Fundamentals AVC For On Load Tapchangers An Introduction
Fundamentals AVC For On Load Tapchangers An Introduction
Fundamentals AVC For On Load Tapchangers An Introduction
An Introduction
Technical White Paper
Vincent Thornley and Elizabeth T. Macharia – Fundamentals Ltd.
Abstract
Due to increasing demand for energy, considerable pressure is being exerted on the power grid. This
is making it progressively difficult for network operators to ensure the precise control of fluctuating
voltages.
One means of controlling these fluctuating voltages is by using tapchanging transformers to safely
switch between the tapped windings of a power transformer and modify its output voltage.
This technical white paper is one of a series which describes how to extract best value from
tapchanging transformers.
The paper introduces Fundamentals, describing its origins and expertise, outlining some of the key
constraints of automatic voltage control (AVC or AVR) with on-load tapchanging (OLTC) transformers,
and the opportunities which present if these constraints are overcome. The paper then goes into detail
on how transformers can be operated flexibly with the Enhanced Transformer Automatic Paralleling
Package (TAPP) method, without the constraints of the traditional master-follower control method.
Two sections then follow outlining the network and increased engineering benefits of security of
supply, reduced losses, increased network utilisation, and more efficient substation expansion. Finally,
the paper draws this together in a succinct plan for network operators to enhance their AVC by using
the Enhanced TAPP method.
Fundamentals Ltd. Registered Office: Unit 2 Hillmead Enterprise Park, Marshall Road, Swindon, Wiltshire,
SN5 5FZ, United Kingdom. Company No. 2939559 VAT No. GB641612170
Technical White Paper
AVC for On-Load Tapchangers – An Introduction
The tapchangers keep “running away” leading to Transformers may be paralleled across networks
extremely high or low voltage conditions Different transformer types may be operated in
No-one understands how they work parallel
AVC/AVR puts constraints on my network The voltage control scheme is easy to implement,
operation even for multiple transformer busbar
arrangements with multiple operating
The last point is key to this paper - the AVC system
configurations
should not act as a constraint for network operation
but in fact should facilitate other opportunities There is an inherent fail-safe fallback which will
relating to: never permit transformer tap positions to run
apart
Complete flexibility on how to operate the
network At the heart of the Enhanced TAPP method is the
Improved security of supply principle that each transformer selects the correct tap
Increased network utilisation position for itself to cause the busbar to be at the
correct voltage while minimising circulating current.
Reduction of system losses
The method ignores the physical tap position as a
measure but rather looks at the power factor of the
But a good AVC system needs to go further than transformer current to determine when this is
this. achieved.
(a) no load situation without LDC (b) full load situation without LDC
(c) no load situation with LDC (d) full load situation with LDC
above nominal to ensure that the network stays is used this will require the approach of Figure 4(a)
within its limits. where an identical transformer is used and it is
connected to the same source with no infeed
5 Network Utilisation arrangements on the incoming line. If the existing
transformer is old, it may be unnecessarily expensive
Increasing the utilisation of expensive assets such as to source an identical transformer from the same
transformers is an effective way to increase capacity. supplier. The master-follower method also imposes a
Paralleling across networks is an easy method to constraint in how the new line is brought to the
achieve this, while maintaining n-1 security criteria, substation – the source impedance needs to be the
as highlighted in Figure 3. same on both lines and there can be no tees which
may draw load or inject generation.
Figure 3 Network utilisation for (a) independent Figure 4 Substation expansion (a) with master-
substations and (b) interconnected follower constraints and (b) flexible
substations expansion options
(a)
(a)
(b)
(b)
Figure 4 shows the expansion of a substation with an Using the Enhanced TAPP methodology of voltage
existing transformer T1, and the addition of a second control provides additional options to the network
transformer T2. If the master-follower method of AVC operator with the benefits of:
Elizabeth T. Macharia is an
Notes electrical and electronics
engineer with technical and
1 AVC and AVR (C=control, R=regulation) are leadership experience within the
both used to refer to the control system for smart transformer technology,
on-load tapchangers in different parts of the electricity utility, building
world. In this paper AVC is used throughout. services, and grid control
industries. Miss Macharia is a
2 Except for fault level restrictions. member of the Institution of
Engineering and Technology (IET) and volunteers as
Abbreviations the Young Professionals ambassador for her local
network. Her interests include but are not limited to
AVC automatic voltage control
power systems, sustainable energy, innovative
AVR automatic voltage regulation, equivalent to technologies that drive change within the engineering
automatic voltage control industry, and STEM education and outreach.
CB circuit breaker
EU European Union
LDC line, or load, drop compensation
LV low voltage, i.e. less than 1 kV
OLTC on-load tapchanger
PV photovoltaic generation
Fundamentals’ Services
Fundamentals’ Application Support
When you buy a Fundamentals product you can expect to receive expert assistance to apply your relay. Please
contact your sales office or agent and we will do our best to advise you. We will gladly provide you with advice
on an ad hoc basis, or if you have an extensive requirement for support, we can offer services for scheme design,
panel build, installation and commissioning.
Our global partners are carefully chosen to ensure that they have application support capabilities which are backed
up by Fundamentals voltage control experts.
Other Services
Fundamentals can assist with all aspects of voltage control applications and transformer and tapchanger
management:
Design and engineering
Panel/cubicle build
Site surveys, installation and commissioning
Tapchanger health check, maintenance and reverse power assessments
Transformer online dissolved gas analysis (DGA)
Technical support and troubleshooting
Power system analysis
Generation connection assessment
TWP-VC01-202010
©2020 Fundamentals Ltd.
Fundamentals Ltd
Unit 2, Hillmead Enterprise Park
Marshall Road, Swindon
Wiltshire, SN5 5FZ
United Kingdom
Tel: +44 (0)1793 847163
www.fundamentalsltd.co.uk
[email protected]