Itp - Electrical Second Fix
Itp - Electrical Second Fix
Itp - Electrical Second Fix
Legend: H=Hold Point, RFIT to be issued and work shall not proceed without acceptance from the responsible party; W=Witness Point- RFIT to be issued and work may proceed
if the responsible party does not attend; S= random surveillance, no signature or RFIT required; R= “Record / Document Review” (submitted separately as necessary)
Verification
Checks Intervention Points
Documents
Checking Activity to Control Documents Acceptance Criteria/ Responsi Required
SL.NO Works
Contr
Contr
actor
Sub‐
be Performed Tolerances (if ble Job Frequency
FD
Vol. Clause applicable) Function
1.0 PRE‐COMMENCEMENT
IFC Drawings,
Project. Approval Method Salam Approved RAMS
Method Statement
Specifications, Section Statement in Technology (risk assessment
and Risk Assessment Review of Method Prior to
Approved 21 - Part Compliance to /Contractor N/A H R and method
1.1 Statements & ITP Start work
Drawings & 8&9 Project Specification QA/QC statement)
QCS 2014- requirements.
Section 21
Review of IFC Design IFC Drawings, Salam Approved Shop
1.2 Drawing Submittal Drawings & Shop Project
Compliance to Design Technology Prior to N/A H R Drawings
IFC drawings Start work
Drawings Specifications. Submittal
Approved
Material Submittal Drawings,
Project. Salam
LIGHT FIXTURES & Compliance to Approved
Review of Material Specification & Technology Prior to N/A
1.3 Accessories Approved Material H R Material
Submittal Material start work
Submittal Submittal
Approval, QCS
2014 Section
21, Part 8 & 9
Legend: H=Hold Point, RFIT to be issued and work shall not proceed without acceptance from the responsible party; W=Witness Point- RFIT to be issued and work may proceed
if the responsible party does not attend; S= random surveillance, no signature or RFIT required; R= “Record / Document Review” (submitted separately as necessary)
Verification
Checks Intervention Points
Documents
Checking Activity to Control Documents Acceptance Responsi Required
SL.NO Works
Contr
Contr
actor
Sub‐
be Performed Criteria/Tolerances ble Job Frequency
FD
Vol. Clause (if applicable) Function
QCS 2014 S.1 Project
Available
Verification of Valid & P.10 cl. 10.5.1 manager, Prior to
1.4 Necessary Permits Valid Permit N/A H R Relevant & valid
relevant permit Approved HSE Start work
permit
RAMS Officer
QCS 2014
Section 2, Salam
Part 7, Comply as per Technolo Each Delivery
Delivery Inspection Verification as per
1.5 cl.7.1.2/ Approved gy delivery at N/A H H Inspection
Request (DIR) Approved Material
Approved materials,data engineer. site Request
Material sheets QA/QC
Submittal Engineer,
Store
Keeper
6. Check the materials are not damaged and are in a good condition.
Light installation supports as per drawing and spec
7.
Light circuit distribution as per design and drawing
8.
2
Site Engineer Salam technology Qatar cool
NAME NAME NAME
Designation Designation Designation
Signature Signature Signature
Date Date Date
LEGEND: INSPECTED BY – “√ “Tick mark selection confirms compliance. “X” Cross mark selection confirms Non-Compliance
REMARKS – Any Deviation of Non-Conformity to be noted
OTHERS – Section for sub-contractors or relevant party responsible for activity.