Karunakaran 2018 IOP Conf. Ser. Earth Environ. Sci. 140 012098

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

IOP Conference Series: Earth and Environmental Science

PAPER • OPEN ACCESS Related content


- Factors affecting the use of modern
Categorization of potential project cost overrun methods and materials in construction
P Mesároš and T Mandiák
factors in construction industry - Efficiency of innovative technology in
construction industry
H Stverkova and V Vaclavik
To cite this article: P Karunakaran et al 2018 IOP Conf. Ser.: Earth Environ. Sci. 140 012098
- Analysis of the causes and consequences
of falls from scaffolding using the Polish
construction industry as an example
A Hoa, B Hoa and M Szóstak
View the article online for updates and enhancements.

This content was downloaded from IP address 112.135.198.173 on 31/10/2019 at 10:30


IConCEES 2017 IOP Publishing
IOP Conf. Series: Earth and Environmental Science 140 (2018)
1234567890 ‘’“” 012098 doi:10.1088/1755-1315/140/1/012098

Categorization of potential project cost overrun factors in


construction industry

P Karunakaran1, A H Abdullah1, S Nagapan1, S Sohu1 and K K Kasvar1


1
Faculty of Civil and Environmental Engineering (FKAAS), Universiti Tun Hussein
Onn Malaysia, Parit Raja, 86400 Batu Pahat, Johor Darul Takzim, Malaysia

E-mail: [email protected]

Abstract. Cost overrun has been severely hit down the economy and reputations for many
construction industry around the world. Many project management tools developed to control
the budget of a project. However, the cost management is still considered poor as there are
many cost overrun issues occurred in the construction industry. Thus, this paper aims to
identify and cluster the potential construction project cost overrun factors according to their
originating groups using the thematic approach. Basically, through literature review, all the
potential factors that may cause cost overrun were screened thoroughly before they were
clustered into seven (7) groups of the originating factors, namely project, contract, client,
contractor, consultant, labour and external. Each potential factor was explained clearly with
some examples based on the Malaysian case studies to illustrate the cost overrun scenario.
These findings may aid in the future to highlight on how to mitigate the critical potential
factors of cost overrun to reduce or overcome its impact on all the stakeholders involved.

1. Introduction
A construction project is conventionally designed by the consultants according to a client’s desire and
it will be executed by the appointed contractors to build the desired design works. Poor cost control
management in the construction industry may cause the project fails to meet its objective to complete
the project on time and within the budget with expected quality. When an organization fails to manage
the finance outflow of a project, then the final construction cost will tend to exceed its initial contract
budget [1] as the cost of correcting error increases as the project goes along [2]. Cost control is
necessary to ensure the money resource does not deplete during the project construction phase which
could lead to unnecessary additional expenses to overcome the excess cost. Thus, it is necessary to
conduct the post-mortem on construction projects to provide lessons for continuous improvement in
project performance [3]. Most of the studies put a great effort to identify and evaluate the potential
factors that may have caused the construction cost to overrun in the last decades [4-6] and some other
related their studies on the effect and cause of the cost overrun factors [7, 8]. However, a deeper
understanding is necessary to understand the originating factors of the poor cost management in the
construction industry. Therefore, this paper focuses on identifying and clustering the potential cost
overrun factors according to their originating groups through literature reviews to clearly understand
how the cost performances of the construction project are actually being affected. Based on the
clustering, a few examples of cost overrun scenarios were included to illustrate the impact of cost
overrun on Malaysian construction industry.

Content from this work may be used under the terms of the Creative Commons Attribution 3.0 licence. Any further distribution
of this work must maintain attribution to the author(s) and the title of the work, journal citation and DOI.
Published under licence by IOP Publishing Ltd 1
IConCEES 2017 IOP Publishing
IOP Conf. Series: Earth and Environmental Science 140 (2018)
1234567890 ‘’“” 012098 doi:10.1088/1755-1315/140/1/012098

2. Related works
An extensive literature on the construction project cost overrun factors has been reviewed
internationally. Cost overrun crisis exists in both developed and developing countries for a very long
time [9]. Most of the studies figured out that more than 50 cost overrun factors are the most commonly
exposed to the construction industry [10-12]. Delay in schedule and increase in the cost are the two
common concerns in the worldwide construction projects. According to [13], time and cost overrun
factors are inseparable since the extension of time normally leads to the overrun of cost.
Different researchers share different opinions on the poor cost performance factors. The Malaysian
construction projects were reported to experience the overruns (time and cost) by 92% [14]. At least
about 90% of the People’s Trust Council (MARA) large construction projects have been facing delay
in a large scale since 1984 [7]. Some blamed the poor working enthusiasm of the lower grade
contractors who do not have proper planning on their cost control strategy, as the general cause of
their failure to achieve the project’s objectives in completing within budget, quality and time [15, 16].
Meanwhile, another portion pointed out that most of the construction industry nowadays had
undergone extensive complexities in terms of convoluted design, adopting advanced technologies as
well as new standards leading the organization fail to manage their finance [17]. Another study
emphasized that the final cost of a project turns uncertain if the size and nature of the project are larger
and complex [18] and one such example is the road or highway construction projects. Unpredictable
geographical location or project topology, bad weather and inaccurate site investigations are the most
common factors faced by the contracted project parties for infrastructural projects [18]. This study is
even similar with the analysis survey conducted by [19] on large construction projects in Malaysia and
with an international comparative assessment analysis performed by [20] on the electricity
infrastructure.
Cost overrun factors can be categorized into several groups. The group of cost overrun factors can
be adapted from [21], for instance, (i) non-compensable factors (unavoidable circumstances faced by
the project parties due to involvement of external parties or environment) and (ii) compensable factors
(circumstances that can be avoided by parties from causing cost overrun). Meanwhile in another study
which is concurrent with the study of [22], [23] also categorized the factors into two similar groups,
but they differentiated the groups as (i) internal cause (circumstances caused by the construction
stakeholders itself) and (ii) external cause (unavoidable circumstance that occurs beyond the control of
the parties involved). In present days, a group of researchers had refined and categorized the factors
into several groups based on the causative factors of the cost overrun factors as tabulated in table 1.

Table 1. Categorization of cost overrun factors by previous researchers.


Number of
Sources Groups of causative factors
groups
Le-Hoai et al. (2008) Owner, consultant, contractor, material/labour, project and external 6
Environmental, construction, construction item, cost estimation and
Ameh et al. (2010) 5
financing
Aziz (2013) Owner, designer, contractor, miscellaneous 4
Derakhshanalavijeh &
Owner, consultant, contractor, project, and material/labour 5
Teixeira (2017)
Niazi & Painting (2017) Client, contractor, consultant, labour, material/equipment and external 6
Cost estimation, construction item, project participant, environmental
Zewdu & Aregaw (2015) 5
and financing
Contract, time, cost, quality, human resource, communications and
Polat et al. (2014) 7
risk

3. Research method
An extensive literature on the common factors influencing the project cost overrun in construction

2
IConCEES 2017 IOP Publishing
IOP Conf. Series: Earth and Environmental Science 140 (2018)
1234567890 ‘’“” 012098 doi:10.1088/1755-1315/140/1/012098

industry all over the world has been reviewed. In order to fully comprehend the meaning of each
causative factor of cost overrun found in the literature, it is extremely important to relate them in the
context of construction project management activities throughout the construction project life cycle.
The causative factors are then clustered and classified carefully into its associated groups. Based on
the aforesaid Table 1, using the thematic approach, the classification or taxonomy of groups of the
causative factors have been refined and presented in Table 2 to fit into seven (7) main categorizations
as shown. The frequency of the repetitive originating factors is taken into consideration to understand
which group well as which originating factor within its associated group is mostly referred to by
previous researchers. Based on Table 2, the descriptions of the related causative factors are delineated
as the followings:

Table 2: Categorization of the cost overrun originating factors’ group.

References
Le-Hoai et al. (2008)

Derakhshanalavijeh

Zewdu et al. (2015)


Ameh et al., (2010)

Niazi et al. (2017)

Polat et al. (2014)


Originating Groups
of Potential Cost

Frequency
et al. (2017)
Aziz (2013)

Overrun Factors

Project x x x 3
Contract x x x 3
Client x x x x x x 6
Contractor x x x x x x 6
Consultant x x x x x x 6
Labour x x x x x 5
External x x x x x 5

4. Potential cost overrun factors

4.1. Project-related factors (PF)


This group defines the uncertainties of project complexities that is being noticed or faced by the
contracted parties only after the contract has been signed [20]. The uncertainties of a project normally
happen due to the presence of unforeseen circumstances during the project life cycle. However, it can
be controlled in the early stages with proper investigations and communications among the
construction stakeholders. Unresolved project uncertainties may cause extension of time which
directly can affect the cash flow. The sudden eruption of disputes due to miscommunication or
relationships problem among the contracted parties are also one type of unexpected uncertainties that
may occur during a construction project.
The design drawings are always based on the client’s requirement, the scope of a project, size of a
project, nature of the project and also geographical location of the project [24] and they are projected
by the architects or consultants. The complications and complexities in the design drawings [12, 25]
which is noticed only during the construction phase may unexpectedly lead to a different level of
technologies to be adopted to construct the structure [24]. For example, hydroelectric projects or the
large construction projects are commonly known for the complexity and such cases have been reported
in the Bakun Hydroelectric Project in Malaysia to have undergone cost overrun against its budget
around US$ 3916 million which is averagely about 417% [20]. It was ranked as the second highest
cost overrun project after the India’s Sardar Sarovar Dam in Gujarat (i.e. cost overrun around 513%
amounting to US$ 6773 million) [20]. Site layout and land acquisition [24, 26] are one of the

3
IConCEES 2017 IOP Publishing
IOP Conf. Series: Earth and Environmental Science 140 (2018)
1234567890 ‘’“” 012098 doi:10.1088/1755-1315/140/1/012098

uncertainty factors that cause schedule slippage in the start of a construction project [18, 27].
Unexpected location difficulties [8, 24] and orientation of the road approach to the site entrance may
cause site mobilization difficulties leading to an increased cost for the transportation services [27, 28].
These factors are the subset of an inappropriate choice of site selection [6, 27]. On the other hand, land
acquisition problems mostly occur in larger construction projects such as roads, bridges, airports and
railway constructions. For example, the area of Kuala Lumpur International Airport 2 (KLIA 2) was
revised and extended from 150, 000 sqm. to 257, 000 sqm. during the construction phase with an
increase of 71% construction area [29]. The authority made last minute decision to increase the
passenger capacity from 30 million to 45 million causing delays in the construction as they had to face
site acquisition problems on the reclaimed lands. The inefficient planning made by the authority
causes the extension of time about two years with the project cost overrun around RM1.6 billion [29,
30].

4.2. Contract-related factors (CF)


This group defines the contract agreement process involved in a construction which directly causes the
cost overrun. This happens due to the involvement of irresponsible contractor, consultant and client
when signing up on an agreement. The over-budget cash flow usually starts from the tendering process
itself due to the improper contract rewarding process by the consultants on behalf of their client.
Awarding the lowest price tender are highly encouraged by the tendering system (procurement
legislation), however, the price bid must be sensible and optimized by ensuring it fully covers the
technical content of the project. Some contractors will go to all lengths (omitting the realistic figure
that may cost the total project completion) just to win the tender without acknowledging the
consequences of their actions by submitting the lowest bid [12, 26, 31, 32]. These type of contractors
are cunning and smart enough to take the opportunities to exploit the weaknesses in the system since
there is no framework for tendering mechanism and it totally depends on the market competition. The
contractors know that many changes will arise in future and contractual claims such as the extension
of time with extra cost claims can be claimed from the clients to cover the omitted realistic figure [8,
12, 32].

4.3. Client-related factors (CiF)


This group defines the cost overrun factors that occurs only because of the clients. For instance, design
changes [24-26] or scope changes [12, 24-26] in a project normally occurs due to the interference of
clients during constructions [25, 26, 31]. Any changes caused by the clients, normally, something that
is acceptable if the clients have the money resource to support the changes and the contractors can
claim the cost once the desired changes have been made. Another matter to be considered is that any
changes related to the designs would take a lengthy period to make decisions among all the parties
involved [25, 26], extra time would be needed for improvements to be made in the standard drawings
[6], extra time to re-evaluate the design and will lengthen the delays in drawings approval [8, 12, 26].
Once the contractor received an approved standard redesigned drawing, additional work [8, 12, 24, 25]
or rework [12] on the project would take place. Eventually, it would result in overtime issues [12, 26]
in order to complete the project on schedule and the extra cost spent on the changes will be reclaimed
from the clients by the contractors through contractual claims. Thus, this is an example of the
sequence flow on how an actual contract sum differs from the final account of a project. Besides that,
changes in owner’s brief [6, 26] could also lead to late decision makings [25, 26] and disputes among
project participants [12, 26]. The longer the delay in decision making, the higher the chances for
project schedule delays and cost overrun.

4.4. Contractor-related factors (CtF)


This group defines the cost overrun factors that are caused by the contractors. For example, it is the
contractor’s responsibility to ensure the capability, capacity and productivity of the equipment is in
compliance with the job requirement prior to the commencement of the construction phase to achieve

4
IConCEES 2017 IOP Publishing
IOP Conf. Series: Earth and Environmental Science 140 (2018)
1234567890 ‘’“” 012098 doi:10.1088/1755-1315/140/1/012098

the highest level of job completion in a shorter period. Utilization of wrong equipment (i.e.
productivity of equipment) may cause the rate of production to be lower than expected during the
construction phase [12, 26]. Mishandling of equipment [26] and misuse of materials [26] may cause
the generation of waste at the site. These issues occur due to the poor monitoring at site [8, 12, 26] by
the appointed site supervisor. In addition, inadequate quality assurance of a project [12, 24, 26] may
end up to be the main factor for the waste generation at the site. The contractors may compromise with
the quality of works due to their benefit realization [6] by using low quality materials [12] or reduce
the quantity of material use below its specification as stated in the design (i.e. fraudulent) [12, 24, 26]
causing the construction work to lose its strength and lead to additional works [6, 12, 31] or reworks
[12].

4.5. Consultant-related factors (CsF)


This group defines the occurrence of cost overrun factors under the consultant responsibility.
Referring to the earlier example of MRT project case as reported by [33], the involvement of
incompetent and inexperienced parties, especially the consulting agencies engaged in examining the
ground conditions are one of the causes of cost overrun of a particular project. The consultants
assumed that the contractors could manage the ground works by piling onto the “very hard, strong
rock” ground condition. Unfortunately, their assumptions failed them. The implications due to their
assumptions were reworked, change in the usage of technology, delay in schedule and re-measurement
of provisional works causing the project to undergone an extensive cost overrun. Apart from that,
incomplete design drawings at the time of tender [8, 12] shows the poor management of consultants
which lead to inaccurate cost estimation at the time of preparing tender [6, 8, 12, 24]. Delay in
reviewing the design document by consultants would also lead to schedule delays and cost
underestimations [6, 8, 12, 27]. Another factor that can affect the schedule delay during the design
phase is lack of required data for the consultants to proceed with the design drawings [25]. The longer
the delay in design, the higher the chances for project cost overrun. Poor design drawings [8, 12, 25],
provision of ambiguous design details [24, 25], impractical and complicated designs [12, 26],
inaccurate site investigation [12] are some of the indicators of inadequate consultant team’s
experience.

4.6. Labour-related factors (LsF)


This group defines the cost overrun factors that are caused by the labours. For example, labour
productivity [6, 8, 12, 24] is one of the essential requirements to ensure the success of projects in the
construction industry. Without active labours, the construction could not achieve its objective to
deliver on time within its contracted budget. Inexperienced labours with poor skills in work may
produce a very low quality of work. Besides that, labour absenteeism [8, 12] shows the morale of
workers towards the working ethics. The absence of labours at the site can be redefined as shortages of
labours [6, 8, 12, 24] which directly affects the productivity of work. This directly leads to schedule
delays and cost overrun. Apart from that, normally the contractors who won contract awards for the
lowest tender bid may try to reduce the salary payment for site workers. This would affect the site
worker’s motivation to perform better [26]. Another point worth to be noted is the cultural clash
among the labours [6, 8, 12, 24]. Most of the construction industries nowadays are hiring to the
foreign labours. Multiple races from different countries with different lifestyles and attitude may cause
frequent arguments among them. The poor relationship among them may also cause the productivity
of the construction work to turn low. Besides that, problems chaining from the financial difficulties by
the clients or contractors may subsequently end up in labour strikes [12, 26]. The construction work
will be abandoned till the payment is being made.

5
IConCEES 2017 IOP Publishing
IOP Conf. Series: Earth and Environmental Science 140 (2018)
1234567890 ‘’“” 012098 doi:10.1088/1755-1315/140/1/012098

4.7. External-related factors (EF)


This group defines unexpected circumstances causing cost overrun that occurs beyond the control of
construction stakeholders such as nature controlled related factors, law, and regulations related factors,
or even other environmental related factors.
Such example of nature controlled related factor is the act of nature [8, 12, 24, 26] which may
cause the construction work to be stopped immediately causing schedule delay and cost overrun such
as weather changes, earthquake, floods and so on.
Examples of law and regulation related factors are the delay in approvals from the local authorities
[26]. Refreshing to the aforesaid case study on the construction of Universiti Malaysia Kelantan, the
delay in submission of the application for a time extension was not the only factor that caused the time
overrun. In actual, the delay was even further prolonged by late approvals from the local authority by
about 176 to 445 days [29]. The late approval from the local authority may have been caused by the
law and regulatory framework of a country [12, 26]. The authority has to follow all the necessary
procedures to approve the applications. The approval may even be longer if it is a public construction
project. Examples of other environmental related factors are inflations [12, 24, 26] and instability of
economy [6, 8, 12, 26] which may indirectly affect the construction projects all over the country. In
Malaysia, [34] reported in short on the impact of financial crisis towards the construction of The Plaza
Rakyat building such that “The RM1.4bil mixed-commercial development was 30% complete about
15 years ago when the developer, Plaza Rakyat Sdn Bhd (PRSB), ran into financial difficulties during
the 1997/1998 Asian financial crisis”. The labour, material, equipment and transportation cost [6, 8,
12, 26] would turn unpredictable during the construction phase due to the inflations [12, 24, 26] and
economic stability [6, 8, 12, 26] of the country.

5. Conclusion
In a nutshell, the intention of the paper has been achieved where the factors that cause cost overrun
together with its group of originating factors have been identified. The findings were limited up to the
scenarios in the Malaysian construction industries. In total, seven originating groups of cost overrun
factors have been refined from previous studies with comprehensive details on how and why the
factors arise with few examples of Malaysian based case study. With the identifications of the
originating cause, it would be helpful in future to further the study by identifying the most critical
factors of cost overrun affecting the construction project cost performances and also corrective actions
for the identified critical factors.

Acknowledgements
In a nutshell, the intention of the paper has been achieved where the factors that cause cost overrun
together with its group of originating factors have been identified. The findings were limited up to the
scenarios in the Malaysian construction industries. In total, seven originating groups of cost overrun
factors have been refined from previous studies with comprehensive details on how and why the
factors arise with few examples of Malaysian based case study. With the identifications of the
originating cause, it would be helpful in future to further the study by identifying the most critical
factors of cost overrun affecting the construction project cost performances and also corrective actions
for the identified critical factors

References
[1] Le-Hoai L, Lee Y. D. and Lee J Y 2008 Delay and Cost Overruns in Vietnam Large
Construction Projects: A Comparison with Other Selected Countries KSCE Journal of Civil
Engineering 12 367
[2] Prabhakar G P 2008 Projects and Their Management: A Literature Review Int. J. Business and
Management 3 3
[3] Williams T 2004 Identifying the Hard Lessons from Projects-Easily Int. J. Project Management
22 273

6
IConCEES 2017 IOP Publishing
IOP Conf. Series: Earth and Environmental Science 140 (2018)
1234567890 ‘’“” 012098 doi:10.1088/1755-1315/140/1/012098

[4] Ameh O J, Soyingbe A A and Odusami K T 2010 Significant Factors Causing Cost Overruns in
Telecommunication Projects in Nigeria J. Const. in Developing Countries 15 49
[5] Aziz R F 2013 Factors Causing Cost Variation for Constructing Wastewater Projects in Egypt
Alexandria Engineering Journal 52 51
[6] Belachew A S, Mengesha W J and Mohammed M 2017 Causes of Cost Overrun in Federal
Road Projects of Ethiopia in Case of Southern District American J. Civil Engineering 5 27
[7] Abdullah M R, Abdul Azis A A and Rahman I A 2009 Potential Effects on Large Mara
Construction Projects due to Construction Delay Int. J. Integrated Engineering (Issue on
Civil and Environmental Engineering) 1 53
[8] Abusafiya H A M and Suliman S M A 2017 Causes and Effects of Cost Overrun on
Construction Project in Bahrain: Part I (Ranking of Cost Overrun Factors and Risk Mapping)
Hedaya Modern Applied Science 11 20
[9] Sambasivan M and Soon Y W 2007 Causes and Effects of Delays in Malaysian Construction
Industry Int. J. Project Management 25 517
[10] Ali M, Mangi S A, Sohu S, Jamali Q B H and Kaleemullah 2017 Major Factors of Budget
Overrun in Construction of Road Project of Sindh, Pakistan Eng. Sci. Tech. Int. Research J.
1 28
[11] Patil Y K and Bhangale P P 2016 Investigation of Factors Influencing Cost Overrun in High
Rise Building Construction Int. J. Latest Trends in Engineering and Technology (IJLTET) 6
338
[12] Memon A H, Rahman I A and Aziz A A A 2011 Preliminary Study on Causative Factors
Leading to Construction Cost Overrun Int. J. Sus. Constr. Eng. Tech. 2 57
[13] Aibunu A A and Jagboro G O 2002 The Effects of Construction Delays on Project Delivery Int.
J. Project Management 20 593
[14] Rahman I A, Memon A H, Karim A A and Azis A A A 2012 Assessing the Effects of
Construction Resources towards Cost Overrun using PLS Path Modelling Sci. Series Data
Report 4 2
[15] Takim R 2005 A framework for successful construction project performance (Glasgow
Caledonian University, UK: Ph. D Thesis)
[16] Endut I R 2008 Framework for minimising time overruns of Malaysian construction projects
(Glasgow Caledonian University, UK: Ph. D Thesis)
[17] Bakhary N A, Adnan H and Ibrahim A 2017 Improving Construction Claim Management in
Malaysian Construction Industry The 6th International Conference of Euro Asia Civil
Engineering Forum (EACEF 2017) vol. 138 (Seoul, South Korea: EDP Sciences) 1
[18] Flyvberg B, Holm M K S and Buhl S L 2002 Cost Underestimation in Public Works Projects:
Error or Lie? J. American Planning Association 68 279
[19] Memon A H, Rahman I A and Aziz A A A 2012 The Cause Factors of Large Project's Cost
Overrun: A Survey in the Southern Part of Peninsular Malaysia Int. J. Real Estate Studies 7
1
[20] Sovacool B K, Gilbert A and Nugent D 2014 An International Comparative Assessment of
Construction Cost Overruns for Electricity Infrastructure Energy Research & Social Science
3 152
[21] Pall G K, Bridge A J, Skitmore M and Gary J 2016 A Comprehensive Review of Delays in
Power Transmission Projects IET Generation, Transmission and Distribution 10 3393
[22] Bolton J 1990 Types of Claims, Construction and Disruption Claims (London: Portman Inter-
Continental)
[23] Ahmed S M, Azhar S, Kappagntula and Gollapudil D 2003 Delay in Construction: A Brief
Study of Florida Construction Industry Proc. of the 39th Annual ASC Conference. (South
Carolina, USA) 257
[24] Hoe Y E 2013 Causes of abandoned construction projects in Malaysia (Universiti Tunku Abdul
Rahman: Master Thesis)

7
IConCEES 2017 IOP Publishing
IOP Conf. Series: Earth and Environmental Science 140 (2018)
1234567890 ‘’“” 012098 doi:10.1088/1755-1315/140/1/012098

[25] Mohammad N, Che Ani A I and Rakmat A O 2017 Causes and Effects of Variations Orders in
the Construction of Terrace Housing Projects: A Case Study in the State of Selangor,
Malaysia Int. Supply of Chain Management 6 226
[26] Niazi G A and Painting N 2017 Significant Factors Causing Cost Overruns in the Construction
Industry in Afganistan Procedia Engineering 182 510
[27] Rathi A S and Khandve P V 2014 Study of Factors Influencing Cost Overrun: An Overview
Int.J. Sci. Research (IJSR) 5 334
[28] Zewdu Z T and Aregaw G T 2015 Causes of Contractor Cost Overrun in Construction Projects:
The Case of Ethiopian Construction Sector Int. J. Business and Economics Research 4 180
[29] Roslan N 2015 Mitigating measures for controlling time and cost overrun factors (Universiti
Tun Hussein Onn Malaysia: Master Thesis)
[30] Malaysia Airports Holdings Berhad 2010 Annual Report 2010 (Malaysia: Malaysia Airports
Holdings Berhad)
[31] Memon A H, Rahman I A, Abdullah M R and Aziz A A A 2010 Factors Affecting Construction
Cost in Mara Large Construction Project: Perspective of Project Management Consultant Int.
J. Sus. Const. Eng. Tech. 1 41
[32] Laryae S 2008 The Tendering Process and Performance Analysis of a Public Building Project in
Ghana RICS Construction and Building Research Conf. 1 (Dublin: RICS) 1
[33] Palansamy Y 2017 Citing ‘Online Challenges’, MRT Corp claims delay unavoidable Retrieved
on July 18, 2017 from http://www.themalaymailonline.com/malaysia/article/citing-onsite-
challenges-mrt-corp-claims-delay-unavoidable
[34] Ravindran S 2017 There’s little news on status of the long abandoned plaza rakyat project
Retrieved on August 11, 2017 from http://www.thestar.com.my/news/community/
2013/08/17/buyers-keep-their-fingers-crossed-theres-little-news-on-status-of-the-
longabandoned-plaza-rakyat-pro/

You might also like