PAM DEPARTMENT WELCOME YOU ALL AT

NTPC BADARPUR

IS/SO-9001:2000

Submitted To –
Presented By - GAURAVE GOYAL
SUNNY
14.02.03
THAKUR DY. MANAGER 1
PAM
PAM stands for plant auxiliary maintenance

Although name include auxiliary, despite of name it


is an integral department of plant and known for
many crucial and variety of jobs

It is not heart of plant but responsible for working of


plant heart systems like boiler and turbine by
providing water for steam generation which is blood
of thermal power plants.
CSPH
CSPH stands for control structure pump house

From CSPH there is overall control of water system


not only for steam generation but also for fire
protection system, service water for cleaning etc.

CSPH is structured on inlet canal.


3 nos. of Clarified water pump, 3500m³/h,
Provide raw water to Geomiller for clarified water
and DM Water
6 nos. of high pressure pumps HP-1 to 4 -500 m³/h
HP 5&6- 400 m³/h
HP 1&2 – Water supply to Ash trench Flushing
HP 3,5&6 – Water supply to Stage 1 ESP de-ashing
HP4- Pressure boost up of U#4, LP header at ESP side

3 nos. of Low Pressure pump


Supply water for ash slurry preparation

3 nos. of travelling water pumps


Pumps used for boosting pressure of DEDS pumps
discharge

CSPH
Discharge water used for cleaning of TWS

2 nos. of Fire Screen pump


Pumps used to supply water for fire fighting system,
as
service water in boiler area and for cleaning of
vertical screens
7 nos. of travelling water screen
Travelling screen used for removing unwanted
material
like polythene, pieces of cloth, debris from water
by
filtration method
Vertical water screens
Used as 2nd filtration system after travelling water
screens
Dust Extraction And Dust Suspension System
Clarified water after generator gas cooling is supplied
by 3 vertical pump and 1 centrifugal pump for
spraying water in coal yard form preventing auto
ignition of coal and to TWS pumps for TWS cleaning
Chlorine
addition
Raw Water
Flash
from CSPH
Mixture Clarified water for different uses.
2 nos. Supply of water maintained with help
Clarifier A & B Clarified water of five 415Volts Pump and three6600
tank
volts pumps named clarified pumps.

Sludge Clarified
removal pump water for
A&B DM water
preparation Clarified Water
Tank

Strong base Weak base Clarified Pump


4 4 A&B
Anion Anion Activated
Exchanger Exchanger Pressure
Carbon filter
A,B,C,D A,B,C,D filter

Cation
Exchanger
Mixed Bed
Exchanger
DM
Degasser Tank A,B,C,D A,B,C,D
Water
DRY ASH HANDLING SYSTEM
In coal based power plants two type of ash generated.
Wet ash and Dry ash.

Ratio of wet ash to dry ash is 30:70

Wet ash is only money consuming by product of coal


plant because it require a lot of money for handling of
wet ash.
Although, dry ash is by product, unlike wet ash it is a
money making by product and utilized in many fields
like in cement industries and for brick making.
Sealing
ESP Hopper Buffer Vacuum Water
Hopper Pump A,B Pump
A&B

Air
Lock
vessel
A&B

Silo A,B,C
Transport Air
Compressor
A,B,C,D
Wet Ash
from
Bottom of
Boilers

Wet Ash Tank


Ash Pond

Slurry Slurry Slurry


Slurry
Pump Pump Pump
Pump
B C D
A
Compressor House
Compressor house is source of compressed air for
plant .
Compressed air as name implies having pressure
above atmospheric pressure and used to operate many
crucial functions.
Compressed air in plant used in two form.
1 Plant Air – It also known as service air and used as service air for cleaning air at
different locations.
2 Instrument Air - It is used to operate pneumatic valve at different areas and
source of energy for air pre heater motor in all five units.
Different compressors used at
Plant
CRS
CRS stands for central repair shop.
In Central Repair Shop repairing related job
performed. In CRS not only repairing jobs are done
but also production jobs are done according to
contingency plans.
CRS is a wonderful tool for emergency and many
times, during exigencies had worked as only tool .
CRS
COOLING TOWERS
There are three cooling towers in BTPS.

Cooling Towers Fulfill the scarcity of water and is that


component which transform open cycle power plant to
closed cycle.

Cooling Towers are nothing more then heat exchanger..

In cooling towers, heat exchange process take place where


cooling medium is environmental air and interaction of hot
water with environmental air brings down temperature of hot
water to environmental temperature.
Thank you