Studi Kasus UTS Manajemen Proyek 2023
Studi Kasus UTS Manajemen Proyek 2023
Studi Kasus UTS Manajemen Proyek 2023
Mata Kuliah
Manajemen Proyek
Format Pengerjaan Studi Kasus
• Studi kasus dikerjakan secara Individu.
• Format kertas ukuran A4, spasi 1,5, font Times New Roman 12pt
• Dikumpulkan melalui MyITSClassRoom paling lambat hari Sabtu 8 April jam 18.00
1. Tentukan satu masalah yang dianggap paling penting yang dihadapi Doodle Noodle Corporation
2. Rancanglah sebuah proyek dalam rangka menyelesaikan masalah tersebut yang terdiri dari :
Prologue
A small business company who produces wet noodle. Both, Mr Arva and Mr Danis are
the owner this business. As they started their business three years ago, their market
is started with small local market which mainly is restaurants and café. Some of the
noodle is distributed to Mr Arva’s wife small restaurant who serves noodle based menu
(fried noodle, noodle soup) and is located next to production area. In 2020, when many
almost three times. This good news suddenly turns around became a big problem as
their production cannot cope with the increasing demand. Moreover, as a food
producer, this business is required to comply with food safety quality. This situation
certainly give Mr Arva and Mr Danis a serious headache. They do not have any idea
This small company is started their business in early 2019 with 11 employees (Fig 1)
It produces one type of noodle, that is wet noodle (Fig 2), with a brand name “Poodle
Doodle Noodle”. In the beginning of their business, they directly sell their noodle to
small number of customers (less than ten restaurants) around town. Now they can sell
the product to different cities in Java Island such as Jakarta, Yogyakarta, Purwokerto,
REPORT TITLE | 3
Semarang, Surabaya, and Cirebon through more than 200 resellers. Most of the
Secretary
/Adminitration staff
7 (seven)
Production Operators
Figure 2 Illustration of wet noodle and its demand (number of box which
contain of 7kg wet noodles) in year 2020
To produce wet noodle, the main ingredient is flour, water, and salt. Water is supplied
daily in gallon from a local vendor (not use tap water). Flour and salt are also supplied
REPORT TITLE | 4
Figure 3 shows process flow of wet noodle production flow. Most of process steps need
one operator except the last step (packing), it needs 3 (three) operators, so operator
who is responsible in steaming process also helping 2 (two) other operators in the
packing process. After packing, the wet noodle is brought to the storage. Since the
production of this noodle does not use any preservative, if it is stored at room
temperature it will expired in 3 (three) days, if is stored in the fridge, it will expired in 4
(four) weeks. Before delivering the noodle, it will be labelled and packed in a box.
and salt. Capacity of their existing fridge can accommodate one shift of production or
7 batches.
Mixing
(20 mins, 1 operator)
Sheeting
(15 mins, 1 operator)
Cutting/Slitting
(15 mins, 1 operator)
Steaming
(45 mins, 1 operator)
Cooling
(15 mins,1 operator)
Packing
(30 mins, 2 + 1 operator)
REPORT TITLE | 5
Every day, the operator works normally in 1 shift (8 hours include 1 hour break) from
8 am to 4 pm. They are running Make to Stock type of production system. The
production supervisor, Bian, makes the rough production planning based on his gut
Mr Arva has just received a shocking phone call and is staring closely at several
batches of wet noodles in the fridge. He several times shake his head sadly and say to
himself “Isn’t this batch has been stored for several weeks, why is still here? It should
Next, he takes his mobile phone and makes a call. “Danis, can I have a word with you
now? It is very critical”. Slowly, then he goes back to his humble office room in second
floor of the shop-house building. Then, he sits down and looks at a group picture of
him, Mr Danis (his business partner), and all his employee at the opening of his small
business three years ago. Until now, those workers are still working with him and
A knock at his door wakes up Mr Arva from his deep in thought. Mr Danis is peeping at
the opened door and said, “May I come in?”. “Sure, come in” replied Mr Arva. Mr Danis
sits down with a letter in his hand. “Sorry to ask you to come straightaway. It is very
urgent. Two of our biggest customers from Jakarta and Surabaya have just called me.
They complained about our late delivery since couple of months. Both of them warned
me if this delay on delivery continuously occur to the next following month, they will
stop doing business with us.” Mr Arva stops a few seconds, inhales his breath very
deeply then continues “And I believe it is easy for them for get a new vendor as we do
have a lot of strong competitors. But you know, I’ve just checked our fridge and we
REPORT TITLE | 6
have several batches of noodle that have been sitting there for a couple of weeks, I
believe. Whereas, our customers is waiting for their order to come. I just don’t
Mr Danis then said “Look, I do not want to add more pressure, but you should know I
have just received a report from the National Agency of Drug and Food Control. They
said that our noodle cannot meet the safety standard based on SNI (Indonesian
National Standard) 2987:2015. Look at this report, there are two parameters does not
comply with regulation”. Mr Danis shows Mr Arva the letter with testing result of their
wet noodle samples last week. Mr Arva looks at the report (Table 1) with shocked. Mr
Danis continues “If we can fulfil it by next month, they are going to withdraw our licence
REPORT TITLE | 7
9 Deoxynivalenol µg/kg Max 750 < 200
Mr Arva could not say anything in few minutes, then with deep voice he said “That is a
disaster … soo bad …okay … it is very urgent … tomorrow morning we should have an
emergency meeting with all supervisors. Now let’s go home and have a good rest” said
Mr Arva. “Okey, I am sending text to them now, see you tomorrow” replied Mr Danis.
Mr Arva stands at the corner while Mr Danis sits and talks to the three supervisors who
are their main persons in this small business. Bian (the production/operations
supervisor), Tika (the marketing supervisors), and Reza (the general affair supervisor)
listen closely and sometimes they look at each other or just look down. After Mr Danis
finishes his explanation, Mr Arva shows the letter from the National Agency of Drug
and Food Control to Bian. His eyes directly look at Ash Level and Total Plate Count that
are out of specification. Well, not to forget about the complaint from our big and long-
time customers, so do you all have any idea, why all of these things are happened?”,
Tika explained “there is a significant rise of order from customer started on March this
year. It is almost twice compared to the previous year. We have a lot of new customers
from different cities while our existing customer are also put more order. Especially our
two biggest customers from Jakarta and Surabaya. They have reported that there are
delay of their order fulfilment since the last couple of months (Table 2)” explains Tika.
REPORT TITLE | 8
Table 2 Delayed delivery data for Customer A and B
A 40 6 Oct 12 Oct
B 50 8 Oct 12 Oct
A 65 15 Nov 20 Nov
B 45 16 Nov 24 Nov
A 70 24 Nov 30 Nov
B 55 26 Nov 30 Nov
Reza adds Tika explanation “As we are in pandemic situation like now, we also need
to comply with the health and safety protocol, so we have made a plan to add more
“Yes, we definitely need a larger production area”, said Bian. “Well, now let’s go down
to observe our production area”, asked Mr Danis. Today, there is 7 (seven) operators
Mr Arva, Mr Danis, and the supervisors are watching at the production area as well as
the whole area in first floor (Fig 5). The production area is only 15 m2 and located at
the back of the building. At the front of the building (level 1), there are restaurant area
REPORT TITLE | 9
Table 3 Noodle production processes
No Process Procedure
1. Mixing - Measure flour, salt and water according to the recipee
- Put flour through a sifter so it break up any lumps in the flour
- Combine a mixture of flour, salt and water become a dough
2. Sheeting - Cut the dough into smaller pieces
- Roll several times each small pieces of dough into thin sheets
3. Slitting - Cut/slit the thin sheets of dough into noodle shape with Slitter machine
- Brush the noodle with oil
4. Steaming - Steam the noodle in the pot with hot boil water (100˚C- 105˚C)
5. Cooling - After steaming, the noodle is cooled down in room temperature (25˚C
- 30˚C)
- The noodle is separated and placed on aluminium tray
6. Packing - The noodle is measured and weight according to the standard and put
it in the packaging
During production, the whole production area is full with raw materials, semi finished
noodle, container, and many more. So it is quite difficult for operator to move around.
Operator also needs to walk back and forth from production area to storage. As, there
is no dedicated place for packing process, the operator should sit down on the floor
(Fig 5).
21 meter
Penyimpan mi
Formulasi
(kulkas dan freezer) Tangga naik 2
Pengukusan
Gudang
Area parkir karyawan dan
bawah tangga
Tangga naik 1
Wastafel
pengunjung
6
Pengemasan
Ruang restoran
Bar
m
Pencetakan
Pembuatan
Kitchen
adonan
mi
Toilet
Pencetakan
lembaran
4 meter
REPORT TITLE | 10
Figure 5 Illustration of production area
“What do you think Mr Arva? I think Bian are right, the production area is kind of tight”,
said Mr Danis. Then Mr Arva replied “You know what, when our wet noodle business is
promising, it is not so for the restaurant. My wife is struggling to run the restaurant
since pandemic. So, my wife has indicated me that she is going to close the restaurant
soon”. “Really…? well if that so, how about we extend space for production by
converting the restaurant area?”, said Mr Danis. “Yes, I agree”, replied Mr Arva and
Bian, “and we definitely need a dedicated space for packing, more proper location to
Mr. Arva responses “And it should be managed properly, I don’t want to see again
undelivered 2 weeks old - noodle while some of our customers waiting for their order
to arrive “. Bian replied “I’ve just remembered that those noodles are supposed to
the noodle it is packed in individual small plastic wrap with weight 100 gram each,
while our standard weight is 200 grams. But the operator mistakenly took and sent
the wrong batch of noodle So, we need to re-packing to sell it to different customers.
REPORT TITLE | 11
“Well then, at least finally we find out that has happened”, said Mr Danis, “How about
the Ash level and Total Plate count? Any idea, why it is out of control? We can refer to
an information on those two parameters from guidelines of SNI 2987:2015. Ash refers
to any inorganic material, such as minerals, present in food. It is called ash because it
is the residue that remains after removing water and organic materials such as fat and
protein. Ash can include both compounds with essential minerals, such as calcium
and potassium, and toxic materials, such as lead. Therefore, the presence of ash does
not mean that ash in a literal sense is allowed to be added to a food product. While,
Total Plate Count (TPC) is an indicator of the shelf-life of products, and also the
After few minutes thinking, Bian says “from my view, there are two potential sources
of contamination. First, since early this month, there is indication that some
components our Slitting machine have been wearing out. Thus, it potentially
contaminates and mix with our noodle dough during cutting process. Second, as we
have a longer than usual dry seasons, thus we have more dust which come from main
street as well as parking lot in front of our building” (see Fig 7).
Shops
Roti Bakso Kom- Koperasi
Petshop Toys
Bakar Mi ayam puter Simpan Pinjam
Masakan
Parking area Noodle
padang
Parkir Mobil
Salon Sembako
Shops
Parking lot/area
Parkir Mobil TheLOKASI
Noodle
Shops
Jalan masuk/keluar
Jalan masuk/keluar
BPR Kelontong
Shops
Taman Nasi goreng
Jalan Raya
Main Road
Jalan Raya
REPORT TITLE | 12
Reza says “on my opinion, the contamination could come from the flour as from last
month we have just bought flour from new vendor since our old main flour vendor close
their business. This new vendor offers cheaper price with others vendor that have been
supplied us before. I have not got a chance to check the quality of this new vendor
flour. Other potential source of contaminant could be from our operators. As you can
see now, all of operator are not using proper work uniform and even some of them are
not using any shirt. I don’t think they wash their hand frequently since they touch many
things other than only the dough. And of course, the working area is far from clean”.
“Well, it seems that we have a lot of potential sources of contamination”, said Mr Arva
while scratching his head. Mr Danis who looks closely into the production area and
says “Maybe our steaming process time is not long enough or maybe the temperature
“Ok so what should we do now? We need to act fast before too late. Next two weeks,
BPOM staff will revisit us and take another sample before decide our fate “ said Mr
Arva anxiously to Mr Danis, Bian, Tika and Reza. “Bian, this is your call . Tika and Reza
please help Bian to solve this by the end of this week” , adds Mr Danis.
REPORT TITLE | 13