Transformer 1 Mos
Transformer 1 Mos
Transformer 1 Mos
Below is a standard method statement which can be used as learning purpose and to prepare further
professional method statement for testing and commissioning of transformers.
Current
3. Before any Item of equipment is accepted for
testing a visual inspection will be carried out on
Visual inspection:
Tightness Checks.
Hold the sensing probes across the conduct between which the contact resistance is to be measured
(Test Current 10A DC).
Ratio Measurement
Ensure that both the Primary and Secondary windings are not connected to any cables/Bus bar.
Apply three phase supply voltage (415 V AC) across the Primary Termination of the Transformer.
Measure the secondary (LV) voltage at the LV termination. Observe the reading and record in the test
format.
If the tap changer is Off load type, switch of the power supply and rise one step and apply the Three
phase 415 V AC across the Secondary termination and measure the voltage at both Secondary and
Primary side.
Alternatively, test is performed with a digital ratio meter which measures the ratio value of the transformer
and simultaneously checks the vector group and the polarity.
Ensure that both the Primary and Secondary windings are not connected to any cables /Bus bars.
Connect the R phase of the Primary winding and R phase of the Secondary winding (Short R phase
of Primary and Secondary termination).
Apply 3 phase supply voltage (415 V AC) across the Primary Termination of the Transformer. Measure
the voltage at the both Primary and Secondary termination at all the phases. Observe the reading and
record in the test format.
Apply the formula or plot the values in the graph to get the vector group.
Ensure that both the Primary and Secondary windings are not connected to any cables/Bus bars.
Apply 3 phase supply voltage (415 V AC) across the 1U & 1V and measure the Corresponding Voltage
for 1U-1V, 1V1W & 1U1W.
Switch off the Supply and repeat the test again by applying the voltage in 1V & 1W and Measure the
corresponding voltage for 1U-1V, 1V1W & 1U1W.
Again, Switch off the Supply and repeat the test again by applying the voltage in 1U & 1W and Measure
the corresponding voltage for 1U-1V, 1V1W & 1U1W.
On site Protection
Until the Equipment is permanently energized, client should ensure that a protective cover will Remain
over all the equipment that is being tested.
Advertisement:
Current
Transformers
HOBUT Current
transformer range
manufactured in the UK.
hobut.co.uk
METHOD STATEMENT FOR Method Statement For Installation & Testing Of Air
TESTING & Installation & Testing Of Handling Units AHU & FAHU
COMMISSIONING OF Lightening Protection System Method Statement
PRESSURIZATION UNIT April 23, 2013 June 9, 2013
July 29, 2013 In "Electrical Method In "HVAC Method Statements"
In "HVAC Method Statements" Statements"