3republic of Tbe Bilippines $upre1ne !court: Second Division
3republic of Tbe Bilippines $upre1ne !court: Second Division
3republic of Tbe Bilippines $upre1ne !court: Second Division
$upre1ne <!Court
;ifl!lan ila
SECOND DIVISION
Promulgated:
PHILKONSTRAK
DEVELOPMENT CORPORATION
and VITO RAPAL,
Respondents.
x--------------------------------------------------- x
DECISION
HERNANDO, J.:
This petition for review on certiorari 1 under Rule 45 of the Rules of Court
assails the January 30, 2015 Decision2 and June 9, 2015 Resolution3 of the Court
of Appeals (CA) in CA-G.R. SP. No. 06515, affirming in toto the October 27,
2011 Decision4 and November 25, 2011 Order5 of the Construction Industry
Arbitration Commission (CIAC) in CIAC Case No. 19-2011 entitled
"Philkonstrak Development Corp. v. Municipality of Corella, represented by
1
Rollo, pp. 3-60.
2
Id. at 85-96. Penned by Associate Justice Renato C. Francisco and concurred in by Associate Justices Gabriel
T. Ing les and Pamela Ann Abell a Maxino.
3
Id. at 101-102.
4
Id. at 62-84. Penned by Chairman Eduardo R. Ceniza and concun-ed in by Me mbers Tomasito Z. Academia
and Guadalupe 0. Mansueto.
5
Id. at 295-297.
Decision 2 G.R. N o. 2 18663
Hon. Jose Nicanor D. Tocmo and Hon. Vito B. Rapa!, in his personal capacity."
The Municipality of Corella, represented by Mayor Jose Nicanor D. Tocmo
(Tocmo), was ordered to pay Philkonstrak6 Development Corporation
(Philkonstrak) the amount of Pl2,844,650.00.
The Antecedents:
Tocmo, in his reply, 19 denied liability and questioned the validity of the
contract. He averred that Rapal had no authority to enter into such contract
during his term as mayor of Corella. 20
On April 28, 2011, Philkonstrak filed before the CIAC a complaint2 1 for
collection of sum of money against Corella and Rapal, as Rapal was the mayor
at the time the contract was signed and whose signature appeared thereon. The
case was docketed as CIAC Case No. 19-2011.
On August 19, 2011, Corella filed its answer,30 denying the material
allegations of the complaint. It asserted that the contract is not binding because
Municipal Ordinance No. 2010-02 was in violation of Article 107(g) of the
19
Id. at 105 .
20
Rollo, p. 86.
21
CA rollo, pp. I3- I 9 .
22
ld.atl 3-l6.
23
Id. at 15.
24
Id.at 16.
25 Id. at 17.
26
Id. at 292-303.
27
Rollo, p. 87.
28
C A rollo, p. 263 .
29 Id.
30
Id. at 260-26 2.
Decision 4 G.R. No. 218663
Implementing Rules and Regulations (IRR) of Republic Act No. (RA) 71603 1
otherwise known as the "Local Government Code of 1991."
Furthermore, Corella contended that Rapal was in bad faith since he knew
that the municipal ordinance was defective and ineffective; thus, he was not
legally authorized to enter into a contract with Philkonstrak for lack of a valid
municipal ordinance. 32
Ruling of the
Construction Industry
Arbitration Commission:
On October 27, 2011, the CIAC issued a Decision33 finding the contract
between Philkonstrak and Corella to be valid. Thus, Corella, through its present
mayor, Tocmo, breached the contract when he refused to honor the obligation.
The CIAC ordered Corella to pay Philkonstrak the total amount of
P12,844,650.00, which includes claims for unpaid billings, delivered but
uninstalled materials, and accrued interest. The CIAC exonerated Rapal from
any liability arising from the repudiation of the contract on the principle of res
inter alias acta. The dispositive portion of the CIAC Decision reads:
WHEREFORE, the Tribunal hereby decides and awards in full and final
disposition of this arbitration, as follows:
(c) [Philkonstrak's] claims for attorney fees and exemplary damages are
denied.
31 Entitled " AN ACT PROVIDING FOR A LOCAL GOVERNMENT CODE OF 1991 ." Approved on October I 0,
1991.
32
Rollo, p. 88.
33 Id. at 62-84.
Decision 5 G.R. No. 218663
(e) All other requests for relief not granted or disposed of here are hereby denied.
Summary of Award
On November 25, 2011 , the CIAC issued an Order3 6 which ruled that
Corella's motion for correction of final award actually partook of a motion for
reconsideration because it sought to change the CIAC ruling; that such motion
for reconsideration of the substantive merits of the dispute is not allowed under
34
Id. at 83-84.
35
CA rollo, pp. 345-346.
36
Id. at 295-297.
Decision 6 G.R. No. 218663
SO ORDERED. 45
Issues
Corella seeks relief in its petition for review on certiorari on the following
questions of law, to wit:
37 Id.
38
Rollo, pp. 300-302.
39
CA rollo, pp. 347-350.
40
Id. at 349.
41
Id. at 3-11.
42 Id.
43 Id.
44
Rollo, pp. 85-96.
45
Id. at 95.
46
Id. at 101-102.
47
Id. at 3-60.
7v
Decision 7 G.R. No. 218663
2. Can a mayor enter into a contract with a corporation without the proper
appropriation of public funds as required by the 1987 Constitution as reflected in
Presidential Decree 1445 and Executive Order 292?
Summarizing all four questions, the main issue in the case at bar is this:
whether or not the CA is correct in affirming the Decision of the CIAC which
found that the contract between Philkonstrak and Corella was valid, and which
ordered Corella to pay Philkonstrak the amount of P12,844,650.00 for breach
of the same.
Our Ruling
Corella, through Tocmo, alleged that then Mayor Rapal failed to secure
proper authorization from the sangguniang bayan of Corella before entering
into the contract with Philkonstrak,49 citing the following laws and provisions
as bases:
First, Section 22(c) of the Local Government Code and Article 107(g) of
its Implementing Rules and Regulations (IRR), to wit:
xxxx
48
Id. at 3.
49
Id. at 14.
Decision 8 G.R. No. 218663
(c) Unless otherwise provided in this Code, no contract may be entered into
by the local chief executive in behalf of the local government unit without prior
authorization by the sanggunian concerned. A legible copy of such contract
shall be posted at a conspicuous place in the provincial capitol or the city,
municipal or barangay hall.
xxxx
xxxx
xxxx
The Procuring Entity shall issue the Notice to Proceed to the winning bidder not
later than seven (7) calendar days from the date of the approval of the contract
by the appropriate authority. All notices called for by the terms of the contract
shall be effective only at the time ofreceipt thereof by the contractor. (Emphasis
supplied)
Tocmo asserts that before then Mayor Rapal entered into the contract on
behalf of Corella with Philkonstrak, two requirements were necessary to be
met: 51 ( 1) prior authorization from the sangguniang bayan of Corella, in
accordance with Section 22(c) of the Local Government Code and Section 3 7
of the Government Procurement Act; and (2) the appropriation ordinance or
resolution authorizing or directing the payment of money or creating a
liability, 52 in accordance with Article 107(g) of the IRR of the Local
Government Code.
50 Entitled " AN ACT PROVIDING FOR THE MODERNIZATION, STANDARDIZATION AND REGULATION OF THE
PROCUREMENT A CTIVITIES OF THE GOVERNMENT AND FOR OTHER PURPOSES." Approved on January I 0,
2003.
51
Ro/lo,pp.15-18.
52
Id. at 18-25.
Decision 9 G.R. No. 218663
Tocmo posits that the two documents or requirements are separate and
distinct from each other. 53 As to the first requirement of prior authorization from
the sangguniang bayan, Tocmo alleged that:
18. The contract merely describes the contracting parties as the "Municipality of
Corella" and "Philkonstrak Development Corporation" and signed by
Respondent Vito B. Rapa! and Jesse J. Ang. Nowhere is there any showing that
the contract contains the "prior authorization of the sanggunian concerned." No
ordinance authorizing respondent Rapal to enter into a contract was made
an integral part of the contract. The contract besides being 149 pages long
does not contain any prior authorization ordinance. Page two of the
contract, which outlines the contract documents, does not include an
ordinance authorizing respondent Rapal to enter into a contract with
Philkonstrak. 54 (Emphasis supplied)
The Court disagrees. It must be emphasized that such issue is not novel.
Explained simply, the [Local Government Code] requires the local chief
executive to secure prior authorization from the sanggunian before he can enter
into contracts on behalf of the LOU. A separate prior authorization is no longer
required if the specific projects are covered by appropriations of the LOU. The
appropriation ordinance passed by the sanggunian is the local chief
executive's authority to enter into a contract implementing the project.
53
Id.at 15- 16.
54 Id.
55
593 Phil. 655-677 (2008).
56
794 Phil. 629-661 (20 16).
Decision 10 G.R. No. 218663
authorization for a project that has been specifically identified and approved by
the sanggunian is antithetical to a responsive local government envisioned in the
Constitution and in the [Local Government Code]. 57 (Emphasis supplied)
In the case at bar, the Court finds that there is no need for a separate
authorization from the sangguniang bayan as the appropriation ordinance,
Municipal Ordinance No. 2010-02, identified the project or program in
sufficient detail, and not just in general or generic terms. The one-paged
appropriation ordinance specifically and expressly set aside an amount of
money, P27,000,000.00, for certain projects, including the purchase of specific
heavy equipment and rehabilitation/improvement of the existing waterworks
system of the municipality. Municipal Ordinance No. 2010-02, having
sufficiently covered the project and the cost in detail, need not be accompanied
by a prior sangguniang bayan authorization any longer.
An appropriation ordinance
requires the affirmative vote of a
majority of all the sanggunian
members.
Article 107(g) of the IRR of the Local Government Code provides the
general rule that no ordinance or resolution shall be passed by the sanggunian
without prior approval of a majority of all the members present. The
exception to the general rule is that for ordinances or resolutions authorizing or
directing the payment of money or creating a liability, what is needed is the
affirmative vote of a majority of all the sanggunian members, whether
present or not. Simply, the quorum in the general rule depends on the number
of the sanggunian members present while the quorum in the exception depends
on the total number of sanggunian members voted into office.
In the case at bar, Corella asserts that Municipal Ordinance No. 2010-02,
the appropriation ordinance in question, directs and authorizes the payment of
money; thus, requires a majority vote of all the members of the sangguniang
bayan, not only of the members present. Thus, since the sangguniang bayan of
Corella is composed of a total of 11 members, the majority vote of six is
required in order for municipal ordinance no. 2010-02 to be valid and binding.
However, the municipal ordinance only obtained five affirmative votes, based
on the quorum on the sanggunian members present at that time, which was
eight members. Thus, Tocmo contends that Municipal Ordinance No. 2010-02
is null and void. Consequently, the contract between Corella and Philkonstrak
is null and void too.
57
Id. at 645-646.
58
See id.
Decision 11 G.R. No. 218663
The CIAC and the CA ruled otherwise. Both tribunals noted that upon
the disapproval 59 of Municipal Ordinance No. 2010-02 by the sangguniang
panlalawigan of Bohol for not meeting the required majority number, then
Mayor Rapal elevated the matter to the Department of Interior and Local
Government (DILG). The Regional Director of the DILG issued an Opinion,60
the pertinent portion of which was cited by both the CIAC and CA in their
Decisions, to wit:
Hence, for all intents and purposes, the legislative process has been
completed, and that the subject ordinance [Municipal Ordinance No. 2010-
02] is now accorded with the presumption of validity. Moreover, it might
interest you to know that DILG Central Office had the occasion to opine, under
DILG Opinion No. 103 S 2001 dated December 18, 2001 , that the Local
Government Code of 1991 does not expressly prescribe for a specific voting
requirement for the passage of an appropriation ordinance. Hence, the
general rule on the passage of an ordinance should be made to apply. The
pertinent provision on the matter is Article 107 (g) of the Rules and Regulations
Implementing R.A. 7160 x x x.61 (Emphasis supplied)
Both the CIAC and the CA applied the opinion of the Regional Director of
the DILG to their Decisions, noting that Tocmo, the present Mayor, did not take
any steps to question the validity of the Opinion, thus, it had become final and
binding on the concerned parties.
Juxtaposing this definition with the exception in Article 107(g) of the IRR
of the Local Government Code, that "any ordinance x x x authorizing or
directing the payment of money x x x, shall require the affirmative vote of a
majority of all the sanggunian members," it is express and clear that an
"appropriation ordinance" is one such ordinance contemplated in the exception.
The Court, thus, holds that the DILG Opinion is erroneous, and the CIAC
and CA wrongfully applied the same to their Decisions.
The CIAC and the CA both ruled that the October 27, 2011 CIAC Decision
had already become final and executory on the ground that Corella's motion for
correction of final award, which was actually a motion for reconsideration, was
a prohibited pleading under Section 17.265 of the CIAC Rules, thus, did not stop
the running of the reglementary period for appeal. The CA ruled that:
Since the motion for correction did not fall under any of the grounds
provided by the CIAC's Rules, it is considered a motion for reconsideration and
a prohibited pleading. It did not interrupt the running of the fifteen (15) days
period for petitioner to file its petition to this Court. Consequently, after the lapse
of the fifteen (15) days from November 10, 20 11 or on November 25, 2011 , the
CIAC's decision has already become final and executory because petitioner
failed to file its petition for review within the period provided by law. The CIAC
was correct to issue on January 19, 2012 an Order, declaring that the Final Award
has become final and executory.
Settled is the rule that a judgment that has become final and executory is
immutable and unalterable. The judgment may no longer be modified in any
respect, even if the modification is meant to correct what is perceived to be
65
Section 17.2 reads:
SECTION 17.2. Motion/or Reconsideration or New Trial. - A motion for reconsideration
or new trial shall be considered a prohibited pleading.
Decision 13 G.R. No. 218663
The Court agrees. As aptly pointed out by Senior Associate Justice Estela
M . Perlas-Bernabe during the deliberations of this case, a CIAC Final Award,
equivalent to a trial court final decision as opposed to a partial award or
decision, is still susceptible to judicial review. However, when availing of
judicial reliefs against a CIAC Final Award, one must still abide by the
procedural framework set therefor, such as the periods of appeal and prohibited
motions. If the said party fails to comply, he or she is equally bound by the
finality of judgment principle.
The CA nor this Court may not anymore step in to modify or correct a
quasi-judicial agency's decision that has already been deemed final and
executory. If this were so, then there would be no end to litigation stemming
from the CIAC, which is against the expeditious nature of such proceedings and
hence, against the public policy underlying arbitration.
66
Rollo, p. 93.
67
G.R. No. 233781, July 8, 20 19.
68 582 Phil. 357, 366-367 (2008).
69 Department of Labor and Employement v. Kentex Manufacturing Corporation, supra.
Decision 14 G.R. No. 218663
Under the CIAC Rules, a party aggrieved by a final award may contest the
same by filing either a motion for correction or a petition for review under Rule
43 of the Rules of Court, both within fifteen (15) days from receipt thereof. 70
However, if a motion for correction is filed and said motion is not based on the
exclusive grounds enumerated under Section 17 .1, such filing will not interrupt
the running of the period to appeal. 71 Consequently, if the period to appeal has
lapsed, a final arbitral award shall be considered as executory. 72 The pertinent
provisions of the CIAC Rules read:
RULE17
Post- Award Proceedings
SECTION 17.1 Motion for Correction of Final Award - Any of the parties may
file a motion for correction of the Final Award within fifteen (15) days from
receipt thereof upon any of the following grounds:
a. an evident miscalculation of figures, a typographical or arithmetical
error;
b. an evident mistake in the description of any party, person, date,
amount, thing or property referred to in the award;
c. where the arbitrators have awarded upon a matter not submitted to
them, not affecting the merits of the decision upon the matter
submitted;
d. where the arbitrators have failed or omitted to resolve certain issue/s
formulated by the parties in the Terms of Reference (TOR) and
submitted to them for resolution; and
e. where the award is imperfect in a matter of fom1 not affecting the
merits of the controversy.
xxxx
17.1.2 A motion for correction upon grounds other than those mentioned in this
section shall not interrupt the running of the period for appeal.
xxxx
RULE 18
Execution of Final A ward
70
Sec. 18.2.
71
Sec. 17.1.2.
72 Sec. 18.1.
Decision 15 G.R. No. 218663
SECTION 18.2 Petition for Review. - A petition for review from a final award
may be taken by any of the parties within fifteen (15) days from receipt thereof
in accordance with the provisions of Rule 43 of the Rules of Court.
xxxx
xxxx
Since Corella's Motion was not based on any of the enumerated grounds
under Section 17.2, the fifteen- ( 15) day period to file a petition for review
before the CA was not suspended. As Corella received the CIAC Decision on
November 10, 2011, 73 it had until November 25, 2011 to file its petition for
review. Thus, when Corella filed its Rule 43 petition before the CA on
December 26, 2011, the same was already filed out oftime and hence, executory
and immutable.
Thus, considering that the CIAC Decision had already attained finality,
the CIAC Decision, as affirmed by the CA, should not be disturbed.
Quantum meruit literally means "as much as he deserves. " 76 This legal
principle, a principle predicated on equity, states that a person may recover a
reasonable value of the thing he delivered or the service he rendered. It is a
73
Rollo, p. 93.
74 Aguinaldo /Vv. People, G.R. No. 226615, January 13, 2021 , citing Uyv. Del Castillo, 8 14 Phil. 61, 74-75
(20 17).
75 See Taisei Shimuzu Joint Venture v. Commission on Audit, G.R. No. 238671, June 2, 2020, citing Argel v.
Singson, 757 Phil. 228, 236-237(20 15).
76 Geronimo v. Commission on Audit, G.R. No. 224 163, December 4, 2018.
Decision 16 G.R. No. 218663
The Court has held in the past that recovery on the basis of quantum meruit
is allowed despite the invalidity or absence of a written contract between a
contractor and a government agency. The absence or invalidity of required
documents would not necessarily preclude the contractor from receiving
payment for the services he or she has rendered for the government. 78
Thus, in the case at bar, despite the invalidity of Municipal Ordinance No.
2010-02, which in turn rendered the contract between Corella and Philkonstrak,
invalid, the latter is still entitled to receive payment for the services it rendered
for the local government of Corella. Corella cannot be unjustly enriched and
allowed to retain the benefits of the services rendered by Philkonstrak without
properly paying for it.
11 Id.
78 Id.
79
Rollo, p. 39.
80 Id .
Decision 17 G.R. No. 218663
SO ORDERED.
WE CONCUR:
ESTELA M. ~~ERNABE
Senior Associate Justice
Chairperson
EDA RICA~ROSARIO
Ass\te Justice
'
&w~
J~~SP.MARQUEZ
~::::i.ate Justice
Decision 19 G.R. No. 218663
ATTESTATION
I attest that the conclusions in the above Decision had been reached in
consultation before the case was assigned to the writer of the opinion of the
Court's Division.
ESTELA ~~BERNABE
Senior Associate Justice
Chairperson
CERTIFICATION
Pursuant to Section 13, Article VIII of the Constitution and the Division
Chairperson's Attestation, I certify that the conclusions in the above Decision
had been reached in consultation before the case was assigned to the writer of
the opinion of the Court's Division.
G.GESMUNDO