Method Statement LV MV Cables
Method Statement LV MV Cables
Method Statement LV MV Cables
: KAP2E2-MS-ELEC-GEN-2449-00
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
Method Statement
Installation & Termination of LV/MV
Cables
Reviewed By Reviewed By Reviewed By Approved By
QA/QC Manager HSE Manager Project Manager Project Director
Name: Eng Matiur Rahman Hussein Alsayed Ahmed AbouElGhar
Signature:
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
Method Statement
Installation & Termination of LV/MV Cables
Technical Department
Planning and Development Section
Method Statement: Installation & Termination of LV/MV Cables
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
Revision: 01
Date: 13 Feb 2017
Document Control
Document Information
Information
BEC-KAP2E2
Document ID
Beijing Emirates International Construction Co.
Document Owner
30 March 2016
Issue Date
23 Feb 2017
Last Saved Date
Document History
Version Issue Date Changes
Document Approvals
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
( P.M.O)
Project Review Group
Project Director
Ahmed Abou ElGhar
IT Manager
Sameh El Ezaby
Method Statement
Installation & Termination of LV/MV Cables
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
Table of Contents
1- SCOPE OF WORK ....................................................................... 6
2- REFERENCES ........................................................................... 6
3- DEFINITIONS ........................................................................... 6
4- RESPONSIBILITY………...............…………………..................... 7 – 9
5- SPECIALIZED TOOLING EQUIPMENT…………………........................ 9
6- PRODUCT/ MATERIAL………………………………....................... 9
7- WORKFORCE…………………………………….......................... 9 - 10
8- PRIOR ACTIVITIES TO BE COMPLETED ………................................... 10
9- HEALTH, SAFETY, & SECURITY ……………..................................... 11 - 12
10- ENVIRONMENT ......................................................................... 12
1. SCOPE OF WORK
This Method Statement covers the nature and type of work for the installation
and termination of LV/MV cables by BEC-MEP to King Abdullah Project (KAP2E2).
This method statement gives guidelines contained herein so as to ensure that
the job execution complies with the requirement of the specifications and the
authorities concerned and serves the intended purpose to satisfactory level.
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
This procedure is to be read in conjunction with the relevant ITP, outlining the
responsibilities and the quality verification to be performed by various parties.
2. REFERENCES
Contractor’s Quality Control Plan Set for Contract
Project Specification Section No. 16120, 16121, 16375
Supplementary Specification Section Nos. 16010, 16195, 16100
Project Health and Safety Plan
Approved Drawing
3. DEFINITIONS
MOI: Ministry of Interior (Client)
NKY: NKY Architect and Engineers (Engineer)
BEC: Beijing Emirates Construction (Main Contractor)
QA/QC: Quality Assurance & Quality Control
ITP: Inspection and Test Plan
LV/MV: Low Voltage/Medium Voltage
RFI: Request For Information
IR: Inspection Request
4. RESPONSIBILITIES
Project Manager
The project manager will have full authority and overall responsibility to
manage, supervise.
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
He will control the works and will have direct responsibility for ensuring safe
working practices and compliance with regulatory authority’s requirement.
He will coordinate with the engineers and the employer’s representative for
execution of the contract scope of works.
Implement the project quality systems to the satisfaction of the project
requirements.
Review changes and variations to evaluate impact of those on time and
schedule.
Project Engineer
Is responsible for ensuring that all works are carried out as per the specifications,
approved shop drawings and method statement as per manufacturer’s instructions
and coordinated with other works.
Site Engineer
The site engineer shall coordinate all the site activities according to work
schedule, installation according to the project specifications, manufacturer’s data
sheet and approved shop drawings.
Shall liaise with site representatives and coordinate safety procedures with
site supervisors and site foremen.
Shall coordinate and explain the work to be carried out to the supervisors/
Site Foreman.
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
Ensure the compliance of work with related approved quality control and
coordinate with BEC QA/QC Engineer/Inspector to advice for the areas to be issued
for internal external inspection.
Site Supervisor and Site Foreman:
The project team of experienced supervisors and foremen shall ensure the
quality of the installation work carried out, and shall also ensure that it is as per the
latest approved construction shop drawing issued for installation and according to
instructions received from the site engineer.
He will provide his subordinates adequate information to carry out their duties.
To ensure that he has adequate resources of machinery, labor, and materials
to carry out all the activities efficiently and to discuss with the site engineer.
To ensure safe and clean working environment to enforce a safe working
habit.
Store Controller:
Review the documents of approved material submittal and verify the items
with the packing list for any shortage or description from approved.
Responsible for proper storage as per site requirement.
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
Verify all documents are forwarded with the item as per the requirement of
purchase order.
The unapproved material shall not be received and stored in store
6. PRODUCT/ MATERIAL:
LV/MV Cable
Cable Ties
Insulation Tape
Identification Tag
Draw Wires for PVC
Cable Pulling Compound
7. WORKFORCE
Construction team will ensure that manpower selected for the specified job is
well trained. Tool box talk shall be carried out before the work commences at site to
the involved workers through the supervisor and foremen in charge the work, under
the directives of in-charge engineer. The work procedure and safety precautions
should be clearly and concisely explained to the workers in their own language so it
is fully understood.
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
Access/ Egress: BEC will provide scaffoldings assembly with attached step ladder
and rubberize wheel. Platforms will be provided on top of the scaffolding assembly
and circulated with tubular railings at adequate height to protect the workers.
Aluminum step ladders will be used in instances where scaffolding is not permitted in
the workplace and for alignment purposes of installation. Safety personnel should be
involved in preparation and approval scaffolding assembly and ladders prior to use.
Housekeeping: The supervisor has the responsibility to ensure the site is kept clean
from any debris. Any material leftovers shall be collected and put into designated
disposal box. Unused materials shall be returned to proper storage in every end of
each day work.
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
10. ENVIRONMENT:
Any wasted generated to above work shall be segregated and disposed of
according to the Site and Authority Norms.
Any chemical/cleaner used for the job will be kept in container to avoid
spillage on the ground.
The QC Inspector has the full-time surveillance during the activities to ensure
that all works has done as per this method statement. Any found deficiency shall be
immediately corrected based on the procedure and specification workmanship
requirements. To check all necessary documents are prepared and approved by
Engineer.
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
Date Issued: 23 Feb 2017 MS: Installation & Termination of LV/MV Cables
LV/MV cables shall be installed in such a way that the number of cable
crossings will be minimized.
Avoid below/above grade obstructions in any cable run to maintain
reasonable enough access.
Backfilling of LV/MV cable trenches shall be as per approved materials,
project specifications, and approved shop drawings.
Protective red tiles, and warning tapes shall be installed as per project
specifications/approved shop drawings.
Continuity Test:
LV/MV cables shall be tested before terminations and should be fully
prepared and completed.
Test shall be performed using a digital multi-meter with valid calibration.
13. ATTACHMENT:
13.1 Safety Risk Assessment
13.2 Inspection and Test Plan (ITP)
13.3 Inspection Check List