UWUCWPhaseIIBNCBSW BOQ
UWUCWPhaseIIBNCBSW BOQ
UWUCWPhaseIIBNCBSW BOQ
BILL OF QUANTITIES
MAIN SUMMARY
AMOUNT
Bill No DESCRIPTION
Rs Cts
1 PRELIMINARIES
LAND PREPARATION
2 DEMOLISHING
3 LAND LEVELLING
CONSTRUCTION OF BUILDING
4 CIVIL WORKS - SUBSTRUCTURE
EXTERNAL WORKS
8 LANDSCAPING & EXTERNAL DRAINAGE SYSTEM
………………………………………………..
Signature of Tenderer Date :-……………………………
54- 1
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
BILL OF QUANTITIES
Note:
1 The Engineer/ Consultant may modify or amended any item , or delete inappropriate
item/s or add new item/s , depending on the nature of the proposed work.
3 The above recommended percentage may be adjusted by the Employer/Consultant to suit the
particular project.
4 The tenderer is advised to visit the site of the proposed work, as it is his responsibility to ascertain the
conditions,govering access to the site, external working space, storage area, status of the adjoining
properties etc.
Mode of Amount
Item Description payment Unit Rs. Cts.
A - PRELIMINARIES
54- 2
Mode of Amount
Item Description payment Unit Rs. Cts.
2 Provisional Sum for providing an Advance Payment A P.S 335,000.00
Security
Engineer's Facilities
Contractor's Facilities
54- 3
Mode of Amount
Item Description payment Unit Rs. Cts.
8 Provide service & maintaining for contractors site D Item
office (getting Telephone, Electricity & water supply
connection and fax & email).
Setting Out
54- 4
Mode of Amount
Item Description payment Unit Rs. Cts.
Health, Safety & Environment
21 Allow lump sum to supply & fix name board, size C Item
3.0mx2.0m as directed and approved by the
Engineer. Rate to include for erection & fixing to the
earth firmly on to the concrete base.
23 Allow Provisional Sum for supplying & fixing of plaque P.S 200,000.00
as directed.
54- 5
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY- BADULLA
BILL OF QUANTITIES
BILL NO 02 - DEMOLISHING WORKS
2.3 Allow provisional Sum for shifting of under ground PS Allow 3,200,000.00
Electrical Fiber cable, water supply pipes etc.
54- 6
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
BILL OF QUANTITIES
3B4 Back Filling with availabe material for filling under m3 500
floors including watering and well ramming using
Whacker or other similar machine in 75mm layers as
directed
54- 7
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
BILL OF QUANTITIES
SUB SUMMARY
AMOUNT
ITEM DESCRIPTION
Rs. Cts.
SUBSTRUCTURE
4C CONCRETE WORKS
4D MASONRY WORKS
4E MISCELLANEOUS WORKS
54- 8
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
BILL NO 04- CIVIL WORKS - SUB STRUCTURE
Excavation
4B-1 Excavation for wall & column foundation to a depth not m3 340
exceeding 1.5m in any material except rock requiring
blasting, part return fill in and rammed and surplus
spreading within the site as directed.
Filling
4B-3 Back Filling with availabe material for filling under 3 340
m
floors including watering and well ramming using
Whacker or other similar machine in 75mm layers as
directed
4B-4 Back Filling with borrowed filling material ( gravel) for 3 150
m
filling under floors including watering and well
ramming using whacker or other similar machine in
75mm layers as directed
54- 9
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
Surface Treatment
Sub Total of Excavation and Earth work Carried to Sub Summary of Bill
4C - CONCRETE WORKS
54- 10
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
Formwork
Rate for formwork shall include for all necessary Note
boarding, supports, erecting, framing, cutting angles,
cleaning, apply approved foam oil, wetting before
placing concrete, removal etc.
Rate for form work shall include for all necessary Note
measures to provide fair face finish.(Concrete faces
should be finished such a way to finish only with cement
base putty. If not additional work involved to level the
surface should be born by the Contractor)
Reinforcement
All reinforcement shall be as per relevant British Note
Standards having minimum characteristic strength of
460 N/mm2 for ribbed tor steel and 250 N/mm2 for
mild steel.
Rate shall include for necessary tests as per BS4449 and Note
SLS 375.
All reinforcement shall be free from mill scale, dirt, oil, Note
paint, grease or loose rust before fixing in position and
shall be brushed with a stiff wire brush as directed.
C15(15) Concrete
54- 11
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
4C-4 In Tie beam 3 18
m
FORMWORK
REINFORCEMENT
Mild steel
4C-18 Mild steel in columns & beams kg 50
4D - MASONARY WORKS
54- 12
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
4E - MISCELLANEOUS WORKS
4E-1 20mm thick 1:3 cement sand rendering for plinth m2 40
plaster including finishing smooth with Grey cement
floating coat.
4E-3 Supplying & laying " Geotextile" layer behind the wall m2 48
Type T.S 30
54- 13
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
BILL OF QUANTITIES
SUB SUMMARY
AMOUNT
ITEM DESCRIPTION
Rs Cts
5 SUPER STRUCTURE
5C CONCRETE
5D BRICK WORK
5E WALL FINISHES
5F FLOOR FINISHES
5G CEILING FINISHES
5H PAINTING
5K ROOFER
5L WATER PROOFING
5M MISCELLANEOUS WORKS
54- 14
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
BILL OF QUANTITIES
Formwork
Rate for formwork shall include for all necessary Note
boarding, supports, erecting, framing, cutting
angles, cleaning, apply approved foam oil, wetting
before placing concrete, removal etc.
54 -15
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
Film coated Plywood or other equivalent quality Note
approved type of shuttering to produced to have
fair faced concrete finish. Mould oil should be
applied to formwork surfaces before using.
Rate for form work shall include for all necessary Note
measures to provide fair face finish.(Concrete
faces should be finished such a way to finish only
with cement base putty. If not additional work
involved to level the surface should be born by the
Contractor)
Reinforcement
All reinforcement shall be as per relevant British Note
Standards having minimum characteristic strength
of 460 N/mm2 for ribbed tor steel and 250
N/mm2 for mild steel.
54 -16
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
FORMWORK
54 -17
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
5C-24 Second floor level to Third floor level 2 130
m
REINFORCEMENT
54 -18
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
High Yield steel reinforcement for slab & beams
Mild steel
5C-54 Mild steel reinforcement kg 250
5D-BLOCK WORK
Rate shall include for lifting, handling, wetting, all Note
rough and fair cuttings, plumbing, reveals, rough
arches, raking out all joints for pointing plastering,
cutting chases, making good at the completion.
54 -19
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
5E - WALL FINISHES
54 -20
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
5F - FLOOR FINISHES
(b) Fair edges, internal angles for Treads and risers Note
Floor Tiling
54 -21
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
Supplying and laying of non slip homogeneous
floor tiles of approved colour & size 600mm x
600mm for floors on 12mm thick, 1:3 cement
mortar, joint filled with tile grout to match the
colour of tiles and cleaning. (Prime Cost of
Rs.1000.00- 1300.00 per tile) ( F1)
54 -22
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
5F12 Supplying and laying of homogeneous rustic floor 2 180
m
tiles of approved colour & size 300mm x 300mm
for stair case on 12mm thick, 1:3 cement mortar,
joint filled with tile grout to match the colour of
tiles and cleaning. (Prime Cost of Rs.200.00-
250.00 per tile)
5G - CEILING FINISHES
5H- PAINTING
54 -23
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
Reveal, Column Projections, undersides of lintels Note
and wall ends less than 300mm shall not be
measured and shall be incorporated in other
measurements. Isolated columns shall be
measured for payments.
54 -24
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
5H-12 Third Floor 2 80
m
54 -25
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
5J2 Supplying and fixing door type D2, size 2 2
m
900x2100mm Alumimium framed single sash
door with bottom solid panel(01 nr).
54 -26
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
5J12 Supplying and fixing type FL1, size 900x600mm, 2 3
m
Powder coated Aluminium framed fanlight (04 nr).
Sub Total for Wood Work Carried Sub Summary of Bill No.05 -
All steel used in the work shall comply with the Note
relevant British Standards and to the
specifications.
All steel shall be new and each member shall be Note
free from any built- weld or other forms of splice
for the full length between joints shown in or
indicated in the drawings unless such splice shall
have been shown in the approved drawings.
Inspections
All steel work shall be subjected for inspection by Note
the Engineer. The steel works shall not be moved
from the place of fabrication nor primed or
painted until the approval of the Engineer has
been obtained for the fabrication of steel work.
54 -27
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
Welding
No welding shall be done until approval of the Note
prepared surface has been obtained. All welding
shall be carried out under the supervision of
qualified persons.
Roof Structure
54 -28
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
5K-4 Allow Provisional Sum for Construction of steel P.S Allow 4,000,000.00
portal frame for first floor roof terrace
Roof Covering
5K-6 Supplying & laying 0.47 TCT colour bonded Zn/Al m2 110
roofing sheet on Steel frame work. Steel frame
work measured separately. Rate to include for
necessary fasteners, gable capping, edge capping
and other fixing arrangements.
Roof Plumber
54 -29
ITEM DESCRIPTION UNIT QTY RATE AMOUNT
Rs. Cts. Rs. Cts.
L- WATER PROOFING
Sub Total for Roof Covering Carried to Sub Summary of Bill No.05 -
5M-2 Allow for unforeseen work during estimating Pro. Allow 1,475,000.00
phase which may occure during construction sum
period.
Sub Total for Roof Covering Carried to Sub Summary of Bill No.05
54 -30
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
BILL OF QUANTITIES
SUB SUMMARY
AMOUNT
ITEM DESCRIPTION Rs Cts
54- 31
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
BILL OF QUANTITIES
General Notes:
54- 32
Item Description Unit Qty. Rate Amount
Rs. Cts. Rs. Cts.
The quantities given in the BOQ are provisional Note
quantities and shall not to be considered as
exact quantities of the works under the
Contract. The Contractor shall determine actual
quantity based on the Specifications and the
Drawings issued under the Contract Agreement.
54- 33
Item Description Unit Qty. Rate Amount
Rs. Cts. Rs. Cts.
(d) All specials such as elbows, bends, tees, Note
junctions, plugs, reducers and similar necessary
pipe fittings. (Valves may be measured
seperately)
Valves
Supplying &fixing following valves.
54- 34
Item Description Unit Qty. Rate Amount
Rs. Cts. Rs. Cts.
DISTRIBUTION MAIN
Pipe Work
54- 35
Item Description Unit Qty. Rate Amount
Rs. Cts. Rs. Cts.
(c) all necessary fixtures for sanitary fittings and Note
special connection to water supply, wastewater
and sewer lines
54- 36
Item Description Unit Qty. Rate Amount
Rs. Cts. Rs. Cts.
Supply and installation of under counter wash
basins in overall white vitreous china including
40mm (1 1/4") dia. plastic bottle trap, 20mm
(1/2") dia. 01 nr. plastic (Water tech or
equivalent) pillar tap of approved quality, 40mm
(1 1/4") dia. waste plug and chain, PVC flexible
hose, brackets with all other accessories and
special connection to complete work in order in
all toilets. Rate to include for fixtures. Angle
valve measured separately. (Prime cost per
wash basin Rs.13,000.00, prime cost of pillar
tap~ RS. 3600.00)
54- 37
Item Description Unit Qty. Rate Amount
Rs. Cts. Rs. Cts.
54- 38
Item Description Unit Qty. Rate Amount
Rs. Cts. Rs. Cts.
54- 39
Item Description Unit Qty. Rate Amount
Rs. Cts. Rs. Cts.
6Q-2 Supplying & Installation of Pre cast soakage pit ( nr 2
1200mm diax 2400mm) with heavy duty cover
slab Rate to include for excavation, concreting
& installation as directed.
54- 40
PROPOSED STUDENT WELFARE CENTER FOR UVA WELLASSA UNIVERSITY - BADULLA
Engineer's Estimate for Electrical Installation
Bill No:07
Item Description Unit Qty. Rate Amount
54- 41
Item Description Unit Qty. Rate Amount
VI All the quantities given here are approximated
values and Quantities may change with the actual
installation at the site.
Note:-
Recommended Brands for Electrical Items
C Fans
KDK Original or brands approved by the Engineer.
E Light Fittings
Japanes, malayasian made or brands approved
by the Engineer.
Philips,Osram or Eq.
G Cables
Kelani,Sierra,ACL or Eq.
54- 42
Item Description Unit Qty. Rate Amount
I PVC Trunking
KTK or brands approved by the Engineer.
2.00 MDB
Supply and installation of wall mounted switch No 1
gear with steel enclosure to the approval of the
engineer with equipments as specified in each
board.Wall recessed mounting type. (wall
mounted surface type)
54- 43
Item Description Unit Qty. Rate Amount
4.00 Cables
Supply and installation (with all materials required
including conduits and termination) of following
cables.
54- 44
Item Description Unit Qty. Rate Amount
5.3.1 In ground floor Nos 1
5.3.2 In first floor Nos 1
5.3.3 In second floor Nos 1
54- 45
Item Description Unit Qty. Rate Amount
6.00 Fans
6.10 Ceiling Fans
Supply & installation of 1400mm (56") , 80W
sweep ceiling fan , complete with regulator, fan
hook, extension rod & attachment.
54- 46
Item Description Unit Qty. Rate Amount
10.00 Drawings
Provide three sets of 'As Built Drawings' (A3 size) Item
to cover electrical distribution system binded as
books.
54- 47
Item Description Unit Qty. Rate Amount
11.30 Wiring of Telephone Socket Outlets
Wiring up to the telephone socket outlets from
the respective floor junction box using approved
type 2 pair UTP ( Unshielded Twisted Pair )
telephone cable drawn through securely fixed
concealed PVC conduits comprising all other
accessories required.
54- 48
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
ENGINEERS ESTIMATE
BILL NO. 08- LANDSAPING & EXTERNAL DRAINAGE SYSTEM
8.5 Allow Provisional sum for storm water P.S Allow 2,000,000.00
drainage system
54- 49
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
ENGINEERS ESTIMATE
SUB SUMMARY
AMOUNT
ITEM DESCRIPTION Rs Cts
54- 50
PROPOSED STUDENT WELFARE CENTRE FOR UVA WELLASSA UNIVERSITY - BADULLA
ENGINEERS ESTIMATE
9.1.8 Supplying & laying " Geotextile" layer behind the 2 200
m
wall Type T.S 30
54-51
Item Description Unit Qty. Rate Amount
Rs. Cts. Rs. Cts.
9.2 TOE WALL ( Random Rubble Masonry )
Parapet wall
54-52
Item Description Unit Qty. Rate Amount
Rs. Cts. Rs. Cts.
9.3.14 Prepare and apply one primer coat and two coats m2 75
of weathershield paint of approved colour and
quality to external rough plastered face of walls
and reveals.
54-53