Method Statement For Wiring Works
Method Statement For Wiring Works
Method Statement For Wiring Works
EMPLOYER
STRUCTURAL
M/S.AECOM INDIA PRIVATE LIMITED
CONSULTANT
AMENDMENT RECORD
Prepared Recommended
Rev. Date Description Reviewed By Approved By
By By
METHOD STATEMENT FOR WIRING WORKS
CONTENTS
Sl.
Content Remarks
No.
01 SCOPE
02 REFERENCE DOCUMENT
03 MATERIAL
04 EQUIPMENT /TOOLS
05 RESPONCIBLE PERSON
06 METHOD OF STORAGE
08 METHOD OF INSTALLATION
This method statement covers the on site Pulling and Testing of Electrical wires in
PVC/GI conduits and trunking for small power and lighting and the requirement of
checks to be carried out.
REFERENCE DOCUMENTS
•Approved Shop Drawings
•Approves Material Submittals
MATERIALS
FRLS CU WIRE
SWITCH SOCKETS
EQUIPMENT/ TOOLS
• Drilling machine
• pulling tar/wire
• Electrician hand tools
RESPONSIBLE PERSONE
• Project Electrical Engineer
• Site Electrical Engineer
• QA/QC Engineer
• Site Supervisor
• Electrician & Helpers
METHOD STATEMENT FOR WIRING WORKS
METHOD OFSTORAGE
1. All material received at site shall be inspected and ensure that the material are
as per approved material submittal.
2. Any discrepancies, damages etc. Shall be notified and reported for further
action.
Materials found not suitable for the project are removed from site immediately.
3.wires and switch sockets shall be stored on racks and lockable conditions
METHOD OF INSTALLATION
METHOD STATEMENT FOR WIRING WORKS
Where in single core PVC insulated cables are enclosed with in the conduits,
core will be taken that no damage will occur to the cables during their installation.
. Number of cables to be pulled into the conduit will be as per TABLE 1
The use of lubricants, grease, graphite or talc will not be used to assist the
drawing of cables/wires.
Cables/wires of different circuit categories will not be mixed with in the same
conduit.
While preparing cable/wires ends, ensure that conductor stands are not
damaged and the strands are twisted together with pliers to ensure neat and firm
connection.
While removing the conductor insulation, ensure that no excess exposed
conductor shall be left.
Final sub circuits will be installed in continuous lengths and no joints will be
permitted along the cable run. The final sub circuits will be wired in the loop - in
method and all terminations are made will be accessible.
Before pulling wire into conduits, ensure that nylon draw ropes have been
installed
The Neutral conductors of lighting will be wired direct to the lighting points and
will not pass through switch boxes.
Where PVC insulated sheathed cable enters or exit the trunking system the hole
will be lined up with rubber grommets or bushes.
METHOD STATEMENT FOR WIRING WORKS
QUALITY
QCE along with Project Engineer and Site Supervisor will monitor that all
components are installed as per contract specifications and approved submittals.
Inspection Request shall be submitted to Consultant after completion of installation
of cable tray before pulling of any wires
SAFETY
Work will commence as per safety regulations laid down in the contract specification
and project safety plan.
Proper safety harness to be used and secured, if required.
All personal protective equipment shall be used as appropriate according to the
nature of job.
Housekeeping shall be of good standard and all cut lengths and debris shall be
removed.