Concurrent Delays
Concurrent Delays
Concurrent Delays
CONCURRENT DELAYS
CONTRACTOR OBLIGATIONS
Complete works by certain date or
within specified period; possibly with
stage or sectional completion
Progress the works regularly and
diligently
Promptly give notice on specific
probable future events or
circumstances, which may adversely
affect the work, increase the Contract
Price or delay the execution of the
Works
EMPLOYER OBLIGATIONS
Completion of obligations specified in
the contract
implied obligation not to hinder
implied obligation to cooperate
Peak Construction v McKinney Foundations (1970) 1 BLR 111