NSI 04 and Guidance - Work On or Near High Voltage Overhead Lines - Issue 9
NSI 04 and Guidance - Work On or Near High Voltage Overhead Lines - Issue 9
NSI 04 and Guidance - Work On or Near High Voltage Overhead Lines - Issue 9
Copyright National Grid plc 2023©, all rights reserved. No part of this publication may be reproduced, stored in a retrieval
system, or transmitted in any form or by any means electronic, mechanical, photocopying, recording or otherwise,
without the written permission of National Grid obtained from the issuing location.
The contents of National Grid documents are based on the needs of National Grid and the conditions under which it
operates. It shall not therefore be assumed that the contents stated therein necessarily meet the particular circumstances
and requirements of other organisations. The principles set out in this document are for information only and therefore
National Grid is not liable to any third party for any loss or damage resulting from reliance on the contents. It is the
responsibility of such external organisations to check that the document is the latest version and is appropriate for their
purposes.
Document History
Key Changes
Section Amendments
2- Definitions Earthing Team definition adjusted to not include the application / removal of
red pennants on towers.
15 - Rule & Guidance New section added to aid in the management of the Control of Objects, Tools
and Access Equipment on or near to towers.
CONTENTS
Page
SECTION 1
STANDARD REQUIREMENTS
CONTENTS
Page
3 Dangers 10
4 General Requirements 11
9 Access / Egress and Work which does not require Circuit Outages 19
11 Tower Demarcation 20
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 5
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
For work on HV Overhead Lines reference to Technical Guidance Notes (TGN) and Asset
Management Business Procedures (AMBP) shall be made.
For information on the Planning Process, then relevant Transmission Procedures should
be referenced.
The layout of this guidance note reflects that of legislative codes of practice, where the rule
(or mandatory obligation) is identified by a green panel on the left-hand side. The guidance
follows after the rule and is identified by a blue panel.
Within National Grid the guidance notes hold equivalent status of an Approved Code of
Practice (ACOP) in law. If not followed, you will be required to demonstrate that your safe
system of work is of an equal or higher standard.
The Schemes detailed in TGN 313 indicate the requirements for the application of portable
Drain Earth(s) and Field Equipment Earths in preparation for various work procedures.
The Schemes detailed may need to be changed or supplemented in exceptional
circumstances. A Senior Authorised Person can initiate such modifications, but all
modifications shall be agreed and recorded on the TGN 313 F1 form.
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 6
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
2 Definitions
Term Definition
Complex Circuit A Dead circuit that has two or more Live circuits inducing current into it.
Disconnected Circuit A permanent Primary Earth rated to protect against inadvertent re-
Primary Earth(s) energisation and of a specific design as detailed in TGN 313 Section 5
As a Single DrESS but having a rated current-carrying capability of 900
Double DrESS
Amps.
The final connection from the bottom of the Downlead to the Substation
Downdropper or other termination equipment (e.g. busbars, line traps, cable sealing
ends etc.) (See Figure 1).
The connection from the terminal tower on a circuit to the Substation
gantry or anchor blocks, or when an OHL connects to an underground
Downlead
cable, the connection from the crossarms to the cable sealing end
structure (see Figure 1).
Type Registered Drain Earth used in Substations to facilitate work on
Duplex Drain Earth
Downleads and Downdroppers.
Earthing for Induced Drain Earth(s) applied to control and manage the flow of induced
Currents currents on the circuit to be worked on.
Earthing for Induced Drain Earth(s) applied to reduce and control induced voltages at the
Voltages point of work/work zone.
A team led by the recipient of the Safety Document or by a Competent
Person under the instruction of the recipient of the Safety Document to
Earthing Team
apply / remove Drain Earth(s) in accordance with an Earthing
Schedule.
An arrangement of conducting metallic footplates, designed to ensure
that during fault conditions, dangerous potential differences do not
Equipotential Zone
appear across the body of Personnel working near ground based
machinery.
Items such as winches, pullers, tensioners, conductor access platforms,
Field Equipment access equipment and cranes which could be subject to dangerous
induced voltages/currents.
Type Registered connections used for bonding items of Field Equipment
Field Equipment
to earth. The earths are distinctively coloured orange to identify them
Earths
from Drain Earth(s) and are not included on an Earthing Schedule.
Fully Conductive A system used in tension stringing where induced currents are allowed
Conductor System to flow in a controlled manner using Type Registered equipment.
Conditions which could cause dangerous induced voltages or currents,
Impressed Voltage differences in earth potential or voltage differences across any break in
the conductive path.
A series of identical Safety Documents that have the same number but
Multiple Safety
a unique suffix to identify the individual document. The suffix is
Documents
alpha/numerical.
A Senior Authorised Person (NSI 4) or a person with sufficient
technical qualifications and / or experience to assess the Drain Earth
OHL Engineer
requirements for Induced Voltage and Current management when
appropriate.
A pre-determined arrangement of portable OHL Drain Earth(s)
providing adequate protection against inadvertent re-energisation in
accordance with the Management Procedure - NSI2 Earthing High
OHL Primary Earth
Voltage Equipment. (The OHL Primary Earth shall have a National
Grid Portable Primary Earth “No unauthorised interference” notice
affixed to it to ensure it is readily identifiable as a Primary Earth).
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 7
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
Downlead
Downdropper
Figure 1
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 8
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 9
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
3 Dangers
The main Dangers to Personnel working on overhead lines and towers are electric
shock and burns arising from:
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 10
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
4 General Requirements
NSI 4 Rules 4.1 For work on OHL circuits Point(s) of Isolation and Primary Earth(s)
Section 1 shall be established to cover all infeeds.
4.1 to 4.4
A Safety Document can then be Consented to, provided the
following is satisfied:
4.2 For Complex Circuit configurations, the section of the circuit identified
to be worked on shall be converted to a Simple Circuit, prior to work
commencing, in accordance with a TGN 313 Earthing Scheme.
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 11
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Rules 4.5 For any work on Downleads and Downdroppers, a separate,
Section 1 dedicated Permit for Work shall be issued.
4.5 to 4.7
4.6 When the work requires use of Multiple Safety Documents, then the
Senior Authorised Person shall issue all the Drain Earth(s) for the
work with one Safety Document (the Master Safety Document).
4 General Requirements
NSI4 Guidance 4.1 Consultation should include the OHL Senior Authorised Person,
Section 1 OHL Team Leader, Control Person (Safety), Substation Senior
4.1 Authorised Person and Engineering and Asset Management to
develop an effective scheme, documented via TGN 313 Form F1.
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 12
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI4 Guidance 4.2 Induced currents (up to 900 A) can flow in the Drain Earth(s) applied
Section 1 to a Complex Circuit. The conversion of a Complex Circuit to a Simple
4.2 to 4.6 Circuit can be achieved by the application of DrESS earthing schemes
to sectionalise the OHL circuit or by the local application of a DrESS
earthing scheme at the point of work.
Induced currents (up to 450 A) can flow in the conductors of a Simple
Circuit. The management of this current involves the provision of
parallel paths to enable the current to flow. This will limit the flow of
current in lifting tackle, winch bonds and conductor stockings. The
Senior Authorised Person shall assess the requirement for Drain
Earth(s).
4.3 The Safety Document recipient shall ensure that Drain Earth(s)
when not in use are kept in safe custody – e.g. in a locked vehicle
4.5 The dedicated Permit for Work may include other work on the towers
being worked on e.g. replacement of insulators on the adjacent side
of the tower or work on other towers where Drain Earth(s) are applied
which are associated with the dedicated Permit for Work.
4.6 The Master Safety Document number generated shall always be
Safety Document Number - MP – Master – i.e. 12345MP Master.
Multiples will be numbered 12345MP 1 of n, 12345MP 2 of n,…….
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 13
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Guidance The Master Safety Document shall record the total number of Drain
Section 1 Earth(s) issued.
4.6 Cont.
The Master Safety Document Section 2 Further Precautions shall be
endorsed with;
“Drain Earth(s) shall be applied as directed by the recipient of this
Master Safety Document and in accordance with attached Earthing
Schedule”.
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 14
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Guidance National Grid QA teams issued with a Secondary Safety Document
Section 1 and a copy of the Earthing Schedule. National Grid Competent
4.6 Cont. to Person shall coordinate with Master Safety Document recipient to
4.7 ensure only towers within Earthed sections are QA checked.
Earthing Schedule(s)
The following statement shall be included on the Earthing Schedule
“A daily check shall be made before work starts that appropriate Drain
Earth(s) are still in place. In accordance with TGN 313.
4.7 Examples of activities that may require the DAR to be switched out:
Tension stringing of conductors
Raising or lowering of earthwire
Raising or lowering of conductors on middle or top phases
Use of Cranes or Mobile Elevated Work Platforms
NSI 4 Rules Drain Earthing Schemes for OHL are referenced in TGN 313
Section 1
5.1 to 5.2 Application of Drain Earth(s)
5.1 The earth end connections of all Drain Earth(s) shall be attached
before any conductor ends are connected, utilising an earthing pole.
5.2 When Sparrow Plates are used, all Connecting Bonds and Drain
Earth(s) shall be connected before any Drain Earth(s) are applied to
the conductors, utilising an earthing pole.
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 15
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Rules 5.3 At tension towers, provided the jumper is connected at both ends and
Section 1 Earthed; the fitting of Drain Earth(s) to the line side of tension
5.3 to 5.6 insulators may be carried out using a 600mm earthing pole, from a
suitable working position at the line end of the insulator set.
5.5 At tension towers, provided the jumper is connected at both ends and
Earthed, the removal of the clamps from the line side of tension
insulators may be carried out using a 600mm earthing pole, from a
suitable working position at the line end of the insulator set.
5.6 Conductor end clamps of all Portable Drain Earth(s) shall be removed
first, using the earthing pole. At no time, shall the earth end clamp of
a Portable Drain Earth(s), a Sparrow Plate or a Sparrow Plate
Connecting Bond be disconnected whilst a conductor end clamp is
attached.
NSI 4 Rules 6.1 A register of all Drain Earth(s) that are applied or removed shall be
Section 1 maintained.
6.1 to 6.5
6.2 Immediately prior to the clearing of Safety Document(s), all issued
Drain Earth(s) shall be accounted for.
6.3 If any Drain Earth(s) / earthing equipment are to be left on the tower
as part of the Safety Document clearance process, then the relevant
sections of the Safety Document shall be completed by the
Competent Person clearing the Safety Document.
6.5 Prior to Return to Service, the Senior Authorised Person will decide
(if any) the extent of any further inspection that is required in order to
verify that all towers are de-earthed prior to Safety Document
cancellation.
NSI 4 Rules 7.1 DrESS earthing schemes shall be controlled via an Earthing
Section 1 Schedule or Safety Document Card Safe.
7.1
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 16
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Guidance 7.1 DrESS earth scheme(s) controlled via an Earthing Schedule.
Section 1
7.1 This will normally be carried out when a single Working Party is
carrying out a task(s) during an OHL outage. The Earthing Schedule
shall make reference to the application / removal of the DrESS earth
scheme(s) and the fact that it shall be applied prior to the task(s) being
carried out and removed only when the task(s) has been completed.
The Senior Authorised Person issuing the Permit for Work shall,
in addition to all other items, issue a Key for the Card Safe holding
the DrESS Permit for Work. This issue will be recorded on the
Permit for Work in Section 4.
NSI 4 Rules 8.1 Access / Egress and work where Safety Distance may be infringed
Section 1 shall be carried out under a Permit for Work.
8.1 to 8.2
8.2 During the issue / transfer of a Permit for Work the recipient of the
Safety Document shall confirm that the Circuit Identification
complies with the details in the Technical Data Sheet(s).
NSI 4 Guidance 8.2 The Senior Authorised Person issuing the Permit for Work shall
Section 1 also issue to the Competent Person receiving the Permit for Work
8.2 the following items:
Sufficient Circuit Identification wristlets for each
member of the Working Party
Sufficient Circuit Identification flags which fit the
sockets or brackets on the towers to be climbed
Sufficient Drain Earth(s) and an associated Earthing
Schedule, where applicable
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 17
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Guidance Prior to the issue of the Safety Document the Senior Authorised
Section 1 Person will confirm to the Competent Person all the relevant
8.2 Cont. information from the Technical Data Sheet, highlighting the flag
bracket identification nomenclature. The Technical Data Sheet shall
be issued with the Safety Document.
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 18
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
9 Access / Egress and Work which does not require Circuit Outages
NSI 4 Rules 9.1 Access / egress and work on towers where there is no significant risk
Section 1 of infringing Safety Distance during the course of the work may be
9.1 carried out with circuit(s) Live.
9 Access / Egress and Work which does not require Circuit Outages
NSI 4 Guidance 9.1 When the Senior Authorised Person decides, it is necessary to
Section 1 confirm these instructions in writing, they shall record the assessment
9.1 and controls to be applied in AMBP 311 RAMS. Where the RAMS
control all Safety from the System hazards there is no requirement to
issue a Limited Access Certificate.
Where contractors are carrying out work near HV Equipment and the
means of achieving Safety from the System is by limiting the work
area, a Senior Authorised Person shall confirm these instructions in
writing by the issue of a Limited Access Certificate. The only
exception to this requirement is where the identified work, and / or work
area, as detailed and controlled in the risk assessment and method
statement are limiting in their own right, thus ensuring there is no risk
from the System.
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 19
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Rules 10.1 For earthwire work Short Drain Earth(s) or Short Bridging Earths shall
Section 1 be used to maintain all earth bonding connections or to maintain
10.1 to 10.4 earthwire continuity.
10.3 Whenever Personnel are required to access the tower peak and carry
out work which may bring them closer than 300 mm to the Earthwire
i.e. Condition Assessment or Tower Painting, then a Short Drain
Earth(s) shall be applied between the tower steelwork and earthwire
using, as a minimum, a Type Registered 600 mm Earthing Pole.
NSI 4 Guidance 10.1 Access is permitted for the duration of applying / removal of the Short
Section 1 Drain Earth(s), utilising, as a minimum, a 600 mm Earth Pole.
10.1
Where Short Drain Earth(s) are applied to earthwires carrying fibre
optic wrap, extra care shall be taken when applying the Short Drain
Earth(s) to ensure that the Fibre Optic Cable is not crushed or
damaged. Where possible the Short Drain Earth(s) shall be applied
to the conductor between the earthwire fitting / anchor clamp and fibre
optic clamps or support frames.
On certain towers OPGW extends from the peak of the tower to base
level. If the integrity of the permanent earth bonds fitted to the OPGW
extending down the tower leg(s) is verified, then there is no
requirement to apply a Short Drain Earth to this OPGW to approach
within 300 mm.
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 20
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
11 Tower Demarcation
NSI 4 Rules 11.1 The Senior Authorised Person shall ensure the tower is demarcated
Section 1 to clearly define the safe working area.
11.1
11 Tower Demarcation
NSI 4 Guidance 11.1 The work area on the tower shall be demarcated by the use of red
Section 1 pennants.
11.1
The Senior Authorised Person, via RAMS, shall provide specific
instructions and / or a detailed sketch of the demarcation position.
The red pennants shall be applied when working under Safety
Documents before work commences. Where RAMS are used in
place of an LAC, the same standard shall be applied.
The Person(s), whilst fixing or removing red pennants, shall be under
the Personal Supervision of a Competent Person.
NSI 4 Rules 12.1 Prior to work the Competent Person shall check the weather forecast
Section 1 and contact NGET Control for lightning risk.
12.1 to 12.4
12.2 In the event of, or near approach of a lightning storm where storm
clouds or lightening is visible, or Thunder can be heard – all work shall
cease until the storm passes.
12.3 When the weather conditions are such that wind induced conductor,
movement could cause Safety Distance from the Live circuit to be
infringed, then the work shall be stopped.
12.4 Work shall also be discontinued if fog or poor visibility prevents
observers from fulfilling their role.
NSI 4 Guidance 12.1 Contact may be via telephone or the SafeGrid app.
Section 1
12.1 to 12.2 On receipt of a Lightening Risk 1 notification, the PIC or site supervisor
shall identify any specific risk associated with a Lightening Risk 1 in
the area. Suitable controls shall be implemented, recorded and
communicated to the working party before work continues.
12.2 Personnel are to withdraw to a minimum of 10 metres from any tower
and connected equipment.
Personnel shall be vigilant with regard to lightning and other adverse
weather. They shall inform colleagues and NGET Control immediately
of any adverse weather conditions which may affect the work. NGET
Control shall pass this information as appropriate.
The Senior Authorised Person shall ensure that the nominated
Competent Person responsible for requesting the Lightning Risk
status is aware of their responsibilities to inform all other working
parties that are affected along the route.
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 21
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Rules 13.1 Where a circuit has been subject to a fault all Earthing Device(s)
Section 1 shall be inspected before further work is carried out.
13.1
NSI 4 Guidance 13.1 Where a circuit has been subject to a fault, the integrity of Earthing
Section 1 Device(s) cannot be guaranteed. Therefore, following a fault on an
13.1 adjacent circuit, all Earthing Device(s) shall be inspected before
further work is carried out.
NSI 4 Rules 14.1 Where items are fitted to overhead line towers that include a third -
Section 1 party system such as low voltage supplies i.e. aircraft warning lights,
14.1 Cellular Installations i.e. radio or microwave frequency transmitters,
a safe system of work shall be implemented.
NSI 4 Guidance 14.1 When work is to be under-taken, which could involve exposing
Section 1 employees or contractors to danger from these systems; a minimum
14.1 of industry standard precautions and controls shall be implemented.
These may be in conjunction with the third-party operator and for all
Work on or Near to Cellular installations further information is
contained within a Management Procedure.
NSI 4 Rules 15.1 Objects, tools and access equipment shall be stored, moved and used
Section 1 in a controlled manner to ensure that they do not infringe Safety
15.1 Distance.
15.2 The Senior Authorised Person shall ensure that the risks of use of
objects, tool and access equipment are considered and recorded via
a Safety from the System Risk Assessment.
NSI 4 Guidance 15.1 Examples of objects could include – tools, ropes, 3rd party equipment,
Section 1 platforms, MEWPs, Drain Earth(s). (not an exhaustive list)
15.1
The Safe System of Work (National Grid or Contractors) shall
specifically identify adequate control measures.
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 22
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Guidance 15.2 When assessing the risks, Safety from the System shall be
Section 1 maintained. The following information should be considered:
15.1 Cont.
Wire clearance diagrams or other methods of checking safety
clearances
The objects, tools and access equipment being operated or
lifted near or on a tower
The type / scope or manner of work being undertaken
Weather conditions that could introduce further / increased
risk
The competence of those using the equipment
Earthing requirements for the object, tool or access
equipment
(not an exhaustive list)
© National Grid plc 2023 – All Rights Reserved Section 1 Standard Page 23
Uncontrolled when printed Requirements
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
SECTION 2
CONTENTS
Page
2 Competency of Staff 29
4 Emergency Procedures 30
5 Weather Conditions 31
© National Grid plc 2023 – All Rights Reserved Section 2 Safety Page 24
Uncontrolled when printed Requirements for Continuous
Tension Stringing of OHL
Phase Conductors and
Earthwire
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Rules 1.1 The safety requirements throughout this section shall be fully
Section 2 understood and implemented by a Senior Authorised Person and
1.1 to 1.9 the Competent Person.
1.2 Prior to agreement that the work can be undertaken, the Senior
Authorised Person shall carry out for all sections of the overhead line
an assessment that includes, the effect of Circulating Currents on
temporary joints i.e. use of conductor stockings, reeving ropes and
polyester slings.
1.3 Ensure that the Delayed Auto Reclose (DAR) is switched out during
all Tension Stringing Operations.
1.4 All Safety from the System measures shall be in place prior to the
commencement of Tension Stringing operations and remain in place
until the work has been completed.
1.5 All Earth Bonding shall be in place prior to the Tension Stringing
Operation.
1.7 The Senior Authorised Person shall satisfy themselves that any
plant, equipment, crossing protection and associated activity does not
infringe safety distance.
1.8 At the end of the work period before Personnel leave site, the
Conductor section shall be pulled through and secured at around
normal erection tension to prevent excessive sag.
© National Grid plc 2023 – All Rights Reserved Section 2 Safety Page 25
Uncontrolled when printed Requirements for Continuous
Tension Stringing of OHL
Phase Conductors and
Earthwire
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Guidance 1.1 The Senior Authorised Person shall have sufficient technical
Section 2 knowledge and experience of the work to be undertaken, the
1.1 to 1.2 techniques to be employed and the Safety from the System
implications to enable them to make the necessary arrangements and
decisions for planning the work. They will also issue the appropriate
Safety Document(s). They shall be specifically appointed to NSI4.
Form F10, Daily Check list for key activities, located in TGN 313 shall
be completed on a daily basis
© National Grid plc 2023 – All Rights Reserved Section 2 Safety Page 26
Uncontrolled when printed Requirements for Continuous
Tension Stringing of OHL
Phase Conductors and
Earthwire
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Guidance 1.3 Before tension stringing is carried out, the Competent Person shall
Section 2 request the Control Person (Operation) to switch out the DAR on the
1.3 Cont.to 1.6 Live circuit. At the end of the restringing, the Competent Person will
request the restoration of the DAR. This will be carried out and
recorded on the daily check sheet.
In the event of the circuit tripping during the work, the Control Person
(Operation) shall not initiate the re-closure of the circuit until they have
obtained the agreement of the Competent Person on site.
1.4 Tension stringing shall not proceed until agreed by the Competent
Person, who shall be present in the section to be worked on during
the installation of the conductors with their attention dedicated to the
task.
1.6 The Senior Authorised Person shall make reference to the tables in
TGN 313 for the correct number of Drain Earth(s) required for sub-
conductors under this section.
© National Grid plc 2023 – All Rights Reserved Section 2 Safety Page 27
Uncontrolled when printed Requirements for Continuous
Tension Stringing of OHL
Phase Conductors and
Earthwire
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
1.7 The Senior Authorised Person may need to refer to the appropriate
overhead line design drawings.
© National Grid plc 2023 – All Rights Reserved Section 2 Safety Page 28
Uncontrolled when printed Requirements for Continuous
Tension Stringing of OHL
Phase Conductors and
Earthwire
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Guidance 1.8 The Senior Authorised Person may need to refer to the appropriate
Section 2 overhead line design drawings.
1.8 to 1.9
The earthwire shall be tensioned, as a minimum, to a position where,
under all conditions, Safety Distance from the Live phase conductors
will not be infringed. It shall be terminated at appropriate towers to
minimise the dependence on the temporary joints and the tensioner /
puller machines and to prevent excessive sag. The Earthwire shall be
caught off avoiding any stocking connections being positioned in the
running block. If this is not possible, bridging earths shall be applied to
reduce any burning of the stockings. At all intermediate connections,
a temporary safety clamp shall be placed onto the Earthwire and
secured to the tower with a metallic sling. Drain Earth(s) can then be
applied outboard of the temporary clamps.
1.9 All the conductor running blocks shall comply with the requirements of
TRL 2.2 part 5. All conductor running blocks at machine end towers
shall be brushed.
2 Competency of Staff
NSI 4 Rules 2.1 The Competent Person(s) in receipt of Safety Document(s) for this
Section 2 work shall understand the relevant sections of TGN 313 and have
2.1 completed the applicable TGN 313 E-Learning course.
2 Competency of Staff
NSI 4 Guidance 2.1 The Competent Person(s) shall have read the relevant sections of
Section 2 TGN 313.
2.1
Documented evidence shall be available confirming the Competent
Person(s) in receipt of Safety Document(s) for this work has
successfully completed the relevant sections of the TGN 313 E-
Learning.
NSI 4 Rules 3.1 An effective and efficient communications system shall be in place
Section 2 prior to any work associated with these procedures.
3.1
© National Grid plc 2023 – All Rights Reserved Section 2 Safety Page 29
Uncontrolled when printed Requirements for Continuous
Tension Stringing of OHL
Phase Conductors and
Earthwire
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Guidance 3.1 The Competent Person responsible for DAR outage requests shall
Section 2 also take responsibility for ensuring that communication is established
3.1 between the site and the Control Person (Operation) using an
effective communication channel.
Before the actual installation work is commenced, the site Personnel
carrying out the work shall explain to the satisfaction of the Competent
Person the method of communication, signalling and control that will
be adopted. This communication system shall be checked each day
before the start of work and immediately prior to the stringing
operation. Work shall be stopped immediately if the communication
system is found to be defective.
4 Emergency Procedures
NSI 4 Rules 4.1 In the event of an unplanned action whereby the conductor or any
Section 2 other equipment or material, could potentially come within Safety
4.1 to 4.2 Distance of a Live circuit, the Competent Person shall immediately
arrange for the Live circuit to be switched out in order to recover the
situation.
4 Emergency Procedures
NSI 4 Guidance 4.1 At the planning stage, NGET Control shall consider emergency
Section 2 outages in the possible fault risk category. Following emergency
4.1 circuit switch out, system security standards may not be met and
therefore NGET Control shall implement any planned action to restore
security standards.
© National Grid plc 2023 – All Rights Reserved Section 2 Safety Page 30
Uncontrolled when printed Requirements for Continuous
Tension Stringing of OHL
Phase Conductors and
Earthwire
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
NSI 4 Guidance 4.2 Personnel carrying out the work shall have a documented emergency
Section 2 plan available on site to instruct all staff in the actions to be taken
4.2 should the conductor or any other equipment or material come within
or have the potential to come within Safety Distance of the Live
circuit. The plan shall include the following:
Should the approved procedures fail, advice shall be sought from the
Senior Authorised Person.
5 Weather Conditions
NSI 4 Rules 5.1 Prior to the tension stringing of conductors, the Competent Person
Section 2 shall contact the appropriate local weather centre to ascertain the
5.1 to 5.4 forecast on wind speed and precipitation and NGET Control for
lightning risk.
5.2 When the weather conditions are such that wind induced conductor
movement could cause Safety Distance from the Live circuit to be
infringed if conductor tension was lost during the stringing, then the
work shall be stopped.
5.3 In the event of, or near approach of, a lightning storm, all work on the
conductors shall cease.
5 Weather Conditions
NSI 4 Guidance 5.1 NGET Control team shall inform the Competent Person of any
Section 2 change in lightning risk that has reached level 1 severity or other
5.1 to 5.3 weather conditions which could adversely affect the work.
5.2 Work on earthwire shall not proceed if the mean average hourly wind
speed is 15 mph or more, measured at a height of 10 metres above
ground level.
5.3 The Control Person (Operation) may request that the DAR be
restored on the Live circuit for the duration of the storm or until such
time as it is agreed work can resume. Personnel shall also keep a
minimum of 10 metres away from the overhead line and the stringing
equipment whilst a lightning storm is in the area.
© National Grid plc 2023 – All Rights Reserved Section 2 Safety Page 31
Uncontrolled when printed Requirements for Continuous
Tension Stringing of OHL
Phase Conductors and
Earthwire
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
APPENDIX A
Additional Authorisations
Senior Authorised Section 2-All Section 2-All
Person Additional
Authorisations
© National Grid plc 2023 – All Rights Reserved Appendix A Authorisation Page 32
Uncontrolled when printed Matrices for Personnel
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
© National Grid plc 2023 – All Rights Reserved Appendix A Authorisation Page 33
Uncontrolled when printed Matrices for Personnel
National Grid UK Electricity Transmission plc NGUK/PM/ETSR/NSI/04/GN
National Safety Instruction Guidance Issue 9
© National Grid plc 2023 – All Rights Reserved Appendix A Authorisation Page 34
Uncontrolled when printed Matrices for Personnel