Project:-Sub Contractor: - Date: - Item: - Period

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Project :- Ampara I Road (AM-02)

Sub Contractor :- SJT Engineering Pvt.Ltd pag -1


Supplier:- NEM Construction Pvt Ltd
Date :- 08.06.2020
Period 31st March 2020
Item :- Asphalt Concrete wearing course (Ex-Plant)

Cummulative
Date Description Unit Previous Qty This Period Qty
Total Qty
24-Feb-2020 Asphalt Wearing Concrete Course MT 125.85 125.85
25-Feb-2020 Asphalt Wearing Concrete Course MT 173.85 173.85
26-Feb-2020 Asphalt Wearing Concrete Course MT 84.76 84.76
27-Feb-2020 Asphalt Wearing Concrete Course MT 205.56 205.56
11-Mar-2020 Asphalt Wearing Concrete Course MT 111.90 111.90
12-Mar-2020 Asphalt Wearing Concrete Course MT 249.57 249.57
13-Mar-2020 Asphalt Wearing Concrete Course MT 403.73 403.73
17-Mar-2020 Asphalt Wearing Concrete Course MT 246.92 246.92
13-Mar-2020 Asphalt Wearing AM-01 MT (403.73) (403.73)
09-Jun-2020 Asphalt Wearing Concrete Course MT 207.30 207.30
10-Jun-2020 Asphalt Wearing Concrete Course MT 173.13 173.13
11-Jun-2020 Asphalt Wearing Concrete Course MT 225.40 225.40
12-Jun-2020 Asphalt Wearing Concrete Course MT 350.02 350.02
13-Jun-2020 Asphalt Wearing Concrete Course MT 245.22 245.22
19-Jun-2020 Asphalt Wearing Concrete Course MT 290.96 290.96
20-Jun-2020 Asphalt Wearing Concrete Course MT 228.68 228.68
21-Jun-2020 Asphalt Wearing Concrete Course MT 328.85 328.85
-
-
-
-
-
-
-
-
-
-
-
-

Total Quantity 1,198.41 2,049.56 3,247.97