INTRODUCTION
Quarry operation is the most common surface mining activities in Nigeria and in the world
which involve the production of dimension stones and aggregates for the purpose of
construction, ornamental and interior decoration. Rocks such as granite, limestone, marble,
dolomite etc. are exploited for production of different sizes aggregates and slabs (Ashmole and
Motloung, 2008).In locating economically viable deposit for aggregates production, the factors
to be considered include, the available tonnage, mineable quality of aggregate, nearness to
market or distance from major use areas, transportation cost, government regulation and
operating cost. The energy required to crush rocks into aggregates is proportional to the amount
of new surface area that is created; hence, a very important percentage of the energy consumed
to produce construction aggregates is spent in producing non-commercial fines.
Aggregates are defined as inert, granular, and inorganic materials that normally consist of stone
or stone-like solids. They can be used alone (in road bases and various types of fill) or can be
used with cementing materials (such as asphalt cement or Portland cement) to form composite
materials or concrete (Guimaraes et al., 2007). The most popular use of aggregates is to form
Portland cement concrete. The importance of using the right type and quality of aggregates
cannot be overemphasized. Fine aggregates generally consist of natural sand or crushed stone
with most particles smaller than 5 mm (Bamigboye et al., 2016). Coarse aggregates is a
combination of gravels or crushed stone with particles predominantly larger than 5 mm (0.2
6
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
in.) and generally between 9.5 mm and 37.5 mm ( 3⁄8 in. and 1½in.). Some natural aggregate
deposits, called pit-run gravel, consist of gravel and sand that can be readily used in concrete
after minimal processing. Aggregates must conform to certain standards for optimum
engineering use i.e. they must be clean, hard, strong, durable particles free of absorbed
chemicals, coatings of clay, and other fine materials in amounts that could affect hydration and
bond of the cement paste (PCA, 2015). Aggregate particles that are friable or capable of being
split are undesirable. Aggregates containing any appreciable amounts of shale or other shaly
rocks, soft and porous materials, Coarse aggregate should be avoided; certain types of chert
should be especially avoided since they have low resistance to weathering and can cause
surface defects such as popouts. Identification of the constituents of an aggregate cannot alone
provide a basis for predicting the behaviour of aggregates in service. Visual inspection will
often disclose weaknesses in coarse aggregates. Service records are invaluable in evaluating
aggregates (Vasarhely and Bobet, 2000).This research discusses cost evaluation in the total
process of aggregate production from extraction through processing.
Classification of Aggregate
According to Zongjin (2014), aggregates can be divided into several categories according to
different criteria.
7
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
Physical Properties of Aggregates
The physical properties of aggregates refer to the physical structure of the particles that make
up the aggregate.
Surface Texture
Surface texture is the pattern and the relative roughness or smoothness of the aggregate particle.
Surface texture plays a big role in developing the bond between an aggregate particle and a
cementing material. A rough surface texture gives the cementing material something to grip,
producing a stronger bond, and thus creating a stronger hot mix asphalt or Portland cement
concrete. Surface texture also affects the workability of hot mix asphalt, the asphalt
requirements of hot mix asphalt, and the water requirements of Portland cement concrete. Some
aggregates may initially have good surface texture, but may polish smooth later under traffic.
These aggregates are unacceptable for final wearing surfaces. Limestone usually falls into this
category. Dolomite does not, in general, when the magnesium content exceeds a minimum
quantity of the material (Balamurali, 2014).
Bulk density: the volume includes the pores inside a single aggregate.
𝑊𝑒𝑖𝑔ℎ𝑡
BD = 𝑉𝑠𝑜𝑙𝑖𝑑+𝑉𝑝𝑜𝑟𝑒𝑠 (2)
8
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
BD can be either BDSSD or BDAD according to the moisture condition of aggregate when it is
weighed.
Specific gravity (SG): mass of a given substance divided by unit mass of an equal volume of
water (it is the density ratio of a substance to water). As an example, specific gravity
information about a particular aggregate helps in determining the amount of asphalt needed in
the hot mix asphalt. If an aggregate is highly absorptive, the aggregate continues to absorb
asphalt, after initial mixing at the plant, until the mix cools down completely. This process
leaves less asphalt for bonding purposes; therefore, a more porous aggregate requires more
asphalt than a less porous aggregate. The porosity of the aggregate may be taken into
consideration in determining the amount of asphalt required by applying the three types of
specific gravity measurements.
Aggregate Voids
There are aggregate particle voids, and there are voids between aggregate particles. As solid as
aggregate may be to the naked eye, most aggregate particles have voids, which are natural
pores that are filled with air or water. These voids or pores influence the specific gravity and
absorption of the aggregate materials. The void within an aggregate particle is not the same as
the void system which makes up the space between particles in an aggregate mass. The voids
between the particles influence the design of hot mix asphalt or Portland cement concrete.
Hardness
The hardness of the minerals that make up the aggregate particles and the firmness with which
the individual grains are cemented or interlocked help to control the resistance of the aggregate
to abrasion and degradation. Soft aggregate particles are composed of minerals with a low
9
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
degree of hardness. Weak particles have poor cementation. None of this type is acceptable. The
Mohs Hardness Scale is frequently used for determination of mineral hardness. Although there
is no recognizable specification or requirement which pertains to Mohs Hardness Scale, the
interpretation, concept, and use of this scale is useful for the field identification of potentially
inferior aggregates (Neville, 2011).
Stripping Operation
As a first step, a producer is required to designate a detailed stripping procedure for each and
every deposit that is mined. The overburden is stripped with an excavator, and is placed in large
dump trucks known as haul trucks. Haul trucks are designed for earth moving across rugged
environment. Overburden is a waste rock consisting of consolidated and unconsolidated
material that must be removed to expose the underlying ore body. It is desirable to remove as
little overburden as possible in order to access the ore of interest.
Drilling Operation
Drilling can be define as an artificial creation of cavity or hole in an ore body for samples
collection for further analysis, for casing sinking and for placement explosive. Drilling is very
important in mining and it determines the cost of production. Some factors influencing the rate
of bit penetration includes: type and size of drill, bit size; bit type and condition, drill mounting,
torque capacity, compressor pressure, flushing medium, lubrication, thrust, rotational speed,
rock type and structure. Drilling is of different types:
i. Primary Drilling: This is done on insitu rock with drilling machine of different type
sach as ROC 601, ROC 301, CM 348, which are powered by compressors. Primary
drilling must give a definite operation in order to carry out primary blasting such as
diameter of the holes, bench height of the rock, burden and spacing on the rock.
ii. Secondary Drilling: This is done on already fragmented rock of larger sizes
(boulders) for purpose of size reduction by the means of secondary blasting. It is
carried out by using a Jack Hammer, which is powered by a pneumatic compressor.
It is also give room for proper haulage to the crushing.
Blasting Operation
Blasting is defined as a fragmentation of rock by means of explosives and its accessories for
the subsequent extraction or process (Sushil, 1997). After the blast holes have been drilled to
the requirement, the next operation is to the charge the holes with explosives and blast. The
10
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
size of the drilling bit is a major factor in the choice of explosive to be used. Both the low
explosives and high explosives are used. The low explosive used is ANFO and the high
explosive used is Gelatine dynamite. Increasing the quantity of fuel added to the ammonium
nitrate will result into red fumes being produced after blasting. So, 96% of ammonium nitrate
and 4% of diesel oil are mixed together to give the required ANFO. In other words, for every
25kg of explosive, 1.75 litres of diesel oil is added, Use a long bamboo rod to through the drill
holes of about 6m depth. Make primer cartridge (i.e. explosive cartridge primer cord). Do the
primer charge and insert an explosive cartridge primer into each drilled hole. Load the holes
after primer charge with high explosives and ANFO. Stem/seal the holes with granite chips.
Connect all the charged holes together (either in series or parallel). Insert MS Delay detonator
in between each holes connected and clipped plain detonator with shock tube. Insert shock
tubes into the Blasting Machine or Exploder and fire. Escape from danger area to safe place,
500m away using a fast moving vehicle. After the blast, go back and check the outcome
(result).The quantity of explosive is also function of the drilling depth and rock mass (Sharma,
2012).
Loading
After blasting operation has been carried out, the fragmented rock materials are usually loaded
into dump trucks and tippers. Both front – end loader and back – hoe shovel are used for loading
fragmented rock materials into dump trucks for haulage. The back-hoe shovel (crawler
mounted) is capable of removing hanging rocks on the quarry face.
Haulage of Material
The fragmented rocks are transported by haulage (primarily horizontal movement) to the
primary crusher. As the blasting cannot be absolutely perfect, boulders bigger than the normal
requirement (1.5m) are kept aside for secondary blasting so that they can pass through the
hopper to the jaw crusher.
Crushing Process
Crushing is the process of reducing blasted rocks into smaller sizes needed for use such as in
construction of bridges, tunnels, roads and building activities (Hadin, 2001).Crushing of
fragmented rocks are unit of communition and particle sizing. The crushing plant is an
assemblage of primary crusher and secondary crusher. The following product sizes (granite)
can be obtained by methods of screening immediately after crushing:
¾ inch 19 – 25mm
½ inch 5 – 19mm
11
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
Cost Estimating
An estimate is a judgment, forecast or prediction. A cost therefore is a judgment or opinion of
the cost of a process, project, product or services. It is a prediction or forecast of what a work
output or work activity will cost (Rodney, 1991). According to the Society of Cost Estimating
and Analysis (SCEA), estimating is the art of approximating the probable worth or cost of an
activity based on information available at that time. Cost finding is the process by which the
company obtain estimates of the costs of producing a product, providing a service, performing
a function, or operating a department.
The most fully developed methods of costs finding are used to estimate the costs that have been
incurred in a factory to manufacture a specific products. The simplest of these methods is
known as process costing. In this method, the accountant first accumulates the costs of each
production operation or process for a specified time frame. This sum is then restated as an
average by dividing the total costs of production by total output in the period. The process
costing can be used whenever the output of an individual processes is reasonably uniform or
homogenous, as in cement manufacturing, flour milling, other relatively continuous production
processes.
The second method is job - order costing, which is used when individual production centres
or department work on a variety of products rather than just one during a typical time period.
Two categories of factory cost are recognised under this method: prime cost and factory
overhead costs. Prime costs are those that can be traced directly to a specific batch, or job lot
of products (Pava, 2014). These are the direct labour and direct materials cost of production.
Overhead costs, on the other hand, are those that can be traced only to the departmental
operations or to the factory as a whole and not to individual job – orders the salary of a
departmental operations or to the factory as a whole and not to individual job – orders the salary
of a departmental supervisor is an example of an overhead cost. Direct materials and labour
costs are recorded on the job – order cost sheets for each job. Although not traceable to
individual jobs, overhead costs are generally assigned to them by means of overhead rates i.e.
the ratio of total overhead costs to total production volume for a time given period (Robert and
Lesile, 2000).
The third method of cost finding, activity-based costing, is based on the fact that many costs
are driven by factors other than product volume. The first task is to identify the activities that
drive costs. The next step is to estimate the costs that are driven by each activity and to state
them as averages per unit of activity. Management can use these averages to guide its efforts
to reduce costs.
METHODOLOGY
Description of the Study Areas
The two quarries sites used as a case study in this research lies between 6°N - 7°N, and 4°E -
6°E at an altitude of between 0 to 1365m. QuarryA is sited in Ijare town while Quarry B is
sited in Iju -Itaogbolu(along Itaogbolu – Akure road) all in Ondo State. Both quarries are sited
12
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
in towns that are closed to the state capital – Akure. The stones are reputed to have compressive
strength of between 164 and 173MPa while the tensile strength is between 10.78 and 12MPa.
13
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
Data Collection
Questionnaire were administered to the two quarries to acquire necessary data such as
personnel, production schedule, production rate, production cost, remuneration/emoluments
with their salary and so on.
14
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
Cost Estimate and Profit/Loss Calculation
Let Overall cost = 𝑃𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑐𝑜𝑠𝑡 + 𝑔𝑜𝑣𝑒𝑟𝑛𝑒𝑚𝑛𝑡 𝑟𝑒𝑣𝑒𝑛𝑢𝑒 ……...(3)
𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑖𝑜𝑛 𝑐𝑜𝑠𝑡
Cost per tonne = …………………………………………..…(4)
𝑇𝑜𝑡𝑎𝑙 𝑜𝑢𝑡𝑝𝑢𝑡
Total revenue = 𝑜𝑢𝑡𝑝𝑢𝑡 𝑝𝑒𝑟 𝑎𝑛𝑛𝑢𝑚 × 𝑠𝑒𝑙𝑙𝑖𝑛𝑔 𝑝𝑟𝑖𝑐𝑒 𝑝𝑒𝑟 𝑡𝑜𝑛 ………(5)
Estimation Techniques
Average Operating Cost
Total cost realized from ton produce per day
Profit = Revenue – Production Cost
To calculate for the estimation and profit, the following are required; capital, life span, cost
per year, production cost, cost per ton, revenue and profit.
RESULTS
The data collected were analysed and presented in the tables below.
15
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
½ inches = 2,600
¾ inches = 2,600
1½ inches = 2000
Stone Dust = 1,500
For Quarry A:
37,242,000
× 100 = 122%
30,618,000
For Quarry B:
22,241,000
× 100 = 219%
10,164,000
16
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
100%
80%
Amount
60%
40%
20%
0%
Particular
Quarry B Quarry A
37,242,000 37,242,000
32,625,000
30,618,000
AMOUNT
22,241,000
10,164,000
DISCUSSIONS
Tables2 shows the operating expenses on aggregate production per month at Quarry A and
Quarry B which includes; salary paid to the workers per month, Explosive used per month for
blasting operation, Lubricant used for the equipment, Diesel used for the equipment, Average
cost of maintaining the quarry site, Cost of Equipment used per month, Land rentage of the
quarry, miscellaneous, and 5% VAT, which are used to derive the cost incurred or less direct
expenses from the operating expenses per month. The table shows the comparison of operating
expenses on aggregate production per month at Quarry A and Quarry B, it can be deduced that
17
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
Quarry A has the highest salary paid, Explosive used, cost of equipment, lubricant used and
even the total cost incurred compared to Quarry B which can lead to improving the aggregate
production. Tables3 shows the income on aggregate production per month at Quarry A and
Quarry B; on the Tons of Aggregate mined per month which gives the total production per
month.Tables4 shows the positive contribution on aggregate production for each quarry, which
include the deduction of total production volume in value from less direct expenses to give the
profit earned from aggregate production. The table also shows the comparison of positive
contribution on aggregate production, which reveals that Quarry A has the highest positive
contribution with N37,242,000 compared to Quarry B with N 22,461,000.
Figure 3 shows the graph of operating expenses on aggregate production: in terms of salary,
Quarry A has the highest salary paid, Explosive used, cost of equipment, lubricant used and
even the total cost incurred with N30,618,000 compared to Quarry B with N10,164,000 which
can lead to improving the aggregate production. Figure 4 shows the graph of positive
Contribution of aggregate production, which include; the total production volume in value for
Quarry A with N37,242,000 is higher than Quarry B with N32,625,000; less direct expenses
and less cost of asset usage for Quarry A with N30,618,000 is higher than Quarry B with
N10,164,000; the positive contribution for Quarry A with N37,241,000 is higher than Quarry
B with N22,241,000.
CONCLUSION
This research examines the cost of production of granite aggregates for Quarry A and Quarry
Bout of quarries sited in Ondo State Nigeria. The results revealed that the total production in
volume value is N 67,242,000 for Quarry A and that of Quarry B is N 32,625,000. Base on the
above values the profit for Quarry A is 37,242,000 while that Quarry B is N22,241,000. From
the above results, it revealed that both quarries are making good profits; however, Quarry A is
making a little above 100% of their monthly input as profit while Quarry B is making more
than 200% of their input as profit.
RECOMMENDATION
Base on the outcome of this research, it is recommended that the cost price of granite aggregates
in Nigeria can be reviewed to make it affordable for masses. This will eradicate the use of
natural gravels that are not free from clays coating and other fine materials that could affect
hydration and bond of cement paste which can lead to building or structure collapse.
Acknowledgement
The author is grateful to the managements and staffs of FM Ltd, Ijare and SN Ltd, Iju-Itaogbolu
for supplying the data used in this research work. Also, effort of Miss Akinbile B.A. in
data/information collection is highly appreciated.
18
ISSN 2053-5783(Print), ISSN 2053-5791(online)
International Journal of Engineering and Advanced Technology Studies
Vol.4, No.2, pp. 6-19, May 2016
___Published by European Centre for Research Training and Development UK (www.eajournals.org)
REFERENCES
Ashmole, I. and Motloung, M. (2008): Dimension stone: The latest trends in exploration and
production technology. The South African Institute of Mining and Metallurgy (published
conference work – surface mining), pp. 36 - 70
Balamurali, A. (2014):Effect of Specific Gravity on Aggregate Varies the Weight Of Concrete
Cube. SSRG International Journal of Civil Engineering (SSRG-IJCE) – volume1 issue 3
pp. 1 - 9
Bamigboye, G.O., Ede, A.N., Umana, U.E., Odewumi, T.O. and Olowu, O.A. (2016):
Assessment of strength characteristics of concrete made from locally sourced gravel
aggregate from South-South Nigeria. British Journal of Applied Science &Technology
BJAST 12(5): 1-10.
David, W. (2015):Physical quality requirements for aggregates used in asphalt plant. Available
online at: https://www.linkedin.com/pulse/physical-quality-requirements-aggregates-
used-asphalt-david-wang?forceNoSplash=true
Guimaraes, M.S., Valdes, J.R., Palomino, A.M. and Santamarina, J.C. (2007): Aggregate
production – fines generation during rock crushing. International Journal of Mineral
Processing, vol. 81, issue 4; pp. 237 – 247.
Hardin B.O, (2001): Crushing of Soil Particles, ASCE Journal of Geotechnical and Geo-
environmental Engineering 111 (10), pp. 1177 – 1192.
Neville, A.M. (2011): Properties of concrete. 5th Edition, Pearson Education Limited
Edinburgh Gate, Harlow, Essex CM20 2JE, England. 2866 p.
Pava, M.L. (2014): Managerial accounting. Available online at:
http://www.britannica.com/topic/accounting/Managerial-accounting
Portland Cement Association - PCA, (2015): Cement and concrete basics – aggregates.
Available online at: www.cement.org
Robert R. and Lesile G.E. (2000): Mining Industry and Developing Countries, 2nd Edition
World Bank Research Publication, USA, ppg 314 – 326.
Rodney, D.S. (1991): Cost estimating; 2 edition, John Wiley and Son Inc. New York. 384 p.
Sharma, P.D. (2012): Rock breakage and blast design considerations in open pit. Available
online at: https://miningandblasting.wordpress.com/category/explosives/
Sushil, B. (1997): Engineering rock blasting operations. A.A. Balkema Publishers, old post
road, Brookfield, VT 05036, USA. 195p
Vasarhelyi B, and Bobet A, (2000): Modeling of Crack Initiation, Propagation and Coalescence
in Uniaxial compression, Rock Mechanics and Rock Engineering 33 (2), pp. 119 – 139.
William, H. (2012): Aggregate resources Act. Ontario, Canada. Available online at:
https://www.ontario.ca/laws
Zongjin L. (2014): Lecture note on Construction materials – Aggregate. Available online at:
http://www.readbag.com/teaching-ust-hk-civl111-chapter3.
19
ISSN 2053-5783(Print), ISSN 2053-5791(online)