EventAnalysis Tutorila
EventAnalysis Tutorila
EventAnalysis Tutorila
Abstract—Event reports have been an invaluable Lightning arresters, one per phase, are positioned on the
feature in microprocessor-based relays since the initial top of the steel support structure. Each arrester is connected by
introduction of the technology. The days of unknown root a jumper to the phase conductor. A bird caused a fault near
cause for an operation, lengthy outages, or unexplained one lightning arrester, which caused its jumper to blow loose
test results are largely over due to this tool and the ability and contact other phases.
of engineers and technicians to use it. We must practice to Open the event report titled 2 – Distribution Feeder Fault
become proficient at analyzing event reports. This session 351S-6.cev to analyze this case. See Fig. 1 for a screen capture
provides real-world event examples, time to evaluate them, from this event.
and solutions. The relay involved was an SEL-351S-6. The instruction
manual is provided as part of the class material and is also
I. INTRODUCTION
available at www.selinc.com.
The event reports provided in this session are from real-
world applications. They have been edited only to the extent
that the owner involved is not revealed. They provide us the
opportunity to learn and improve our power system. We want
to thank the engineers and technicians who share information
and what they know for the benefit of our industry.
We provide a number of example case studies. These come
from a wide variety of power system and protection
applications. We have distribution, transmission, transformer,
bus, generator, and motor event examples.
In each case, we provide the following:
• A brief introduction to the application and problem.
• The event reports required to solve the problem.
• References for future reading and further instruction. Fig. 1. Distribution Feeder Fault (2 – Distribution Feeder Fault 351S-6.cev)
Students are required to use their own personal computer Questions:
with SEL Compass®, ACSELERATOR QuickSet® SEL-5030
Software, and ACSELERATOR Analytic Assistant® SEL-5601 II-a Before the fault, in what direction is power flowing?
Software installed. These programs are available for download
at no cost from www.selinc.com. II-b What is the system phase rotation?
Students are invited to answer the questions asked in this II-c What type of fault occurred?
document. These questions are intended to guide analysis,
keep the class efforts focused in the same direction, and II-d What protection element within the relay caused
highlight the main lesson points. Please document the solution the trip?
to each case study in the format of a Microsoft® Word
II-e How long did it take for the relay to operate?
document with appropriate software screen captures and notes.
Last, instructors are available to answer questions, share II-f How long did the breaker take to clear the fault?
tips, and highlight lessons learned. Have fun!
II-g Did the relay and protection system operate correctly
II. DISTRIBUTION FEEDER FAULT and as expected?
This event occurred on a distribution collector at a wind Another event report from a different system is provided
farm. For practical purposes, faults on the collector behave for comparison. Open the event report titled 2 – Distribution
like faults on a radial feeder fed from a Dy1 transformer. The Feeder Fault 351A.cev to analyze that case. See Fig. 2 for a
wind turbines do not contribute any significant fault current. screen capture from this event. The relay involved was an
The location and connection of the potential transformers SEL-351A. The instruction manual is provided as part of the
(PTs) are not known at the time of publication. class material and is also available at www.selinc.com.
2
Note in Fig. 1 that the phase fault current is largest during Open the event report titled 3 – Frequency Load Shed
the single-line-to-ground fault period. In Fig. 2, the phase fault Test One 451-5.cev to analyze the first test. See Fig. 3 for a
current is largest during the three-phase fault period. screen capture from that event. The relay involved was an
SEL-451-5. The instruction manual is provided as part of the
class material and is also available at www.selinc.com.
Three problems were noted by technicians. First, the output
contact used by the underfrequency element 81D1T chattered
continuously after the frequency was lowered below the set
point, and it would not stop until the frequency was returned
to normal. Second, the trip time for the underfrequency event
was slightly longer than expected. Third, the frequency
metering stopped tracking at 58.0 Hz, despite the test set being
lowered below this level.
Question:
II-h On a radial distribution feeder, what type of fault do
you expect to produce the largest phase fault current?
Does the type of transformer used as a source matter?
Does the fault location make a difference? Can you
provide an explanation for the fault type current
magnitudes in these two event reports?
The SEL University classes PROT 301: Protecting Power Fig. 3. Frequency Test 1 (3 – Frequency Load Shed Test One 451-5.cev)
Systems for Technicians and PROT 401: Protecting Power
Systems for Engineers review necessary symmetrical Open the event report titled 3 – Frequency Load Shed
components and fault analysis fundamentals. Register for Test Two 451-5.cev to analyze the second test. See Fig. 4 for
these classes and more at www.selinc.com. a screen capture from this event. The trip logic was changed
for the second test, setting TR equal to NA. The only other
III. UNDERFREQUENCY LOAD-SHEDDING TEST change made for this test was the addition of the FREQOK
(frequency tracking okay) and FREQFZ (freeze frequency
These events were recorded from laboratory tests. An
tracking) Relay Word bits to the digital elements recorded
SEL-451-5 was being applied for underfrequency load
with event reports.
shedding. Laboratory tests were conducted to prove the
protection scheme would perform as intended.
The scheme was designed to trip groups of 7 kV feeders at
various underfrequency set points. The first group of feeders
should have tripped at 58.7 Hz. A different group of feeders
would have tripped at different frequencies. Therefore,
frequency elements were programmed directly into individual
output contacts. All frequency elements were originally
connected by OR gates in the trip logic only to provide a local
trip light-emitting diode (LED) indication; the trip logic was
not used by any output contacts.
The feeders were on the low side of a 66 kV/7 kV
transformer. The relay voltage inputs were fed from the 66 kV
bus PTs. Fig. 4. Frequency Test 2 (3 – Frequency Load Shed Test Two 451-5.cev)
A standard test set applied secondary voltages. The
frequency of VA was lowered in steps, rather than using a Questions:
ramp. Trip unlatch (TULO) was set for Option 3. With no III-a Using event data, can you determine if the voltage
current applied and no breaker status simulated during the test magnitude applied is correct for this application?
(see Page A.1.14 of the SEL-451-5 Instruction Manual), the
trip will unlatch when trip conditions expire or after a III-b At what point in the event data did the test set actually
minimum time of 12 cycles (TDUR3D). change frequency?
3
III-c Is a step change in frequency an appropriate test The utility had a lightning arrester failure at a customer-
method for an underfrequency load-shedding owned substation several terminals away from this plant. The
application? 67P relay tripped for this fault.
Open the event report titled 4 – Main Breaker Directional
III-d Does the frequency element time delay match the
Element 351A.cev to analyze the event. See Fig. 6 for a
expected scheme settings?
screen capture from this event.
III-e In the first test, the frequency element can be seen
asserting and then deasserting. What element do you
suspect turned the frequency element off?
III-f In an SEL-451-5, can frequency elements be included
directly in the trip equation?
The technical paper “Frequency Tracking Fundamentals,
Challenges, and Solutions” is available at www.selinc.com
and is recommended reading for more information on this
subject.
The SEL-387-6 Instruction Manual is provided as part of See Fig. 12. Two 1200:5 MRCTs, tapped at 900:5, are
the class material and is available at www.selinc.com. Open paralleled and connected to the Winding 1 inputs of the relay.
the event report titled 6 – Transformer REF 387-6.cev to A single 1200:5 MRCT, tapped at 1200:5, is connected to the
analyze this event. See Fig. 11. Winding 1 feeders are radial Winding 2 inputs of the relay. The transformer is rated
loads. 12/16/20 MVA and 138 kV/12.47 kV. From Fig. 12, the
polarity of H1 is connected to the nonpolarity of H2. A-phase
is connected to H1, B-phase is connected to H2, and C-phase
is connected to H3. The system phase rotation is ABC.
Fig. 11. REF Application (6 – Transformer REF 387-6.cev) The SEL-587 Instruction Manual is provided as part of the
class material and is also available at www.selinc.com. Open
Questions: the event report titled 7 – Transformer Commissioning
VI-a Where was the fault (internal to the transformer or 587.cev and the settings file titled 7 – Transformer
external to the protection zone)? Commissioning Settings 587.pdf to analyze this event.
VI-b Was the tie breaker open or closed at the time of the
event?
VI-c What element operated to trip the transformer?
VI-d Was the transformer relay operation correct or incorrect
for the fault location?
VI-e For an external ground fault, what phase angle
relationship do you expect between the Winding 1 and
Winding 4 currents?
VI-f Why is the ground current magnitude on Winding 1
different than Winding 4?
VI-g A current transformer (CT) wiring problem is
suspected. Can you prove which winding has the error?
The technical paper “Analysis of an Autotransformer Fig. 13. IOP and IRT (7 – Transformer Commissioning Settings 587.pdf)
Restricted Earth Fault Application” is available at
www.selinc.com and is recommended reading for more
information on this subject.
Fig. 18. Third Event, Terminal A (9 – A Delayed Fault Clearing 3rd Event
311C.cev)
Fig. 16. First Event, Terminal A (9 – A Delayed Fault Clearing 1st Event
311C.cev)
Fig. 19. First Event, Terminal B (9 – B Delayed Fault Clearing 1st Event
311C.cev)
Fig. 20. Second Event, Terminal B (9 – B Delayed Fault Clearing 2nd Event
311C.cev)
8
IX-i What relay setting change can you suggest to XI. BUS DIFFERENTIAL OPERATION
drastically improve tripping sensitivity to high-
resistance faults and therefore speed up tripping? An engineer has applied two high-impedance bus
differential relays on the same bus and connected the
The technical paper “Very High-Resistance Fault on a differential elements in series. This was done to provide
525 kV Transmission Line – Case Study” is available at backup protection against a single relay failure. The high-
www.selinc.com and is recommended reading for more impedance bus protection is assumed to have two failure
information on this subject. modes. One failure mode is a relay disabled (power supply,
processor failure, and so on), but with its high impedance still
X. DOUBLE-ENDED FAULT LOCATION in the CT circuit. The other failure mode is a metal oxide
A fault occurred on an 82-mile-long 161 kV line. The left varistor (MOV) failed shorted, removing the high-impedance
terminal (R) provided a fault location estimate of 13.95 miles input of the relay.
(from the left). The right terminal (S) provided a fault location For internal faults, the series connection limits the
estimate of 56.5 miles (from the right). minimum sensitivity of the scheme. However, for solidly
9