Qeourt: 3aepublic of Tbe Ftbilippines !fflanila
Qeourt: 3aepublic of Tbe Ftbilippines !fflanila
Qeourt: 3aepublic of Tbe Ftbilippines !fflanila
x----~--------~--~--~----~--~~~~~~~~~~-------~--~-~~~~~~~~~~
DECISION
BRION, J.:
We resolve the petition for review on certiorari 1 assailing the June 27,
2005 decision2 and October 21, 2005 resolution3 of the Court of Appeals
(CA) in CA-G.R. CV No. 64715. The CA dismissed, for lack of cause of
action, the complaint4 for breach of contract and damages filed by Angel V.
Talampas, Jr. (petitioner) against Moldex Realty, Inc. (respondent).
The Facts
Designated as Acting Member of the Second Division in lieu of Justice Marvic M.V.F. Leonen,
per Special Order No. 2056 dated June 10, 2015.
1
Under Rule 45 of the Rules of Court.
Rollo, pp. 42-64; penned by Associate Justice Perlita J. Tria Tirona and concurred in by Associate
Justices Delilah Vidallon-Magtolis and Jose C. Reyes, Jr.
3
Id. at 66.
4
Docketed as Civil Case No. Q-93-18183 before the Regional Trial Court (RTC), Branch 96,
Quezon City.
5
~
Id. at 68.
Decision 2 G.R. No. 170134
On December 16, 1992, the petitioner entered into a contract6 with the
respondent to develop a residential subdivision on a land owned by the
latter, located at Km. 41, Aguinaldo Highway, Cavite, and known as the
Metrogate Silang Estates.
On June 16, 1993, the petitioner received from the respondent’s Vice
President, Engr. Jose Po, an antedated April 23, 1993 letter15 that contained
the respondent’s decision to terminate the parties’ contract. The April 23,
1993 letter stated:
Gentlemen:
6
Denominated as “Contract for Site Development Works at Metrogate Silang Estates.”
7
Paragraph 1, Contract.
8
Paragraph 2, Contract.
9
Paragraph 3, Contract.
10
Paragraph 4, Contract.
11
Rollo, p. 43.
12
Paragraph 6, Contract.
13
Rollo, p. 48.
14
Exhibit E for the Plaintiff, RTC records.
15
Exhibit G for the Plaintiff, RTC records.
Decision 3 G.R. No. 170134
The letter bore the signature of Engr. Almeida and gave the petitioner the
‘go signal’ to demobilize his equipment from the site.16
In a letter17 dated August 18, 1993, the petitioner demanded from the
respondent the payment of the following amounts: (a) P1,485,000.00 as
equipment rentals incurred from May 14, 1993 to June 16, 1993 the
period of suspension of construction works on the Metrogate project, and (b)
P2,100,000.00 or twenty percent (20%) of the P10,500,000.00 contract price
as cost of opportunity lost due to the respondent’s early termination of their
contract. The respondent received the letter on August 18, 1993,18 but
refused to heed the petitioner’s demands.
8.1 The OWNER may terminate this CONTRACT upon ten (10) days written notice to
the CONTRACTOR in the event of any default by the CONTRACTOR. It shall be
considered a default by the CONTRACTOR whenever he shall:
a) declare bankruptcy, become insolvent, dissolve the corporation, or assign its assets
for the benefit of his creditors;
b) disregard, violate or not comply with important provisions of the Plans and
Specifications or the OWNER’s instructions, or incur a delay of more than fifteen
percent (15%) in the prosecution of the work as evaluated against the work schedule
to be submitted by the CONTRACTOR; or
c) fail to provide a qualified superintendent, competent workmen, or materials or
equipment meeting the requirements of the Plans and Specifications.
xxxx
21
In finding fraud, the RTC held:
“As the owner/developer of the Silang project, the defendant (referring to the
respondent) was fully aware of the requirement for a conversion clearance from the DAR
on account of the land being tenanted and was obliged to satisfy the requirement prior to
starting the works on the project, or, if the clearance was not yet obtained, to reveal its
lack before contracting with the plaintiff (referring to the petitioner). It cannot be denied
that the conversion clearance was a material consideration for the contractor in land
development. Yet, the defendant did not disclose that lack to him during the negotiations
Decision 4 G.R. No. 170134
On appeal, the CA reversed and set aside the RTC’s ruling and
dismissed the petitioner’s complaint for breach of contract for lack of cause
of action.23 The CA held:
ENGR. JOSE PO
Vice-President
Moldex Realty, Inc.
West Avenue, Q.C.
Thank you.
and at the time of the conclusion of the contract. More probably than not, this failure to
reveal was deliberate, with the defendant hoping to resolve the deficit before the
plaintiff’s completion of his contract. The defendant’s concealment unavoidably caused
serious prejudice to the plaintiff, for, in the first place, he would not have entered into the
contract had he known of the lack of clearance before. Thereby, the defendant was guilty
of fraud, because its failure to disclose facts when there is a duty to reveal them constitute
fraud.”21
22
Rollo, p. 84.
23
Supra note 2; Decision dated June 27, 2005.
Decision 5 G.R. No. 170134
This letter of June 15, 1993 of Angel Talampas, Jr. to Engr. Jose
Po, Sr., Vice-President of Moldex Realty, Inc., confirms that previous to
said date or specifically on May 21, 1993, Engr. Jose Po, Sr. met with Jose
Angel Talampas, the Project Manager of the plaintiff-appellee, to discuss
the possibility of either suspending or terminating the contract due to a
redesign of the project necessitated by the acquisition of a larger tract of
land adjacent to the original project. Engr. Talampas opted for the
termination of the contract instead of its suspension.
The Petition
24
Rollo, pp. 53-55.
25
Id. at 56
26
Supra note 3.
Decision 6 G.R. No. 170134
In a resolution28 dated June 28, 2006, this Court gave due course to
the petition and required the parties to submit their respective memoranda.
27
Rollo, pp. 17-18.
28
Id. at 166-167.
29
Id. at 229-232.
30
Id. at 225-226.
31
Id. at 230-231.
32
Id. at 226-227.
33
Id. at 234.
Decision 7 G.R. No. 170134
The petitioner’s issues are largely factual in nature and are therefore
not the proper subjects of a Rule 45 petition.35 Specifically, the
determination of the existence of a breach of contract is a factual matter that
we do not review in a Rule 45 petition.36 But due to the conflicts in the
factual findings of the RTC and the CA, we see the need to re-examine the
facts and the parties’ evidence to fully resolve their present dispute.37
On May 14, 1993, the respondent, through Engr. Almeida, ordered the
suspension of construction work on the site, instead of terminating the
project in accordance with the respondent’s instructions in its (belatedly
received) April 23, 1993 letter to the petitioner.
34
Rollo, pp. 232-233.
35
Section 1, Rule 45 of the Rules of Court provides:
SECTION 1. Filing of petition with Supreme Court. – A party desiring
to appeal by certiorari from a judgment or final order or resolution of
the Court of Appeals xxx, may file with the Supreme Court a verified
petition for review on certiorari. The petition shall raise only
questions of law which must be distinctly set forth. (emphasis
supplied)
36
Omengan v. Philippine National Bank, G.R. No. 161319, January 23, 2007, 512 SCRA 305, 309.
37
In Development Bank of the Philippines v. Traders Royal Bank (G.R. No. 171982, August 18,
2010, 628 SCRA 404), the Court held:
“The jurisdiction of the Court in cases brought before it from the appellate court is
limited to reviewing errors of law, and findings of fact of the Court of Appeals are
conclusive upon the Court since it is not the Court’s function to analyze and weigh the
evidence all over again. Nevertheless, in several cases, the Court enumerated the
exceptions to the rule that factual findings of the Court of Appeals are binding on the
Court: (1) when the findings are grounded entirely on speculations, surmises or
conjectures; (2) when the inference made is manifestly mistaken, absurd or impossible;
(3) when there is grave abuse of discretion; (4) when the judgment is based on a
misapprehension of facts; (5) when the findings of fact are conflicting; (6) when in
making its findings the Court of Appeals went beyond the issues of the case, or its
findings are contrary to the admissions of both the appellant and the appellee; (7) when
the findings are contrary to that of the trial court; (8) when the findings are
conclusions without citation of specific evidence on which they are based; (9) when the
facts set forth in the petition as well as in the petitioner’s main and reply briefs are not
disputed by the respondent; (10) when the findings of fact are premised on the supposed
absence of evidence and contradicted by the evidence on record; or (11) when the Court
of Appeals manifestly overlooked certain relevant facts not disputed by the parties,
which, if properly considered, would justify a different conclusion.” (emphasis supplied)
38
Supra note 15.
Decision 8 G.R. No. 170134
On June 1, 1993, the petitioner wrote Engr. Almeida to ask for the
confirmation of the Metrogate project’s status.
On June 10, 1993, the petitioner received from the respondent the
amount of P474,679.28 as payment for Progress Billing No. 339 (which
billing the petitioner requested in a letter40 to the respondent dated May 31,
1993).
On June 15, 1993, the petitioner wrote Engr. Po, informing the latter
that he had not yet received from the respondent the letter officially
terminating their contract.
On June 16, 1993, the petitioner received from the respondent a letter
dated April 23, 1993, expressing the respondent’s decision to terminate the
parties’ contract. The petitioner alleged that it was only then (June 16,
1993) that he was formally informed of the respondent’s decision to
terminate their contract.
On August 13, 1993, the petitioner received from the respondent the
amount of P297,090.43 as payment for earthworks and road base
preparations done on the Metrogate subdivision as of July 12, 1993
(Progress Billing No. 4).41
39
Exhibit 9-b for the Defendant, RTC records.
40
Exhibit 7 for the Defendant, RTC records.
41
Exhibits 9-c and 14 for the Defendant, RTC records.
42
Retention fee is the amount retained by the owner “when[ever] the contractor bills for his
accomplishment [and] xxx is a percentage of his accomplishment that the owner keeps so that the owner
can be protected from whatever damages incurred during the prosecution of the contract. (TSN , July 17,
1997, pp. 22-32)”
43
Exhibit 9-e for the Defendant indicates that the release of all retention fees was paid to the
petitioner on August 27, 1993. The respondent, in its memorandum to this Court, states that said amount
was paid to the petitioner on September 26, 1993. In any case, the payment for the release of all retention
fees was made to the petitioner between August 18, 1993, the date of the petitioner’s formal demand, and
November 5, 1993, the date the petitioner filed the complaint for breach of contract with the RTC.
Decision 9 G.R. No. 170134
Contracts have the force of law between the parties and must be
complied with in good faith.44 A contracting party’s failure, without
legal reason, to comply with contract stipulations breaches their contract
and can be the basis for the award of damages to the other contracting
party.45
8.1. The OWNER may terminate this CONTRACT upon ten (10) days
written notice to the CONTRACTOR in the event of any default by
the CONTRACTOR. It shall be considered a default by the
CONTRACTOR whenever he shall:
44
Panlilio v. Citibank, N.A., G.R. No. 156335, November 28, 2007, 539 SCRA 69, 82-83;
citing CIVIL CODE, Art. 1159.
45
In RCPI v. Verchez, et al., G.R. No. 164349, January 31, 2006, (citing FGU Insurance
Corporation v. G.P. Sarmiento Trucking Corporation, 435 Phil. 333, 341-342 (2002), the Court held:
“In culpa contractual x x x the mere proof of the existence of the contract and the failure
of its compliance justify, prima facie, a corresponding right of relief. The law,
recognizing the obligatory force of contracts, will not permit a party to be set free from
liability for any kind of misperformance of the contractual undertaking or a contravention
of the tenor thereof. A breach upon the contract confers upon the injured party a
valid cause for recovering that which may have been lost or suffered. xxx” (emphasis
supplied).
Decision 10 G.R. No. 170134
xxxx
The respondent could not have validly and unilaterally terminated its
contract with the petitioner, as the latter has not committed any of the
stipulated acts of default. In fact, the petitioner at that time was willing and
able to perform his obligations under their contract; he expressed this in his
June 1, 1993 letter to the respondent, which stated:
Dear Sir:
Please be advised that as per last meeting, you made mention that
works at Silang Estates, Cavite will be temporarily stopped for
reason/reasons of redesigning of the subdivision plan. Stoppage will only
be for one week and that we will be informed in writing of your decision.
It has been three weeks now, going a month that we have not received
your decision on the matter. Meantime, our timetable for the completion
of the work is hampered, considering also the good weather condition
prevailing in the area which is also a big factor for our early completion of
our contract with you.
The respondent alleged that there had been mutual termination of the
parties’ contract during a meeting held between Engr. Po of Moldex Realty
Inc. and Engr. Talampas of AVTJ Construction on May 21, 1993. However,
this claim is not supported by evidence.
In the first place, the respondent failed to fully establish that a meeting
took place as alleged. Except for the self-serving testimony of Engr. Po
that the May 21, 1993 meeting took place, the respondent presented no other
evidence to prove that Engr. Po and Engr. Talampas met on that date to
discuss the fate of their contract. No document or record the minutes of
their May 21, 1993 meeting appeared to have been made despite the
importance of their alleged discussion. The questions that this evidentiary
gap raised cannot but be resolved against the respondent.
46
Supra note 14.
Decision 11 G.R. No. 170134
Even assuming that the May 21, 1993 meeting between Engr. Po and
Engr. Talampas did indeed take place, we cannot discern from the
developments the petitioner’s claimed agreement or consent to the
termination of the construction contract.
A close reading of petitioner’s June 15, 1993 letter shows that the
petitioner’s intent was solely to confirm whether the respondent would still
push through with its decision to terminate the contract. The petitioner’s
June 15, 1993 letter to the respondent stated:
Sir:
Please be informed that as of this writing, we have not received
your official letter regarding the untimely termination of our contract with
you, due to reason that stoppage of work is due to business decision.
In order for us to demobilize our personnel, construction
equipments, we need your official letter of termination soonest possible
time.
Thank you.
To our mind, the petitioner fully disclosed the intent behind his letter and it
was not consent. Thus, we find it erroneous to conclude, based on this letter,
that the petitioner had consented to the termination of the construction
contract.
47
Article 1319, Civil Code.
48
Articles 1319 and 1320, Civil Code.
Decision 12 G.R. No. 170134
The respondent does not deny that the petitioner’s equipment was
idled from May 14, 1993 to June 16, 1993, but refused to pay the petitioner
equipment rentals because the idling was allegedly due to the petitioner’s
fault; the respondent posits that the petitioner should have demobilized his
equipment as soon as the latter gave his consent to terminate their contract.
Also, it questioned the petitioner’s use of ACEL51 rates in the computation
of the accrued rent.
49
Traders Royal Bank v. Cuison Lumber Co., Inc., G.R. No. 174286, June 5, 2009, 588 SCRA 690,
701, 703.
50
In Manila Metal Container Corporation v. Philippine National Bank, G.R. No. 166862,
December 20, 2006, 511 SCRA 444, 465-466, the Court ruled:
A qualified acceptance or one that involves a new proposal constitutes a counter-
offer and a rejection of the original offer. A counter-offer is considered in law, a rejection
of the original offer and an attempt to end the negotiation between the parties on a
different basis. Consequently, when something is desired which is not exactly what is
proposed in the offer, such acceptance is not sufficient to guarantee consent because
any modification or variation from the terms of the offer annuls the offer. The
acceptance must be identical in all respects with that of the offer so as to produce consent
or meeting of the minds. (emphasis supplied).
51
The Associated Construction Equipment Lessors, Inc. (ACEL) introduced the system of
equipment leasing which is accepted as the best possible alternative to acquiring heavy equipment for
immediate use, where outright purchase may not be possible because of the huge capital outlay involved.
Decision 13 G.R. No. 170134
The petitioner cannot be faulted for the idling of his equipment on the
project site. First and foremost, the order to suspend the construction work
on May 14, 1993 came from the respondent. Second, the suspension of
construction works was supposedly temporary; thus, the petitioner’s
equipment were placed on standby at the site. Third, it was only on June 16,
1993, that the respondent gave the final word and formal authority for the
demobilization of the petitioner’s equipment.
Hence, even assuming that the petitioner had earlier given his consent,
such consent was for the suspension of the contract, not for its termination.
The petitioner could not have properly demobilized his equipment earlier
than June 16, 1993 without an official and definite letter of termination from
the respondent.
We find merit in the respondent’s contention that the basis of the cost
of opportunity lost should not be the total contract price, as the ‘cost of
ACEL aimed for the standardization of rental rates covering all ACEL members who have the same
equipment. See http://www.acel.com.ph/Page.aspx?id=71&pid=54, last accessed May 4, 2015.
Decision 14 G.R. No. 170134
opportunity lost’ must represent only the profits that the petitioner failed to
obtain due to the contract’s early termination. Thus, from the total contract
price, the amounts paid to the petitioner for work accomplished must be
subtracted, including the P500,000.00 down payment that the respondent
gave at the start of the contract; the difference would be the basis for
determining the cost of opportunity lost.
Article 1339 of the Civil Code provides that “failure to disclose facts,
when there is a duty to reveal them, as when the parties are bound by
confidential relations, constitutes fraud.” Otherwise stated, the innocent
Decision 15 G.R. No. 170134
non-disclosure of facts, when no duty to reveal them exists, does not amount
to fraud.
52
Magat v. Court of Appeals, G.R. No. 124221, August 4, 2000; Far East Bank & Trust Company v.
Court of Appeals, 311 Phil. 783 (1995).
53
Cervantes v. Court of Appeals, 304 SCRA 25, 33 (1999).
54
ABS-CBN Broadcasting Corporation v. Court of Appeals, 361 Phil. 499, 529 (1999).
55
Article 2208 of the Civil Code provides:
ART. 2208. In the absence of stipulation, attorney’s fees and expenses of litigation, other
than judicial costs, cannot be recovered, except:
(1) When exemplary damages are awarded;
(2) When the defendant’s act or omission has compelled the plaintiff to
litigate with third persons or to incur expenses to protect his
interest;
(3) In criminal cases of malicious prosecution against the plaintiff;
(4) In case of a clearly unfounded civil action or proceeding against
the plaintiff;
(5) Where the defendant acted in gross and evident bad faith in
refusing to satisfy the plaintiff’s plainly valid, just and demandable
claim;
(6) In actions for legal support;
(7) In actions for the recovery of wages of household helpers,
labourers and skilled workers;
(8) In actions for indemnity under workmen’s compensation and
employer’s liability laws;
(9) In a separate civil action to recover civil liability arising from a
crime;
(10) When at least double judicial costs are awarded;
(11) In any other case where the court deems it just and equitable that
attorney’s fees and expenses of litigation should be recovered.
No pronouncement as to costs.
SO ORDERED.
aMPfifki-
Associate Justice
WE CONCUR:
ANTONIO T. CARPIO
Associate Justice
Chairperson
Associate Justice
ATTEST A TI ON
I attest that the conclusions in the above Decision had been reached in
consultation before the case was assigned to the writer of the opinion of the
Court's Division.
ANTONIO T. CARPIO
Associate Justice
Chairperson, Second Division
Decision 17 G.R. No. 170134
CERTIFICATION