Open Networks 2020 Ws1b p3 Operational Tripping Scheme Arrangements

Download as pdf or txt
Download as pdf or txt
You are on page 1of 27

Open Networks

Project
OTS Functional Design and
Data Exchange Requirements
Report

10 December 2020 | Version 1

WS1B P3
Real Time Data Exchange and
Forecasting
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

DOCUMENT CONTROL

Authorities

Version Issue Date Authorisation Comments

Final report for publication following


0.1 27/07/2020 Ali Ahmadi, John West ON Steering Group review and
inclusion of Appendix A

Updated the report with N-3


Ali Ahmadi, John West,
0.2 14/12/2020 deployment and testing results
Kanan Ganakesavan
between IEMS and DMS (PowerOn).

1.0 18/12/2020 Vivian Ng New Template

ACKNOWLEDGEMENTS

We would like to thank P3 stakeholders for their contributions to this report and wider WS1B P3 deliverables
including Ali R. Ahmadi, Matthew White, John West, Kanan Ganakesavan, Charlotte Grant, Steve Davenport,
Steve Gough, Paul Hartshorne, John Stapleton, Grant McBeath and Malcolm Grisdale.

│2
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

TABLE OF CONTENTS

1 Introduction ........................................................................................ 5
i. Open Networks Project ................................................................................ 5
ii. Scope of this report .................................................................................. 5
iii. Structure of this report .............................................................................. 6

2 OTS Basics and Recap of 2019 Work .......................................................... 7


i. Introduction to OTS Arrangements .............................................................. 7
ii. Capped Generation Approach .................................................................. 7
Figure 1 – Capped Generation Approach. ................................................................................................... 8

iii. Scheme Architecture and OTS Stages ..................................................... 8


Figure 2 – High Level OTS Architecture and Data Flows........................................................................... 9

iv. OTS Performance and Data Exchange Requirements .............................. 9


v. Implementation and System Integration .................................................. 10

3 Description of Ongoing OTS Projects ........................................................ 11


i. Transmission OTS Capability and Interface Development ......................... 11
ii. OTS Scheme in UKPN Area ................................................................... 12
iii. OTS Scheme in SSEN Area ................................................................... 13
iv. OTS Scheme in WPD Area .................................................................... 14

4 OTS Performance & Data Exchange Requirements ................................... 16


i. OTS Performance & Component Redundancy ........................................... 16
ii. OTS Data Exchange Requirements ........................................................ 17

5 Standard Requirements / Differences Across Schemes ............................. 19


i. Similarities & Differences across OTS Arrangements ................................ 19
ii. Emerging Issues & Good Practice .......................................................... 19

│3
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

6 Data Transparency .................................................................................... 21

7 UK Power Networks and NGESO N-3 Deployment Results ....................... 22


i. Test Approach ........................................................................................... 23
ii. Test stages ............................................................................................ 23
iii. Test Environments, Harness and Simulation .......................................... 23
iv. Test Environment Exit Criteria ................................................................ 24
v. Lessons Learnt....................................................................................... 24

8 Appendix A ................................................................................................ 26

│4
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

1 Introduction

i. Open Networks Project


The Open Networks (ON) Project is a major industry initiative that will transform the way our energy networks
operate, underpinning the delivery of the smart grid. The project looks to change how the networks operate to
facilitate the transition to a smart, flexible energy system. A key objective is to bring consistency in approaches
across networks through existing and new processes to support the transition to Distribution System Operations,
interactions with each other and interactions with customers. Open Networks is being delivered through a number
of Workstreams and Products.
Workstream 1B of the ON project focuses on Planning and Forecasting activities. These include Product 3 on
Real Time Data Exchange which is intended to cover the data exchange requirements to manage whole system
activities including Operational Tripping, Connect and Manage arrangements and Service Conflict Management.

ii. Scope of this report


This report covers initial work on N-31 Operational Tripping Scheme (OTS) arrangements being implemented on
DNO networks to enable the tripping of Distributed Energy Resources (DER) for faults on the GB transmission
network.
The 2020 Project Initiation Document for the ON project includes the following scope for Product 3 work on OTS
arrangements. A report on activity 1 to document OTS requirements including functional and data exchange
requirements is due to be completed by June 2020. The work on OTS arrangements are covered by activities 2
and 3 below:
Table 1 – OTS Activities 1, 2 and 3.

1
An N-3 condition in transmission network is defined as a circuit is on planned outage followed by a double circuit fault
reducing the transmission capacity by 3 circuits

│5
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

Ref Product Element Activities Deliverables

1 Identify data exchange [A] Operational Tripping Scheme (OTS)


specifications & implementation design & specification to secure N-3 Activity 1 Report
plan for Whole System activities contingencies on the transmission network. Jun 2020
based on Regional Development 1. Document OTS requirements including
Programme (RDP) outcomes. functional & data exchange. Activities 2 & 3
2. Review the OTS algorithm and review trial Report Nov 2020
(This will draw on the results.
implementation of OTS, C&M 3. Review end-to-end ESO-DSO system
and Service Conflict integration and go-live.
Management solutions through This work will draw on ongoing OTS work
RDPs. including implementations in the UKPN, WPD
There is a dependency on ESO- and SSEN areas. An initial report will focus on
activity 1. This will be extended to cover
DNO commercial agreements.)2
activities 2 and 3 when OTS implementations
are further progressed.

iii. Structure of this report


This report is focussed on the requirements for data exchange as identified for ongoing OTS projects. Section 2
of the report recaps the position laid out tin the 2019 report for Workstream 1B Product 3 including the agreed
approach to operational tripping arrangements and high level descriptions of the scheme architectures and data
exchange requirements.
Section 3 provides more detailed descriptions of the OTS arrangements being installed in the UKPN, SSEN and
WPD distribution areas. Section 4 details the performance requirements for OTS arrangements and the data
exchange associated with these arrangements.
Section 5 brings out conclusions in respect of the different implementations including areas where a similar or
standard approach is being agreed and areas where differences are evident. Emerging good practice is
highlighted together with problems that have been identified to date.
In line with network company undertakings to consider where data can be made more transparent, Section 6
considers whether the data being handled for OTS arrangements would have wider value to industry stakeholders
and the extent to which the data can be shared more widely.

2
Progress on certain RDP activities through 2020 is dependent on commercial arrangements being agreed in respect of how
services are used. This dependency does not apply to the OTS work.

│6
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

2 OTS Basics and Recap of 2019 Work

i. Introduction to OTS Arrangements


Historically, OTS arrangements have been used to allow transmission connected generation to operate freely
pre-fault in systems where post-fault transmission capacity is limited. In the event of defined network faults
occurring, an intertripping signal is sent to certain generators to remove a predefined volume of generation post-
fault and so manage thermal, voltage or stability issues. As the generation output would be reduced only in the
event of a network fault occurring, the generation will operate freely for most of the time. It is worth noting that the
defined network faults, and therefore the activation generation intertripping, are very infrequent events. Historical
data shows that a particular double circuit fault in the transmission system is typically a 1 in 100-year event. The
double circuit fault happening during another single circuit outage (the N-3 scenario) makes it an even smaller
probability event.
With increasing levels of DER being connected to networks, as part of the Regional Development Programmes
(RDPs) between NGESO and DNOs, OTS arrangements are being extended to utilise DNO network management
systems to curtail DER output under certain N-3 transmission conditions to manage thermal overloads. As well
as easing real-time transmission capacity limits, this will increase the connection capacity that is available to DER
in an economic fashion. This is an effective alternative to more extensive transmission reinforcements that are
likely to take several years to complete.
UKPN, NGESO, WPD and SSEN have jointly agreed to implement N-3 OTS arrangements to curtail DER output
following specific faults on certain parts of the transmission network on a ‘trial by doing’ basis. This approach will
ensure that regional demand remains secure and avoids scenarios whereby the transmission network could be
thermally overloaded under certain N-3 transmission conditions. The three DNOs and NGESO have agreed to
implement a “Capped Generation Approach” as part of their RDPs. This approach is based on capping generation
in the GSP that has agreed to be curtailed through connection agreements.
It is important to highlight that Operational Tripping will only be used to secure double circuit faults which coincide
with other outages on the transmission system. In other words an N-3 condition is a rare event. The transmission
network will be secured in line with both the Connect and Manage criteria and the security and quality of supply
standards (SQSS) which will rely primarily upon the use of DER flexibility followed by the N-3 OTS scheme where
appropriate.

ii. Capped Generation Approach


In broad terms, under the Capped Generation approach, if DER curtailment is required post-fault, NGESO would
send the DNO a CAP per Grid Supply Point (GSP) (see Figure 1) to ensure that the post-fault transmission
boundary capability would not be exceeded. The DNO’s control system would subtract the CAP from the total
DER generation behind that GSP to determine the curtailment required for N-3 events affecting that GSP. For
example, if GSP1 has 95MW total DER capacity and NGESO sends a CAP of 70MW, to determine the curtailment
required for N-3 under that GSP, the CAP of 70MW is subtracted from the total DER capacity of 95MW (95MW-
70MW=25MW). To achieve this curtailment of 25MW at GSP1, the DNO control system could send a 10MW
curtailment signal to Solar1_1 and a 15MW curtailment signal to Solar 1_2.
As well as the Capped Generation Approach, other logics could be used to curtail DER, for example, predefined
MW blocks and delta MW reduction. The Capped approach is preferred as it fits well with existing NGESO
processes and allows unconstrained DNO system operation pre-fault including ANM system operation.

│7
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

The cap for each GSP applies to the generation in the GSP that has agreed to be curtailed through connection
agreements and that is part of DNO control arrangements. The cap does not affect all of the distributed generation
connected to the GSP as many of the previously connected generators do not have agreements which allow
output to be curtailed.
Under the Capped Generation Approach, NGESO would send the required MW values to the DNO as an
instruction from an iEMS screen via an ICCP link. This enables the DNO to act on the instruction automatically if
it chooses to do so. The DNO control scheme is designed to achieve an overall response time and the DNO must
also ensure that OTS actions are not countermanded by other real-time systems acting on the generation, such
as ANM schemes.

Figure 1 – Capped Generation Approach.


The design and development of the N-3 OTS algorithm with a Capped Generation Approach began in June 2019
between UKPN, SSEN, WPD and NGESO.

iii. Scheme Architecture and OTS Stages


To manage transmission constraints post-fault using DER, a system is needed to curtail DER quickly by automatic
action in the event of an N-3 condition reducing the transmission capacity available in real time. The approach
being adopted extends the existing OTS capabilities in such a way that allows managed curtailment of DER.
Signals will therefore be sent on a per GSP basis to DNO control systems to curtail generation behind the required
GSPs. To enable the successful deployment and utilisation of this new capability, NGESO will instruct the DNO
on the requirements for generation curtailment via an ICCP link and DNO RDP partners are fully automating their
response to such instructions.
Figure 2 shows the overall communications architecture of the N-3 intertripping system and the 4 key stages to
the process – prior to arming, arming, tripping/triggering and disarm/restore. Implementation of these stages can
differ from region to region depending on the systems in place. This is discussed further in section 3.

│8
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

Figure 2 – High Level OTS Architecture and Data Flows.

“Prior to arming” (i.e. steady state), the DNO will provide visibility of all DER generation available to be curtailed
under each GSP to NGESO. NGESO will continue to monitor the outputs and system conditions.
At the “arming” stage, NGESO identifies a possible N-3 event and requests the DNO for a MW volume to be
available for reduction on a per GSP basis. At this stage, this is a request to be ready and the DNO control system
will not curtail generation. After the generation is made available to be reduced, NGESO will instruct the TO OTS
to start monitoring circuits for N-3 outage combinations and enable any transmission outages to be released.
The third stage is the “tripping/triggering” phase where, if the fault occurs on the transmission system, a trip
signal will be sent from the TO OTS to the DNO control system. Upon receipt of the TO trip signal, the DNO
control system will have an agreed duration to reduce the generation to the cap level set at the arming stage.
The fourth stage is to “disarm/restore” when the conditions on the transmission system no longer present a risk
of an N-3 event. If there is no longer a requirement for the OTS to be armed as system conditions have changed,
NGESO will coordinate the disarming of the OTS. If the OTS has operated to curtail generation and system
conditions have changed so that curtailment is no longer necessary, then the generation will be restored.
As noted previously, an N-3 event and therefore the activation of the third stage (generation tripping) does not
happen very often. The occurrence of a particular double circuit fault in the transmission system is typically a 1 in
100-year event and occurrence during another single circuit outage (the N-3 scenario) makes it an even smaller
probability event.

iv. OTS Performance and Data Exchange Requirements


The OTS will only include DER resources that can be controlled by the DNO and that have had intertripping
requirements placed on them through respective Bilateral Connection Agreements (BCAs). It is not proposed to
include generators that were connected prior to the inclusion of these specific terms and conditions.

│9
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

DER resources that are part of an OTS scheme might be quickly tripped or ramped down to meet the OTS
requirement. Much of the N-3 OTS infrastructure is being built such that a single software or hardware failure will
not result in the whole system being unavailable, though there are some exceptions to this due to cost benefit
considerations. For example, the individual DER connectivity to DNO ANM/PowerOn system does not have dual
redundancy. The OTS design and level of redundancy is intended to make the operational intertripping of DER
equivalent to transmission protection arrangements and will allow NGESO to utilise it in managing the whole
system.
To make the OTS arrangements work, a number of data points are expected to be exchanged between the ESO,
TO and DNOs. At a high level it is summarised as follows:
• DNOs will share real time controllable DER at each GSP with the ESO. This will be via ICCP link.
• The TO will share outage and circuit status information with ESO. This is a business as usual process.
• The ESO will send arming and restore instructions to the DNO and TO.
• The TO will send trip signals to the DNO via a dedicated link.
OTS performance and data exchange are considered further in section 4 of this report.

v. Implementation and System Integration


Currently, OTS arrangements are being implemented on the south coast where transmission constraints for
certain N-3 conditions are either exacerbated by increasing DER volumes alongside other causes such as
HVDCs and offshore wind connection to transmission network. UKPN, WPD and SSEN are working with NGESO
and NGET to implement N-3 intertripping arrangements. UKPN already have an ICCP link with NGESO and WPD
and SSEN are implementing similar links. At the same time, NGET is working with the DNOs to establish
dedicated trip signal links from its OTS systems (Sellindge OTS in the South East and Melksham OTS in the
South West). The first OTS will be operational from late 2020 in the South East followed by the South West in Q4
2021.

│ 10
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

3 Description of Ongoing OTS Projects


The areas to be covered by the 3 OTS projects are shown in Figure 3. NGESO and NGET have developed the
transmission OTS arrangements at Sellindge and Melksham so that these also can provide signals to DNOs if
any of the N-3 combinations arise. These signals are then used to initiate curtailment of distributed generation
that has agreed to be connected as part of an OTS arrangement. With these OTS arrangements in place, the
pre-fault transmission capacity into the South East, the South West and along the South Coast will be increased.

Figure 3 – Areas Covered by OTS Arrangements

i. Transmission OTS Capability and Interface Development


As noted in earlier sections, the N-3 functionality relies on the ability for NGESO to be able to send curtailment
caps to GSPs in each DNO area, coupled with the development of the necessary trip links between existing OTS
schemes and the respective DNO SCADA systems.
To achieve this overall functionality, NGESO has had to develop additional capability within core SCADA systems
and increase the amount of data sent over ICCP links with each DNO. New SCADA screens have also been
developed which enables better overall visibility and control of the DER that will be subject to the N-3 conditions
and is one of the first such developments in this area. In addition, business processes and project-specific training
has been provided to key resources within the planning and operational control functions to ensure successful
delivery of the project outcomes.
NGET have also had to develop additional capability across two existing OTS schemes to ensure the correct
transmission apparatus is monitored and the trip signals are generated in accordance with the allowable
timescales and post-fault ratings of the transmission network. To achieve this work, NGESO, NGET and the
DNOs have collaborated closely to ensure the appropriate transmission system outages were scheduled, specific
contractor resource was made available and commissioning activities were co-ordinated. These activities have
further demonstrated the ‘whole system’ nature of this project and have laid the foundations for further work in
this area, incorporating lessons learnt so far.

│ 11
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

ii. OTS Scheme in UKPN Area


This OTS is being delivered through the NGESO-UKPN Regional Development Programme. It utilises the existing
transmission OTS at Sellindge and is intended to help secure critical transmission outages on the double circuit
400kV route from Kemsley through to Bolney. In addition, it means that DERs have continued access to the
distribution network capacity without the need for costly transmission network reinforcement. The OTS will cover
five GSPs on the South Coast including Bolney, Ninfield, Sellindge, Canterbury and Richborough (once fully
commissioned). The UKPN interface substation is at Sellindge.
It is anticipated that around 300MW of DER resources will be available via the OTS arrangements by the end of
the ED1 in March 2023. A further 400MW of DER resources could be added during the ED2 period. The
generators included in the scheme have agreed to this through their connection agreements and a full list of the
generators for each GSP is being maintained through NGESO-UKPN BCAs for the relevant GSPs (Appendix G
of the Bilateral Connection Agreement which is updated every month to capture new connections).

Figure 4 – UKPN OTS Scheme Architecture

The UKPN OTS architecture is illustrated on Figure 4. Co-ordination of the DNO OTS operation is being achieved
by extending UKPN’s Distribution Management System (DMS) PowerOn functionality.
Data Exchange from UKPN to NGESO is via an ICCP Link. (There is an existing lCCP link between NGESO and
UKPN in the SPN license area.) UKPN will send the aggregated MW level of generation available to be tripped
per GSP to NGESO. Data will be sent on a near real time basis at an interval of 10 seconds. If the UKPN RTU
metering data is not updated, a repetitive value will be sent.
Reduction in DER generation output will be achieved via SCADA through tripping of UKPN circuit breakers.
PowerOn is also being configured to interact with ANM arrangements to ensure that the ANM system acts in line
with the OTS requirements.

│ 12
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

Considering the 4 key stages of the intertripping process – prior to arming, arming, tripping/triggering and
disarm/restore:
Table 2 – Four stages of the intertripping process
Prior to Arming UKPN will provide visibility of the DER controllable generation available to be curtailed
at each GSP to NGESO. NGESO will monitor the outputs and system conditions.
Arming NGESO identifies a possible N-3 event and requests UKPN for MW volumes to be
available to be reduced per GSP. (PowerOn will not actually curtail any generation at
this stage.) NGESO will also instruct NGET to start monitoring circuits for fault outages.
Tripping/Triggering If the relevant double circuit fault occurs, a trip signal will be sent from the NGET OTS
to UKPN’s DMS System (PowerOn). On receipt of the trip signal, PowerOn will have
an agreed duration to reduce the generation to the cap level set at the arming stage.
Currently the agreed timescale is 30 seconds.
Disarming/Restoring When system conditions are back to normal, NGESO will coordinate the process of
resuming normal system operation.

Implementation & System Integration


The OTS is being implemented on the South Coast where transmission constraints for certain N-3 conditions are
exacerbated by increasing DER volumes UKPN already have an ICCP link with NGESO.
As of November 2020, NGESO, NGET and UKPN had worked through a programme of testing to prove end-to-
end capability and the OTS achieved go-live on 20th November 2020. Further information on OTS testing and
lessons learned is provided in section 7 of this report.

iii. OTS Scheme in SSEN Area


This OTS is being delivered through normal connection process arrangements using RDP concepts. It utilises a
new transmission NGET OTS at Melksham and is intended to help secure transmission outages on the double
circuit lines that support the South West and South Coast (Bramley-Fleet-Lovedean etc). The OTS will cover eight
GSPs including Axminster, Botley Wood, Chickerell, Fawley, Fleet, Lovedean, Mannington and Nursling. The
SSEN interface substation will be at Fleet and it is anticipated that upwards of 1000MW of DER resources will be
available via the OTS arrangements.
The Appendix G process allows National Grid to set additional capacity limits at GSP sites, providing new
generation can be controlled and curtailed in response to transmission network issues such as an N-3 scenario.
This enables increased connection capacities at GSPs.
To provide the OTS functionality and control the new generation, SSEN are implementing a wide area ANM
system which would present a T-D (Transmission to Distribution) interface, monitoring and control functions at
generator sites and an overarching control mechanism to facilitate the trimming/tripping of generation across
multiple sites to meet the requirements of the transmission network conditions. This system is known as the South
West Active Network (SWAN) scheme. The SWAN scheme will interface with SSEN’s DMS (PowerOn) to provide
alarm and status indications for the OTS.
When the OTS is to be armed, NGESO will notify SSEN via an ICCP link of the MW Cap per GSP. In the event
of a transmission circuit trip, the NGET OTS sends trip signals to the SWAN system at Fleet for each GSP at
which DER is to be deloaded.
SSEN’s implementation of generator curtailment at each GSP is based on a LIFO approach. Signals are sent to
selected DERs to ramp down to new generation set points. If this is not achieved within 25 seconds, a trip signal

│ 13
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

is sent to the DNO circuit breaker to ensure that the generation output is reduced within the agreed timescale of
30 seconds.
The architecture for this scheme is illustrated on Figure 5 below. A process diagram illustrating the interactions
between NGESO, NGET, SSEN and the DER is shown in Appendix A.

Figure 5 – SSEN OTS Scheme Architecture


Implementation & System Integration
With respect to progress, SSEN are completing installation of ANM software. ICCP and DCP3 links have been
configured in readiness for testing. Test case development should begin in July 2020. Installation of OTS
functionality at generator sites is scheduled to begin in August. By September 2020, N-3 functionality is to be
complete across all 8 GSPs with interfaces to the Distribution Management System, the TO and the first two
generator local ANM controllers completed.
Overall scheme completion is dependent on the ICCP cable installation. This will take around 12 months such
that go-live is likely to be during summer 2021.

iv. OTS Scheme in WPD Area


This OTS is being delivered through the NGESO-WPD Regional Development Programme. It utilises the new
transmission OTS at Melksham and is intended to help secure transmission outages on the 400kV double circuit
routes that support the South West (Melksham-Hinkley Point-Taunton, Mannington-Chickerell-Exeter etc). The
OTS will cover eight GSPs in the South West including Abham, Alverdiscott, Axminster, Bridgewater, Exeter,
Indian Queens, Landulph and Taunton. The WPD interface substation will be at Taunton.
It is anticipated that a maximum of 550MW of aggregated and controllable DER will be available via the OTS
arrangements; noting that this maximum is based upon each generator exporting at their maximum capacity.

│ 14
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

Co-ordination of the DNO OTS operation will be achieved by extending WPD’s PowerOn functionality. Deload or
tripping of DER’s will be achieved either by utilising existing ANM arrangements, by direct control of DER where
this has been established or through tripping WPD circuit breakers at DER sites.
Implementation & System Integration
This OTS is being delivered through the NGESO-WPD RDP. Work is ongoing with procurement almost complete.
The ICCP implementation is close and is awaiting WPD approval.
Overall timescales are likely to be driven by completion of NGET’s works at Melksham. These have been delayed
due to COVID-19 impacts and go-live for the OTS is anticipated around April 2021.

│ 15
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

4 OTS Performance & Data Exchange Requirements

i. OTS Performance & Component Redundancy


This section considers the performance requirements of the OTS arrangement in more detail including the need
to provide equipment redundancy to increase reliability.
Each OTS will only act on DER resources that that have agreed intertripping through BCAs. The DER resources
that are part of an OTS scheme might be tripped or ramped down to prevent thermal overloads on the
transmission network. The timescale required to trip or download DER is 30 seconds from receipt of trip signal.
So far, for the implementation of OTS schemes, UKPN and WPD are choosing to trip DER resources whereas
SSEN is choosing to ramp down DER resources. UKPN can facilitate DER ramp down for those DERs which
have fast ramp down rate as part of their OTS solution. The ramp down functionality will be used if a timeline of
<30 seconds can be met following rescript of the trip signal from NGESO.
On the resilience of the OTS arrangements, no single hardware or software failure should lead to the loss of the
OTS system. To achieve this objective, much of the OTS infrastructure is being built to be fully dual redundant
such that a single control system or communications failure will not result in the whole system being unavailable.
This includes having two ICCP communication links between NGESO and DNO which are separately routed
between different NGESO and DNO locations.
The signalling and interfacing from NGET to DNOs is hard-wired to the interface substation. Dual channels are
provided for the transmission signals and the interface to the DNO system (PowerOn or ANM) must also be robust
against a single failure. This may require dual DNO RTUs at the interface site with separate electrical supplies,
but other approaches are acceptable if a single failure can be secured. As the NGET OTS system interfaces to a
single DNO site, 5m separation is required between the dual DNO interfaces. Where 5m separation can’t be
provided further review should be undertaken.
As per section 2 iv), there are exceptions to the dual redundancy requirements. These include the control and
communications links to individual DER sites from the DNO control system. These links and RTUs at DER sites
are not duplicated due to cost benefit considerations. Instead, NGESO and DNOs will provide failsafe
arrangements. For example, if a link is lost to a DER site, this is detected, and the DNO control system discounts
the contribution of the generator.
A summary of the OTS performance and redundancy requirements is given in Table 3.

Table 3 – Main OTS Elements and Redundancy Requirements


OTS Element / Function Equipment Dual Redundancy Comments (e.g. how redundancy is provided)
Owner (Yes/No)
DER Monitoring to determine DNO No DNOs to determine how DER is monitored and
DER Available the frequency of updates to NGESO. Satellite and
radio comms are being used.
DNO to ESO comms to notify ESO/DNO Yes 2 way comms are provided via ICCP. Redundancy
available DER and ESO to DNO is provided through the use of physically separate
comms to note curtailment communications routes. The bulk of the comms
volumes and arming infrastructure is owned by NGESO with some
requirements etc remote-end elements owned by DNOs.
ESO-TO comms to notify circuit ESO/TO Yes Provided via existing NGESO IEMS system.
monitoring requirements
Transmission circuit monitoring TO Yes Provided by NGET protection arrangements.
and trip signal generation
TO-DNO interface substation TO Yes Trip signals are provided to the DNO interface
comms to trigger DER tripping substation from TO substations included in the
OTS. Duplicate trip channels are in place.

│ 16
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

TO-DNO interface substation DNO Yes At the DNO interface site, duplicate RTUs are
requirement including RTU to provided.
receive and handle trip signal
DNO system to determine DER DNO Yes Provided via DMS (PowerOn) or through separate
tripping/de-load requirements ANM system (e.g. SWAN).
DNO system to send tripping DNO Yes Provided via DMS (PowerOn) or through separate
/de-load requirements to DER ANM system (e.g. SWAN).
DNO communication links to DNO No Dual redundancy is not provided due to cost.
DER substations and RTUs Other failsafe arrangements to be used.
DNO remote substation RTU to DNO/DER No In some cases, DER deloading is achieved
DER interface through circuit breaker trip, in some cases through
revising the generator set point.
Dual redundancy is not provided due to cost.
Other failsafe arrangements to be used.

Cyber security has been considered as part of the OTS design. In particular, the control room to control room
links use the Inter-Control Centre Communications Protocol (ICCP) to link two secure, private networks. The
NGESO-UKPN OTS utilises a previously established ICCP link. For the NGESO-WPD OTS, given the
establishment of new control room links, the proposals have also been shared with the National Cyber Security
Centre (NCSC). To ensure any new ICCP links are suitably future-proofed, NGESO and WPD are currently
assessing the options available to provide full end-to-end encryption of data sent between each organisation and
a decision will be taken on how to proceed once further analysis has been completed.

ii. OTS Data Exchange Requirements


A number of data points would be exchanged between NGESO, NGET and DNOs. At a high level:
• DNOs will share the levels of real time controllable DER behind each GSP with NGESO.
• NGET will share transmission outage and circuit status information with NGESO.
• NGESO will send arming and restore instructions to the DNOs and NGET.
• NGET will send trip signals to the DNO via a dedicated link.

Prior to Arming
The DNO will monitor DER and provide the aggregated MW level of DER generation per GSP that is available to
be selected to the OTS scheme. Data will be sent on a near real time basis at an interval of 10 seconds. Data
Exchange from the DNO to NGESO is via an ICCP Link.
Arming
NGESO sends an arming instruction to the DNO via ICCP Link. This instruction includes the capped generation
level for each GSP.
NGESO also sends an instruction to NGET to arm the OTS scheme to produce trip signals in the event of
particular transmission circuit trips. Data exchange from NGESO to NGET uses the IEMS system.
Tripping
If a fault occurs, the fault information and likely duration is sent from NGET to NGESO. After an actual N-3 event,
NGET will wait 120 seconds before sending a trip signal to the DNO. This delay is to check if the fault is transient
in nature.

│ 17
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

Adjust/Disarm
Following a trip signal, the DNO control system adjusts MW generation at each GSP based on the capped
generation level. The DNO systems should curtail DER on armed GSPs within 30 seconds.
If the OTS is to be disarmed, NGESO will provide an instruction to the DNO and NGET. The DNO control system
will cancel the potential DER generation curtailment such that there are no capped values on the GSPs.
Table 4 – Summary of Data Exchange Requirements for OTS
Stage From To Data Exchanged Comms Further Detail
Prior to DNO NGESO Aggregated generation per GSP that ICCP DER available for curtailment.
Arming is available to be selected to OTS.
Prior to NGET NGESO Transmission circuit status. IEMS
Arming
Arming NGESO UKPN Request for DER volumes to be ICCP This sets the capped DER levels
armed and capped level of per GSP.
generation per GSP.
Arming NGESO NGET Request to monitor circuits and arm IEMS
OTS.
Tripping NGET NGESO Fault information and likely duration. IEMS Look to establish is the trip is
transient or sustained.
Tripping NGET DNO After 120 seconds. Trip signal from Hard- This is delayed to avoid tripping
OTS to DNO control scheme. wired DER for a transient fault.
Tripping DNO DER Signal to deload generation within Could be a signal to deload DER by
30 seconds of receiving NGET trip tripping circuit breakers or by
signal. revising generator set points.
Disarm NGESO DNO Request to disarm DER volumes. ICCP
Disarm NGESO NGET Request to disarm OTS scheme. IEMS
Disarm DNO DER Within 30 seconds, signal to cancel
generation curtailment.
Cancel NGESO DNO Request DNO to stop curtailing after ICCP This is required as NGET OTS will
Trip a trip event not issue a cease signal after a trip
event.

│ 18
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

5 Standard Requirements / Differences Across Schemes


This section is to further draw out elements that are standard or different across the three OTS arrangements,
emerging good practice and any problems identified to date.

i. Similarities & Differences across OTS Arrangements


The three 3 OTS’s are compared in Figure 8.
Table 5 – Summary of Data Exchange Requirements for NGESO-UKPN OTS
NGESO - UKPN NGESO - SSEN NGESO - WPD

OTS Coverage South East / South Coast – South of England / South South West / South Coast -
5 GSPs Coast - 8 GSPs 8 GSPs
NGET OTS Scheme Sellindge Melksham Melksham
Interface Substation to DNO Sellindge Fleet Taunton Main
DNO Architecture / Control DMS / PowerOn Being South West Active Network DMS / PowerOn Being
Extended (SWAN) scheme. Extended
DER Type Generation Generation Generation
DER Selection LIFO LIFO – there is some further LIFO
selection based on ramp
rates to ensure sufficient
generation is deloaded.
Performance Trip to capped level or more Deload to capped level Trip to capped level within
within 30 seconds of trip within 30 seconds of trip 30 seconds of trip signal.
signal. signal.
DER Deload Achieved by ramp down or Achieved by ramp down to Achieved by ramp down or
via DNO circuit breaker new set point within 25 by circuit breaker tripping
tripping. DER ramp down seconds, then trip if this is depending on DER.
can be utilised in the OTS not achieved.
solution for those generators
which have a fast ramp rate
(i.e. <30 seconds).
Dual Redundancy All elements have dual All elements have dual All elements have dual
redundancy bar the redundancy bar the redundancy bar the
connections to DER sites. connections to DER sites. connections to DER sites.
Failsafe Arrangements Utilise manual “work Utilise manual “work Utilise manual “work
arounds” when DER visibility arounds” when DER visibility arounds” when DER visibility
or control is lost. or control is lost or control is lost
System Restoration Restoration through manual Automated restoration. Some automated
following OTS Trip Event actions. restoration.

The main differences between the 3 OTS arrangements currently being implemented by DNOs include:
• The SSEN system implements the distribution control requirements in its SWAN system rather than through
extension of PowerOn.
• The SSEN system will attempt to deload generation by ramping this down to a new set point rather than trip
the generation.

ii. Emerging Issues & Good Practice


The following points have been identified:
• Cyber security aspects have been discussed with the NCSC. Existing ICCP arrangements are sufficient
however, options of further enhancing security using full end-to-end data encryption are being considered.

│ 19
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

• DNO network running arrangements may lead to different distributions of DER across GSPs. SSEN are
considering how to accommodate this within the design of its control system.
• NGESO, the TO and the DNO need to remain aware of OTS component availability and planned outages.
For the NGESO-NGET-UKPN scheme, a “Standard Operating Protocol” is being developed for use by
Operational Planners.

│ 20
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

6 Data Transparency
The nature of the data being transferred to achieve the OTS arrangements is described in section 4 of this report.
As the actual data transfers are real-time and rely on secure and dedicated communications links, wider
dissemination of this data is not proposed.

│ 21
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

7 UK Power Networks and NGESO N-3 Deployment Results


The purpose of this section is to summarize what was covered in the N-3 testing phase. This section is also
intended to inform the stakeholders about the summary of achievements, test approach and any lesson learned.

Operational Inter-tripping is a mechanism to ensure that the UK transmission network remains operable by
reduction of load on it during an N-3 event (Planned Transmission Outage followed by double circuit fault),
preparation for which is carried out ahead of the potential event via an ‘arming’ request from the NGESO ENCC
to the UKPN Control Room using a dedicated ICCP link.

This request is concurrently visible to the NG TO Control Room (TNCC) in case of the actual event, the TO OTS
will initiate a 'trip' instruction to the DNO ANM/PowerOn (using a dedicated OTS link). The DNO ANM/PowerOn
receives the trip instruction and de-loads relevant flexible generation to achieve a pre-defined MW cap within the
selected GSP(s).

The capability to manage ‘Operational Inter-tripping’ at DER level in an efficient and cost-effective way falls within
the scope of the Regional Development Program work stream of the UKPN ANM Project.

UK Power Networks and NGESO’s N-3 OTS system went live on 20th of November 2020. The deployment of
other N-3 schemes on WPD, and SSEN networks have been delayed until late 2021 as a result of the need to
undertake further transmission outages to provide the necessary monitoring locations into the OTS.

The architecture diagram for the N-3 to DER inter-tripping Service is shown below.

NGESO/NGET IEMS UKPN PowerON DER 1


System Fully dual redundant ICCP link system
for operational data transfer and arming
instructions
Single gateway link
for remote arming

DER 2
indications
alarm and

DER 3

Fully dual redundant trip signal link


SELL OTS System
DER n

Figure 6: N-3 to DER Inter-tripping Service Architecture

│ 22
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

i. Test Approach
The delivery of N-3 intertripping system between UKPN and NGESO followed an agile development/delivery
methodology. During the design and development, the business, functional and non-functional requirements are
gathered in the form of user stories and use cases. From a test point, an acceptance criterion has been defined
to each user story and use case. The test strategy was designed to prove that the acceptance criteria have been
met. This means each user story or use case will have one or more test cases attached to them. During the test
execution, a test case would be accepted as passed if the acceptance criteria has been met.

ii. Test stages


The following test stages are defined for the N-3 to DER Inter-tripping Solution:

Table 6: Test stages


Test Stage Description
Unit Testing Independently of each other UKPN and NGESO will conduct informal bench
or unit testing of their respective GE solutions. This will include local
simulation of interfaces where required/feasible.
Data Point Configuration Carried out in conjunction with NGESO to confirm correct data transfer of all
(Signal Connectivity) signals.
Testing
Non-Functional Testing Carried out both individually and jointly by UKPN and NGESO.
Regression Testing Carried out by UKPN to confirm that existing SPN PowerOn functionality is
not adversely affected by introduction of the N-3 Solution.
System Integration Testing Carried out jointly by UKPN and NGESO against the Functional Test Cases
(SIT) defined by UKPN.
User Acceptance Testing Carried out both individually and jointly by UKPN and NGESO to gain
respective Control Room acceptance of the N-3 Solution – expected to be
achieved for UKPN by Control Engineer engagement with SIT & E2E
testing focused around exercising the N-3 N.O.P.
Operational Acceptance Defined as required to provide UKPN Business Stakeholders confidence to
Testing (OAT) authorise N-3 to DER Inter-tripping Solution to be promoted from SPN
PowerOn Pre-Production into Production.
End-to-End (E2E) Testing Expected to be a repeat of a subset of SIT tests involving UKPN, NGESO
and TO.
Production Testing As required by either NGESO or UKPN, following deployment of the N-3
Solution into this environment.

iii. Test Environments, Harness and Simulation


All development and bench testing was conducted on the UKPN Virtual Test environment before migrating the
N-3 Solution to the UKPN Main Environments, requiring the interface to the NGESO Pre-Prod environment.

│ 23
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

Once testing is complete and Operational Acceptance Testing (OAT) has been achieved the N-3 Solution will be
promoted to the UKPN main environment as part of UKPN Go-Live subsequent connection to the live UKPN
Electricity Network and the NGESO Main environments.

iv. Test Environment Exit Criteria


The basis for achieving Business agreement to moving N-3 solution into Production environment is as follows:

a. All planned testing is complete (functional and non-functional).


b. All approved test cases have been run, changes identified and results captured.
c. Business Stakeholders (as part of OAT) have agreed to any planned tests not executed i.e.,
Suspended or Out of Scope.
d. All required re-work, bug fixes and regression testing cycles completed satisfactorily.
e. All defects fully triaged, root cause identified and fix action assigned with clear resolution
timescales.
f. Defects trend and root cause analysed and no underlying systematic defect revealed.
g. No defects significantly impacting User experience – either UI or performance.
h. OAT successfully completed and signed off.

v. Lessons Learnt
This section consists some of the lessons learnt from defects/issues faced during System Integration Testing and
proposed actions in order to avoid same kind of issues in future projects. This is valuable for NGESO and NGET
for next N-3 intertripping projects with SSEN and WPD.
Table 7: Issues and lesson learned
# Issue Description lessons learnt
1 ICCP link should be ACTIVE on both sides We need to make sure the ICCP link is ACTIVE on both
(ESO<-> DNO’s). sides (ESO<-> DNO’s) before the starting of SIT.
Link was not active during the start of testing
phase, which lead to block some of the test
cases.
2 Issue with System configuration between We need to make sure before the SIT starting the
DMS and IEMS versions on both sides should be same.

Root cause: In Prod NG the TASE version is


1996 but in DDS NG changed it to 2000 which
is now reverted to 1996.

3 Incorrect mapping table for ICCP in the data Action:


mapping sheet (earlier IEMS mapping table This was a missed from NGESO for the interpretation of
was provided instead of ICCP). data point/values between IEMS and ICCP.
NGESO updated the Data Mapping sheet with the ICCP
For digital points, the IEMS deals in pure binary; values UKPN will receive, with the corresponding states
the equivalent status value is either a 0 or a 1. they should convert them to. UKPN updated their
The ICCP protocol deals in 1's and 2's. When program as per the latest data mapping sheet provided.
ICCP picks up a digital value for onward
transmission, it converts an IEMS 1 to an ICCP For the other DNO’s NGESO are planning to test at
1, but an IEMS 0 gets converted to an ICCP 2. least few ICCP datapoints are transferring the data
This has always worked OK previously, but on

│ 24
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

this occasion, UKPN's PowerOn seems to properly as expected as per the Data mapping sheet
convert the ICCP 2 to a PowerOn 2. before the SIT starts.

NOTE: As of now UKPN has updated the program at


their end for this issue but discussions is on how to deal
this with SSEN/WPD. It’s like whether code fix needs to
happen in NGESO side or to inform and send the
updated Data Mapping sheet to SSEN/WPD.

This issue could have been prevented by doing the


simulation testing between the IEMS and ICCP data
conversion at source.
4 Flexible DER set up is not responding to The electrical requirement should be presented, and the
Arming instructions and curtailment event operational procedure agreed before any algorithm
interface points agreed rather than being specified and
Root Cause: The specification provided by working backwards.
NGESO was not covering the IEMS-ICCP
interpretation and UKPN’s solution aborted as
per NG specification before triggering. The spec
was revised to match the iEMS systems output
and the UKPN Solution was re-written.
5 Availability of the key resources for the Test Project need to get the commitments form Key
activities resources for the Project work.
We have seen some instances where Key Project should share the detailed plan with Key
resources from either/both the sides were busy resources well in advance.
in other BAU activities/priority work. This have If there is any deviation to the Project/Test Schedule,
delayed the joint testing sessions. the resource manager should be informed, and updated
plan should be shared.
6 Turnaround time for defect resolution. - If there are any 3rd parties (development team)
UKPN did not have a single defect in the involved, project should engage the 3rd parties well in
PowerOn N-3 program, there were some issues advance for any possible issues/support to fix the
with the simulation environment, however these defects.
issues got fixed for SIT considering a new - Based on the priority of the defect need to accelerate
automation program was designed from the efforts (daily engagement/mobile support/weekend
scratch. work).

│ 25
Open Networks Project
OTS Functional Design and Data Exchange Requirements Report
December 2020

8 Appendix A
Process diagram illustrating interactions between OTS parties

│ 26

You might also like