Electrical Tender Specfication
Electrical Tender Specfication
Electrical Tender Specfication
iii ) Criteria for the Prequalification for the Project : Applicant has to pass the below mentioned criteria, each criteria will lead applicant to next stage. Applicant must fulfil all the criteria mentioned below. Applicant must submit the attested supporting document to support all his claims. a) Eligibility : 1) Applicant must in electrical contract business from last 5 years as on 30th September, 2008 & also have the electrical contractor licence. 2) Applicant must be registered contractor with the R & B Department of the Govt. Of Gujarat & must be listed in or above B grade contractor list or Contractor who have worked minimum 3 nos. of the similar Kind & magnitude project. 3) Joint Venture formed between two or more electrical contractor for this project will not be accepted b) Financial : c) 1) The Applicants audited gross financial turnover in the Electrical Installation work computed as average of the last three financial years should be over 100 lacs. 2) The applicant must have completed the 1 single electrical installation work of the 45 lacs during the last 3 financial years. Applicant must attach the order copy & completition certificate for the same. 3) The Applicants organisation must be profit making organisation.
d) Technical : 1) The applicant should have completed minimum 2 nos. of the similar magnitude & Class of the project. 2) The applicant should give the information about their organisation, technical experience, technical & supportive staff, spare capacity and their competency. iv ) Instruction : 1) Following document should be attached in following order by the applicant with the prequalification bid document ( On A4 document & initialled on every page ). Complete Organization profile with the detail CV of the Partner / Directors & key persons in the organisation with the organisation chart. Address, Contact Details. Electrical Contractors Licence no. & registration document Pan No. of the Organisation with the Income Tax clearance certificate. Sales Tax (VAT) No. & Clearance certificate. Audited balance sheet of the last 3 years & a separate sheet showing the Annual gross Turnover of the company for the last 3 years attested by the Partner / Director Details of the Bank Facilities : Over Draft, Bonds & Guarantee, Letter of Credit, Solvency certificate of the 75 lacs etc Previous Experience of projects. List of the Completed Projects ( Maintenance Contract & Only Supply tender will not be considered ) with the cost & completion Certificate. List of the on going Project with the cost & Work Order. List of the completed Similar Magnitude & class of the project with the Completion Certificate & cost. List of the on going Similar Magnitude & class of the project with the work order & cost (If any). ( Above all project details should be given with the following details ) i. Name of the Project & Year ii. Clients Name Contact Details. iii. Architect & Consultants Name iv. Value & time Period. v. Nature of the work.
-2-
Applicant should have the following policies. ( Details should be given ) i. Workman full compensation ii. Contractors all risk policies Even though the bidders meet the above qualifying criteria, they are subject to be disqualified if they have made misleading or false representations in the forms, statements and attachments submitted in proof of the qualification requirements; and/or record of poor performance such as abandoning the works, not properly completing the contract, inordinate delays in completion, litigation history, or financial failures etc., and/or All pending litigation shall be treated as resolved against the bidder and so shall in total not represent more than 10% of the Bidders net worth.
Page No.
1 2 3 4 5 6 Part B
M V Cable Distribution Board Internal Wiring Light Fixtures Earthing Telephone & Data Distribution Testing
1 4 6 11 15 18 20 21
PART C ERECTION, TESTING & COMMISSIONING OF ELECTRICAL INSTALLATIONS Part D Make of Material
35
-4-
1.2
Indian Electricity Act and Rules. 1.3 MEASUREMENTS The cables will be measured in meters. The unit rate shall include cutting the cable into required lengths, packing , loading , unloading, insurance, transportation, delivery to stores/site as per work order, stocking in stores, testing of cables at stores etc. of medium voltage cable. GENERAL The medium voltage cables shall be supplied, laid, connected, tested and commissioned in accordance with the drawings, specifications, relevant Indian Standards specifications, manufacturers instructions. The cables shall be delivered at site in original drums with manufacturers name, size, and type, clearly written on the drums. MATERIAL Medium voltage cable shall be PVC insulated. PVC sheathed, aluminium or copper conductor, armoured and unarmoured heavy duty, conforming to IS : 694 Part I & II, IS : 1554 Part I. TYPE : The cables shall be circular, multi core, annealed copper or aluminium conductor, PVC insulated and PVC sheathed, armoured or unarmoured. CONDUCTOR : Uncoated, annealed copper / aluminium, of high conductivity upto 4 mm. size, the conductor shall be solid and above 4 mm., conductors shall be concentrically stranded as per IEC : 228. INSULATION : Polyvinyl chloride (PVC) rated 70 c. extruded insulation as per IEC : 502. CORE IDENTIFICATION : Two core Three core Four core Single core
1.4
1.5
1.5.1
1.5.2
1.5.3
1.5.4
: : : :
Red and Black Red, Yellow and Blue Red, Yellow, Blue and Black Green, Yellow for earthing
Black shall always be used for neutral. 1.5.5 ASSEMBLY : Two, three or four insulated conductors shall be laid up, filled with nonhygroscopic material and covered with an additional layer of thermoplastic material.
-5-
1.5.6
ARMOUR : Galvanised steel flat strip / round wires applied helicaly in single layers complete with covering the assembly of cores. For cable size upto 25 Sq. mm. For cable size above 25 Sq. mm. : Armour of 1.4 mm dia G.I. round wire : Armour of 4 mm wide 0.8 mm thick G.I. strip
1.5.7
SHEATH : Polyvinyl chloride (PVC), 70 deg.c. rated extruded as per IEC : 502. Inner sheath shall be extruded type and shall be compatible with the insulation provided for the cables. Outer sheath shall be of an extruded type layer of suitable synthetic material compatible with the specified ambient and operating temperature of cables. The sheath shall be resistant to water, ultraviolet radiation, fungus, termite and rodent attacks. The colour of outer sheath shall be black.
1.5.8
RATING : Upto and including 1100 Volts. GENERAL All cables shall be adequately protected against any risk of mechanical damage to which they may be liable in normal conditions of handling during transportation, loading, unloading etc. The cable shall be supplied in single length i.e. without any intermediate joint or cut unless specifically approved by the client. The cable ends shall be suitably sealed against entry of moisture, dust, water etc. with cable compound as per standard practice.
1.6
1.7 1.1.1
TESTING FINISHED CABLE TESTS AT MANUFACTURERS WORKS : The finished cables shall be tested at manufacturers works. Following routine tests for each and every length of cable and copy of test results shall be furnished for each length of cable alongwith supply. If specified, the cables shall be tested in presence of clients representative. VOLTAGE TEST : Each core of cable shall be tested at room temperature at 3 KV A.C. R.M.S. for a duration of 5 minutes. CONDUCTOR RESISTANCE TEST : The D.C. Resistance of each conductor shall be measured at room temperature and the results shall be corrected to 20 c. to check the compliance with the values specified in IS 8130 1976. Prior to despatching cables, and at the time of delivering the cables at stores, following tests shall be carried our : Insulation Resistance test between phases and phase to Neutral and phase to earth. Continuity test of all the phases, neutral and earth continuity conductor. Sheathing continuity test. Earth resistance test of all the phases and neutral.
(a)
(b)
1.1.2
-6-
All tests shall be carried out in accordance with relevant Indian Standard Code of practice and Indian Electricity Rules. The Ven dor shall provide necessary instruments, equipments and labour for conducting the above test and shall bear all expenses in connection with such tests. All tests shall be carried our in the presence of the client and results shall be recorded in the prescribed forms. 1.8 CABLE MARKING EMBOSSING ON OUTER SHEATH : The outer sheath shall be legibly embossed with following legend : ELECTRIC CABLE : 1100 V, SIZE : 3.5 C x mm . Manufacturers Name & year of manufacturing. 1.9 SEALING, DRUMMING & PACKING After tests at the manufacturers works, both ends of the cable shall be sealed to prevent the ingress of moisture during transportation and storage. Cable shall supplied in length of 500 10% meters on packed nonreturnable drums of sufficiently sturdy construction. Cables of length more than 250 meters shall also be supplied on nonreturnable drums. The spindle hole shall be 110 mm minimum diameter. Each drum shall bear on the outside flange, legibly and indelibly in the English literature, a distinguishing number, the manufacturers name and particulars of the cable i.e. voltage grade, length, conductor size, cable type, insulation type and gross weight shall also be clearly visible. The direction for rolling shall be indicated by an arrow. The drum flange shall also be marked with manufacturers name and year of manufacturing etc.
-7-
2.0
DISTRIBUTION BOARDS
1)Scope : It includes supply & Installation ,commissioning, Distribution Boards standard company fabricated or to be fabricated by fabricator. 2) Standards : AS PER SCHEDULE OF INDIAN STANDARDS, ATTACHED IN THE DOCUMENT. 3) Distribution Boards : 4) Distribution boards along with the controlling MCBs/Fuse or Isolator as shown shall be fixed in an M.S. Box with hinged door suitable for recessed mounting in wall. Distribution boards shall be made of 18 SWG steel sheet duly rust inhibited through a process of de greasing, acid pickling, phosphating and powder coated to an approved colour of adequate micron rating duly approved by architect/consultant. Three phase boards shall have phase barriers and a wire channel on three sides. Neutral bars shall be solid tinned copper bars with tapped holes and chase headed screws. For 3 phase DBs, 3. independent neutral bars shall be provided. All DBs shall be internally pre wired using copper insulated PVC wires brought to a terminal strip of appropriate rating for outgoing feeders. 5) Conduit knockouts shall be provided as required/shown on drawings and the entire board shall be rendered dust and vermin proof with necessary sealing gaskets. The top and bottom side of DB should be detachable. 6) MCBs shall have quick make and break nonwelding self wiping silver alloy contacts for 10 KA short circuit both on the manual and automatic operation. Each pole of the breaker shall be provided with inverse time thermal over load and instantaneous over current tripping elements, with tripfree mechanism. In case of multipole breakers, the tripping must be on all the poles and operating handle shall be common. Breakers must conform to BS 3871 with facility for locking in OFF position. Pressure clamp terminals for stranded/solid conductor insertion are acceptable upto 4 sq.mm. aluminum or 2.5 sq.mm. copper and for higher ratings, the terminals shall be suitably shrouded. Wherever MCB isolators are specified they are without the tripping elements. 7) Fuses shall be HRC link type rewireable with necessary fuse carriers and with rating of not less than 25 MVA. Bottle type fuses are not acceptable. Fuse carrier terminals shall be suitably shrouded. Rewireable fuse carriers shall be porcelain. HRC fuses for motor duty should be time lag type. 8) Distribution boards shall have HRC/rewireable fuses as shown on the schedule and drawings. Board shall meet with the requirements of IS 2675 and marking arrangement of busbars shall be in accordance with I.S. standards. Bus bars shall be suitable for the incoming switch rating and sized for a temperature rise of 35 C over the ambient. Each board shall have two separate earthing terminals. Circuit diagram indicating the load distribution shall be pasted on the inside of the DB as instructed. One earthing terminal for single phase and two terminals for 3 phase DBs shall be provided with an earth strip connecting the studs and the outgoing ECU earth bar. 9) In the case of MCB distribution boards, the backup fuses wherever shown shall be not less than 63 A with a delayed characteristic and a minimum prearcing time of 0.5 sec. At 9 KA/3 KA fault current.
-8-
10) All outgoing feeders shall terminate on a terminal strip which in turn is interconnected to the MCB/Fuse base by means of insulated single conductor copper wires as follows : Upto 15 A 25 A 32 A 2.5 sq.mm. 4.0 sq.mm. 6.0 sq.mm. 63 A 40 A 10 sq.mm. 16 sq.mm.
11) RCCB / MCB : A The RCCB should suffices all the requirements of IS as per code IS 12640 1988. The RCA should be current operated and not on line voltage. The RCCB should ensure mainly the following functions. Measurement of the fault current value. Comparison of the fault current with a reference value. C The RCCB should have a torroidal transformer witch has the main conductors of primary (P N) which check the sum of the current close to zero. All metal parts should be inherently resistant to corrosion and treated to make them corrosion resistant. It should be truly current operated. It should operate on core balance torroidal transformer. Its accuracy should be 5 %. It should operate even in case of neutral failure. It should trip at a present leakage current within 30 M.S. Its enclosure should be as per IP 30. Its mechanical operation life should be more than 20,000 operations. It should provide full protection as envisaged by IE rules 61A, 71 ee, 73 ee, 1985 and also rule 50 of IE rule1956. It should conform to all national and international standards like IS 8828 : 1993, IS 12640 1988, BS 4293 1983, CEE 27 (International commission Rules for the approved of electrical equipment).
E F G H I J K L
-9-
3.0
INTERNAL WIRING
This section covers, definition of point wiring, system of wiring and supply, installation, connection, testing and commissioning of point wiring for light points, ceiling fan points, exhaust fan points, convenience socket outlet points, power socket outlet points etc. including fixing of light fixtures, ceiling fan, exhaust fan, wall fan etc.
1.1
STANDARDS The following standards and rules shall be applicable : STANDARD NO. IS : 732 IS : 1646 IS : 2509 IS : 6946 IS : 1293 IS : 8130 IS : 3854 IS : 3415 IS : 4648 PARTICULAR Code of practice for electrical wiring installation (System voltage not exceeding 650 V) Code of practice for fire safety of buildings (General) Electrical installation. Rigid nonmetallic conduits for electrical wiring. Flexible (Pliable) nonmetallic conduits for electrical installation. 3 pin plugs and sockets. Specifications of conduits for electrical installation. Switches for domestic purpose. Fittings for rigid nonmetallic conduits. Guide for electrical layout in residential building Indian electricity act and rules.
Regulations for the electrical equipment in buildings issued by the Bombay Regional Council of Insurance Association of India. All standards and codes mean the latest. 1.2 POINT WIRING A point shall consist of the branch wiring from the distribution board together with a switch as required, including the ceiling rose or pendant holder or swan holder, or ceiling fan box or socket or suitable termination. A point shall include, in addition, the earth continuity conductor / wire from the distribution board to the earth pin / stud of the outlet / switch box and to the outlet points. The point wiring shall be carried out in the under mentioned manner : 1.2.1 1.2.2 1.2.3 1.2.4 Supply, installation, fixing of conduits with necessary accessories, junction / pull / inspection / switch boxes and outlet boxes. Supplying and drawing of wires of required size including earth continuity wire. Supply, installation and connection of flush type switches, sockets, cover plates, switch plates, etc. The point shall be complete with the branch wiring from the Switch board to the outlet point, Pre laid conduit with accessories, junction, pull, inspection boxes, control switch, socket, outlet boxes, ceiling roses, button / swan holder, connector etc.
1.3
POINT RATE The rate per point shall include supply, installation, connection, testing and commissioning of point as described under point wiring. The measurements of the points will be enumerated.
- 10 -
Circuit Mains shall not be paid extra. Rate for the point shall consist of wiring from the out let point to the switch board as required with a connector/ plate/ ceiling rose fan box with hook socket with switch. The point rate shall include in addition to phase and neutral wire a PVC insulated earth continuity wire from switch to outlet. The unit rate for the point shall consist of the circuit wiring form LDB to outlet point through switch and/or socket, switch board as required and including the outlet points with connector, fan hook box or sockets. A point shall include in addition to phase and neutral wire a PVC insulated Earth continuity wire from LDB to the final termination at outlet points. No extra rate shall be paid for circuit mains for looping switch board to switch board. . 1.4 SYSTEM OF WIRING Unless otherwise mentioned on the drawings, the system of point wiring shall be as follows: The system of wiring shall consist of single core, PVC insulated, 650/1100 volt grade, copper conductor FRLS wires laid through exposed (surface mounted) PVC conduits as directed. 1.5 GENERAL The contractor shall submit for approval, the shop drawing of conduit layout indicating the route of the conduits, number and size of the conduits, location of junction / inspection / pull / outlet boxes, size and location of switch boxes, number and size of wires pulled through each conduit and all other necessary relevant details prior to laying of conduits. Only after the drawings are approved, the contractor shall proceed the work of conduit laying. MATERIAL PVC CONDUITS : All nonmetallic PVC conduits shall conform to IS : 9537. The conduit shall be plan and type as specified in IS : 9537 and shall be used with the corresponding accessories (Refer IS : 3419 specification for fittings for rigid non PVC metallic conduits). PVC conduits shall be rigid unplasticised, heavy gauge having 2.0 mm. wall thickness upto 20 mm. diameter conduit and 2.5 mm. wall thickness for all sizes above 20 mm. diameter. BOXES : All the boxes for switches, sockets and other receptacles, junction boxes, pull boxes and outlet boxes shall be fabricated from 2.0 mm. thick mild sheet painted with two coats of redoxide and then two coats of enamel paints as called for. Colour of the paints shall be as approved by the client.The boxes shall have smooth external and internal finished surface. Boxes in contact with earth or exposed to the weather shall be of 2 mm. mild steel and hot dip galvanized after fabrication. Separate screwed earth terminal shall be provided in the box for earthing purpose. All boxes shall have adequate no. of knock out holes of required diameter for conduit entry. Switch boxes to receive switches, socket outlets, power outlets, telephone outlets, fan regulators, etc. shall be fabricated to the approved shape and size to accommodate all the devices without overcrowding. Outlet boxes to receive ceiling fan shall be fitted with adequately sized rod / hook to fix ceiling fan. The boxes shall be of minimum depth of 65 mm. COVER PLATE : The cover of the boxes to receive outlet points shall be of best anodized sheet cut to shape and size or plate of approved manufacturers of switches. CABLES : The cables shall conform to IS : 694. For all internal wiring FRLS wires of 650 / 1100 volts grade, single core shall be used. The conductors shall be plain annealed copper conductors complying with IS : 1554. The conductors shall be circular copper conductor. - 11 -
1.6 1.6.1
1.6.2
1.6.3
1.6.4
The insulation shall be XLPE compound complying with the requirements of IS : 694. It shall be applied by an extrusion process and shall form a compact homogenous body. The thickness of XLPE insulation shall be as set out in the relevant standards The cores of all cables shall be identified by colours in accordance with the following sequence. Single phase Three phase Neutral Earth Red Red, Yellow, Blue Black Green or Green/Yellow
Means of identifying the manufacturer shall be provided throughout the length of cable. Unless otherwise specified in the drawings the size of the cables used for internal wiring shall be as follows : In case of circuit wiring for lights, exhaust fans,convenience socket outlet points (P+N+E) : 2 nos. of 2.5 mm. + 1 no. of 1.5 mm. boards. 3 nos. of 1.5 mm. 2 nos. of 4.0 mm. + 1 no. of 2.5 mm. socket. 1.6.5 From MCB at Panel/DB to switch From switch boards to outlet points From MCB at Panel/DB to 16/20 Amp
SWITCHES : Switches shall conform to IS : 3854, IS : 1293 and IS : 4615. The switches shall be single pole, single or two way and shown on the drawings or as specified. They shall be of moulded type rated for 250 volt, and of full 5 / 15 A capacity. They shall be provided with insulated dollies and covers. The switches shall be rocker operated with a quite operating mechanism with bounce free snap action mechanism enclosed in an arc resistant chamber. The switches shall have pure silver and silver cadmium contacts. The switches shall be flush moduler type The make of the switches shall be as indicated in the drawings or BOQ or make of material or as suggested and approved by the client. The switches installed in outdoor area shall be industrial, metal clad type, and shall be provided in weather proof enclosures, complete with weather proof gasketed covers.
1.6.6
SOCKETS : The sockets shall conform to IS : 1293. Each socket shall be provided with control switch of appropriate rating. The sockets shall be moulded type, rated for 250 volts, and either of full 5 A or 15 A capacity, as mentioned on the drawings. Sockets shall be of three pin type, the third in being connected to earth continuity conductor. The socket shall be flush modular type. The sockets installed in machine room, plant room or wet / damp area shall be metal clad weather proof type. The finishing and make of all the sockets shall be same as light switch. The socket shall have fully sprung contacts and solid brass shrouded terminals to ensure positive electrical connections. The sockets shall be provided with automatic shutters, which opens only when earth pit of the plug inserts in the socket. The socket shall be provided with three pin plug top suitable to the socket and of the same make as socket.
- 12 -
1.7
DRAWING OF CONDUCTORS The drawing and joining of copper conductor or wires shall be executed with due regard to the following precautions, while drawing insulated wires into the conduits, care shall be taken to avoid scratches and kinks which may cause breakage of conductors. There shall be no sharp bends. Insulation shall be shaved off for a length of 15 mm at the end of wire like sharpening of a pencil and it shall not be removed by cutting it square or ringing. PVC insulated copper conductor wire ends before connection shall be properly soldered (at least 15 mm length) with soldering flux / copper solder, for copper conductor. Strands of wires shall not be cut for connecting to the terminals. The connecting brassscrews shall have flat ends. All looped joints shall be soldered and connected through terminals block / connectors. The pressure applied to tighten terminal screws shall be just adequate, neither too much nor too less. Conductors having nominal cross section are exceeding 4 sq. mm shall always be provided with crimping type cable sockets. At all bolted terminals, brass flat washer of large area and approved steel spring washers shall be used. Brass nuts and bolts shall be used for all connections. Only certified wire man and cable jointers shall be employed to do joining work. For all internal wiring PVC insulated wires of 650 / 1100 volts grade shall be used. The sub circuit wiring for point shall be carried out in looping system and no joint shall be allowed in the length of the conductors. No wire shall be drawn in to any conduit, until all work of any nature that may cause injury to wire is completed. Care shall be taken in pulling the wires so that no damage occurs to the insulation of the wire. Before the wires are drawn into the conduits the conduits shall be thoroughly cleaned of moisture, dust, and dirt or any other obstruction by forcing compressed air through the conduits. JOINTS The wiring shall be by looping back system, and hence all joints shall be made at main switches, distribution boards, socket outlets, lighting outlets and switch boxes only. No joints shall be made inside conduits and junction boxes. Joints where unavoidable , due to any specified reasons, prior permission in writing shall be obtained from the client before making such connections. Joints by twisting conductors are prohibited. LOAD BALANCING Balancing of circuit in three phase installation shall be planned before the commencement of wiring and shall be strictly adhered to. EARTHING All earthing systems shall be in accordance with IS : 3043 1985 code of practice for earthing. TESTING OF INSTALLATION Before a completed installation is put into service, the following tests shall be complied with INSULATION RESISTANCE The insulation resistance shall be measured by applying 500 volt megger with all fuses in places, circuit breaker and all switches closed. The insulation resistance in gegohms of an installation, measured shall not be less than 50 megohms divided by the number of points on the circuit. The insulation resistance shall be measured between EARTH TO PHASE EARTH TO NEUTRAL PHASE TO NEURAL PHASE TO PHASE
1.8
1.9
1.10
1.11
1.11.1
- 13 -
1.11.2
EARTH CONTINUITY PATH : The earth continuity conductors shall be tested for electrical continuity and the electrical resistance of the same along with the earthing lead but excluding any added resistance or earth leakage circuitbreaker, measured from the connection, with the earth electrode to any point in the earth continuity conductor in the completed installation and shall not exceed one ohm.
1.11.3
POLARITY OF SINGLE POLE SWITCHES : A test shall be made to verify that every nolinked, single pole switch is connected to one of the phase of the supply system.
1.11.4
COMPLETION CERTIFICATES : All the above tests shall be carried out in presence of client and the results shall be recorded in a prescribed forms. Any default during the testing shall be immediately rectified and that section of the installation shall be re tested. The completed test result from shall be submitted to the client for approval. On completion of an electric installation a certificate shall be furnished by the contractor, countersigned by the certified supervisor under whose direct supervision the installation was carried out. This certificate shall be in a prescribed form as required by the local electric supply authority.
- 14 -
4.0
1.1
SCOPE : Scope of work under this section shall include inspection at suppliers/manufacturers premises at site, receiving at site, safe storage, transportation from point of storage to point of erection, erection and commissioning of light fittings, fixtures and accessories including all necessary supports, brackets, down rods and painting etc as required. STANDARDS : The lighting and their associated accessories such as lamps, reflectors, housings, ballasts etc., shall comply with the latest applicable standards, more specifically the following:
General and safety requirements for Luminaires : Part1 Tubular flourescent lamps Industrial lighting fittings with metal reflectors Decorative lighting outfits Bayonet lamp holders Bipin lamp holders for tubular fluorescent lamps Electronic Ballasts for fluorescent lamps General & Safety requirement Electronic Ballasts for fluorescent lamps Performance requirement Ballast for HP MV lamps Tubular Fluorescent lamps Luminaries General requirement Luminaries Constructional requirement Luminaries Screw and Screwless termination Luminaries Methods of Tests Particular requirement General purpose Luminaries 1) Particular requirement Recessed Luminaries 2) Particular requirement Luminaries for Road and Street lighting 3)
1.2
IS 13021 (Part1)
IS 13021 (Part2) IS 6616 IS 2418 (Part1 to 4) IS 10322 (Part1) IS 10322 (Part2) IS 10322 (Part3) IS 10322 (Part4) IS 10322 (Part5/Sec
IS 10322 (Part5/Sec
IS 10322 (Part5/Sec
Particular requirement Portable General purpose Luminaries (Part5/Sec4) Particular requirement Flood Lighting 5)
IS
10322
IS 10322 (Part5/Sec
- 15 -
High pressure mercury vapour lamps Tungsten filament general electric lamps
1.3
LIGHT FITTINGSGENERAL REQUIREMENTS : a). Fittings shall be designed for continuous trouble free operation under atmospheric conditions without reduction in lamp life or without deterioration of materials and internal wiring. Degree of protection of enclosure shall be IP65 for outdoor fittings except bulkhead fitting. Bulkhead fitting shall be provided with IP54 protection. b) Fittings shall be so designed as to facilitate easy maintenance including cleaning, replacement of lamps/ ballasts. All fittings shall be supplied complete with lamps. All mercury vapour and sodium vapour lamp fittings shall be complete with accessories like ballasts, power factor improvement capacitors, starters, etc. Out door type fittings shall be provided with weather proof junction boxes (IP55) and IP54 Control gear boxes. Each fitting shall have a terminal block suitable for loopout connection by 1100 V PVC insulated copper conductor wires upto 4 sq.mm. the internal wiring should be completed by the manufacturer by means of standard copper wire and terminated on the terminal block. All hardwares used in the fitting shall be suitably plated or anodized and passivated. Earthing : Each lighting fitting shall be provided with an earthing terminal. All metal or metal enclosed parts of the housing shall be bonded and connected to the earthing terminal so as to ensure satisfactory earthing continuity throughout the fixture. Painting/Finish : All surfaces of the fittings shall be thoroughly cleaned and degreased and the fittings shall be free from scale, rust, sharpedges, and burns. The housing shall be powder coated/stoveenamelled or anodised as required. The surface shall be scratch resistant and shall show no sign of cracking or flaking when bent through 90 deg. over 12 mm dia mandrel. Metal used in BODY of lighting fixtures shall be not less than 22 SWG or heavier if so required to comply with specification of standards. Sheet steel reflectors shall have a thickness of not less than 20 SWG. The metal parts of the fixtures shall be completely free from burns and tool marks. Solder shall not be used as mechanical fastening device on any part of the fixture.
c).
d)
e) f)
g)
h)
i)
1.4.
LIGHT FITTINGS SPECIAL REQUIREMENTS Box Channel Type Industrial Fittings Box type slim line channel must be in screw less construction manufactured from M.S. CRCA sheet steel powder coated with MS CRCA cover, powder coated white. Light reflection surface in Box/Channel type fittings shall be in a POLYESTER PRECOATED STEEL having a reflection factor of not less than 80%. SCREWLESS DESIGN & CONSTRUCTION Light fixtures shall be preferred due to their ease of maintenance, especially for box/channel for box/channel type fixtures. Moisture Proof Industrial Fittings Surface mounted totally enclosed moisture proof fixtures must be in polycarbonate body and diffuser with transparent prismatic interior and smooth exterior and frosted end. Fixture must be completely sealed with polyerethane double gasket to achieve IP 65 protection. Fixture is complete with CRCA steel white powder coated / enameled finish reflector.
- 16 -
18 W / 36 W Fluorescent and 36 W CFL Low Glare Light Fittings Recessed mounted, modular fluorescent lighting fixture made of CRCA Sheet steel powder coated (white) housing, electro chemically brightened and anodised reflector, three dimensional cross louvers with concave contours, fresnel top at louver saddle to increase efficiency. The luminance of <200 cd/M2 at 63 degree viewing angle in all directions so as to confirm Cat2 classification of CIBSELG3 Highbay Industrial Fittings Industrial Highbay luminaries shall be provided with pressure die cast housing along with all accessories, orthocyclically woundopien construction ballast, capacitor & semi parallel ignitor connected to terminal block and mounted on the gear plate. The gear shall have side entry for ease in maintenance. The spun aluminium reflector is suitable for narrows well as wide beam distribution. The luminaire will be suitablefor metal halide lamp HPI BU + 250 W which has 25500 lumens and 2.5 min restrike time (when operate with son gear). 1.5 ACCESSORIES FOR LIGHT FITTINGS REFLECTORS The reflectors shall be made of CRCA sheet steel/aluminium /Silvered glass/Chromium plated sheet copper as required. The thickness of reflectors shall be as per relevant standards. Reflectors made of steel shall have stove enameled/ vitreous enameled/epoxy coating finish. Aluminium used for reflectors shall be anodized/epoxy stove enameled /mirror polished. The finish for the reflector shall be as specified. The reflectors shall be free from scratches / blisters and shall have a smooth and glossy surface having optimum light reflecting coefficient. Reflectors shall be readily removable from the housing for cleaning and maintenance without use of tools. 1.6 1.6.1 LAMPS TLD Lamp shall be environment friendly low pressure mercury discharge lamp with mercury content less than or equal to 5 mg. The lamp shall have minimum lumen maintenance of 85 and CRI of 85. The lamp must comply to ROSH (Restriction of Hazardous substances) and covered by WEEE. Lamp should be fully recyclable. The lamp should be low on maintenance with life of 40 K hours in case of electromagnetic ballast and 65 K hours in case of HF ballast upto 10% failure. The discharge glass shall be lead free. TLD Lamps shall be minimum triphosphor type and have bipin bases. Colour spectrum of light shall be equivalent to PHILIPS color 84 or color 86 color 82 or OSRAM color 21 or color 11 or color 41 (as required at site) . The fluorescent Tubes (TLD) should have cool daylight colour designation. But Architects reserve the right to prescribe either Cool Daylight or Bright White or Incandescent Colour Designations for TLD. NO extra payment will be made over the quoted rate of bidder for this. The 36 W fluorescent tubes will have Nominal Luminous Flux of not less than 3350 lumens whether so mentioned in the Schedule of Quantities or not. T 5 HIGH EFFICIENCY ECOFRIENDLY LAMPS T5 lamp shall be environment friendly low pressure mercury discharge lamp with mercury content less than or equal to 3 mg. lamp should have lowest CO2 emission compared to any other comparable light source (40% less than a TLD standard lamp, 26% less than TLD / 80). T5 lamp shall be 100% lead free. T5 lamp shall be designed for operation with electronic gear and well suited for dimming. Maximum lumen output to be reached at approx 35oC in free burning position. T5 lamp can be ignited from 15oC to + 50oC. Lamp should be fully recyclable and must comply to ROSH (Restriction of Hazardous substances) and shall be covered by WEEE. T5 shall have 16 mm in diameter service life of TL5 lamp should be 10%
- 17 -
more than TLD lamps. T5 lamp shall have lumen efficacy of upto 104 Lux / W and shall have excellent colour rendering to En 12464 (Ra 80 to 89). 1.6.2 Compact fluorescent lamp shall have same luminous flux and power consumption as fluorescent tubes but less than half the length and more compact than Ushaped and circulator lamps. CFL shall be suitable for use with conventional control gear & standers and for HF electronic control gear. CFL lamp shall be non integral type of OSRAM / GE / PHILIPS/ Havells Sylvania only. HIGH FREQUENCY ELECTRONIC BALLAST High frequency electronic ballast shall be used with fluorescent / Compact Fluorescent Lamps wherever specified in the schedule of quantities. High frequency electronic ballast shall comply to the following: IEC 927, IEC 928 for 10% total harmonic distortion. EMI / RFI Confirming to FCC / VDE Class A/B. Line Transient as per IEEE C62.41. Ballast Crest Factor C1.7%. No Stroboscopic Effect Constant Wattage / Light output between 240 V 10%. Circuit protection for surge current and inrush current. Short circuits, open lamp protection PF > 0.99 for fluorescent / T5 lamp and 70.95 for CFL. Deactivated lamp protection Suitable for use with single and twin lamps RFI < 30 MHz EN 55015 Total Harmonic Distortion (THD) 10% Immunity to interference EN 61547 Safety EN 60928 / IEC 928 / IS 13021 (Part I) Performance EN 60929 / IEC 929 / IS 13021 (Part II) Vibrations & Bump tests IEC 6826 FC IEC 9001 Quality Standard ISO 9001 Environmental Standard ISO 14001 DC Operation EN 60924 Emergency Lighting Operation VDE 0108
1.7
Total System consumption (lamps + ballast) for 1 x 36 W TLD, shall not exceed 40 W 1 x 28 W T5, shall not exceed 32 W 1 x 35 W T5, shall not exceed 40 W 1 x 14 W T5, shall not exceed 16 W 1 x 18 W CFL, shall not exceed 20 W 1 x 36 W CFL, shall not exceed 40 W
- 18 -
5.
1.1
EARTHING
EARTHING The system shall be TNS with four wire supply system (R,Y,B,N and 2 Nos. E) brought from the main L T Panel. All the noncurrent carrying metal parts of electrical installation and all metal conduits trunking, cable sheaths, switchgear, distribution panels, light fittings and all other parts made of metal shall be bonded together and connected by means of specified earthing conductors to an efficient earthing system. All metal work such as pipe lines, ducts, cable trays, stair case railing etc shall be bonded to earth. All earthing shall be in conformity with IS:3043 1987, and the basic system of earthing shall be TNS.
1.2
EARTHING CONDUCTORS Earthing conductors shall be of copper / GI as mentioned in schedule of quantities and shall be protected against mechanical injury and corrosion.
1.3
SIZING OF EARTHING CONDUCTORS The cross sectional area of earthing conductor shall not be smaller than half of the largest current carrying conductor subject to an upper limit of 80 Sq.mm. If the area of the largest current carrying conductor or bus bar exceeds 160 sq.mm then two or more earthing conductors shall be used in parallel, to provide at least half the cross sectional area of the current carrying conductor or bus bars. All fixtures, outlet boxes, junction boxes and power circuits upto 15 amps shall be earthed with PVC insulated copper wire. All 3 phase switches and distribution panels upto 60 amps rating shall be earthed with 2 Nos. distinct and independent 4 mm dia copper / GI wires. All 3 phase switches and distribution panels upto 100 amps rating shall be earthed with 2 Nos. distinct and independent 6 mm dia copper / GI wires. All switches, bus bar, ducts and distribution panels of rating 200 amps and above shall be earthed with minimum of 2 nos separate and independent 25 mm x 3 mm copper / GI tape.
1.4
CONNECTION OF EARTHING CONDUCTORS Main earthing conductors shall be taken from the earth connections at the main L T panel to an earth electrode with which the connection is to be made. All joints in tapes shall be with four rivets and shall be brazed in case of copper and by welding bolting in case of GI, wires shall be connected with crimping lugs, all bolts shall have spring washers. Sub mains earthing conductors shall run from the main distribution panel to the sub distribution panel. Final distribution panel earthing conductors shall run from sub distribution panel. Circuit earthing conductor shall run from the exposed metal of equipment and shall be connected to any point on the main earthing conductor, or its distribution panel. Metal conduits, cable sheathing and armouring shall be earthed at the ends adjacent to distribution panel at which they originate, or otherwise at the commencement of the run by an earthing conductor in effective electrical contact with cable sheathing. Where equipment is connected by flexible cord, all exposed metal parts of the equipment shall be earthed by means of an earthing conductor enclosed with the current carrying conductors within the flexible cord. Switches, accessories, lighting fitting etc. which are rigidly secured in effective electrical contact with a run of metallic conduit shall not be considered as a part of the earthing conductor for earthing purposes, even though the run of metallic conduit is earthed.
- 19 -
1.5
PROHIBITED CONNECTIONS Neutral conductor, sprinkler pipes, or pipes conveying gas, water or inflammable liquid, structural steel work, metallic enclosures, metallic conduits and lightning protection system conductors shall not be used as a means of earthing an installation or even as a link in an earthing system. The electrical resistance measured between earth connection at the main L T panel and any other point on the completed installation shall be low enough to permit the passage of current necessary to operate or circuit breakers, and shall not exceed 1 ohm. All switches carrying medium voltage shall be connected with earth by two separate and distinct connections. The earthing conductors inside the building wherever exposed shall be properly protected from mechanical injury by running the same in G I pipe of adequate size. The overlapping in strips at joints where required shall be minimum 75 mm. The joints shall be riveted and brazed in case of copper and by welding / bolting in case of GI in an approved manner. Sweated lugs of adequate capacity and size shall be used for termination of all conductor wires above 6 sq.mm size. Lugs shall be bolted to the equipment body to be earthed after the metal body is cleaned of paint and other oily substances and properly tinned. Equipotential bonding of all metallic structures shall be done.
1.6.
EARTHING The following must always be ensured in earthing system. All earths must be interconnected at the earth pits. This includes generator neutrals, transformer neutrals, transformer body, lightning protection system earths, UPS earths etc. Extraneous conductive parts such as gas pipes, other service pipes and ducting risers and pipes of fire protection equipment and exposed metalic parts of the building structure.
1.7
The Contractor shall get the soil resistivity test done at his own cost of the area where earthing pits are to be located before starting the installation. RESISTANCE TO EARTH The resistance of earthing system shall not exceed 1 ohm.
1.8
1.9
SPECIFICATION FOR HOT DIP GALVANIZING PROCESS FOR MILD STEEL USED FOR EARTHING FOR ELECTRICAL INSTALLATION GENERAL REQUIREMENTS I. Quality of Zinc Zinc to be used shall conform to minimum Zn 98 grade as per requirement of IS:2091992. Coating Requirement Minimum weight of zinc coating for mild steel flats with thickness upto 6 mm in accordance with IS:67451972 shall be 400 g/sqm. The weight of coating expressed in grams per square metre shall be calculated by dividing the total weight of Zinc by total area (both sides) of the coated surface. The Zinc coating shall be uniform, smooth and free from imperfections as flux, ash and dross inclusions, bare patches black spots, pimples, lumpiness, runs, rust stains bulky white deposits, blisters.
II.
- 20 -
Mild steel flats / wires shall undergo a process of degreasing pickling in acid, cold rinsing and then galvanizing. Jointing of earthing tape shall be by welding. All joints and cut ends shall be properly painted with aluminium paint.
- 21 -
6
1.0 1.1
iii) Telephone wiring in conduits 1.2 2.0 2.1 The telephone exchange and the hand sets shall be supplied by the clients. Conduits : Conduits shall be as given below : Indoor : medium gauge Rigid PVC conduit. The conduit shall generally be as specified under section `CONDUIT WIRING'. 3.0 3.1 Cables and Wires : The type of cables and the services shall be as follows : i) ii) 3.2 Indoor Multi pair, PVC insulated sheathed armored and sheathed. Inside Twin core PVC insulated with conduit twisted cores.
All multi core cables and wires shall be of tinned copper conductor of not less than 0.5 mm dia and shall be colour coded twisted pairs with rip cord. The conductor resistance shall be less than 150 ohms per KM and the insulation resistance between the conductors not less than 50 mega ohms and the nominal capacitance of about 0.1 micro farad per kilometer. Cables laid under ground or locations subject to dampness and flooding shall be filled with polyethylene compound and shall have sufficient protection against moisture and water ingress. All armoring shall be of galvanized steel wires and protected against corrosion by an outer sheath of PVC in the case of indoor cables and polyethylene in the case of outdoor cables. Outer sheathing must be fire retarding and antitermite. All unarmoured single core cables and inner sheath of armored cables shall be provided with rip cord. All single pair cables for final extension to the telephone outlet box shall be unarmoured tinned copper conductors of not less than 0.6 mm. diameter and shall be drawn in conduits. All telephone outlets shall consist of 2 A 2 pair polythene connector in G.I box with 6 mm perspex cover with beveled edges and chromium plated brass hardware. Tag blocks : The telephone tag blocks shall be suitable for the multi core telephone cables and shall have two terminal blocks, cross connect type. All incoming and outgoing cables shall be
3.3
3.4
3.5
3.6
3.7
4.0 4.1
- 22 -
terminated on separate terminal blocks and termination shall be silver soldered. The cross connecting jumpers shall be insulated wires of same diameter and screw connected. 4.2 The tag blocks shall be mounted inside fabricated sheet steel boxes with removable hinged covers and shall be fully accessible. The enclosure shall be painted with 2 coats of red oxide and stove enameled. Installation : The installation of conduits shall generally be as specified under section `CONDUIT WIRING'. All cables shall be on cable racks and neatly stitched together. The connection at the tag blocks shall be silver soldered so as to achieve minimum contact resistance. The final branch connections with single pair cables in conduits and the maximum number of cables in each conduit shall be as follows :
5.0 5.1
5.2 5.3
5.4
Conduit diameter inch mm. 3/4"20 1" 25 1" 32 1" 40 6.0 6.1
2 Nos. single pair 6 Nos. single pair 12 Nos. single pair 18 Nos. single pair
Mode of measurement : The main telephone cables shall include supply and laying of multi pair cables on ceiling/wall/on cable trays/racks including all supports and shall be measured and paid on running length basis. Cable trays/racks shall be paid for separately. The multi pair tag blocks shall consist of two telephone connectors strips, jumpered interconnections silver soldered enclosure etc. and shall be measured and paid as one unit. The conduit wiring for telephone shall include single pair 0.6 diameter cable in heavy duty rigid, PVC conduits and shall include junction boxes, pull boxes, 2 pair 2 A connector in GI box, Perspex cover etc. and shall from one point.
6.2
6.3
- 23 -
PART B : TESTING
1.1 GENERAL At the completion of the work, the entire installation shall be subject to the following tests in the presence of the Owners site representative. Wiring continuity test. Insulation resistance test. Earth continuity test. Earth resistivity test. Test as per Appendix `E' of IS:732 1989 Besides the above, any other test specified by the local authority shall also be carried out. All tested and calibrated instruments for testing, labour, materials and incidentals necessary to conduct the above tests shall be provided by the Contractor at his own cost. 1.2 TESTING OF WIRING All wiring systems shall be tested for continuity of circuits, and earthing after wiring is completed and before installation is energized. 1.3 INSULATION RESISTANCE TEST The insulation resistance shall be measured between earth and the whole system of conductors, or any section thereof, with all switches closed and except in concentric wiring all lamps in position of both poles of the installation otherwise electrically connected together, a direct current pressure of not less than twice the working pressure provided that it does not exceed 660 volts for medium voltage circuits. Where the supply is derived from AC three phase system, the neutral pole of which is connected to earth, either direct or through added resistance, pressure shall be deemed to be that which is maintained between the phase conductor and the neutral. The insulation resistance measured as above shall not be less than 50 divided by the number of points provided on the circuit, the whole installation shall have an insulation resistance greater than one megaohms. The insulation resistance between the frame work of housing of power appliances and all live parts of each appliance shall not be less than that specified in the relevant standard specification or where there is no such specification, shall not be less than one a megaohms. All equipments, cables shall be inspected at works by the Architect as per relevant IS and testing commissioning of installation as per Appendix `E' of IS:732 1989 shall be done and all record to be maintained. 1.4 TESTING OF EARTH CONTINUITY PATH The earth continuity conductor metallic envelopes of cables shall be tested for electric continuity and the electrical resistance of the same, along with the earthing lead but excluding any added resistance or earth leakage circuit breaker, measured from the connection with the earth electrode to any point in the earth continuity conductor in the completed installation, shall not exceed one ohm. 1.5 TESTING OF POLARITY OF NONLINKED SINGLE POLE SWITCH In a two wire installation a test shall be made to verify that all nonlined single pole switches have been connected to the same conductor throughout, and such conductor shall be labeled or marked for connection to an outer or phase conductor or to the nonearthed conductor of the supply. In the three or four wire installation, a test shall be made to verify that every nonlinked single pole switch is fitted to one of the outer or phase conductor of the supply. The entire electrical installation shall be subject to the final acceptance of the Owners site representative as well as the local authorities.
- 24 -
1.2
10.2.1 The work shall be carried out in the best workman like manner in conformity with this
10.2.2 In addition to the standards mentioned in 2.1, all works shall also conform to the
requirement of the following : Indian Electricity Act and Rules framed thereunder. Fire Insurance Regulations. Regulations laid down by the Chief Electrical Inspector of the State / State Electricity Board / Union Territory. Regulations laid down by the Factory Inspector of the State / Union Territory. Any other regulations laid down by the local authorities. Installation & operation manuals of original manufacturers of equipment. 1.3 EQUIPMENT AND ACCESSORIES SPECIFICATIONS: This defines specifications and requirements mainly for the equipment and accessories, which are generally supplied by the erection agency. All materials, accessories, consumable to be supplied by the contractor shall be selected from the list of specified make and shall conform tot he specification given here under. The equipment shall be manufactured in accordance with current Indian Standard specifications wherever they exist or with the BS or NEC specifications, if no such IS standards are available. In the absence of any specification, the materials shall be as approved by the owner / consultant or his authorised representative. All similar materials and removable parts shall be uniform and interchangeable with one another. Makes of bought out items selected by the contractor must be furnished by him as per the proforma given in elsewhere in this tender document. 1.3.1 CONTROL CABLES: Control cables for use on 415 V system shall be of 1100 volts grade, copper conductor, PVC insulated, PVC sheathed, armoured and overall PVC sheathed, strictly as per IS: 1554 (PartI) 1976. Unarmoured cables to be used only if specifically mentioned in schedule of quantities. The size of these cables shall be as specified in bill of quantities or as per approved drawing. The minimum conductor size shall be 2.5 sq.mm. (Cu.). 1.3.2 CABLE TRAYS: These shall be channel type, fabricated from structural steel, hot dip galvanised, complete with all accessories such as bends, tees and reducers. Only aluminium flat clamps with G.I. / Chrome plated bolts, nuts/screws to be used for clamping cables. Sizes of these trays shall be as specified in bill of quantities or approved by client. CABLE GLANDS: Cable glands shall be heavy duty compression type of brass, chrome plated. These shall have a screwed nipple with conduit electrical thread and check nut. These shall be suitable for armoured/Unarmoured cables, which are being used.
1.3.3
- 25 -
1.3.4
CABLE CONNECTORS: Cable connectors, lugs/sockets, shall be of copper/aluminium alloy, suitably tinned, solderless, crimping type. These shall be suitable for the cable being connected and type of function (such as power, control or connection to instruments etc.). CABLE INDICATORS These shall be self sticking type of 2 mm. thick lead strap for overall cable. PVC identification number, ferrules shall be used for each wire. G.I. PIPE FOR CABLES: For laying of cables under floor, G.I. class A pipes shall be used. M.S. conduits are not acceptable for this purpose. All accessories of pipes shall be threaded type. Size of pipe shall depend upon the overall outer diameter of cable to be drawn through pipe. NO G.I. pipe less then 40 MM. I.D. Shall be used for this purpose. To determine the size of pipe, assume that 40% area of pipe shall be free after drawing of cable. PUSH BUTTON STATIONS: These shall be floor / wall mounted type as specified in bill of quantities. These shall be fabricated from 1.6 mm. thick stainless steel sheets (SS 304). In case of floor mounted station, these shall be supported on 51 mm. A class G.I. pipe. Front cover shall be removable type with suitable rubber gaskets to make them dust vermin and moisture proof. Each feeder shall be provided with ON (green) push button, OFF (red) push button, name plate (white bakelite), indication lamp etc. Green & red push buttons shall have contact elements having 1NO + 1NC. OFF push button shall be provided with lockable (key operated) arrangements to prevent accidental starting. No. of feeders shall be specified in bill of quantities. The indication lamp can be combined with ON push button.
1.3.5
1.3.6
1.3.7
1.4
ERECTION The contractor shall make his own arrangement for safe transportation of all the items to the erection site and also carry out complete loading / unloading during transportation. Equipment shall not be removed from packing cases unless the floor has been made ready for installing them. The cases shall be opened in presence of the client / consultant or his authorised representative. The empty packing cases shall be returned to the stores and any document if found with the equipment shall be handed over to the client's representative. Any damage or shortage noticed shall be reported to the client / consultant in writing immediately after opening of packing cases. ONAN TYPE TRANSFORMER ERECTION Before erection of transformer, the level of rails on foundation shall be checked and minor corrections if necessary shall be carried out. After the completion of erection, necessary stoppers shall be provided at the wheels. All loosely supplied fittings / accessories shall be cleaned and mounted on the transformer and connections made. After completely assembling & installation, the transformer shall be cleaned and touched up with a paint supplied by the manufacturer applied wherever necessary. All cover bolts shall be checked for proper tightness. All the civil foundation work required shall be in the scope of contractor. TESTING : Winding insulation resistance shall be measured from primary and secondary to ground and between primary and secondary. Check the polarity of terminals and the phase sequence.
1.4.1 (a)
(b)
(c)
- 26 -
b) c)
Operation of the tap changer. Operation of the tap at tap No. 1 Operation of the tap at tap No. 2 Operation of the tap at tap No. 3 Operation of the tap at tap No. 4 Operation of the tap at tap No. 5 Polarity marking and phase sequence. Earth resistance : Body as well as Neutral link. [This proforma shall be jointly signed by the CLIENT / CONSULTANT and the contractor in duplicate]. 1.4.2 (a) MOTOR CONTROL CENTER, DISTRIBUTION BOARDS : ERECTION : Electrical panels his own arrangement for safe transportation of all the items to the erection site and also carry out complete loading / unloading during transportation. The contractor shall be responsible for final assembly and interconnection of busbars / wiring. Foundation channel shall be delivered in convenient shipping section by the manufacturer. The contractor shall make shall be grouted in the flooring by the contractor. Switchgear shall be aligned and levelled on their base channels and bolted to them as per the instructions of the client / consultant. The earth bus shall be made continuous throughout the length. Loosely supplied relays and instruments shall be mounted and connected on the switchgear. The contacts of the drawout circuit breaker shall be checked for proper alignment and inter changeability. After erection, the switchboard shall be inspected for dust and vermin proof. Any hole which might allow dust or vermin etc. to enter the panel shall be plugged suitably at no extra cost. If the instrument transformers are supplied separately, they shall be erected as per the direction of the client / consultant. The contractor shall fix the cable glands after drilling the bottom / top plates of all switchboards with suitable holes at no extra cost. Range of overload relays / timers etc. shall be checked with requirement of motor actually to be connected at site and if the same is undersized / oversized, it shall be brought to the notice of the client / consultant, who shall arrange procurement of corrected components. However, the contractor shall not charge anything extra for labour for such replacements. (b) TESTING : Before electrical panel is energised, the insulation resistance of each bus shall be measured from phase to ground. Measurement shall be repeated with circuit breakers in operating positions and contacts open. Before switchgear is energised, the insulation resistance of all control circuits shall be measured from line to ground. The following tests shall be performed on all circuit breakers during erection. Contact alignment and wipe shall be checked and adjustment where necessary in accordance with the breaker manufacturers instructions. Each circuit breaker shall be drawn out of its cubicles, closed manually and its insulation resistance measured from phase to phase and phase to ground.
- 27 -
All adjustable direct acting trip devices shall be set using values given by the consultant/ manufacturer. The dielectric strength of insulating oil wherever applicable, shall be checked. Before switchgear is energised, the following tests shall be performed on each circuit breaker in its test position. Close and trip the circuit breaker from its local control switch push button or operating handle. Switchgear control bus may be energised to permit test operation of circuit breaker with A.C. closing with prior permission of the client / consultant. Test tripping of the electrically operated circuit breaker by operating mechanical trip device. Test proper operation of circuit breakers latch, check carriage limit switch if provided. Test proper operation of lockout device in the closing circuit. Wherever provided by simulating conditions which would cause a lockout to occur. Trip breaker either manually or by applying current or voltage to each of its associated protective release. Before switchgear is energised, the tests covered above shall be repeated with each breaker in its normal operating position. Capacitor banks shall be tested as per manufacturers instructions. In addition, test for output and/or capacitance, insulation resistance test and test for efficiency of discharge device shall be carried out. All electrical equipment alarms shall be tested for proper operation by causing alarms to sound under simulated abnormal conditions. (c) PROFORMA FOR PCC, MCC, DB, CONTROL PANEL TEST : Circuit breaker or contactor module designation / bus no. Insulation resistance test (contacts open, breaker racked in position) a) between each phase of bus : Mega ohm b) between each phase and earth : Mega ohm c) DC and AC control and auxiliary circuits : Mega ohm d) between each phase of CT / PT and between CT & PT circuit if any : Mega ohm CT checks : a) CT ratio
b)
CT secondary resistance
c) CT polarity check Check for contact alignment and wipe. Check / test all releases / relays. Check mechanical interlocks. Check electrical interlocks. Check switchgear / control panel wiring. Check breaker / contactor circuit for : a) Closing local & remote (wherever applicable) b) Tripping local & remote (wherever applicable) Opening time of breaker / contactor. Closing time of breaker / contactor. [This proforma shall be jointly signed by the CLIENT / CONSULTANT and the contractor in duplicate].
12.4.3 INSTALLATION OF CABLE NETWORK : Cable network shall include power, control and lighting cables which shall be laid in underground trenches, cable trays, G.I. pipes, or on building structures as detailed in the relevant drawings, cable schedules or as per the client / consultants instructions. Supply & installation of cable trays, G.I. pipes / conduits, cable glands and sockets of both end isolators, junction boxes, remote push button stations, etc. shall be under the scope of the contractor.
- 28 -
(a)
General requirements for handling cables : Before laying cables, this shall be tested for physical damage, continuity, absence of cross phasing, insulation resistance to earth and between conductors. Insulation resistance tests shall be carried out with 500 / 1000 V megger. The cables shall be supplied at site, wound on wooden drums as far as possible. For smaller length and sizes, cables in properly coiled form can be accepted. The cables shall be laid by mounting the drum of the cable on drum carriage. Where the carriage is not available, the drum shall be mounted on a properly supported axle, and the cable laid out from the top of the drum. In no case the cable will be rolled on as it produces kinks which may damage the conductor. Sharp bending of cable shall be avoided. The bending radius for PVC insulated and sheathed, armoured cable shall not be less than 10 D, where D is overall diameter of the cable. While drawing cables through G.I. pipes, conduits, RCC pipes, ensure that size of pipe is such that, after drawing cables, 40% area is free. After drawing cables, the end of pipe shall be sealed with cotton / bituminous compound. High voltage (11 kV and above), medium voltage (240 V and above) and other control cables shall be separated from each other by adequate spacing or running through independent pipes / trays. Armoured cables shall never be concealed in walls / floors / roads without G.I. pipes, conduits or RCC pipes. Joints in the cable throughout its length of laying shall be avoided as far as possible and if unavoidable, prior approval of site engineer shall be taken. If allowed, proper straight through epoxy resin tight joint shall be made, without any additional cost. A minimum loop of 3 mtr. shall be provided on both ends of the cable, and on both ends of straight through cable joint. This additional length shall be used for fresh termination in future. Cable for this loop shall be paid for supply and laying. Cable shall be neatly arranged in the trenches / trays in such manner so that crisscrossing is avoided and final take off to the motor / switchgear is facilitated. Arrangement of cable within the trenches / trays shall be the responsibility of the contractor. All cable routes shall be carefully measured and cable cut to the required lengths and undue wastage of cables to be avoided. The routes indicated in the drawings is indicative only and the same may be rechecked with the client / consultant before cutting of cables. While selecting cable routes interference with structures, foundations, pipelines, future expansion of buildings etc. should be avoided. All temporary ends of cables must be protected against dirt and moisture to prevent damage to the insulation. For this purpose, ends of all PVC insulated cables shall be taped with an approved PVC or rubber insulating tapes. Use of friction type or other fabric type tape is not permitted. Lead sheathed cables shall be plumbed with lead alloy. Wherever cable rises from underground / concrete / masonry trenches to motors / switchgears / push buttons, these shall be taken in G.I. pipes of suitable size, for mechanical protection upto 300 mm. distance of concerned cable gland or as instructed by the client / consultant. The cable pass through foundation / walls of other underground structures, the necessary ducts for opening will be provided in advance for the same. However, should it become necessary to cut holes in existing foundation of structures the electrical contractor shall determine the location and obtain approval of the client / consultant before cutting is done.
- 29 -
(b)
LAYING OF CABLES (UNDERGROUND SYSTEM) Cables shall be so laid in trench that this will not interfere with other underground structure. All water pipes, sewage lines or other structures which become exposed by excavation shall be properly supported and protected from injury until the filling has been rammed solidly in places under and around them. Any telephone or other cables coming in the way are to be properly shielded / diverted as directed by the owner / consultant. Cable shall be laid at minimum depth of 750 mm. in case of L.T. and 1200 mm. in case of H.T. from ground level. Excavation will be generally in ordinary soil. The width of trench shall be sufficient for laying of required no. of cables. Sand bedding 75 mm. thick shall be made below and above the cables. Layer of bricks (full size) shall be laid above sand bedding on the sides and above the cables to cover cables completely. More than one cable can be laid in the same trench. However, the relative location of cables in trench shall be maintained till termination. The surface of the ground after back filling the earth shall be made good so as to conform in all respects to the surrounded ground and to the entire satisfaction of the client / consultant. For all underground cables, route markers should be used : a) Separate route markers should be used for LT, HT and telephone cables. b) Route markers should be grounded in ground with 1:2:4 cement concrete pedestal size 230 x 230 x 300 mm.. c) Cable markers should be installed at an interval not exceeding 30 mtr. along the straight routes of cables at a distance of 0.5 mtr. away from centre of cable with the arrow marked on the cable marker plate indicating the location of cable. Cable markers should also be used to identify change in direction of cable route and for location of every joint in underground cable. RCC Hume pipe for crossing road in cable laying shall be provided by employer. No deduction shall be made for cable laying in Hume pipe for not providing bricks, sand and excavation. RCC hump pipe at the ends shall be sealed by bituminous compound after laying and testing of cables by electrical contractor without any extra charge.
(c)
LAYING OF CABLE IN MASONRY TRENCHES Masonry / concrete trenches for laying of cables shall be provided by employer. However, steel members such as M.S. angles / flats etc. shall be provided and grouted by electrical contractor to support the cables without any extra charge. Cables shall be clamped to these supports with minimum saddles / clamps. More than one tier of cables can be provided in the same trench if the no. of cables are more. Entry of cables in trenches shall be sealed with bituminous MASTIC compound to stop entry of water in trenches.
(d)
LAYING OF CABLES IN CABLE TRAYS Cable trays and steel members such as M.S. angle / channel / flats etc. shall be provided and fixed by the contractor. Cable shall be fixed in cable trays in single tier formation and cables shall be clamped with flat clamps and galvanised bolts / nuts. Earthing flat / wire can also be laid in cable tray alongwith cables. After laying of cables, minimum 20% area shall be spare.
(e) i.
TERMINATION AND JOINTING OF CABLES : a) For HT cables suitable size of push on type termination kit shall be used.
- 30 -
b) Use of glands : All PVC cables upto 1.1 kV grade, armoured or Unarmoured shall be terminated at the equipment / junction box / isolators / push buttons / control accessories, etc. by means of suitable size single compression type cable glands. Armour of cable shall be connected to earth point. The contractor shall drill holes for fixing glands wherever necessary. Wherever threaded cable gland is to be screwed into threaded opening of different size, suitable galvanised threaded reducing bushing shall be used of approved type. In case of termination of cables at the bottom of the panel over a cable trench having no access from the bottom, a close fit holes should be drilled in the bottom plate for all the cables in one line, then bottom plate should be split in two parts along the centre line of holes. After installation of bottom plate and cables with glands, it shall be sealed with cold sealing compound. ii. USE OF LUGS / SOCKETS : All cable leads shall be terminated at the equipment terminals, by means of crimped type solderless connectors unless the terminals at the equipment ends are suitable for direct jointing without lugs / sockets. The following is the recommended procedure for crimped joints and the same shall be followed : a) Strip off the insulation of the cable and with every precaution, not in severe or damage any strand. All insulations to be removed from the stripped portion of the conductor and ends of the insulation should be clean and square.
b)
The cable should be kept clean as far as possible before assembling it with the terminal / socket. For preventing the ingress of moisture and possibility of re oxidation after crimping of the aluminium conductors, the socket should be filled with corrosion inhibiting compound. This compound should also be applied over the stripped potion of the conductor and the palm surface of socket. Correct size and type of socket / ferrule / lug should be selected depending on size of conductor, and type of connection to be made. Make the crimped joint by suitable crimping tool. If after crimping the conductor in socket / lug, some portion of the conductor remains without insulation the same should be covered sufficiently with PVC tape. For HT cable the manufacturers recommendation should be followed.
c) d) e) f)
iii)
DRESSING OF CABLE INSIDE THE EQUIPMENT : After fixing of cable glands, the individual cores of cable shall be dressed and taken along the cable ways (if provided) or shall be fixed to the panels with polyethylene straps. Cable shall be dressed in such a manner that small loop of each core is available inside the panel. For motors of 20 HP and above, terminal box if found not suitable for proper dressing of aluminium cables, the erector shall modify the same without any additional cost. Cables inside the equipment shall be measured and paid for on lug to lug basis.
iv)
IDENTIFICATION OF CABLES / WIRES / CORES : Power cables shall be identified with red, yellow and blue PVC tapes. For trip circuits identification, additional red ferrules shall be used only in the particular cores of control cable at the termination points in the switchgear / control panels and control switches.
- 31 -
In case of control cables all cores shall be identified at both ends by their wire numbers by mean of PVC ferrules or self sticking cable markers, wire numbers shall be as per schematic / connection drawing. For power circuit also, wire numbers shall be provided if required as per the drawings of switchgear manufacturer / supplier. (f) i. TESTING OF CABLES : Before energising, the insulation resistance of every circuit shall be measured from phase to ground. This requires 3 measurements if one side is grounded and 6 measurements for 3 phase circuits. Where splices or terminations are required in circuits rated above 650 volts, measure insulation resistance of each length of cable before splicing and/or terminating. Repeat measurements after splices and/or terminations are complete. DC high voltage test shall be made after installation on the following : All 1100 volts grade cables in which straight through joints have been made. All cables above 1100 V grade. For record purpose test data shall include the measured values of leakage current versus time. The DC high voltage test shall be performed as detailed below : Cables shall be installed in final position with all the straight through joints complete. Terminations shall be kept unfinished so that motors, switchgear, transformer etc. are not subjected to test voltage. The test voltage and duration shall be as per relevant codes and practices of Indian Standards Institution.
ii.
iii.
a) b)
iv.
PROFORMA FOR TESTING CABLES : DATE OF TEST a) Drum No. from which cable taken. b) Cable from to c) Length of run of this cable meter d) Insulation resistance test i) between core1 to earth ii) between core2 to earth iii) between core3 to earth iv) between core1 to core2 v) between core2 to core3 vi) between core3 to core1 vii) duration used : 1 kV e) High voltage test Voltage i) between core an earth. ii) between individual cores
[This proforma shall be jointly signed by the CLIENT / CONSULTANT and the contractor in duplicate]. 12.4.4 (a) EARTHING NETWORK : INSTALLATION AND CONNECTION : The plate/pipe electrode, as far as practicable, shall be buried below permanent moisture level but in no case not less than 2.5 M below finished ground level. The plate/pipe electrode shall be kept clear of the building foundation and in no case, it shall be nearer by less than 2 M from outer face of the respective building wall / column. The plate electrode shall be installed vertically and shall be surrounded with 150 mm. thick layers of Charcoal dust and Salt mixture.
- 32 -
19 mm. dia. G.I. pipe for watering, shall run from top edge of the plate / pipe electrode to the mid level of block masonry chamber. Top of the pipe shall be provided with G.I. funnel and screen for watering the earth / ground through the pipe. The funnel with screen over the G.I. pipe for watering to the earth shall be housed in a block masonry chamber as shown in the drawing. The masonry chamber shall be provided with a Cast Iron hinged cover resting over the Cast Iron frame which shall be embedded in the block masonry. Construction of the earthing station shall in general be as shown in the drawing and shall conform to the requirement on earth electrodes mentioned in the latest edition of Indian Standard IS : 3043, Code of Practice for Earthing Installation. The earth conductors (Strips / Wires copper / Hot dip G.I.) inside the building shall properly be clamped / supported on the wall with Galvanised Iron clamps and Mild Steel Zinc Passivated screws / bolts. The conductors outside the building shall be laid atleast 600 mm. below the finished ground level. The earth conductors shall either terminate on earthing socket provided on the equipment or shall be fastened to the foundation bolt and / or on frames of the equipment. The earthing connection to equipment body shall be done after removing paint and other oily substances from the body and then properly be finished. Over lapping of earth conductors during straight through in joints, where required, shall be of minimum 75mm. long. The earth conductors shall be in one length between the earthing grid and the equipment to be earthed. (b) EARTH LEADS AND CONNECTIONS : Earth lead shall be bare copper or Galvanised steel as specified with sizes shown on drawings. Copper lead shall have a phosphor content of not over 0.15 %. G.I strips buried in the ground shall be protected with bitumen and hessian wrap or polythene faced hessian and bitumen coating. At road crossing necessary Hume pipes shall be laid. Earth lead run on surface of wall or ceiling shall be fixed on saddles so that strip is at least 8 mm away from the wall surface. The complete earthing system shall be mechanically and electrically bonded to provide an independent return path to the earth source. (c) TEST : The entire earthing installation shall be tested as per requirements of Indian Standard Specification IS : 3043. The following earth resistance values shall be measured with an approved earth megger and recorded. 1) Each earthing station 2) earthing system as a whole 3) Earth continuity conductors Earth conductor resistance for each earthed equipment shall be measured which shall not exceed 5 ohm in each case. Measurements of earth resistance shall be carried out before earth connections are made between the earth and the object to be earthed.
- 33 -
All tests shall be carried out in presence of the clients rePmc 12.5 12.5.1 SURFACE CONDUIT WORKS : CEILING / WALL OUTLET BOXES FOR LIGHTS / FANS : Outlet boxes shall be of steel with cover and so installed as to maintain continuity throughout. These shall be protected at the time of laying by filling with jute / earth / cotton etc. so that no cement mortar finds its way inside during concerning or plastering etc. In beams conduit socket shall be provided in place of outlet boxes. The same shall be used for installation of luminaries. For fixing light fixtures / brackets, outlet boxes complete with knock out for holding conduits shall be used. For lighting fixture suitable for 40/20 watts fluorescent tubes / incandescent lamps / mercury vapour lamps, only one outlet box is required. For fixing ceiling fans, circular outlet boxes, 100 mm. diameter, complete with 12 mm. dia. Mild Steel rod 300 mm. long, for holding 12 mm. dia. Mild Steel cover 125 mm. dia. at bottom shall be used. 12.5.2 DRAW OUT JUNCTION BOXES : Steel drawout boxes at angle dimensions shall be provided at a convenient points on walls / ceilings to facilitate pulling of long runs of cables / wires. The location of these boxes is to be decided prior to fixing, as per site requirement and following should be treated as general guidance for deciding the location of these : These should be provided at a place where these are not in direct view. Recommended place is 400 / 450 mm. below ceiling, if conduits are running vertically. Junction box in the offset of bottom of RCC beam and vertical wall should not be provided. If junction boxes are coming side by side for two or more conduits, one common M.S. box of proper size can be used to act as junction box. If junction box is to be provided in ceiling, its position should be so located that it is in line with other light / fan points. Junction boxes should never be used for splitting one conduit into two or more. Junction box for such functions is avoidable and for this, number of conduits to be connected to one switch board should be calculated correctly as per drawing before laying conduits in ceiling. Locating junction boxes on outer surface of exterior walls of building should be avoided as these are in direct view and are also exposed to weather.
(a)
(b) (c)
(d)
(e)
(f)
12.5.3
SWITCH BOXES : Steel boxes of required sizes, shall be provided to house speed regulators of fans, switches for lights, fans, plug sockets etc. as per requirement of drawings. These should be so designed that accessories on sheet could be mounted with tapped holes and brass machine screws, leaving ample space at the back and on the sides for accommodating wires and check nuts at conduit entries. These shall be attached to conduits by means of check nuts on all walls of the boxes through which the conduits are entering. These shall be completely connected leaving edges flush with finished wall surfaces. Cover should be fixed to these switch boxes by means of brass chrome plated machine screws and cup washers. Utmost care shall be taken by contractor to ensure that all switch boxes are in line and level. Inside each switch box, one bolt shall be welded to receive earthing wire.
12.5.4
SWITCH AND SOCKET : Switches shall be installed at 900 mm above finished floor level unless otherwise indicated on the drawings.
- 34 -
The switch controlling the light point or fan shall be connect on to the phase wire of the circuit and neutral shall be continuous, having no fuse or switch installed in the line except at the D.B. All fan regulators shall be fixed inside the switch boxes The cover plates to the switch box shall be fixed by means of sunk head brass cadmium screws. Where two or more switches and fan regulators are installed together, they shall be provided with one gang cover plate with knockouts to accommodate required number of switches, sockets and regulators. The switch controlling the socket outlet shall be on the phase wire of the circuit. The third pin of the socket shall be connected to the earth continuity conductor of the circuit The switch boxes, installed backtoback in the same wall shall be offset from each other, 150 mm horizontally, to preclude noise transmission. 12.5.5 CLEANING AND PROTECTION OF CONDUIT SYSTEM : The entire conduit system including outlet boxes, junction boxes and switch boxes shall be thoroughly cleaned after completion of erection and tested for not blockage by air / sound or steel wire prior to finishing of building by air / sound or steel wire prior to finishing of building and before drawing in of cables / wires to safeguard conduit system against filling up with the plaster / cement slurry / water etc. all the outlet and switch boxes will have to be provided with temporary jute / cotton filling, covers and plugs etc.. Within tendered cost which shall be replaced later on by hylem / sheet cover after wiring as required.
12.5.6
TESTING OF INSTALLATION : Before a completed installation is put into service, the following tests shall be complied with: INSULATION RESISTANCE : The insulation resistance shall be measured by applying 500 volt megger with all fuses in places, circuit breaker and all switches closed. The insulation resistance in gegohms of an installation, measured shall not be less than 50 megohms divided by the number of points on the circuit. The insulation resistance shall be measured between EARTH TO PHASE EARTH TO NEUTRAL PHASE TO NEURAL PHASE TO PHASE
(a)
(b)
EARTH CONTINUITY PATH : The earth continuity conductors shall be tested for electrical continuity and the electrical resistance of the same along with the earthing lead but excluding any added resistance or earth leakage circuitbreaker, measured from the connection, with the earth electrode to any point in the earth continuity conductor in the completed installation and shall not exceed one ohm. POLARITY OF SINGLE POLE SWITCHES : A test shall be made to verify that every nolinked, single pole switch is connected to one of the phase of the supply system. COMPLETION CERTIFICATES : All the above tests shall be carried out in presence of client and the results shall be recorded in a prescribed forms. Any default during the testing shall be immediately rectified and that
(c)
(d)
- 35 -
section of the installation shall be re tested. The completed test result from shall be submitted to the client for approval. On completion of an electric installation a certificate shall be furnished by the contractor, countersigned by the certified supervisor under whose direct supervision the installation was carried out. This certificate shall be in a prescribed form as required by the local electric supply authority. 12.6 12.6.1 INSTALLATION OF LIGHTING FIXTURES / FANS : INSTALLATION OF LIGHTING FIXTURES : Scope of work under this item shall start from light point, with 3 nos. 1.5 mm. PVC insulated wires from connector to the connector inside the lighting fixture, connections, fixing of lighting fixture complete with all accessories, lamps on wall / roof / steel truss etc. testing the lighting fixture and commissioning. If wire length of light point is enough to reach connector of light fitting, connector in light point can be deleted. INSTALLATION OF EXHAUST FANS : Scope of work under this system shall start from exhaust fan point, with a ceiling rose, 2 core 2.5 mm. PVC insulated wire from ceiling rose to connector of exhaust fan, connections, making fan opening in walls including repair / finishing fixing of exhaust fan complete with accessories and louvers on walls with holdfasts, testing the exhaust fans and commissioning. INSTALLATION OF EXTERNAL LIGHT FIXTURES : Street lighting installation shall be carried out as per details shown in the drawing. The poles shall be erected in perfect plumb with concrete foundation at a location shown in the drawing. The foundation shall be designed to withstand the static load as well as wind velocity and bending moment of the pole and shall be approved by the client prior to execution. The junction box shall then be clamped to the erected pole as per details shown in the drawing. The luminaires shal also be installed on the pole and be electrically wired to the respective junction box. The cable lay out shall follow the tentative route as shown in the drawing. In case of any constraint on the cable route the same shall be brought to notice of the client. The cable lay out shall be carried out in an underground manner and the said installation complete with electric connections. Earthing installation shall follow the details for the same shown in the drawing. The earthing station ( coil type ) and the earthing grid installation shall be carried out as per the specification for the said works given in section under title Earthing of this tender document. On completion of the installation, the street light poles shall be painted with two coats of metal primer ( Red Oxide ) followed by two coats of Synthetic enamel of the shade as approved by the Engineerincharge. The brackets shall be made of 38 mm. NB MS class B pipe approx. 1.8 mtr. long bent at the centre at an angle 120 C. with necessary holding brackets, hold fasts etc. with special reducer at the end to accommodate type of street light fitting to be fixed. Bracket shall have 1 coat of anticorrosion paint before despatch to site and 2 coats of approved make and shade of aluminium paint. This bracket shall also be provided with one M.S. water tight box complete with the connector, neutral link, rewireable fuse etc.. See enclosed drawings of street light poles. - 36 -
10.6.2
12.7
Installation of poles shall be done as per enclosed drawings of street light poles. The depth of pole to be burried in ground shall be 1/5th of the total pole length or as specified in drawing, whichever is more. Special care shall be taken in erecting poles so that these are not strained or damaged during erection and are firmly stayed till the foundation are secured. The pole shall be grouted inside ground pit (crosssection 600 x 600 mm.) with cement concrete 1:2:4. Before the placement of concrete around pole in the pit, necessary conduit pipes (not less than 25 mm. dia.) shall be placed for facilitating drawing of cables. Separate conduit shall be provided for incoming and outgoing cables. The cement concrete shall be protected from prematured drying by curing for atleast 7 days after pouring. All concrete surface from 150 mm. below ground level to top shall be finished smooth with cement mortar 1:4. This includes fixing of street light fittings complete with accessories and lamps at the end of the pole / bracket, connecting it with 3 x 2.5 mm. aluminium conductor, PVC insulated cable from water tight M.S. box, testing, commissioning. Third core shall be connected with earthing point of light fitting at one end and earthing point of marshalling box at the other end. 12.8 GENERAL NOTES FOR STREET LIGHTING : For supplying and laying of cables, technical specification (wiring) shall be applicable reference shall be made under heading Cable Work elsewhere in the tender. For street light poles along roads, nearest finished road level shall be taken as ground level and for poles along compound wall / away from roads, existing ground / finished ground shall be taken as ground level. Distance of 1 mtr. shall be maintained between centre of pole and centre of kerb of road. For compound wall poles, distance between compound wall and poles shall be 3 mtrs. A loop of 1.5 mtr. of cable shall be provided near each street light pole for all incoming and outgoing cable. 12.9 COMPLETION TESTS : After supply and installation of complete project or a particular building / area, following tests shall be carried out by the contractor before switching on the power to installation and the results shall be recorded and submitted to the SiteEngineer. If results are not satisfactory / as per standards set herewith, the contractor shall identify the defects / short coming and shall rectify the same. Nothing extra shall be paid for carrying out these tests and contractor has to arrange all necessary instruments.
12..9.1 INSULATION RESISTANCE TO EARTH : This is to be measured with all fuse links in place, all switches ON, all lamps and appliances in position by applying a voltage not less than twice the working voltage (subject to a limit of 500 V). Insulation resistance of the whole or any part of the installation to earth must not be less than 50 megaohms divided by the number of outlets (points and switch positions) except that it need not exceed one megaohm for the whole installation. 12.9.2 INSULATION RESISTANCE BETWEEN CONDUCTORS : Tests to be made between all the conductors connected to one pole or phase conductor of the supply and all the conductors connected to the middle wire or neutral or the other pole or phase conductors of the supply. For this test, all lamps shall be removed and all switches put ON. The result of the test must be 50 megaohms divided by the number of outlets (points and switch positions) but need not exceed 1 megaohm for the whole installation. POLARITY OF SINGLE POLE SWITCHES : Tests shall be made to verify that all nonlinked single pole switches are on phase conductor (live) and not on neutral or earth conductor. This can be done by connecting test lamps
12.9.3
- 37 -
between two terminals of switch and earth. If the lamp lights up when switch is ON and either terminal is touched, the switch is correctly installed. 12.9.4 RESISTANCE OF METAL CONDUITS / SHEETS (EARTH CONTINUITY TEST) : In case of cables encased in metal whether conduit of metallic sheathing, the total resistance of the conduit or sheathing from the earthing point any other position in the completed installation shall not exceed 2 ohms. This can be carried out by following circuit : One end of the load is connected to the ECC and its connection with the electrode and the other to the farthest point of the ECC. First, current through the circuit is measured with the resistance of 2 ohms short circuited by the link. Next, current is measured through the two ohms resistance by disconnecting the two leads from the ECC and joining them together. If current is more in the first case, the resistance of ECC is less than 2 ohms. 12.10 HANDING OVER / TAKING OVER : After completion of works and tests specified above, the various installations of the project can be taken over by the employer as and when these are ready in all respects. The defect liability period of 12 months shall start from the date, when all the installations of the project have been executed, tested as described above, successfully commissioned and handed over.
- 38 -
Make OF Material
Sr.No 1) 2) 3) 4)
Item Rigid PVC Conduit Accessories for conduit Flexible Copper Wires Switches
Approved Make Precision Plastic Industries, Nihir Same make as of pipe. R.R. Kable (FRLS), Havell's(FRLS),Finolex (FRLS). MK India(Logic), Toyoma (Accura Plus), MDS (My linc), Crabtree Schneider MG, L&T
5)
Main Switch fuse upto 60 Amps AC 23 duty Above 60 AmpsA.C. 23 duty HRC Fuses MCBs/ELCBs/ELMCBs Distribution boards
6)
7) 8) 9)
Schneider MG, L&T Legrand (MDSlexic),Schneider MG ( Multi 9) Legrand (MDSlexic), Schneider MG Factory fabricated.double door type with additional JB on both side CPL, KEW. Finolex, Delton, RR cable, Havell's. Finolex, Delton, GTCL. Steel grip, Anchor XLPE armoured cable for 1.1 KV as per ISI 1554. Finolex, Havells, Torrent, Poly Cab Compression type, Heavy duty and deep threding with rubber ring and double washers. HMI Dowells, 3D. Indoor MDS, Outdoor Clipsal, Gewiss, RR PCE, MDS. Technoplast, Porcelain. Anchor, CPL
Rewirable Porcelain Fuse Telephone wires Telephone cables Jelly Filled PVC tape Cables
16)
Glands
17) 18)
19) 20)
Connectors Button holder, Angle holder, ceiling rose M.S. Conduit ISI Anti vibration Ball
21) 22) - 39 -
23)
M.S. Boxes
Fabricated out of 16 gauge continuously welded (sample to be approved) with Powder coating. Krone. Schneider MG Simpact , Legrand(MDS) Rushabh, L &T,Conzerv Flaxi Hose
Telephone tag block MCCB Meter ( Analog Onnly ) Steel Wire Rain Forced PVC Flexible Hose Cable Tray
28)
i) Ladder/Perforated Hot deep GI Indiana,MEK,Superfab, Rushabh ii) Metal M.S. fabricated. Finolex, RR Cable, Havell's. MDS Anchor Ashlok L &t, Conserve, Schneider, HPL
TV Cable/CCTV Cable UPVC Cable truncking Call Bell Chemical Type Earthing Energy Meter
Special Notes : 1) All the material used shall be ISI & FIA approved only. 2)
The successful tenderer will have to supply the makes from above in consultation with the Client/Architect/Consultant without any extra cost. Client /Architect/Consultant reserve the rights to choose any make out of above list Tenderer should have to specify the list of makes considered in the tender while quoting the rates in the tender, in covering letter of separate letter enclosure. However, the final decision for accepting make specified by tenderer would be of client/Architect/Consultants. As far as possible, the successful tenderer will have to place order directly to the manufacturer OR its authorized dealer.
3)
4)
5) 6) 7)
The Client/Architect/Consultants have right to check the challans of supplier. The MCB, MCB DBs and its junction boxes must be of same make.
Within a week of work order, the contractor shall submit the sample of each item / component of above mentioned approved make for the approval of the Client/Architect/Consultant.
8)
Make of components required to be used by contractor to complete the installation, if not mentioned anywhere, shall be required to GOT IT APPROVED by Client/Architect/Consultant before installation in writing manner.
- 40 -