Fire Pump
Fire Pump
Fire Pump
connections.
'Star and Delta' are power control switches which give a constant power supply to
pumps.
Primarily power supply goes through star connections and then delta connection will
carry a non-interrupted constant power supply to pumps.
At the top of panel, we can see 3 LED lamps which indicate Power ON/OFF and
trouble. 3 Ampere meters and one volt meter are installed near at top portion of
panel. There is a switch which helps us to know voltage in power supply. The voltage
indicates by voltage meter as we control the volt meter knob.
Pump can run either manually or automatically. There is a knob for controlling auto-
manual function on each pump panel.
Every panel is controlled by ON/OFF livers. 3 press switches and 4 LED bulbs are
installed on every panel.
Before starting pump, must check for voltage of power in three lines. We can check
it by controlling voltage regulator switch which installed on top near voltage meter.
The voltage must in between 360V and 440V.
We are keeping the Jockey pump in auto mode and others in manual mode.
Panel carries a high voltage power. Do not operate without knowledge and
inappropriate condition.
Pumps
Three centrifugal pumps —Jockey Pump, Main Pump, Stand by Pump and one terrace
mounted pump.
Positive Suction — Water coming directly from tank to suction head by gravitational
force.
Negative Suction— Suction line with a foot valve. Priming should require in negative
Working
In auto mode
If a pressure drops in hydrant line below 7 bars, the Jockey pump starts
automatically and maintains the line pressure as 7 bars. If pressure drop persists
and the level decreases below 5 bars, the Main pump will start and gives a high
pressure water supply. Jockey pump will automatically go off when main pump
starts.
Standby pump kept for an immediate use, when main pump failed in operation. It
will start automatically if pressure drops below 2bars.
Before switching off manually, ensure the Auto-Manual switch is in manual position.
Then press the OFF switch (Red in colour)
Always ensure pump ampere level is 150 amps.
In Manual mode
Panel & Pump operating procedure
Before operating always check for voltage level.
ON the Fire pump panel by using ON/OFF liver.
Ensure the Auto-Manual switch on each pump panels is in manual position.
ON the pump panel by using ON/OFF liver. Then ON the pump by pressing ON switch
(Green in colour)
Check the ampere for pump in ampere meter, installed at the top. The normal
ampere level 150 amps.
Before switching off manually, ensure the Auto-Manual switch is in manual position.
Then press OFF switch (Red in colour).
Maintenance
Run all the pumps once in a week.
Hydrant Line
Hydrant line consists of MS pipes, NRV's, Butterfly Valves, Air releasing valves/vessels,
pressure gauges, pressure switches, male/female couplings and hose boxes.
The main electric pump
The pump shall be set to start at 6.5kg /sq.cm an external hydrant valve using a single length of hose
and branch pipe shall be fully opened to cause a drop of pressure in the system. At first, the jockey
pump shall start when the pressure drops to 6.5 kg. Further, drop in the pressure up to 5 kg. should be
allowed to test automatic start-up of the electrical pump. The electrical pump shall continue to run at-
least for 5 minutes and register rise in the pressure up to 7.5kg. The Jockey Pump shall be
automatically start at this.
The electrical pump shall be stopped manually by pressuring the stop button.
All these tests mentioned above shall be repeated after one hour interval. The result of all the tests
shall be identical again. After the system has satisfactorily withstood the above tests, it can be taken
over from the contractor.