S.

No

Power system
studies

Dynamic Stability
study

Description of the study

In response to a fault condition under the


most onerous case (a close in 3-ph fault
applied for 150 ms as defined under UK
Gridcode) ;Fault ride through performance
of the generator

Support Required
Guidance required on the following:
a) Inputs required for the studies
b) Set up the model;
c) Perform the studies
d) Outputs to be provided in the
report.
e) Directions on recommendation
and standards documents to be
referred for the study
f) Review the study report
Guidance required on the following:

Motor starting
studies

It will be done to calculate motor starting


times, torque ,speed ,system voltage drop
and relay interactions

a) Inputs required for the studies


b) Set up the model;
c) Perform the studies
d) Outputs to be provided in the
report.
e) Directions on recommendation
and standards documents to be
referred for the study
f) Review the study report

S.No

Power system
studies

Harmonic studies

Description of the study

Harmonic study will be performed to


notify at the earliest opportunity if it is
recommended that a harmonic filter might
be required to mitigate harmonic issues
found.

Support Required
Guidance required on the following:
a) Inputs required for the studies
b) Set up the model;
c) Perform the studies
d) Outputs to be provided in the
report.
e) Directions on recommendation
and standards documents to be
referred for the study
f) Review the study report
Guidance required on the following:

Transformer
energisation
studies

Transformer energisation study is done inorder to verify the


voltage change is within limit specified in
P28. ??

a) Inputs required for the studies


b) Set up the model;
c) Perform the studies
d) Outputs to be provided in the
report.
e) Directions on recommendation
and standards documents to be
referred for the study
f) Review the study report

S.No

Power system
studies

Arc Flash study

Description of the study


Arc flash study will be completed to IEEE
1584 standards and for one operational
arrangement only for the site: to
determine the incident energy, the arcing
time (the amount of time for full fault
clearance), the arc flash hazard distance
and the required personal protective
equipment (PPE). This proposal isbased
on Siemens PTI UK using only three-phase
fault currents, since one-phase or twophase faults with arcs, according to IEEE
1584, always become three phasephase
faults.

Support Required
Guidance required on the following:
a) Inputs required for the studiesb)
Set up the model;c) Perform the
studies d) Outputs to be provided
in the report.e) Directions on
recommendation and standards
documents to be referred for the
studyf) Review the study report