ensure all involved personal shall be aware of the
same.

11. Supporting Documentation


This method Statement should be read in conjunction with the below referenced
documentations.

 ITP for Anti – termite Treatment


 Insulation Resistance and continuity Test Report
12. Distribution
Copy of this method statement shall be issued to the following for information/ action/
comments:

1. Project Manager
2. Site Engineer
3. Foremen

13. Inspection And Test Plan For Installation of


DB, SMDB and MDB
ITP
Inspection Type of Reference Testing Requirement/ Verifying / Control
Clause
Description Inspection Document Acceptance Criteria Data Forms
No
Design drawings,
Design and Review of Design Authorities
1 All the Drawings
Drawings Documents Drawings Departments
Requirements.
2 Material Approval Review of Approved Should be as per the Submittals
Documents Drawing and approved drawing and Documents
Specification Specification
Properlocation installation,
Check Switchgear Visual, Insulation
Approved termination etc Material
installation and Resistance and Approved Drawing
3 Method should have minimum status
cable Continuity Method Statement
Statement of – NO Objection with
terminations. TestReport
comments
Visual, Insulation
Request for
Resistance and Approved No obstructions Level, and it
4 inspection of Approved Drawings
Continuity Test Drawing is in proper position
works
report.

You might also like