Tender For AMF Panel
Tender For AMF Panel
Tender For AMF Panel
FOR
ISO 9001:2008
CORPORATION LTD.
M/s. -----------------------------------------------------------------
-------------------------------------------------------------
Sub: Supply, installation, testing and commissioning of AMF panel for 500 KVA
DG set at NSIC STP Complex, Okhla Industrial Estate, New Delhi -110020.
Sir,
The Tender should be signed on each page, dated and witnessed in all places
provided for in the documents; all other papers should be initialed.
This letter shall form part of the “CONTRACT” and must be signed
and returned along with the tender documents.
Yours faithfully
Encl. 35 Pages
Sealed item rate tenders are hereby invited on behalf of NSIC Ltd. from
experienced Contractors
2. The tenders should have completed minimum two works of similar nature
of minimum value of Rs. 3.00 lacs each or one work of Rs. 6.00 lacs in
their name, during last 5 years. Photocopies of the completion
certificates/award letters should be submitted along with the tender.
Completion certificate issued by the reputed organization / MNC shall also
be accepted. In case of certificates issued by the private party, copies of
TDS should also be enclosed. Similar nature means that bidder should
have executed the work of design, supply, erection, testing and
commissioning of AMF Panel/LT Panel/DG Set work.
3. Work of similar nature means “Supply, installation, testing and
commissioning of AMF Panel/LT Panel/DG Set work” as mentioned in the
schedule of work.
4. While applying for the tender document, the intending tenderers shall also
furnish valid work contract tax /sales tax/ VAT/TIN numbers as applicable.
5. The tender issuing authority reserves the right to issue or refuse to issue
the tender document to any party without assigning any reason.
7. NSIC reserves the right to reject all or any tender wholly or partly without
assigning any reason whatsoever.
S.
DESCRIPTION PAGES
NO.
4 APPENDIX 22
SPECIAL CONDITIONS 23
5
1.0 GENERAL
Tenderers are advised to inspect and examine the site and its
surroundings and satisfy themselves before submitting their tenders as to
site conditions, means of access to the site.
The tender complete in all respects shall be submitted along with Earnest
Money as stipulated in the Notice / Letter Inviting Tender ONLY. Tenders
without Earnest Money Deposit will be out rightly rejected.
I) Technical Bid
Name of work :
Tender no. :
Details of the minimum two works of similar nature of value of Rs.3.00 Lacs each
or one work of Rs 6.00 Lacs in their name, during last five years. Photocopies of
the completion certificates/award letters should be submitted along with the
tender. Completion certificate issued by the reputed organization / MNC shall
also be accepted. In case of certificates issued by the private party, copies of
TDS should also be enclosed.
Valid registration with Sales Tax department for Work Contract Tax/VAT/TIN.
Tender cost in requisite form if tender down loaded from the Website.
This envelope shall contain the tender document with PRICES and amount duly
filled by the party against each item prescribed in the Schedule of quantity
of tender document and no conditions (i.e. deviations / assumptions /
stipulations / clarifications / comments / any other request) whatsoever and the
conditional offers will be rejected.
If it is noticed that the unit rates quoted by the Tenderer for any items are
unusually high or unusually low, it will be sufficient cause for rejection of the
tender unless the Corporation is convinced about the reasonableness of the unit
rates on scrutiny of the analysis for such unit rate to be furnished by the tenderer
on demand.
5.0 DEVIATIONS TO TENDER CLAUSES:
Tenderers are advised to submit the tenderers strictly based on the terms and
conditions and specification contained in the Tender Documents and not to
stipulate any deviations. Conditional tenders are liable to be rejected.
Tender submitted by tenderers shall remain valid for acceptance for a minimum
period of 90 days from the date of opening of the tenders.
Corporation reserves the right to split the job into two or more parts and to award
the work to separate agencies/contractors. Work shall be awarded to the lowest
bidder, subject to the work experience and fulfillment of other terms & conditions
and specifications.
9.0 CORRECTIONS
The rates quoted by bidder shall remain firm till completion of all works
even during the extended period, if any, on any account what so ever. It is
provided that the contractor shall not change any of the rates, quoted in
the tender till the completion of work.
General Manager (Works)
GENERAL CONDITIONS OF CONTRACT
1. Where the context so requires, words importing the singular only also
include the plural and vice versa.
3. Inspection of Site:
The Contractor shall inspect and examine the Site and its surroundings
and shall satisfy himself before submitting his tender as to the nature of
the Site, the quantities and nature of work and material necessary for the
completion of the Works and the means of access to the Site, the
accommodation he may require and in general shall himself obtain all
necessary information as to risks, contingencies and other circumstances
which may influence or affect this tender.
4. Sufficiency of Tender:
All errors in totaling in the amount column and in carrying forward totals
shall be corrected.
6. Security Deposit:
Total security deposit shall be 10 % of the accepted tender cost and shall
be deposited within ten (10) days of receipt of the letter of
intent/notification of acceptance of the tender by him. The earnest money
deposited shall be converted into initial security deposit.
6.1 All compensation or other sums of money payable by the contractor under
the terms of this Contract or any other Contract or any other account
whatsoever may be deducted from the security deposit.
6.2 Refund of Security deposit: Security deposit refundable to the Contractor
worked out on the basis of the value of work completed shall be refunded
to the Contractor after defect liability period of 12 months on the Engineer-
In-Charge certifying in writing that the work has been completed
satisfactorily.
6.3 No interest shall be payable to the contractor on the Security Deposit
furnished/ recovered from the contractor, by the Corporation.
7.1 The time for completion of the works shall, in the event of any
deviations resulting in additional cost over the tendered value sum
being ordered, be extended if requested by the contractor, as follows:
ii) 25% of the time calculated in (i) above or such further additional
time as may be considered reasonable by the Engineer-in-Charge.
8. Deviation, Extra Items and Pricing
Rates for Extra/ Additional Items
ii) If the rate for any altered, additional or substituted item of work is
not specified in the schedule of Quantities, the rate for that item
shall be derived from the rate for the nearest similar item specified
therein.
iii) If the rate for any altered, additional or substituted item of work
cannot be determined in the manner specified in sub-paras (i), and
(ii) above, the contractor shall, within 7 days of the date of receipt of
the order to carry out the said work, inform the Engineer-in-Charge
under advice to the Accepting Authority of the rate which he
proposes to claim for such item of work, supported by analysis of
the rate claimed, and the Engineer-in-Charge shall, within fifteen
days thereafter, after giving due consideration to the rate claimed
by the Contractor determine the rate on the basis of market rate(s).
In the event of the contractor failing to inform the Engineer-in-
Charge within the stipulated period of time, the rate which he
proposes to claim, the rate for such item shall be determined by the
Engineer-in-Charge on the basis of market rate(s) and the same
shall be final. Payment of such items shall be made accordingly.
9.1 The time allowed for execution of the works as specified in the Appendix
or the extended time in accordance with these conditions shall be the
essence of the Contract. The execution of the works shall commence
from the 10th day after the date on which the Corporation issues written
orders to commence the work or from the date of handing over of the site,
which ever is earlier.
(f) Any other cause, which, in the absolute discretion of the authority
mentioned in Appendix, is beyond the Contractor’s control;
9.4 Then upon the happening of any such event causing delay, the Contractor
shall immediately give notice thereof in writing to the Engineer-in-Charge
but shall nevertheless use constantly his best endeavors to prevent or
make good the delay and shall do all that may be reasonably required to
the satisfaction of the Engineer-in-Charge to proceed with the Works.
10 The Contractor shall arrange, at his own expense, all tools, plant and
equipment hereafter referred to as (T & P) labour, P.O.L. &
electricity/water required for execution of the work.
11 FORCE MAJEURE
Any delays in or failure of the performance of either party herein shall not
constitute default hereunder or give rise to any claim for damages, if any,
to the extent such delays or failure of performance is caused by
occurrences such as Act of god or the public enemy; expropriation or
confiscation of facilities by Government authorities, or in compliance with
any order or request of any Governmental authorities or due acts of war,
rebellion or sabotage or fires, floods, explosions, riots or illegal joint strikes
of all the workers of all the contractors.
12 MATERIALS
13 Labour:
a.) The Contractor shall employ its labour in sufficient numbers to maintain
the required rate of progress and of quality to ensure workmanship of the
degree specified in the Contract and to the satisfaction of the Engineer-in-
Charge. The Contractor shall not employ in connection with the Works
any person who has not completed eighteen years of age.
c.) The Contractor shall pay to labour employed by him directly wages not
less than fair wages as per Minimum Wages Act. Fair Wage’ means
wages, which shall include wages for weekly day of rest and other
allowances whether for time or piece work, after taking into consideration
prevailing market rates for similar employment in the neighborhood but
shall not be less than the minimum rates of wages fixed under the
payment of Minimum Wages Act.
d.) The Contractor shall in respect of labour employed by him or his sub-
contractor comply with or cause to be complied with the Contractor Labour
Regulation in regard to all matters provided therein.
e.) The Contractor shall comply with the provisions of the payment of
Wages Act, 1936, Minimum Wages Act, 1948, Employers’ Liability Act,
1938. Workmen’s Compensation Act, 1923, Industrial Disputes Act, 1947,
Maternity Benefit Act, 1970 or any modification thereof or any other law
relating thereto and rules made there under from time to time.
f) The Contractor shall indemnify and keep indemnified the Corporation
against:
i) Any claim arising out of third party loss/ damage to life or property
caused by/ during execution of the work.
ii) Any claim arising out of loss/ damage to the workmen engaged by
the Contractor during execution of the work.
All work embracing more than process shall be subject to examination and
approval at each stage thereof and the Contractor shall give due notice to
the Engineer-in-Charge or his authorized representative when each stage
is ready. The Engineer-in-Charge or his representative shall have powers
at any time to inspect and examine any part of the Works and the
contractor shall give such facilities as may be required for such inspection
and examination, at manufacturers works if necessary.
15 Liquidated Damages for Delay
16.2 All instructions, notices and communications, etc., under the contract shall
be given in writing and if sent by registered post to the last known place of
abode or business of the Contractor shall be deemed to have been served
on the date when in the ordinary course of post these would have been
delivered to him.
If at any time after acceptance of the tender the Corporation shall decide
to abandon or reduce the scope of the works for any reason whatsoever
and hence not require the whole or any part of the Works to be carried out
the Engineer-in-Charge shall give notice in writing to that effect to the
Contractor and Contractor shall have no claim to any payment of
compensation or otherwise whatsoever, on account of any profit or
advantage which he might have derived from the execution of the works in
full but which he did not derive in consequence of the foreclosure of the
whole or part of the works.
16.4 The Contractor shall be paid at Contract rates full amount for works
executed at Site as certified by the Engineer-in-Charge.
17 Cancellation of Contract in Full or in Part:
If the Contractor:
a. At any time makes defaults in proceeding with the Works with due
negligence and continues to do so even after a notice in writing of 7 days
from the Engineer-in-Charge; or
19 Urgent Works:
If any Urgent work (in respect whereof the decision of the Engineer-in-
Charge shall be final and binding) becomes necessary and Contractor is
unable or unwilling at once to carry it out, the Engineer-in-Charge may by
his own or other workpeople carry it out, as he may consider necessary. If
the urgent work shall be such as the Contractor is liable under the contract
to carry out at his expenses, the expenses incurred on it by the
Corporation shall be recoverable from the Contractor and be adjusted or
set off against any sum payable to him.
20.2 All items having a financial value shall be entered in Measurement Book,
etc. prescribed by the Corporation so that a complete record is obtained of
all work performed under the contract.
20.3 Payments against running bills may be released subject to value of work
executed and measured being not less than Rs. 2.00 lac.
20.4 Payment will be made on actual measurement basis as carried out at the
site. The quantities given in the schedule of quantities are only
approximate and contractor will have to carry out the work as per the
increased/decreased quantity of work as per the directions of Engineer-in-
Charge, for which no extra claim over and above the tender rate will be
considered. For releasing the payment up-to accepted tender amount the
General Manager (Works) is the approving authority.
20.5 The Contractor shall, without extra charge, provide assistance with every
appliance, labour and other things necessary for measurements. In regard
to measurement, variation; the decision taken by the Engineer-in-charge
shall be final.
No escalation will be paid even in extended period, if any.
21 Methods of Measurement:
22 Income Tax/WCT/VAT
22.1 Income tax including surcharge if any, at the prevailing rate shall be
deducted from the Contractor’s bills as per the provision of Income Tax
Act.
22.2 The Contractor shall ascertain from the concerned commercial tax
department regarding the applicability of Works Contract Tax / VAT/TIN.
Necessary deductions will be made from the contractor’s bill as applicable.
If the contractor fails to pay the required sum within the aforesaid period of
30 days, the Engineer-in-charge shall have the right to sell any or all of the
contractors’ unused materials, constructional plant, implements, temporary
building at site etc. and adjust the proceeds of sale thereof towards the
dues recoverable from the contractor under the contract and if thereafter
there remains any balance outstanding, it shall be recovered in
accordance with the provision of the contract.
Except where otherwise provided for in the contract all questions and
disputes relating to the meaning of the specifications, designs, drawings
and instructions herein before mentioned and as to the quality of
workmanship or materials used onto work or as to any other question,
claim right matter or thing whatsoever in any way arising out of or relating
to the contract, designs drawings, specifications, estimates, instructions,
orders and these conditions or otherwise concerning the works, or the
execution or failure to execute the same whether arising during the
progress of the work or after the completion or abandonment thereof shall
be referred to the sole arbitration of the Chairman-cum-Managing Director
of the National Small Industries Corporation Ltd. and if the Chairman-
cum-Managing Director is unable or unwilling to act, to the sole arbitration
of some other person appointed by the Chairman cum Managing Director,
National Small Industries Corporation Ltd. willing to act as such arbitrator.
There will be no objection if the arbitrator so appointed is an employee of
the National Small Industries Corporation Ltd. and that he had to deal
with the matters to which the contract relates and that in the course of his
duties as such he had expressed views on all or any of the matters in
dispute or difference. The arbitrator to whom the matter is originally
referred being transferred or vacating his office or being unable to act for
any reason as aforesaid at the time of such transfer, vacation of office or
inability to act., Chairman and Managing Director, National Small
Industries Corporation Ltd. shall appoint another person to act, as
arbitrator in accordance with the terms of the Contract. It is also a term of
this contract that no person other than a person appointed by C.M.D.,
National Small Industries Corporation LTD., as aforesaid should act as
arbitrator and if for any reason, that is not possible, the matter is not to be
referred to arbitration at all.
The arbitrators may from time to time with consent of this party enlarge the
time, for making and publishing the award.
The work under the contract shall, if reasonably possible continue during
the arbitration proceedings and so payment due to payable to the
Contractor shall be withheld on account of such proceedings.
The award of the arbitrator shall be final, conclusive and binding on all
parties to this contract.
The cost of arbitration shall be borne by the parties to the dispute, as may
be decided by the arbitrator(s).
The Indian Laws shall govern this contract for the time being in force. The
courts at New Delhi / Delhi only shall have the jurisdiction
To
Signature of contractor………………………
………………………………
Dated………………………
Witness……………………
Date……………………….
Address……………………
……………………………
APPENDIX
1. Any facility not mentioned in this scope, but which is vital for erection and
commissioning of AMF Panel is assumed to be included in the scope of
work.
2. Electricity, if required, for erection at site will be provided free of cost at
NSIC substation. However, cable, T &P etc will have to be managed by
the contractor
3. Contractor has to ensure safety and provide adequate supervision.
4. During working at site, some restrictions may be imposed by Engineer-in-
Charge/Security staff of Corporation or Local Authorities regarding safety
and security etc., the contractor shall be bound to follow all such
restrictions/instruction & nothing extra shall be payable on this account.
5. No compensation shall be payable to the contractor for any damage
caused by rains lightening, wind, storm, floods Tornado, earth quakes or
other natural calamities during the execution of work. He shall make good
all such damages at his own cost; and no claim on this account will be
entertained.
6. The tender shall be based on Conditions of Contract and tenderers are
required to quote their own rates against each item in schedule of
quantities, which is enclosed. All rates shall remain firm for the contract
period/extended contract period.
7. If the contractor fails to proceed with the work within the stipulated time as
specified from the date of issue of letter of intent/letter to proceed with the
work, the Corporation shall forfeit the earnest money deposited by him
along with the tender.
8. All the works to be carried out in accordance with latest CPWD/BIS
Specifications and as per the directions of Engineer-in-charge.
9. COST OF TESTS
The contractor is bound to carry out the tests as per the
CPWD/BIS/Applicable codes guidelines for ascertaining the quality of the
works executed/ materials used as and when directed by the Engineer-in-
charge. The cost of preparing samples and carrying out tests for quality of
material or workmanship will be borne by the contractor except for such
exclusions as are specifically mentioned in the specifications laid down in
the contract. The cost of all test carried out in Laboratories as directed by
the Engineer-in-charge will be borne by the contractor.
b) Auto/Manual/Test/Off selector
switch
Make: Ceilzer/L&T/Havells
k) Restoration timer
make: L&T/Siemens
p) DG hour meter
make: Trinity or equivalent
7. One
Making of foundation platform of job
suitable size for above mentioned
AMF Panel with cement concrete of
1:1.5:3 complete as required.
8. 10
Supply and laying of 150mm GI Pipe mtr
in ground 75 cm below ground level
including excavation and refilling the
same etc complete as required.
Make:Jindal/Tata
Total:
A. Operation:-
3. When the main is restored, the relay should monitor the mains
for healthiness for 05 minutes. Disconnect the DG Supply and
connect the mains ACB ON.
The DG should stop after 1 minute (cool off time) and should go
on stand by mode again.
B. General Features:
The AMF panel shall be indoor type, floor mounted, dust and
vermin proof in sheet steel construction. The panel shall have
doors at the front and back for proper maintenance. The panel
shall have steel channel fabricated kick-plate and bolted type
cable gland plate fitted at the bottom. The panel shall be
constructed from 2 mm thick steel sheet. All the joints shall have
proper gaskets.
AMF Logic
• One Main supply voltage monitor
• One Alternator supply voltage monitor
• One set of DC control relays and timers
• One Set of control relays for the automatic control
system
Battery Charger
• One Battery charging transformer/ rectifier unit
• One DC Ammeter
• One DC Voltmeter
Indications
• Set running
• Set on Load
• Phase Indication
• Hour indication meter
C. Terminal Blocks and wiring
Terminal blocks of robust type and generally not less than 15 amps capacity,
250/500 volts grade for DC upto 100 volts and 660/1100 volts grade for AC
and rest of the junction shall be employed in such as manner so that they are
freely accessible for maintenance. All control and small wiring from unit to
unit inside the panel shall also be done with not less 2.5 sqmm copper
conductor PVC insulated and 660/1100 volts grade. All ends shall be
identified with ferrules at the ends.
D. Labeling:
E. Painting:
The entire panel shall be given primer coat after proper treatment and
powder coating with 7 tank process before assembly of various items.
F. Equipment requirements:-
The control cubical shall incorporate into assembly general equipment and
systems as under:-
a) Control system equipments and components such as relays,
contactors, timers etc. both for automatic operation on main failure
and as well as for manual operation.
b) Equipments and components necessary for testing generating sets
healthiness with test mode and with load on mains.
c) Necessary instruments and accessories such as voltmeter, power
factor meter, KW meter, KVAH/KWH Meter, Ammeter,
Frequency meter etc. in one energy analyzer unit with selector
switch to obtain the readings of desired parameters.
d) Necessary indication lamps, fuses, terminal blocks, push buttons,
control switches etc as required.
e) Necessary engine/generating set shut down devices due to
faults/abnormalities.
f) Necessary visual audio alarm indication and annunciation facility,
as specified.
g) Necessary battery charger.
h) Necessary excitation control and voltage regulating equipment.
i) Breakers as specified in the schedule of work.
G. System Operation:-
Following shut down and protection system shall be integrated in the control
panel:-
a) Engine:-
i) Over load
ii) Short circuit
iii) Earth fault
iv) Over voltage
J. Operating devices:-
a) Master engine control switch: this shall cut off in ‘OFF’ position
DC control to the entire panel, thus preventing start-up of engine
due to any cause. However, battery charger and lamp test button
for testing the healthiness of indication lamps, DC volt
meter/ammeter etc. shall be operative. It shall be feasible to lock
the switch in OFF position for maintenance and shut down
purposes.
b) Operation selectors switch OFF/AUTO/MANUAL/TEST position.
c) Energy analyzer unit for display of various electrical parameters
like voltage, current, frequency, KW, power factor etc.
d) A set of push button as specified.
e) Relays, contactor, timers, circuit breakers as required.
f) Necessary battery charger with boost/trickle selector, DC voltmeter
and DC ammeter.
LT CABLES
GENERAL
INSTALLATION OF CABLES
Cables shall be laid directly in ground, pipes, masonry ducts, on cable tray,
surface of wall etc. as indicated in BOQ and/or as per the direction of Engineer-
in-charge, and as per CPWD specifications.
INSPECTION
All cables shall be inspected at site and checked for any damage during transit.
JOINTS IN CABLES
The contractor shall take care to see that the cables received at site are
apportioned to various locations in such a manner as to ensure maximum
utilization and avoiding of cable joints. This apportioning shall be got approved
from Engineer-in-charge before the cables are cut to lengths.
At all changes in direction in horizontal and vertical planes, the cables shall be
bent smooth with a radius of bent not less than 12 times the diameter of cables.
Minimum 3 metre long loop shall be provided at both end of cable.
PROTECTION OF CABLES
The cables shall be protected by bricks laid on the top layer of the sand for the
full length of underground cable. Where more than one cables is laid in the same
trench, the bricks shall cover all the cables and shall project a minimum of
approximately 80mm on either side of the cables. Cable under road crossings
and any other places subject to heavy traffic shall be protected by running them
through Pipes of suitable size.
All excavation and back fill required for the installation of the cables shall be
carried out by the Contractor in accordance with the drawings and requirements
laid down elsewhere. Trenches shall be dug true to line and grades. Back fill for
trenches shall be filled in layer not exceeding 150 mm. Each layer shall be
properly rammed and considered before laying the next layer.
The contractor shall restore all surface, roadways, side walks, kerbs wall or the
works cut by excavation to their original condition to the satisfaction of the
Engineer-in-Charge.
TESTING OF CABLES
On completion of cable laying work, the following tests shall be conducted in the
presence of the Engineer-in-Charge.
All tests shall be carried out in accordance with relevant Indian Standard code of
practice and Indian Electricity Rules. The Contractor shall provide necessary
instruments, equipments and labour for conducting the above tests & shall bear
all expenses of conducting such tests.
PROTECTIVE EARTHING
The scope of work shall cover earthing stations, laying copper/GI earth strips and
connecting the power panels, DBs and switch boards.
The work shall be done as per the CPWD specification
Materials of which the protective system is composed shall be resistant to
corrosion or be adequately protection against corrosion. All apparatus and
equipment transmitting or utilizing power shall be earthed.