HCPM Tutorial 4 Network Analysis
HCPM Tutorial 4 Network Analysis
HCPM Tutorial 4 Network Analysis
Tutorial No. 04
NETWORK ANALYSIS
8. Draw a network (AOA as well as AON) consisting of six activities given below.
Interrelationships among various activities are:
i. Activity A is the starting activity and precedes activities B and C.
ii. Activity D depends on activity B.
B.Tech IV Heavy Construction and Project Management CE 401
a. Earliest start and finish times and latest start and finish times for all activities.
b. Total float, free float, independent float, and interfering float for each activity.
c. The critical path for the project and show it on the network.
11. For the project data given in the following table, draw an AOA network diagram and
determine the following:
Activity Duration (days) Succeeding Activity
A 3 D, E
B 2 F, I
C 3 G
D 1 H
E 2 I
F 4 K
G 4 K
H 5 J
I 2 K
J 3 -
K 1 L
L 4 -
i. Earliest and latest start and finish time for each activity.
ii. Critical path for the project and project duration.
iii. All types of floats for each activity.
12. The network for the project is shown. Calculate the expected time for each path. Which
path is critical? Draw the network showing expected time.
B.Tech IV Heavy Construction and Project Management CE 401
13. Draw the network diagram for the project with the following data. The time estimates (in
weeks) are given below.
Activity Optimistic Time Most Likely Time Pessimistic Time
1-2 1 5 9
1-3 5 6 7
1-4 3 5 7
2-6 2 4 6
3-5 1 3 5
4-5 2 3 4
5-6 4 6 8
5-7 6 8 10
6-7 1 4 7
6-8 3 7 11
7-8 2 5 8
8-9 1 2 3
i. Determine the critical path.
ii. What is the probability of completing the project within 20 weeks?
iii. Compute the expected completion time for the project with a 75% probability.
iv. What is the probability of completing the project within 30 weeks?
14. A small project consists of seven activities. The time estimates are given below:
Activity 1-2 1-3 1-4 2-5 3-5 4-6 5-6
Optimistic Time 1 1 2 1 2 2 3
Most Likely Time 1 4 2 1 5 5 6
Pessimistic Time 7 7 8 1 14 8 15
i. Draw the network.
ii. Determine the critical path.
iii. What is the probability of completing the project within 18 weeks?
15. The activity of plastering of a room takes its longest time to get completed. Considering
the delay in completion the contractor immediately takes up the next activity of laying
down the tiles. Explain with a suitable diagram the excess time available to the contractor
between the two activities.
Division A Division B
Date of Tutorial: 30/08/2022 26/08/2022
Date of Submission: 13/09/2022 09/09/2022