VTP-VPC Manual 71569224 01-2019 (G) A4

Download as pdf or txt
Download as pdf or txt
You are on page 1of 77
At a glance
Powered by AI
The document provides instructions for installing, operating, maintaining and servicing vertical turbine pumps.

Vertical turbine pumps are used to pump water and other liquids from wet wells or suction barrels.

The main components of a vertical turbine pump include the impeller, bowls, suction bell, thrust stand, driver and coupling.

USER INSTRUCTIONS

Vertical Turbine Pumps Installation


Wet Pit (VTP)
Double Casing (VPC) Operation
E, S and A series VTPs in wet pit and suction barrel designs Maintenance
ranging in sizes from 50 mm (6 in.) to 1300 mm (52 in.) with
a single or multiple stages. (This manual does not cover
VTPs fitted with thrust bearing assemblies and VTPs built
for cryogenic service).

PCN=71569224 01-19(G), Based on VTP-QS-0896 Original


Instructions

These instructions must be read prior to installing,


operating, using and maintaining this equipment
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

CONTENTS
PAGE PAGE
1 INTRODUCTION AND SAFETY ....................... 4 6 MAINTENANCE ............................................... 47
General ............................................................ 4 General .......................................................... 47
CE Marking and Approvals .............................. 4 Maintenance Schedule .................................. 48
Disclaimer ........................................................ 4 Spare Parts .................................................... 49
Copyright ......................................................... 4 Recommended Spares and Consumables .... 50
Duty Conditions ............................................... 4 Tools Required ............................................... 50
Safety .............................................................. 5 Fastener Installation ....................................... 51
Safety Labels Summary .................................. 8 Setting Impeller Clearance............................. 52
Specific Machine Performance........................ 8 Disassembly ................................................... 52
Noise Level ...................................................... 8 Examination of Parts ...................................... 53
Specific machine performance ................ 9 Assembly ...................................................... 56
2 TRANSPORT AND STORAGE ....................... 10 7 FAULTS; CAUSES AND REMEDIES ............. 57
Consignment receipt and unpacking ............. 10
8 DRAWINGS AND PARTS LISTS .................... 59
Handling ........................................................ 10
Cross Section: Product Lubricated VTP ........ 59
Lifting ............................................................. 10
Cross Section: Enclosed Tube VTP ............... 62
Storage .......................................................... 14
Cross Section: Suction Barrel VTP ................ 65
Recycling and End of Product Life ................ 14
General Arrangement Drawing ...................... 68
3 DESCRIPTION ................................................ 14
9 CERTIFICATION .............................................. 68
Configuration ................................................. 14
Nomenclature ................................................ 15 10 OTHER RELEVANT DOCUMENTATION AND
Design of Major Parts .................................... 17 MANUALS........................................................ 68
Performance and Operation Limits................ 21 Supplementary User Instructions ........... 68
Change Notes ........................................ 68
4 INSTALLATION ............................................... 21
Location ......................................................... 21 11 APPENDIX ....................................................... 69
Preparation .................................................... 21 Bill of Materials Reference Numbers ..... 69
Foundation/Anchor Bolts ............................... 21
Grouting ......................................................... 24
Lifting and Assembly ..................................... 24
Initial Alignment ............................................. 30
Piping ............................................................. 31
Electrical Connections ................................... 34
Final Shaft Alignment Check ......................... 34
Protection Systems ...................................... 34
5 COMMISSIONING, STARTUP, OPERATION
AND SHUTDOWN ........................................... 35
Pre-commissioning Procedure ...................... 35
Pump Lubricants............................................ 35
Impeller Adjustment ....................................... 38
Direction of Rotation ...................................... 42
Guarding ........................................................ 42
Priming and Auxiliary Supplies ...................... 42
Starting the Pump .......................................... 42
Operating the Pump ...................................... 45
Stopping and Shutdown ................................ 46
Hydraulic, mechanical and electrical duty .... 46

Page 2 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

INDEX
PAGE PAGE

Alignment, Final 4.9 ................................................ 35 Location 4.1............................................................. 22


Alignment, Initial 4.6................................................ 31 MAINTENANCE 6 …………………………………48
Assembly 6.10......................................................... 57 Maintenance Schedule 6.2 ..................................... 49
Atex Marking 1.6.4.2 ................................................. 8 Motor start/stop frequency 5.7.8............................. 46
Bill of Materials Reference Numbers 11.1 .............. 70 Nameplate 1.7.1........................................................ 9
CE Marking and Approvals 1.2 ................................. 5 Noise Level 1.9 ......................................................... 9
CERTIFICATION 9…………………………..………69 Nomenclature 3.2.................................................... 16
Change Notes 10.2 ................................................. 69 Normal vibration levels, alarm and trip 5.7.7 ......... 46
Compliance, ATEX 1.6.4.1........................................ 7 Operating limits 3.4.1 .............................................. 22
Configuration 3.1 ..................................................... 15 Operating the Pump 5.8 ......................................... 46
Consumables, Recommended 6.4 ......................... 51 Parts Lists 8...………..………………………………60
Copyright 1.4 ............................................................. 5 Performance 3.4 ..................................................... 22
Design of Major Parts 3.3 ....................................... 18 Piping 4.7 ................................................................ 32
Direction of Rotation 5.4 ......................................... 43 Pre-commissioning Procedure 5.1 ......................... 36
Disassembly 6.8 ...................................................... 53 Priming and Auxiliary Supplies 5.6 ......................... 43
Disclaimer 1.3 ........................................................... 5 Protection Systems 4.10......................................... 35
DOCUMENTation AND MANUALS 10 ................... 69 Pump Lubricants 5.2 ............................................... 36
DRAWINGS, Sectionals 8..…………………………60 Receipt and Unpacking 2.1 .....................................11
Duty Conditions 1.5................................................... 5 Recycling 2.5........................................................... 15
Electrical Connections 4.8 ...................................... 35 Safety action 1.6.3 .................................................... 6
End of Product Life 2.5 ........................................... 15 Safety labels 1.7.2 .................................................... 9
Examination of Parts 6.9......................................... 54 Safety markings 1.6.1 ............................................... 6
Fastener Lubrication 6.6.2 ...................................... 53 Spare Parts, Ordering 6.3.1 ................................... 50
Fastener Sequencing 6.6.3 .................................... 53 Spare Parts, Storage 6.3.3 ..................................... 51
Fastener Torques 6.6.1 ........................................... 52 Spares, Recommended 6.4.................................... 51
Forces and Moments 4.7.2 ..................................... 33 Specific Machine Performance 1.8 .......................... 9
Foundation 4.3 ........................................................ 22 Starting the Pump 5.7 ............................................. 43
Grouting 4.4 ............................................................ 25 STARTUP, OPERATION AND SHUTDOWN 5 …36
Guarding 5.5 ........................................................... 43 Stopping and Shutdown 5.9 ................................... 47
Handling 2.2 .............................................................11 Storage 2.4.............................................................. 15
Hydraulic, mechanical and electrical duty 5.10...... 47 Stuffing box 3.3.7 .................................................... 20
Impeller, Setting Clearance 6.7 .............................. 53 Supplementary User Instructions 10.1 ................... 69
Inspection, Periodic 6.2.2 ....................................... 49 Thermal expansion 4.6.1 ........................................ 31
Inspection, Routine 6.2.1 ........................................ 49 Tools Required 6.5 .................................................. 51
INSTALLATION 4……………………………………22 Trouble Shooting 7…..………………………………58
Lifting 2.3 ..................................................................11

Page 3 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

INTRODUCTION AND SAFETY of technical documents and safety instructions. Where


applicable this document incorporates information
General relevant to these Directives and Approvals.
To confirm the Approvals applying and if the product is
These instructions must always be kept CE marked, check the serial number plate markings
close to the product's operating location or and the Certification. (See section 9, Certification.)
directly with the product.
Disclaimer
Flowserve products are designed, developed and Information in these User Instructions is believed
manufactured with state-of-the-art technologies in to be complete and reliable. However, in spite of
modern facilities. The unit is produced with great all of the efforts of Flowserve Corporation to
care and commitment to continuous quality control, provide comprehensive instructions, good
utilizing sophisticated quality techniques, and safety engineering and safety practice should always be
requirements. used.

Flowserve is committed to continuous quality Flowserve manufactures products to exacting


improvement and being at service for any further International Quality Management System Standards
information about the product in its installation and as certified and audited by external Quality Assurance
operation or about its support products, repair and organizations. Genuine parts and accessories have
diagnostic services. been designed, tested and incorporated into the
products to help ensure their continued product quality
These instructions are intended to facilitate and performance in use. As Flowserve cannot test
familiarization with the product and its permitted use. parts and accessories sourced from other vendors the
Operating the product in compliance with these incorrect incorporation of such parts and accessories
instructions is important to help ensure reliability in may adversely affect the performance and safety
service and avoid risks. The instructions may not features of the products. The failure to properly select,
take into account local regulations; ensure such install or use authorized Flowserve parts and
regulations are observed by all, including those accessories is considered to be misuse. Damage or
installing the product. Always coordinate repair failure caused by misuse is not covered by the
activity with operations personnel, and follow all plant Flowserve warranty. In addition, any modification of
safety requirements and applicable safety and health Flowserve products or removal of original components
laws and regulations. may impair the safety of these products in their use.

These instructions must be read prior to Copyright


installing, operating, using and maintaining the All rights reserved. No part of these instructions may
equipment in any region worldwide. The be reproduced, stored in a retrieval system or
equipment must not be put into service until all transmitted in any form or by any means without prior
the conditions relating to safety noted in the permission of Flowserve.
instructions, have been met. Failure to follow Duty Conditions
and apply the present user instructions is This product has been selected to meet the
considered to be misuse. Personal injury, specifications of your purchase order. The
product damage, delay or failure caused by acknowledgement of these conditions has been sent
misuse are not covered by the Flowserve separately to the Purchaser. A copy should be kept
warranty. with these instructions.
CE Marking and Approvals
It is a legal requirement that machinery and equipment The product must not be operated beyond
put into service within certain regions of the world shall the parameters specified for the application. If
conform with the applicable CE Marking Directives there is any doubt as to the suitability of the
covering Machinery and, where applicable, Low Voltage product for the application intended, contact
Equipment, Electromagnetic Compatibility (EMC), Flowserve for advice, quoting the serial number.
Pressure Equipment Directive (PED) and Equipment for
Potentially Explosive Atmospheres (ATEX). If the conditions of service on your purchase order
are going to be changed (for example liquid pumped,
Where applicable the Directives and any additional temperature or duty) it is requested that the user
Approvals cover important safety aspects relating to seeks the written agreement of Flowserve before
machinery and equipment and the satisfactory provision start up.

Page 4 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Safety used in potentially explosive atmospheres


section 1.6.4 also applies.
Safety markings
These User Instructions contain specific safety NEVER DO MAINTENANCE WORK
markings where non-observance of an instruction would WHEN THE UNIT IS CONNECTED TO POWER
cause hazards. The specific safety markings are:
GUARDS MUST NOT BE REMOVED WHILE
This symbol indicates electrical safety THE PUMP IS OPERATIONAL
instructions where non-compliance will involve a high
DRAIN THE PUMP AND ISOLATE PIPEWORK
risk to personal safety or the loss of life.
BEFORE DISMANTLING THE PUMP
This symbol indicates safety instructions where The appropriate safety precautions should be taken
non-compliance would affect personal safety and where the pumped liquids are hazardous.
could result in loss of life.
FLUORO-ELASTOMERS (When fitted.)
This symbol indicates “hazardous and toxic fluid” When a pump has experienced temperatures over
safety instructions where non-compliance would affect 250 ºC (482 ºF), partial decomposition of fluoro-
personal safety and could result in loss of life. elastomers (example: Viton) will occur. In this
condition these are extremely dangerous and skin
This symbol indicates safety contact must be avoided.
instructions where non-compliance will involve some
HANDLING COMPONENTS
risk to safe operation and personal safety and would
Many precision parts have sharp corners and the
damage the equipment or property.
wearing of appropriate safety gloves and equipment
This symbol indicates explosive atmosphere is required when handling these components. To lift
zone marking according to ATEX. It is used in safety heavy pieces above 25 kg (55 lb) use a crane
instructions where non-compliance in the hazardous appropriate for the mass and in accordance with
area would cause the risk of an explosion. current local regulations.

This symbol is used in safety instructions to APPLYING HEAT TO REMOVE IMPELLER


remind not to rub non-metallic surfaces with a dry There may be occasions when the impeller has either
cloth; ensure the cloth is damp. It is used in safety been shrunk fit on to the pump shaft or has become
instructions where non-compliance in the hazardous difficult to remove due to products of corrosion.
area would cause the risk of an explosion.
If you elect to use heat to remove the impeller, it must
This sign is not a safety symbol but indicates be applied quickly to the impeller boss. TAKE
an important instruction in the assembly process. GREAT CARE!

Personnel qualification and training Before applying heat ensure any residual hazardous
All personnel involved in the operation, installation, liquid trapped between the impeller and pump shaft is
inspection and maintenance of the unit must be thoroughly drained out through the impeller keyway
qualified to carry out the work involved. If the to prevent an explosion or emission of toxic vapor.
personnel in question do not already possess the This must be carried out with the shaft in the vertical
necessary knowledge and skill, appropriate training position. On some pump sizes a cavity exists in the
and instruction must be provided. If required, the impeller bore so on occasions a significant volume of
operator may commission the manufacturer/supplier liquid may drain out.
to provide applicable training.
THERMAL SHOCK
Rapid changes in the temperature of the liquid within
Always coordinate repair activity with operations and
the pump can cause thermal shock, which can result
health and safety personnel, and follow all plant
in damage or breakage of components and should be
safety requirements and applicable safety and health
avoided.
laws and regulations.
HOT (and cold) PARTS
Safety action If hot or freezing components or auxiliary heating
This is a summary of conditions and actions to
supplies can present a danger to operators and
prevent injury to personnel and damage to the
persons entering the immediate area action must be
environment and to equipment. For products

Page 5 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

taken to avoid accidental contact. If complete the motor and cause cavitation. Low flow rates may
protection is not possible, the machine access must cause a reduction in pump/bearing life, overheating of
be limited to maintenance staff only, with clear visual the pump, instability and cavitation/vibration.
warnings and indicators to those entering the
immediate area. Note: bearing housings must not be Products used in potentially explosive
insulated and drive motors and bearings may be hot. atmospheres

If the temperature is greater than 80 ºC (175 ºF) or Measures are required to:
below -5 ºC (23 ºF) in a restricted zone, or exceeds · Avoid excess temperature
local regulations, action as above shall be taken. · Prevent build up of explosive mixtures
· Prevent the generation of sparks
HAZARDOUS LIQUIDS · Prevent leakages
When the pump is handling hazardous liquids care · Maintain the pump to avoid hazard
must be taken to avoid exposure to the liquid by
appropriate siting of the pump, limiting personnel The following instructions for pumps and pump units
access and by operator training. If the liquid is when installed in potentially explosive atmospheres
flammable and/or explosive, strict safety procedures must be followed to help ensure explosion protection.
must be applied. For ATEX, both electrical and non-electrical
equipment must meet the requirements of European
Gland packing must not be used when pumping Directive 94/9/EC. Always observe the regional legal
hazardous liquids. Ex requirements e.g. Ex electrical items outside the
EU may be required certified to other than ATEX e.g.
PREVENT EXCESSIVE EXTERNAL IECEx, UL.
PIPE LOAD
Do not use pump as a support for piping. Do not Scope of compliance
mount expansion joints, unless allowed by Flowserve
in writing, so that their force, due to internal pressure, Use equipment only in the zone for which it is
acts on the pump flange. appropriate. Always check that the driver, drive
coupling assembly, seal and pump equipment are
ENSURE CORRECT LUBRICATION
suitably rated and/or certified for the classification of the
(See section 5, Commissioning, startup, operation
specific atmosphere in which they are to be installed.
and shutdown.)

START THE PUMP WITH OUTLET Where Flowserve has supplied only the bare shaft
VALVE PARTLY OPENED pump, the Ex rating applies only to the pump. The
(Unless otherwise instructed at a specific point in the party responsible for assembling the ATEX pump set
User Instructions.) shall select the coupling, driver and any additional
This is recommended to minimize the risk of equipment, with the necessary CE Certificate/
overloading and damaging the pump motor at full or Declaration of Conformity establishing it is suitable for
zero flow. Pumps may be started with the valve the area in which it is to be installed.
further open only on installations where this situation
cannot occur. The pump outlet control valve may The output from a variable frequency drive (VFD) can
need to be adjusted to comply with the duty following cause additional heating affects in the motor and so, for
the run-up process. (See section 5, Commissioning pumps sets with a VFD, the ATEX Certification for the
start-up, operation and shutdown.) motor must state that it is covers the situation where
electrical supply is from the VFD. This particular
NEVER RUN THE PUMP DRY requirement still applies even if the VFD is in a safe area.

INLET VALVES TO BE FULLY OPEN


WHEN PUMP IS RUNNING
Running the pump at zero flow or below the
recommended minimum flow continuously will cause
damage to the pump and mechanical seal.

DO NOT RUN THE PUMP AT


ABNORMALLY HIGH OR LOW FLOW RATES
Operating at a flow rate higher than normal or at a flow
rate with no back pressure on the pump may overload

Page 6 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Marking The temperature rise at the seals and bearings and


An example of ATEX equipment marking is shown due to the minimum permitted flow rate is taken into
below. The actual classification of the pump will be account in the temperatures stated.
engraved on the nameplate.
The operator is responsible to ensure that the
II 2 GD c IIC 135 ºC (T4) specified maximum liquid temperature is not
exceeded
Equipment Group
I = Mining
Temperature classification “Tx” is used when the
II = Non-mining
liquid temperature varies and the pump could be
Category installed in different hazarous atmospheres. In this
2 or M2 = high level protection case the user is responsible for ensuring that the
3 = normal level of protection pump surface temperature does not exceed that
permitted in the particular hazardous atmosphere.
Gas and/or dust
G = Gas If an explosive atmosphere exists during the
D = Dust installation, do not attempt to check the direction of
c = Constructional safety rotation by starting the pump unfilled. Even a short
(in accordance with EN13463-5) run time may give a high temperature resulting from
contact between rotating and stationary components.
Gas Group
IIA – Propane (typical) Where there is any risk of the pump being run
IIB – Ethylene (typical) against a closed valve generating high liquid and
IIC – Hydrogen (typical) casing external surface temperatures, fit an external
surface temperature protection device.
Maximum surface temperature (Temperature Class)
(see section 1.6.4.3.)
Avoid mechanical, hydraulic or electrical overload by
using motor overload trips, temperature monitor or a
Avoiding excessive surface
power monitor and make routine vibration monitoring
temperatures
checks.
ENSURE THE EQUIPMENT TEMPERATURE
CLASS IS SUITABLE FOR THE HAZARD ZONE In dirty or dusty environments, make regular checks
and remove dirt from areas around close clearances,
Pumps have a temperature class as stated in the bearing housings and motors.
ATEX Ex rating on the nameplate. These are based
on a maximum ambient of 40 ºC (104 ºF); refer to Preventing the buildup of explosive
Flowserve for higher ambient temperatures. mixture

ENSURE THE PUMP IS PROPERLY FILLED


The surface temperature on the pump is influenced
AND VENTED AND DOES NOT RUN DRY
by the temperature of the liquid handled. The
Ensure the pump and relevant suction and discharge
maximum permissible liquid temperature depends on
pipeline system is totally filled with liquid at all times
the temperature class and must not exceed the
during the pump operation, so that an explosive
values in the table that follows.
atmosphere is prevented. In addition, it is essential
Temperature class Maximum surface Temperature limit of to make sure that seal chambers, auxiliary shaft seal
to EN13463-1 temperature permitted liquid handled * systems and any heating and cooling systems are
T6 85 °C (185 °F) Consult Flowserve properly filled.
T5 100 °C (212 °F) Consult Flowserve
T4 135 °C (275 °F) 115 °C (239 °F)
T3 200 °C (392 °F) 180 °C (356 °F) If the operation of the system cannot avoid this
T2 300 °C (572 °F) 275 °C (527 °F) condition, fit an appropriate dry run protection device
T1 450 °C (842 °F) 400 °C (752 °F) (for example liquid detection or a power monitor).
* The table only takes the ATEX temperature class into consideration.
Pump design or material, as well as component design or material,
may further limit the maximum working temperature of the liquid. To avoid potential hazards from fugitive emissions of
vapor or gas to atmosphere the surrounding area
must be well ventilated.

Page 7 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Preventing sparks adversely affect the ambient conditions. Where there


is a risk from such tools or materials, maintenance
To prevent a potential hazard from mechanical must be conducted in a safe area.
contact, the coupling guard must be non-sparking.
It is recommended that a maintenance plan and
To avoid the potential hazard from random induced schedule is adopted. (See section 6, Maintenance.)
current generating a spark, the base plate must be
properly grounded. Safety Labels Summary

Avoid electrostatic charge: do not rub non-metallic Nameplate


surfaces with a dry cloth; ensure cloth is damp. For details of nameplate, see the Declaration of
Conformity, or separate documentation included with
For ATEX applications the coupling must be selected these User Instructions.
to comply with 94/9/EC. Correct coupling alignment
must be maintained. Safety labels

Additional requirement for metallic pumps on


non-metallic base plates
When metallic components are fitted on a non-
metallic base plate they must be individually earthed.

Preventing leakage

The pump must only be used to handle liquids


for which it has been approved to have the correct
corrosion resistance.

Avoid entrapment of liquid in the pump and associated


piping due to closing of suction and discharge valves,
which could cause dangerous excessive pressures to
occur if there is heat input to the liquid. This can occur if
the pump is stationary or running.

Bursting of liquid containing parts due to freezing


must be avoided by draining or protecting the pump Oil lubricated units only:
and ancillary systems.

Where there is the potential hazard of a loss of a seal


barrier fluid or external flush, the fluid must be
monitored.

If leakage of liquid to atmosphere can result in a Specific Machine Performance


hazard, install a liquid detection device. For performance parameters see section 1.5, Duty
conditions. When the contract requirement specifies
these to be incorporated into User Instructions these
Maintenance to avoid the hazard are included here. Where performance data has
been supplied separately to the purchaser these
CORRECT MAINTENANCE IS REQUIRED TO should be obtained and retained with these User
AVOID POTENTIAL HAZARDS WHICH GIVE A Instructions if required.
RISK OF EXPLOSION
Noise Level
The responsibility for compliance with maintenance Attention must be given to the exposure of personnel
instructions is with the plant operator. to the noise, and local legislation will define when
guidance to personnel on noise limitation is required
To avoid potential explosion hazards during and when noise exposure reduction is mandatory.
maintenance, the tools, cleaning and painting This is typically 80 to 85 dBA.
materials used must not give rise to sparking or

Page 8 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

The usual approach is to control the exposure time to Typical vertical motor noise data
the noise or to enclose the machine to reduce (Hollow and Solid shafts)
emitted sound. You may have already specified a
Motor RPM Sound Sound
limiting noise level when the equipment was ordered, Frame Pressure Power
however if no noise requirements were defined, then Size. (dBA) (dBA)
attention is drawn to the following table to give an NEMA (WP- I (WP- I
enclosure) enclosure
indication of equipment noise level so that you can 180 3600 70.0 78.0
take the appropriate action in your plant. 1800 60.0 68.0
1200 & slower 55.0 63.0
Pump noise level is dependent on a number of 210 3600 70.0 78.2
operational factors, flow rate, pipework design and 1800 60.0 68.2
1200 & slower 55.0 63.2
acoustic characteristics of the building, and so the
250 3600 75.0 83.4
values given are subject to a 3 dBA tolerance and 1800 70.0 78.4
cannot be guaranteed. 1200 & slower 60.0 68.4
280 3600 75.0 83.8
Similarly, the motor noise assumed in the “pump and 1800 70.0 78.8
motor” noise is that typically expected from standard 1200 & slower 60.0 68.8
320 3600 75.0 84.0
and high efficiency motors when on load directly driving 1800 65.0 74.0
the pump. Note that a motor driven by an inverter may 1200 & slower 65.0 74.0
show an increased noise at some speeds. 360 3600 75.0 84.2
1800 65.0 74.2
If a pump unit only has been purchased for use with 1200 & slower 65.0 74.2
400 3600 80.0 89.5
customer driver, then the “pump only” noise levels in the 1800 70.0 79.5
table should be combined with the level for the driver 1200 & slower 65.0 74.5
obtained from the supplier. Consult a noise specialist if 440 3600 80.0 90.0
assistance is required in combining the values. 1800 70.0 80.0
1200 & slower 70.0 80.0
449 1800 85.0 97.8
It is recommended that where exposure approaches
1200 & slower 80.0 92.8
the prescribed limit, then site noise measurements 5000 3600 90.0 102.8
should be made. 1800 85.0 97.8
1200 & slower 80.0 92.8
The values are in sound pressure level, LpA, at 1 m 5800 3600 90.0 103.7
(3.3 ft) from the machine for “free field conditions 1800 90.0 103.7
1200 & slower 80.0 93.7
over a reflecting plane”. 6800 1800 90.0 103.9
1200 & slower 85.0 98.8
For estimating sound power level, LWA (re 1pW), add 8000 1800 90.0 104.7
17 dBA to the sound pressure value. 1200 & slower 85.0 99.7

Specific machine performance


The noise levels shown in table 1.9.1 are For performance, parameters see section 1.5, Duty
extracted from typical motor manufacturer’s conditions. Whenever there is a contract
data/catalogue to provide the average expected requirement to incorporate specific machine
motor noise values at no load for reference only and performance into User Instructions, those are
are not guaranteed. The values could vary included here. In cases where performance data has
depending upon the test and surrounding conditions. been supplied separately to the purchaser, the same
The combined noise level of the pump and the motor should be retained with these User Instructions, if
could exceed the values shown. It is to be noted that required.
adding motors with similar noise levels increases the
total noise level. Therefore, the dB correction to the
values listed above is required to obtain the
combined noise levels of motor and the pump.
Actual on-site noise measurement by experts is
recommended and safety measures are to be taken
accordingly.

Page 9 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

2 TRANSPORT AND STORAGE


Lift of the discharge head with or without the
Consignment receipt and unpacking complete pump assembly shall not be performed with
Immediately upon receipt of the equipment, the the driver mounted to the discharge head.
packing list must be checked against the delivered
components to confirm completeness of shipment Refer to the driver manufacturer’s instructions for
and ensure that there has been no damage in proper lifting procedure for the driver.
transportation. Any shortages and/or damage must
be reported immediately to Flowserve, and report
must be received in writing within one month of
receipt of the equipment. Later claims cannot be Exercise caution when lifting complete pump
accepted. assembly or pump components to prevent injury or
loss of life.
Check crates, boxes and wrappings for any
accessories or spare parts which may be packed Lifting of cast discharge head only
separately with the equipment or attached to side (without pump assembly components)
walls of the box or equipment. Lift the cast discharge heads (without pump
assembly components) by installing eyebolts as
Both pump and driver have unique serial numbers, shown thru the driver mounting flange holes.
and these serial numbers are located on the
corresponding nameplates. The pump nameplate is
affixed to the discharge head or bowl assembly, and
motor nameplate is affixed to the motor housing.
These serial numbers must be referenced for all
product correspondences.

Example of typical pump nameplate.

Do not use the lift pins at the base of


the discharge head while lifting the cast discharge
head only unless the discharge head is secured by
slings to prevent overturning. Never lift the
complete pump assembly with eyebolts through
Handling the driver mounting flange.
Boxes, crates, pallets or cartons may be unloaded
using fork lift vehicles or slings dependent on their
size and construction.
Lifting
Equipment in excess of 25kg (55lbs) should be
lifted by mechanical means. Fully trained personnel
must carry out lifting, in accordance with local
regulations.

Page 10 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Lifting of cast discharge head with Typical lift pin sizes of fabricated discharge heads.
complete/partial pump assembly Fabricated heads with discharge size mm (in.)
Cast discharge heads with attached pump 100-200 250-600 700-900
(4-8) (10-24) (28-36)
components are recommended to be lifted using lift
Pin
pins sized in accordance with the pump weights Dia. 32 (1.25) 38 (1.50) 44 (1.75)
provided on the general arrangement and/or
Weight <2300 (5000) <4500 (10000) <6800 (15000)
nameplate. Alternative lift method would be to use
minimum of two straps on the cast discharge head,
placing each strap around two ribs on the head. Pins shall be sized in accordance with the pump
weights provided on the general arrangement and/or
Typical lift pin sizes of cast discharge heads. nameplate.
Cast heads with discharge size mm (in.)
100 150 200 250 300 Fabricated discharge head with lift holes
(4) (6) (8) (10) (12) in lugs.
Pin 25 32 32 32 38
Dia. (1) (1.25) (1.25) (1.25) (1.5)

The slings are attached to the lift pin shall maintain a


minimum 12 inch length of the sling from the shaft
end as shown in the detail below.

Fabricated discharge head with lift holes


in ribs.

Lifting of fabricated discharge heads


with or without the complete pump
assembly
When provided, the fabricated discharge head may be
supplied with one of two styles of lifting configurations:
lift holes in lugs (ref 2.3.3.1) or lift holes in ribs (ref
2.3.3.2). The quantity/style of lift holes may vary
based on the discharge head design; however, the
intention is that all available lift holes are utilized when
lifting the pump with or without the complete pump
assembly.

Page 11 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Lifting of suction barrel


Lifting of bowl assembly only Suction barrel (also referred as ‘Can’) is to be
Carefully lift the bowl assembly to vertical with clamp installed prior to the installation of the pump
and straps. See below. assembly. Install eyebolts on the flange of the
suction barrel and use straps to bring the suction
When installing a long 6” or 8” bowl assembly, leave barrel to a vertical position. See below.
the bowl assembly securely fastened to the wooden
skid that is attached for shipping until the bowl
assembly is raised to vertical position. Provide support to prevent the suction barrel
from swaying during movement.

Do not allow the weight of the bowl assembly to


rest on the bell lip.

SUCTION BARREL (CAN)

Page 12 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Lifting of complete pump assemblies


When fully assembled, the pump assembly shall be
adequately strapped and supported at least two
places prior to lifting. See below.

Pump must be supported


at least two places
when lifted.
Do not use chains
to wrap around.

Two (2)
cranes are
required

Examples shown here are for illustration only. See section 2.3 1~2.3.6 for specific lifting
instructions based on design variations.

Pump must be supported at


least two places when lifted.
Do not use chains to wrap around.

Page 13 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Storage
Make sure that hazardous substances or
Store the pump in a clean, dry toxic fluids are disposed of safely and that the correct
location away from vibration. Leave protective personal protective equipment is used. The safety
covers in place to keep dirt and other foreign material specifications must be in accordance with the current
out of pump assembly. Turn the pump at frequent regulations.
intervals to prevent brinelling of the bearings and
sticking of the seal faces, if supplied. 3 Description
When contacting Flowserve pump division for
Inspection before storage assistance, the pump and driver serial numbers will
a) Inspect the preservative coating/painted surfaces be required. Both pump and driver have unique
on the various parts. Touch up the areas as serial numbers, and these serial numbers are located
needed. on the corresponding nameplates. The pump
b) Inspect all protective covers over pump openings nameplate is affixed to the discharge head or bowl
and piping connections. If damaged, remove the assembly, and motor nameplate is affixed to the
covers and inspect interiors of the opening for any motor housing. These serial numbers must be
deposits of foreign materials or water. referenced for all product correspondences.
c) If necessary, clean and preserve the interior parts
as noted above to restore the parts to the "as
shipped" condition. Replace covers and fasten Configuration
securely. VTPs, are engineered pumps typically configured as:
d) Exercise caution with pumps exposed to weather. a) Wet pit or b) suction barrel (can) pumps. Most
Containers are not leak proof. Parts may be pumps are built with customer specific features and
coated with a residual amount of protective for applications such as water pumping stations,
coating, which will wash away if exposed to deep wells, storm water service, industrial and
elements. cryogenic applications. The pumps vary in hydraulic
type and size, and can be of open shaft or enclosed
Short term storage (up to 6 months) shaft designs depending on the application.
Follow the steps given in section 2.4.1. Select a
storage space so that the unit will not be subjected to See 3.1.1 and 3.1.2 for typical configuration
vibration, excess moisture, extreme weather representations.
conditions, corrosive fumes, or other harmful
conditions.
Some units will not require a column
Refer to the driver manufacturer’s instructions for assembly. In such cases, the bowl assembly is
proper short term procedure for the driver. connected directly to the discharge head. Vertical
turbine pumps can have single or multiple stages.
Long term or extended storage
If long-term storage is required, (more than 6
months), please contact Flowserve for special
storage instructions and warranty related information.

Recycling and End of Product Life


At the end of the service life of the product or its
parts, the relevant materials and parts should be
recycled or disposed of using an environmentally
acceptable method and local regulations. If the
product contains substances which are harmful to the
environment, these should be removed and disposed
of in accordance with current regulations. This also
includes the liquids and or gases in the "seal system"
or other utilities.

Page 14 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Sump and deep well VTP Suction barrel (Can) VTP

DRIVER

DRIVER

DISCHARGE
HEAD
ASSEMBLY
DISCHARGE
HEAD
ASSEMBLY

COLUMN
ASSEMBLY

COLUMN
ASSEMBLY

BOWL
SUCTION
ASSEMBLY BARREL
(CAN)

BOWL
ASSEMBLY

Nomenclature
Pump assemblies are designated by pump models
which are specific to the hydraulics utilized for the
bowl assembly. Common bowl models are EB, EG,
EH, EJ, EK, EL, EM, EN, EP, EQ, SK, SL, SN, SP,
SR, ST, & AV. The pump size is expressed in terms
of nominal bowl diameter in inches, and those sizes
could vary from 150mm (6 in) to 1300 mm (52 in.).

The impeller model in each of these bowl assemblies


are designated separately. See section 3.2.1 for
more details.

Page 15 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Nominal discharge diameter in inches


The pump type/size (model) will be engraved on the
nameplate and affixed to the discharge head or bowl W = Cast head- for horizontal above ground discharge
HF/HFL/HFH = Fabricated head for above the ground discharge
assembly:
LF/LFL/LFH= Fabricated heads with base flange for above ground
discharge
TF = Fabricated heads with base flange for above ground suction
and discharge
UF = Fabricated head for below ground discharge

See section 3.2.2.1 for pictorial representation of


discharge head types.

ypes of discharge heads


Typical discharge head types are shown in details (a)
thru (e).

a) W type cast discharge head

Pump model nomenclature

12 E J H-3

Nominal Bowl Diameter-inches b) HF/HLF/HFH type fabricated discharge head


(Typical representation with square base plate)
Impeller Model Type (A or E or S)
A=Axial, E=Enclosed, S=Semi-open

Bowl Model Types


B,J,K,H,L,M,N,P,Q,R,T,V….

Impeller Model Designation


L, M, H, Y…..

No. of Stages

Discharge head nomenclature


Consists of alphanumeric code as follows.
Examples: 8W16, 10HF20, 6TF16,…….

10 HF 20
c) LF/LFL/LFH type fabricated discharge head
(Typical representation with a circular base
flange)
Nominal driver base diameter in inches

Discharge head type (see details below)

Page 16 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

The discharge heads shown in section


3.2.2.1 (a) thru (e) are for illustration only. For the
actual configuration of the pump that has been
purchased, refer to the order specific general
arrangement and/or cross sectional drawing.

Design of Major Parts

Please refer to appendix for Europump part


number equivalents

Drivers
A variety of drivers may be used; however, electric
d) TF type fabricated discharge head motors are most common. For the purposes of this
(Typical representation with a circular base manual, all types of drivers can be grouped into two
flange) categories.

a) Hollow shaft drivers: The head shaft extends


through a tube in the center of the rotor and is
connected to the driver by a clutch assembly at the top
of the driver.

b) Solid shaft drivers: The rotor shaft is solid and


projects below the driver-mounting base. This type
driver requires an adjustable coupling for connecting
to the pump.

Discharge Head Assembly


The discharge head contains the suction and
discharge pipe connections, as applicable, and
supports the driver, column assembly and bowl
assembly, as supplied. See section 3.2.2.1.

e) UF type fabricated discharge head The shaft sealing arrangement is located in the
(Typical representation with square base plate) discharge head which contains the pumpage at the
point where the shaft exits from the liquid chamber.

The shaft seal will usually be either a mechanical


seal assembly or stuffing box with an open lineshaft
or a tube-packing box with an enclosed lineshaft.

Column assembly
The column assembly consists of the column pipe,
bearing, bearing retainer, and shaft assembly. The
column pipe connects the bowl assembly to the
discharge head and directs the pumped fluid to the
discharge head. Typical column assemblies are:

Page 17 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Suction strainers
a) Flanged column assembly: VTPs can also be fitted with strainers [316] to prevent
foreign particles from entering the pump. The type of
strainers and the mesh size depends on the
application. Examples are shown below. Strainers
are fastened [422] directly to the suction bell [55] or
attached using clips [421]. Cone shaped strainers
are provided with internal or external threads to
attach it to the main assembly.

a) Slip-on strainer

b) Threaded column assembly: from 100 mm~355


mm (4~14 in.) sizes only.

b) Clip-on strainer
SUCTION BELL (55)

CLIP
(421)

CAP SCREW (422)


STRAINER (316)

Supported within the column is the shaft assembly.


The shaft types are threaded or keyed, and the c) Cone (threaded) strainer
construction types are either:

a) Open lineshaft construction utilizing the fluid being


pumped to lubricate the lineshaft bearings.
Or
b) Enclosed lineshaft construction has an enclosing
tube around the lineshaft and utilizes oil or other
fluid to lubricate the lineshaft bearings.

See sectional drawings supplied with the pump for


exact column assembly details as per the order. The
size and configuration vary depending upon the d) Bolt on strainer
specific order requirements and application criteria.

Bowl assemblies
The bowl assembly consists of impellers rigidly
mounted on the pump shaft coupled to an electric
motor. Impellers are cast wheels with multiple diffuser
vanes and are generally coated to meet the hydraulic
requirements. See section 8.0 for cross sectional and
part details.

Page 18 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Impellers
VTP’s are supplied with enclosed, or semi open Low pressure stuffing box
impeller types. Impellers are low, medium and high This type of packing box is fitted on to an open
capacity type designed for maximum coverage of all lineshaft for pressures less than 6.5 bar (100 psi) and
VTP applications. Impellers are cast and machined used only on W-type discharge heads (see Section
to match each order and to provide required surface 3.2.2.1 to see for W type discharge head detail).
finish to achieve hydraulic characteristics. Impellers
are dynamically balanced and held in position on the
shaft by a tapered lock collet or split ring and key. SLINGER (346)

(17) PACKING GLAND


STUD (326A)
Stuffing box
HEX NUT (327A)
Some VTPs are fitted with stuffing boxes. In such (354) STUD
cases, stuffing boxes are normally adequate for
(355) HEX NUT
working pressures up to 20.7 bar (300 psi). Refer to
stuffing box User Instructions for specifications.
O-RING (347)

STUFFING BOX (83)

(13) PACKING SET

PRESSURE
REDUCING
BUSHING (117)

High pressure stuffing box


This type of packing box is fitted on to an open lineshaft for pressures up to 20 bar (300 psi) uses six rings of
packing with two lantern rings and allows grease lubrication.

Page 19 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Extra high pressure stuffing box


In cases where the pressures are expected to cross 20 bar (300 psi) up to 65 bar (1000 psi), extra high-
pressure stuffing box is used.

3.3.8 Mechanical shaft seal


VTP’s can also be fitted with a mechanical seal. The requirement to fit the mechanical seal is to be provided at
the time of contract.

Page 20 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Accessories
Accessories may be fitted when specified by the Preparation
customer. The pump should be located to allow room for access,
ventilation, maintenance and inspection with ample
Performance and Operation Limits headroom for lifting and should be as close as
This product has been selected to meet the practicable to the supply of liquid to be pumped.
specifications of the purchase order. See section 1.5.
Refer to the general arrangement drawing for the pump
The following data is included as additional information to dimensions and details.
help with the installation. It is typical and factors such as
temperature, materials and seal type may influence this General installation check-list
data. If required, a definitive statement for your particular The following checks should be made before starting
application can be obtained from Flowserve. actual installation.

Operating limits a) Make sure that motor nameplate ratings and the
power supply system match correctly.
Pumped liquid temperature 5 ºC (40 ºF) to +80 ºC (176 ºF) b) Check the sump depth and pump length match-
limits* up.
Maximum ambient Up to +40 ºC (104 ºF) c) Check the liquid level in the sump.
temperature*
Maximum pump speed refer to the nameplate
d) Check the installation equipment to be sure that it
will safely handle the pump weight and size.
*Subject to written agreement from Flowserve. e) Check all pump connections (bolts, nuts etc.) for
Special designs and materials may be available for any shipping and handling related problems.
pumps operating above and below these specified
limits. Contact Flowserve for upgrade options
available for your specific application. Always support shafting in at least
three places when lifting or installing. No installation
should be attempted without adequate equipment
4 INSTALLATION necessary for a successful installation.
Equipment operated in hazardous locations
must comply with the relevant explosion protection
regulations. See section 1.6.4, Products used in · On hollow shaft drivers, check the clutch size
potentially explosive atmospheres. against the shaft size, which must go through the
Location clutch
When equipment has been in storage for greater than 6 · On solid shaft drivers, check the motor shaft size
months, a complete inspection should be conducted in against the coupling bore size
accordance with section 2.4.3. The pump should be
located to allow room for access, ventilation,
maintenance and inspection with ample headroom for Apply thread lubricant sparingly to
lifting and should be as close as practicable to the male shaft threads only at the time of making up
supply of liquid to be pumped. Refer to the general shaft connection. Excess lubricant should be
arrangement drawing for the pump set. avoided.

Inspection prior to installation


Always check motor rotation before
Six months prior to the scheduled installation date, a
connecting driver to pump. Reserve rotation due to
Flowserve Pump Division representative is to be
improper motor direction can cause extensive damage
employed to conduct an inspection of the equipment
to the pump.
and the facility. If any deterioration of equipment is
noticed, the Flowserve Pump Division representative
may require a partial or complete dismantling of the Foundation
equipment including restoration and replacement of
some components.
There are many methods of installing
pump units to their foundations. The correct method
depends on the size of the pump unit, its location and
vibration limitations. Non-compliance with the

Page 21 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

provision of correct foundation and installation may Grout is poured under the mounting plate and
lead to failure of the pump and, as such, would be allowed to cure per the manufacturer’s instructions
outside the terms of the warranty. before the foundation bolts are fully torqued or any
further work is done on the pump.
The foundation must consist of material that will afford
rigid support to the discharge head and will absorb Example of a typical discharge head with the
expected stresses that may be encountered in service. mounting plate

Concrete foundations should have anchor bolts


installed in sleeves that allow alignment and have
holes in the mounting plate as illustrated in the detail
below. Sleeve should be filled with non-bonding
moldable material after sleeve is set in place.

When a suction barrel is supplied as in the case of the


type "TF" discharge head, the suction vessel must
provide permanent, rigid support for the pump and
motor.

All foundation / anchor bolt


recommendations should be verified by prevailing
industry standards.

Detail of a typical foundation bolt, grouted.


MOUNTING PLATE ANCHOR BOLT
NUT
Directly mounted pumps are not user
GROUT friendly for service. Re-installation of these pumps
FOUNDATION requires re-leveling and re-grouting.

NON-BONDING Leveling of pumps mounted on a


MOLDABLE MATERIAL
grouted soleplate
Wet pit pumps can be installed on an intermediate
plate known as soleplate [23]. The soleplate [23] is
installed on the foundation and aligned with the
anchor bolts [372], and the pump is mounted on top
of the soleplate.

The soleplate is shimmed to achieve the required


Leveling of pumps mounted on the
levelness of no greater than 0.051 mm (0.002 in.)
discharge head mounting plate between any two points taken on the top surface of the
Wet pit pumps can be installed directly on the soleplate, and the levelness is measured by using a
foundation by using the mounting plate that comes as
precision machinist’s level. The data is to be
an integral part of the discharge head. The pump is
recorded for future reference. Anchor bolt nuts [373]
lowered into the pit and aligned with the anchor bolts
are tightened sufficient enough to hold the soleplate
[372]
in place.
The mounting plate is shimmed to achieve the Grout is poured under the soleplate and allowed to
required levelness of no greater than 0.127 mm
cure per the manufacturer’s instructions before the
(0.005 in.) between any two points taken on the motor
foundation bolts are fully torqued and the pump is
mounting surface (top of the discharge head), and the
installed on the soleplate.
levelness is measured by using a precision
machinist’s level. The data is to be recorded for future
reference. Anchor bolt nuts [373] are tightened
sufficient enough to hold down the pump in place.

Page 22 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Example of pump mounted on a soleplate


Example of a pump mounted on a suction barrel.

Leveling of pumps mounted on a


Leveling of pumps with suction barrel
grouted suction barrel (also referred as
mounted on a grouted soleplate
“suction can”)
For ease of installation, vertical pumps can be
Vertical pumps can be installed in a suction barrel
installed in a suction barrel [315] which is mounted
[315]. The suction barrel [315] is lowered into the
on a grouted soleplate [23]. The addition of the
sump, and the suction barrel [315] mounting flange is
grouted soleplate allows for the pump and suction
installed on the foundation and aligned with the
barrel to be removed without disturbing the existing
anchor bolts [372]. The pump is mounted on top of
foundation. The soleplate [23] is installed on the
the suction barrel.
foundation and aligned with the anchor bolts [372];
however, the leveling of the soleplate can be
The suction barrel mounting flange is shimmed to
performed with or without the suction barrel being
achieve the required levelness of no greater than
installed on the soleplate.
0.051 mm (0.002 in.) between any two points taken
on the top surface of the suction barrel mounting plate,
Leveling of the grouted soleplate
and the levelness is measured by using a precision
The soleplate is shimmed to achieve the required
machinist’s level. The data is to be recorded for future
levelness of no greater than 0.025 mm (0.001 in.)
reference. Anchor bolt nuts [373] are tightened
between any two points taken on the top surface of the
sufficient enough to hold the suction barrel in place.
soleplate, and the levelness is measured by using a
precision machinist’s level. The data is to be
Grout is poured under the suction barrel mounting
recorded for future reference. Anchor bolt nuts [373]
flange and allowed to cure per the manufacturer’s
are tightened sufficient enough to hold the soleplate
instructions before the foundation bolts are fully
in place.
torqued and the pump is installed in the suction
barrel.
Grout is poured under the soleplate and allowed to
cure per the manufacturer’s instructions before the
foundation bolts are fully torqued and the suction
barrel and pump are installed on the soleplate.

Page 23 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Leveling of the grouted soleplate with If leveling nuts are used to level the
the suction barrel assembled to the base, they must be backed off as far as possible prior
soleplate to grouting.
The suction barrel is lowered into the sump, and the
suction barrel mounting flange is installed on the
soleplate. The soleplate with the assembled suction Lifting and Assembly
barrel is shimmed to achieve the required levelness Motors may be supplied separately from the pumps.
of no greater than 0.051 mm (0.002 in.) between any It is the responsibility of the installer to ensure that
two points taken on the top surface of the suction the motor is assembled to the pump and aligned as
barrel mounting plate, and the levelness is measured detailed in section 4.5. Discharge head column
by using a precision machinist’s level. The data is to piping and the pump assembly are supplied either
be recorded for future reference. Anchor bolt nuts separately or as fully assembled depending upon the
[373] are tightened sufficient enough to hold the pump size and weight. If the parts are shipped
suction barrel with assembled suction barrel in place. separately, it is the customer’s responsibility to install
and align the pump with driver to the satisfaction of
Grout is poured under the soleplate and allowed to Flowserve’s installation instructions.
cure per the manufacturer’s instructions before the
foundation bolts are fully torqued and the pump is Installation of pumps that are shipped
installed in the suction barrel. unassembled

Example of pump mounted on a suction barrel with a Lifting


soleplate See lifting methods in section 2.3.

Equipment and tools required for


installation of unassembled pumps

The following list covers the principal tools/items


required for installation.

a) Two (2) mobile cranes capable of hoisting and


lowering the pump and/or motor.
b) Two (2) steel clamps of suitable size.
c) Two (2) sets of chain tongs & cable sling for
attaching to the pump and motor lifting eyes.
d) Pipe clamp for lifting bowl assembly and the
column pipe. Approximately 4.5 m (15 ft) of 19
mm (3/4 in.) diameter rope may be required.
e) General purpose hand tools, pipe wrenches, end
wrenches, socket set, screwdrivers, Allen
wrenches, wire brush, scraper and fine emery
cloth.
Grouting f) Thread sealing compound designed for stainless
Grouting should provide solid contact between the steel and light machinery oil.
pump unit and foundation that prevents lateral
movement of running equipment and reduces the
Parts and accessories may be placed
chance of resonant vibrations. Care should be taken
inside shipping containers or attached to skids in
to ensure complete surface contact with grout
individual packages. Inspect all containers, crates
between the pump base, sole plate, suction can and
and skids for attached parts before discarding.
foundation. Voids in the grout cause a risk of
significantly lowering the structural natural frequency.

Foundation bolts should only be fully


torqued after the grout has been cured.

Page 24 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Installation of discharge head with product


Uncrating and cleaning of unassembled lubrication
pump
a) Clean the parts of any dirt, packing material and Pump head may be shipped with the sealing
other foreign matter. housing installed. For ease of assembly and to
b) Flush the pump inside and outside with clean prevent damage, we recommend removing the
water. Clean all machined surfaces. housing before putting the head on the pump.
c) Remove any rust spots found on the machined
surfaces with fine emery cloth.
For pumps supplied with hollow shaft drivers and a
d) Clean all threaded connections and any accessory
one-piece headshaft (headshaft couples below
equipment.
sealing housing) proceed to step (a).
Lineshaft when shipped separately For pumps supplied with a two-piece headshaft
should be left in the crate to avoid damage or loss of (headshaft couples above the sealing housing) or
straightness. solid shaft drivers, proceed to step (b) directly
skipping step (a).
Installing the bowl and column
assembly a) Attach the headshaft to the lineshaft with a
a) Sump and piping should be thoroughly cleaned coupling and tighten (left hand threads).
of all loose debris before starting installation. b) Lift discharge head over shaft and lower carefully
b) Check all bolts for tightness. into place (See section 2.3 for recommended
c) Do not lift or handle the bowl assembly by the lifting methods and safety instructions). Be sure
pump shaft. not to bend the shaft. Fasten the top column
d) When installing bowl assemblies in sizes of 152 flange and bearing retainer, if supplied to bottom
mm (6 in.) or 203 mm (8 in.), leave bowl securely of head. (Note that W heads do not have a
fastened to the wooden skid that is attached for bearing retainer at the top column flange).
shipping until the bowl assembly is raised to a c) If baseplate is not included use shims or wedges
vertical position. This will help prevent breaking between the pump and foundation to level the
the bowls or bending the shaft. pump. The shaft must be centered in the
e) If a strainer is to be used, attach it to the bowl discharge head.
assembly using fasteners as necessary.
f) Position lifting equipment so it will center over the See section 4.4.4 for coupling installation on solid
foundation opening. shaft drivers and section 4.2.1~4.2.4 for pump leveling
g) If a base plate is used, level the plate to 0.16 mm details
per m (0.002 in. per ft) and then grout and anchor
in place. Installation of discharge head with the
h) Check for axial clearance or endplay and record enclosing tube
that number for future reference (while bowls are
in a horizontal position you should be able to push Pump head may be shipped with the sealing
or pull the pump shaft indicating axial clearance). housing installed. For ease of assembly and to
i) Carefully lift the suction barrel and the bowl prevent damage, we recommend removing the
assembly with suitable straps or clamps (See housing before putting the head on the pump.
section 2.4 for lifting and safety rules).
j) Lower the bowl assembly into the well or sump. For pumps supplied with hollow shaft drivers and a
Set clamp or holding device that is attached to one-piece headshaft (headshaft couples below
bowls on a flat surface. This is to stabilize bowl sealing housing) proceed to step (a). For pumps
assembly and reduce possibility of cross threading supplied with a two-piece headshaft (headshaft
the shaft. couples above the sealing housing) or solid shaft
k) Proceed to install the column assembly (refer to drivers, proceed to step (b) directly skipping step (a).
specific column pipe drawings). a) Attach the headshaft to the lineshaft with a
coupling and tighten (left hand threads).
Installation of discharge head b) Attach the top enclosing tube to the column
enclosing tube and tighten (left hand threads).
Choose one of the following discharge head type c) Lift the discharge head over shaft and enclosing
installation procedure that is appropriate to the pump tube then lower carefully into place (See section
configuration that has been purchased 2.3 for recommended lifting methods and safety

Page 25 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

instructions). Be sure, not to bend the shaft. b) Flush the pump inside and outside with clean
Fasten the top column flange and alignment ring if water.
supplied to bottom of head. (W heads do not have c) Clean all machined surfaces. Remove any rust
an alignment ring at the top column flange). spots found on the machined surfaces with fine
d) Use shims or wedges between the pump and emery cloth.
foundation to level the pump. The shaft must be d) Clean all threaded connections and any accessory
centered in the discharge head. equipment.
See section 4.4.4 for coupling installation on solid
shaft drivers and section 4.2.1~4.2.4 for pump leveling Installing the fully assembled pump
details. If a base plate is used, level the plate to 0.16 mm per
m (0.002 in. per ft), grout and anchor in place.
Installation of pumps that are shipped
fully assembled See sections 4.2.1~4.2.4 for pump leveling details.

Lifting Position lifting equipment so it will center over the


See lifting methods in section 2.3. foundation opening.

Equipment and tools required for


installation of a fully assembled pump Sump and piping should be
a) Mobile crane capable of hoisting and lowering the thoroughly cleaned of all loose debris before starting
entire weight of the pump and motor. installation.
b) Cable slings for attaching to the pump and motor
lifting eyes. Set up installation unit so that the lifting cable will be
c) centered directly over the well or sump. Carefully lift
Ordinary hand tools: Pipe wrenches, end the bowl assembly and suction barrel with a clamp.
wrenches, socket set, screwdrivers, Allen Lower the bowl assembly into the well or sump. Set
wrenches, wire brush, scraper and fine emery the clamps or holding device that is attached to bowls
cloth. on a flat surface. This is to stabilize bowl assembly
d) Thread sealing compound designed for type of and reduce possibility of cross threading the shaft.
connection and light machinery oil.
a) When installing 152 mm (6 in.) or 203 mm (8 in.)
pump assembly, leave the pump securely
The single most common cause of pump fastened to the wooden skid (as shipped) until the
vibration is from a bent shaft. Shafting is bowl assembly is raised to a vertical position
straightened to stringent tolerances prior to shipping b) Lift the pump to a vertical position. If a strainer is
and great care must be exercised in its handling. used, attach it to the bowl assembly.
c) Position pump over sump or suction barrel. Align
Always support shafting in at least three places when the discharge of the pump with external piping
lifting or installing. then lower onto the base. Level the entire pump.
d) If a stuffing box and a hollow shaft driver are
included, attach the head shaft to the pump shaft
Parts and accessories may be placed (left hand threads).
inside shipping containers, or attached to skids in e) If a mechanical seal is included, install the seal at
individual packages. this point per the attached instructions.
Inspect all containers, crates and skids for attached If the pump includes a suction barrel (can), follow the
parts before discarding. procedure as listed below. (See lifting instructions in
section 2.3)
Lifting heavy objects is dangerous. Use of
appropriate tools and procedures is must. a) Install the suction barrel first and grout the
mounting flange and bolts directly to the
Uncrating and cleaning of a fully foundation.
assembled pump b) If soleplate is used, mount and grout the
soleplate and mount the suction barrel onto the
a) Clean the parts of all dirt, packing material and soleplate.
other foreign matter. c) Level the soleplate & the suction barrel flange as
required.

Page 26 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

d) Check to ensure suction barrel is free of debris


and other foreign material. i) Check the fit of the straight key and split thrust
e) Install the pump. rings [312A] in their respective keyseats. (Refer to
Installation of couplings on solid shaft paragraph (a) regarding fit of the straight key).
drivers. j) Install straight key into keyseat. The bottom of the
key must be above the top of circular keyseat for
If the pump purchased has a solid shaft the split thrust rings.
driver, one of the following coupling arrangements k) Lubricate driver half coupling lightly and slide it
between the driver and the pump shaft is applicable. onto driver shaft. Slide bottom of coupling above
Choose the procedure appropriate to the coupling the top of the keyseat for split thrust rings.
arrangement required. l) Install split thrust rings into circular keyseat and
slide the coupling down over them.
m) Tighten the coupling bolts as follows.
Clean threads on pump shaft and on
adjusting nut. Check for burrs and nicks. Coupling bolts tightening torques
Coupling Flange diameter Torque N·M
All burrs, nicks and rust must be removed from all size mm (in.) (in·lb)
mating parts of flanged coupling and pump before 112 & 137
1&2 121.5 (1075)
installation. Failure to remove all burrs, nicks and (4.4 & 5.4)
rust may result in misalignment causing pump to fail. 156, 188, & 213
3, 4 & 5 237.0 (2100)
(6.1, 7.4, & 8.4)
251
Installation of adjustable flanged 6 424.0 (3750)
(9.9)
coupling WA/PA. Torque values are for standard fasteners lubricated with a high
a) The key [46A] for the driver shaft keyseat should stress lubricant (such as, graphite and oil, moly-disulphite, white lead
be a snug or tight fit in the shaft keyseat, and a etc.). For stainless steel bolts, multiply listed torques by 0.80.
sliding fit in the keyseat of the driver half coupling
[42]. n) Proceed with the driver installation.
b) The key with pin [46] should be a sliding fit in
pump shaft keyseat and a snug or tight fit in pump MOTOR SHAFT
half coupling [44] keyseat.
c) Side clearance of keys in keyseats should be
checked with a feeler gauge. Clearance for (42) DRIVER COUPLING
WA/PA coupling should not exceed 0.076 mm HALF
(0.003 in.) for a snug fit or 0.127mm (0.005 in) for
a sliding fit. These are maximum allowable (46A) DRIVE KEY
clearances. Closer fits are preferred, if possible.
It may be necessary to file-dress keys to obtain (312A) SPLIT THRUST
proper fit. RING
d) Insert the key [46] with pin into pump half of (66A) ADJUSTING NUT
coupling [44] putting the pin in the hole in keyseat.
The key should not extend below coupling. (44) DRIVEN COUPLING
e) Lubricate pump coupling half and key assembly HALF
with light oil and slide it onto pump shaft [12A] with
flange up. Slide it past threads.
f) Lubricate adjusting nut [66A] with light oil and (364) CAP SCREW
thread it onto pump shaft [12A] (left hand threads)
with male register down. Thread it on until top of
(46) KEY ASSEMBLY
shaft and top of nut are even.
g) Uncrate and lift driver to allow access to drive
shaft.
(12A) TOP SHAFT
The driver must be set on supports
capable of carrying the entire weight of the driver
before proceeding to step (h). Failure of supports
could cause damage to the motor or loss of life. TYPE WA/PA COUPLING DETAIL

h) Clean and check driver shaft. Remove any burrs.

Page 27 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Installation of adjustable flanged spacer Installation of non-adjustable flanged


coupling WSA/PSA. coupling WNA/PNA.
Follow procedure from (a) thru (e) as listed in section
Follow procedure from (a) thru (l) as listed in section 4.5.4.1.
4.5.4.1.
f) Install one set of split thrust rings [312A] in to the
c) Bolt spacer [314] to the driver half coupling [42] circular keyway in pump shaft. Pull up the pump
using the short set of socket head cap screws half of the coupling [44] over the split keys.
[364]. The male register should be pointing g) Slide driver half coupling [42] onto driver shaft in
down. Tighten all cap screws evenly to the bolt the same manner as the pump half of the
torques as listed in 4.5.4.1 under item (m). coupling.
d) Proceed with the driver installation. h) Set the spacer ring [314] between the two halves
of the coupling together. Tighten all cap screws
[364] evenly to the bolt torques as listed in
MOTOR SHAFT 4.5.4.1 under item (m).
i) Proceed with the driver installation.
(42) DRIVER COUPLING
HALF MOTOR SHAFT

(46A) DRIVE KEY (42) DRIVER COUPLING


HALF
(312A) SPLIT THRUST
RING
(363) HEX NUT
(314) SPACER
(364) CAP SCREW
(46A) DRIVE KEY

(363) HEX NUT (312A) SPLIT THRUST


RING
(314) SPACER RING

(312A) SPLIT THRUST


(44) DRIVEN COUPLING RING
HALF

(44) DRIVEN COUPLING


(364) CAP SCREW HALF
(364) CAP SCREW

(46) KEY ASSEMBLY (46) KEY ASSEMBLY

(12A) TOP SHAFT


(12A) TOP SHAFT
TYPE-WNA/PNA COUPLING DETAILS

TYPE- WSA/PSA COUPLING DEATILS

Page 28 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Installation of drivers k) Check the packing slip to see if a guide bushing is


required, if so, determine if the bushing is already
Drivers will come with either hollow shaft or mounted or not and proceed accordingly. Refer to
solid shaft as specified on the order/contract. motor instruction manual.
Choose the correct installation procedure from the l) Carefully install drive clutch on driver making sure
following paragraphs. that it fits down properly.
m) Clean threads on top of head shaft and head shaft
nut. Lubricate male threads lightly. Install head
Reverse rotation with the pump shaft shaft.
connected can cause extensive damage to the pump. n) Install gib key [335] in clutch and shaft. This must
Always check rotation before connecting driver to be a sliding fit and may require filing and dressing.
pump. Do not force.
o) Thread adjusting nut down on shaft until it bears
Installation of hollow shaft driver against clutch. (Threads on 43 mm (1.68 in.) and
a) Clean driver mounting flange on discharge head larger head shaft adjusting nuts are left-handed
and check for burrs or nicks on the register and and all others are right handed). Do not thread
mounting face. Oil lightly. nut further at this time. See impeller adjusting
b) Remove driver clutch. instructions in section 5.3.
c) See (j) regarding installation of motor guide
bushing, if required. (334) LOCK SCREW HEAD SHAFT (10)
d) Lift driver and clean mounting flange, checking for HEAD SHAFT NUT (66)
burrs and nicks. DRIVER
e) Center motor over pump and rotate to align COUPLING GIB KEY(335)
mounting holes.
Electric motors - rotate junction box into desired
position.
Gear Drives - rotate input shaft into desired
position.
f) Lower carefully into place making certain that the
female register on the driver mates over the male Installation of solid shaft driver without
register on the pump. jacking screws
g) Bolt driver to discharge head.
h) Check the driver manufacturer's instruction When lowering the motor and driver
manual for special instructions including half of coupling onto pump, do not let pump half of
lubrication instructions and follow all "startup" the coupling touch the driver half of the coupling.
directions.
i) Electric motors should be checked for rotation at Before bumping motor make sure coupling halves
this time. Make certain the driver clutch has been are not touching and that the driver can rotate freely,
removed. Make electrical connections and without rotating the pump
"bump" motor (momentarily start, then stop) to
check rotation. DRIVER MUST ROTATE Driver half coupling must be in proper position so the
COUNTERCLOCK-WISE when looking down at circular key will not come out.
top end of motor. To change the direction of
rotation on a three-phase motor, interchange any a) Clean driver mounting flange on discharge head
two line leads. To change direction of rotation on and check for burrs or nicks on the register and
a two phase motor, interchange the leads of either mounting face. Oil lightly.
phase b) Center motor over pump and rotate to align
j) Some motors will be supplied with a "lower guide mounting holes.
bushing" or "steady bushing" which is installed at Electric motors: Rotate junction box into desired
the bottom of the motor to stabilize the shaft at this position.
point. Some motor manufacturers mount this Gear Drives: Rotate input shaft into desired
guide bushing before shipping while others will position.
ship the guide bushing with instructions for field c) Lower driver carefully into place making certain
mounting. that the female register on the driver mates over
the male register on the pump.
d) Bolt driver to discharge head.

Page 29 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

e) Check driver manufacturer's instructions for two line leads. To change direction of rotation on
special instructions including lubrication a two-phase motor, interchange the leads of
instructions and follow all "startup" instructions. either phase.
f) Electric drivers should be checked for rotation at f) See impeller adjustment instructions (section 5.3
this time. Make electrical connections "bump" before bolting the pump and driver half of the
motor (momentarily start, then stop) to check coupling together.
rotation. DRIVER MUST ROTATE
COUNTERCLOCKWISE when looking down at Initial Alignment
top end of motor. To change the direction of
rotation on a three-phase motor, interchange any Thermal expansion
two line leads. To change direction of rotation on
a two-phase motor, interchange the leads of either
phase. The pump and motor will normally
g) See impeller adjustment instructions (section 5.3) have to be aligned at ambient temperature and
before bolting the pump and driver half of the should be corrected to allow for thermal expansion at
coupling together. operating temperature. In pump installations
involving high liquid temperatures greater than 300°F,
Installation of solid shaft driver with the unit should be run at the actual operating
jacking screws temperature, shut down and the alignment checked
immediately.
a) Clean driver mounting flange on discharge head
and check for burrs or nicks on the register and Preparation before alignment
mounting face. Oil lightly. To ensure proper alignment the following items are
b) Center motor over pump and rotate to align very important.
mounting holes.
Electric motors: Rotate junction box into a) All machined mating surfaces (such as the
desired position. mating flanges of pump and motor) must be
Gear Drives: Rotate input shaft into desired clean and free of burrs and nicks.
position. b) Exterior strain must not be transmitted to the
c) Lower driver carefully into place. Mount the dial pump. The most common cause of trouble is
indicator base on the O.D. of the motor half forcing the piping to mate with the pump. It is
coupling. Set the indicator on the pump shaft, recommended that flexible connectors be installed
position the dial to zero being careful that the in the piping adjacent to the pump.
indicator is in direct line with one of the c) All threads should be checked for damage and
jackscrews. Record this reading then rotate the repaired if necessary. Lubricate all threaded
motor shaft and indicator 180 degrees. Record connections with a suitable thread lubricant (an
this reading being careful to note plus or minus anti-galling compound).
values. Take the difference of the two readings
and using the jackscrews move the motor one- Alignment methods
half of the difference. Repeat this step until the
Ensure pump and driver are isolated
T.I.R. reading is a maximum of 0.051mm
electrically and the half couplings are disconnected.
(0.002in.). Then repeat this step for the set of
jack screws located 90 degrees to the first set.
Once all readings are within 0.051mm (0.002in.),
The alignment MUST be checked.
tighten motor bolts and check for any movement
Although the pump will have been aligned at the
in readings.
factory it is most likely that this alignment will have
d) Check driver manufacturer's instructions for
been disturbed during transportation or handling.
special instructions including lubrication
If necessary, align the motor to the pump, not the
instructions and follow all "startup" instructions.
pump to the motor.
e) Electric drivers should be checked for rotation at
this time. Make electrical connections and
"bump" motor (momentarily start, then stop) to The motor assembly may also have to be
check rotation. DRIVER MUST ROTATE adjusted in the horizontal direction to line up the
COUNTER-CLOCKWISE when looking down at driver and shaft centers. Alignment screws are
top end of motor. To change the direction of provided to lock the motor assembly in its final
rotation on a three-phase motor, interchange any aligned position.

Page 30 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

See section 5.3.2.1 for final coupling alignment for Parallel


solid shaft.

Before bumping motor, make sure that the


coupling halves are not touching and that the driver
can rotate freely without rotating the pump. Driver Angular
half coupling must be in proper position so the
circular key will not come out.

Angular and parallel misalignment


a) Pumps with thick flanged non-spacer couplings
can be aligned by using a straight-edge across
Check the direction of pump rotation the outside diameters of the coupling hubs and
before the coupling is fully connected. The power measuring the gap between the machined faces
supply to the driver to be connected only after the using feeler gauges, measuring wedge or
final alignment is complete. calipers.

b) When the electric motor has sleeve bearings, it is


necessary to ensure that the motor is aligned to
a)
run on its magnetic centerline.

Axial offset
Angular offset
&Refer to the motor User Instructions for details.
b)
If the motor does not run in its
magnetic center the resultant additional axial force
may overload the pump thrust bearing.
c)
If the pump is handling hot liquid, the alignment must
be rechecked in warm condition of the unit. The
Parallel offset alignment of the unit shall be checked again after 200
service hours.
a) Angular Offset: The median lines of shaft Piping
intersect halfway between the ends of the two
shafts.
b) Axial Offset: Another offset is the displacement Protective covers are fitted to the pipe
of one or both of the shafts. A typical example is connections to prevent foreign particles or objects
thermal expansion. entering the pump during transportation and
c) Parallel Offset: The median lines run parallel. installation. Ensure that these covers are removed
The maximum allowable parallel offset depends from the pump before connecting pipes.
on the size of coupling and is indicated in the
instruction manual of manufacturer of coupling. Pipe work velocities
In order to minimize friction losses and hydraulic
For couplings with narrow flanges use a dial indicator noise in the pipe work it is good practice to choose
as shown in the detail to check both parallel and pipe work that is one or two sizes larger than the
angular alignment. pump suction and discharge.

Typically, main pipe velocities should not exceed 2


m/s (6 ft/sec) on the suction and 3 m/s (9 ft/sec) on
discharge.

Take into account the available NPSH that must be


higher than the required NPSH of the pump.

Page 31 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

b) Never draw piping into place by applying force to


Never use the pump as a support for pump flange connections.
piping. c) Do not mount expansion joints so that their force,
due to internal pressure, acts on the pump
Maximum forces and moments allowed flange.
on VTP pump flanges (See table
4.6.2.1)
Maximum forces and moments allowed on the pump Ensure piping and fittings are flushed
flanges vary with the pump size and type. To before use.
minimize these forces and moments that may, if
excessive, cause misalignment, hot bearings, worn Ensure that the piping arrangement has been
couplings, vibration and possible failure of the pump provided to flush the pump before removal in cases
casing. The following points should be strictly of hazardous liquid pumps.
followed.

a) Prevent excessive external pipe load.

DISCHARGE

SUCTION

Page 32 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Typical forces and moments allowed on VTP pump flanges for Standard Applications

Discharge Head Size mm (in.)


Head Forces &
Type Moments 100 150 200 255 305 355 400 460 508 610 760 915
(4) (6) (8) (10) (12) (14) (16) (18) (20) (24) (30) (36)
0.53 0.80 1.13 1.47 1.67 1.78
Fx (120) (180) (255) (330) (375) (400)

0.67 1.00 1.47 1.83 2.00 2.23


Fy (150) (225) (330) (410) (450) (500)

0.45 0.67 0.94 1.22 1.34 1.45


Fz (100) (150) (210) (275) (300) (325)
W
0.50 0.75 1.06 1.37 1.52 1.59
Mx (370) (550) (780) (1015) (1125) (1175)

0.26 0.39 0.53 0.67 0.74 0.78


My (190) (285) (390) (495) (550) (575)

0.37 0.57 0.77 1.04 1.15 1.18


Mz (275) (425) (570) (770) (850) (875)

1.07 1.60 2.27 2.94 3.34 3.56 4.23 4.90 5.34 6.01 7.12 8.46
Fx (240) (360) (510) (660) (750) (800) (950) (1100) (1200) (1350) (1600) (1900)

1.34 2.00 2.94 3.65 4.00 4.45 5.12 5.79 6.23 7.12 8.46 9.79
Fy (300) (450) (660) (820) (900) (1000) (1150) (1300) (1400) (1600) (1900) (2200)

0.89 1.36 1.87 2.45 2.67 2.89 3.34 4.00 4.45 4.90 5.56 6.23
HF Fz (200) (300) (420) (550) (600) (650) (750) (900) (1000) (1100) (1250) (1400)
&
1.00 1.49 2.11 2.75 3.05 3.18 3.66 4.06 4.47 5.42 6.50 7.60
LF Mx (740) (1100) (1560) (2030) (2250) (2350) (2700) (3000) (3300) (4000) (4800) (5600)

0.51 0.77 1.06 1.34 1.49 1.56 1.83 2.03 2.51 2.71 3.25 3.80
My (380) (570) (780) (990) (1100) (1150) (1350) (1500) (1850) (2000) (2400) (2800)

0.75 1.15 1.54 2.09 2.30 2.37 2.71 3.05 3.39 4.07 4.88 5.70
Mz (550) (850) (1140) (1540) (1700) (1750) (2000) (2250) (2500) (3000) (3600) (4200)

1.07 1.60 2.27 2.94 3.34 3.56 4.23 4.90 5.34 6.00 7.12
Fx (240) (360) (510) (660) (750) (800) (950) (1100) (1200) (1350) (1600)

1.34 2.00 2.94 3.65 4.00 4.45 5.12 5.79 6.23 7.12 8.46
Fy (300) (450) (660) (820) (900) (1000) (1150) (1300) (1400) (1600) (1900)

0.89 1.34 1.87 2.45 2.67 2.89 3.34 4.00 4.45 4.90 5.56
Fz (200) (300) (420) (550) (600) (650) (750) (900) (1000) (1100) (1250)
(1)
TF
1.00 1.49 2.11 2.75 3.05 3.18 3.66 4.07 4.47 5.42 6.50
Mx (740) (1100) (1560) (2030) (2250) (2350) (2700) (3000) (3300) (4000) (4800)

0.51 0.77 1.06 1.34 1.49 1.56 1.83 2.03 2.51 2.71 3.25
My (380) (570) (780) (990) (1100) (1150) (1350) (1500) (1850) (2000) (2400)

0.75 1.15 1.54 2.09 2.30 2.37 2.71 3.05 3.39 4.07 4.88
Mz (550) (850) (1140) (1540) (1700) (1750) (2000) (2250) (2500) (3000) (3600)

Fx
CONTACT FLOWSERVE CUSTOMER SERVICE
Fy
Fz
UF
Mx
CONTACT FLOWSERVE CUSTOMER SERVICE
My
Mz
Units: Force (F) in kN (lbf); Moments (M) in kN-m (lbf-ft)
1. Forces and moments used for the TF head should correspond to the specific flange size. I.e. the discharge flange loads should be
based on the discharge flange size and the suction flange loads should be based on the suction flange size.

Order specific loads are located on the General Arrangement drawing for the order. Loads shown above
are maximum allowable for a typical application.

Page 33 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Auxiliary piping any connected devices. If in doubt, contact


Flowserve for advice.
Drains
Normal pump leaks and gland leakage are to be The motor must be wired up in
drained through a separate piping arrangement or accordance with the motor manufacturer's
back into the suction/sump. instructions (normally supplied within the terminal
box) including any temperature, earth leakage,
Pumps fitted with gland packing current and other protective devices as appropriate.
The pumped liquid is allowed to flow through the The identification nameplate should be checked to
gland packing at discharge pressure and drained out ensure the power supply is appropriate.
of the pump or re-circulated back into the suction. A
separate flush supply may be required in some A device to provide emergency stopping must
cases. The piping plans and flush supply are to be be fitted.
selected based on the application and operating If not supplied pre-wired to the pump unit, the
parameters. controller/starter electrical details will also be
supplied within the controller/starter.
In some special cases where the discharge pressure
exceeds 6.5 bar (100 psi) a special flushing plan is For electrical details on pump sets with controllers
recommended. see the separate wiring diagram.

Pumps fitted with mechanical seals See section 5.4, Direction of rotation
Auxiliary piping to circulate the flushing liquid back before connecting the motor to the electrical supply.
into the suction is required. In case of external clean
Final Shaft Alignment Check
source requirements for pump applications such as
After connecting piping to the pump, rotate the shaft
high temperature service, contaminated fluids,
several times by hand to ensure there is no binding
oxidizing fluids, a special piping plan to carry the
and all parts are free. Recheck the coupling
clean liquid into the seal chamber with adequate
alignment, as previously described, to ensure no pipe
pressure is required and several piping plans are
strain. If pipe strain exists, correct piping.
available to suit the specific pump application.
Protection Systems
See section 5.4 for Direction of
rotation before connecting motor to the power supply. The following protection systems are
recommended particularly if the pump is installed in a
Final checks potentially explosive area or is handling a hazardous
After connecting the piping to the pump, rotate the liquid. If in doubt, consult Flowserve.
shaft several times by hand to ensure no pipe strain.
If pipe strain exists, correct piping. If there is any possibility of the system allowing the
pump to run against a closed valve or below
Electrical Connections minimum continuous safe flow a protection device
should be installed to ensure the temperature of the
Electrical connections must be made
liquid does not rise to an unsafe level.
by a qualified Electrician in accordance with relevant
local national and international regulations.
If there are any circumstances in which the system
It is important to be aware of the EUROPEAN can allow the pump to run dry, or start up empty, a
DIRECTIVE on potentially explosive areas where power monitor should be fitted to stop the pump or
compliance with IEC60079-14 is an additional prevent it from being started. This is particularly
requirement for making electrical connections. relevant if the pump is handling a flammable liquid.

It is important to be aware of the EUROPEAN If leakage of product from the pump or its associated
DIRECTIVE on electromagnetic compatibility when sealing system can cause a hazard it is
wiring up and installing equipment on site. Attention recommended that an appropriate leakage detection
must be paid to ensure that the techniques used system is installed.
during wiring/installation do not increase To prevent excessive surface temperatures at the
electromagnetic emissions or decrease the bearings, it is recommended that temperature and/or
electromagnetic immunity of the equipment, wiring or vibration monitoring is done on a regular basis.

Page 34 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

5 COMMISSIONING, STARTUP,
Pump Lubricants
OPERATION AND SHUTDOWN Other than the stuffing box lubrication, mechanical
seal and/or lineshaft lubrication, the pump will not
These operations must be carried out require further periodic lubrication. On water pumps,
by fully qualified personnel. Turn off power supply for the suction bearing on the bowl assembly should be
safety while pump commissioning is in progress. repacked when required. Pumps that pump
hydrocarbons or have carbon, rubber, epoxy or
Pre-commissioning Procedure Teflon suction bearings do not have the suction
bearings packed. If the pump will be started after a
The gland is to be filled with grease, and flush supply longer storage period, the bearings should be first
to be in place. Flush piping is to be checked for flushed and cleaned by using a suitable cleaning
leaks. Mechanical seals are to be checked for leaks, agent. It is not necessary to remove the oil sprayed
flush flow, and pressure. for short or long-term storage as this will mix up
thoroughly with the lubrication oil.
a) Pumps with the enclosing tubes and oil-lubed
bearings must be filled with the proper lubricant to
avoid running dry and to guarantee acceptable Re-checking the motor lubrication should
performance of the pump. A separate oil tank is be in accordance with the motor manufacturer’s user
attached to the pump (see detail in section 5.2.2). instructions supplied separately with the pump.
b) For can pumps check all vent connections for
complete filling of the pump. The venting Open lineshaft lubrication
procedure can take from 10 minutes up to 2 hours, Open lineshaft bearings are lubricated by the pumping
depending on the kind of fluid. fluid; however, when the static water level is greater
c) Check the direction of rotation of the pump (pump than 15 m (50 ft) below the discharge head, the
rotor uncoupled). Rotation should be counter lineshaft bearings will require pre or post-lubrication.
clockwise when viewed from the driver end. Care is to be taken to ensure that the gland or seal is
d) The pump rotor and the shaft seal must be in supplied with the required flush flow.
correct axial position.
e) Check the readiness of all auxiliary systems (seal All open lineshaft pumps where the static water level is
system, lubrication system etc.,) for startup. more than 15 m (50 ft) below the discharge head
f) All pipe work, including the internal and the should be adequately pre-lubricated before starting the
auxiliary pipe work, must be connected correctly pump.
and must be absolutely tight. Check the tightness
of all connections of the auxiliary pipe work. The Pre-lubrication duration
suction valve must be in the open position. The Allow clean flush water to flow down the shaft for
discharge valve shall be in the closed or partially sufficient time to completely wet the bearings prior to
open position as required. operation. When provided, the fittings for pre-lube
g) Turn the pump by hand, if required with the help of are located at the discharge head.
a lever, to check the free rotation of the rotor. The
rotor must turn uniformly and noiselessly. Some Typical pre-lube pipe connection
resistance may be felt due to the friction in the (examples (a) thru (d))
bearings and seals. In general, all W type cast discharge heads are
h) Check the readiness of the driver for startup. Refer provided with a standard size pipe fitting for pre-lube
to the manual for the driver to be sure that all connection. Fabricated discharge heads are not
precautions are in place to energize the motor. fitted with a special piping arrangement to allow pre-
lube liquid flow onto the shaft. This is an optional
feature for the fabricated discharge head.

It is the responsibility of the user to install a


reliable pre-lube system to achieve the pump pre-
lubrication. Flowserve will not supply these types of
systems or accessories with the pump.

Page 35 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Examples of typical pre-lube methods used in the industry are as follows.

Example (a)

TANK

PIPING MUST BE
KEPT TO LENGTH AS
MINIMUM
POSSIBLE
GATE VALVE SHOULD
WITHSTAND
MAX. DISCHARGE
PRESSURE
1" MIN PIPE
LINE

PRESSURE
GAGE

Pre-lubrication recommended tank volume for pumps started at rated RPM’s for all cases of pre-lubrication
methods suggested in this section
Depth to water level Pre-Lubrication tank size
(at the time of starting the m3 (US gal)
pump) m (ft)
More than Up to
0 9 (30) 0
9 (30) 30 (100) 0.19 (50)
30 (100) 60 (200) 0.38 (100)
60 (200) 150 (500) 0.75 (200)

Example (b)

VENT LUBRICATION
TANK

LEVEL
MAX GAUGE
LEVEL

STARTUP
LEVEL

GATE VALVE SHOULD WITHSTAND


25 mm (1in.) MIN DRAIN
MAX. DISCHARGE PRESSURE
PIPE LINE PLUG
PIPING MUST BE KEPT TO
MINIMUM LENGTH AS POSSIBLE

Page 36 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Example (c)

VENT LEVEL
SWITCH

MAX
LEVEL
LUBRICATION
TANK

STARTUP
LEVEL

SOLENOID GATE VALVE SHOULD


25mm (1in.) PIPE DRAIN WITHSTAND MAX. DISCHARGE PRESSURE
LINE PLUG
PIPING MUST BE KEPT TO
MINIMUM LENGTH AS POSSIBLE
Example (d)
FLOAT
LEVEL

VENT LEVEL
GAUGE
TIME DELAY RELAY

MAX
LEVEL
LUBRICATION
TANK

STARTUP
LEVEL

SOLENOID GATE VALVE SHOULD


25mm (1 in.) MIN DRAIN WITHSTAND MAX. DISCHARGE PRESSURE
PIPE LINE PLUG
PIPING MUST BE KEPT TO
MINIMUM LENGTH AS POSSIBLE

Page 37 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Enclosed shaft lubrication


VTPs with the enclosed shafting are lubricated by a The injected lubricant flow is never stopped for short
dedicated oil supply system or injection lubricated by ‘off’ periods. Adequate care should be taken to
extraneous liquid; usually clean water to meet the make sure that the flow is available and consistent
application requirements. for subsequent startups and operation. Injection
pressure to be adjusted as recommended before the
Oil lubricated pumps startup.
The lubricating oil must be available and should be
allowed to run into the enclosing tube in sufficient Enclosed shaft lubricants
quantity to thoroughly lubricate all lineshaft bearings. The following oils are recommended for enclosed
The gravity flow system is the most commonly lineshaft bearing lubrication under normal operating
utilized system for oil. conditions. See tables 5.2.3.1 and 5.2.3.2.

The oil reservoir (example shown in detail below)


must be kept filled with a good quality light turbine oil It is recommended that detergent type
(about 30 cSt) at the operating temperature and oils not be used.
adjusted to feed a minimum of 3 drops per minute
per 30 m (100 ft) of column length, at never less than Non-food/food grade lubricant oils
5 drops per minute total.
Equivalent turbine oil (food or non-food grades as
required) with the matching properties has to be
(77) LUBRICANT TANK selected. Oils with a viscosity range of 30 cSt
(79) TANK BRACKET
(mm2/sec) to 37 cSt (mm2/sec) at 40 °C (100 °F) with a
minimum viscosity index of 90 are recommended.
(341) SHUT OFF VALVE
The pour point of the oil must be in accordance with
(342) FLOW REGULATION the lowest expected temperature of the bearing
VALVE housing during a stop of the pump.
(344) LUBRICANT SUPPLY
Oil level
Pre-lubrication of oil lubricated pumps The correct oil level is in the middle of the oil sight
As a general rule, the oil must be allowed to flow by glass and shall be checked when the pump is not in
gravity at least 45 minutes before the pump is started operation. Periodically check if the lubricating oil is
for the first time or in case the pump was turned off mixed with any condensed water. Careful opening of
for a longer duration. Adequate care should be taken the oil drain during a stop of the pump will show any
to make sure that the flow is available and is water.
consistent for subsequent startups.
After the initial start the level will decrease
Injection lubricated pumps due to circulation of the oil through the bearings.
Enclosed lineshaft bearings are lubricated by
extraneous liquid (usually clean water), which is fed If the oil level is higher than specified, it could
to the tension nut either by gravity flow, or by a result in higher bearing temperatures resulting in
pressure injection system. poor lubrication.

Injection systems are designed for each Impeller Adjustment


installation. Injection pressure and quantity of liquid Proper impeller adjustment positions the impeller
will vary. Normally 0.45-0.90 m3/h (2-4 gpm) at 0.7- inside the bowl assembly for maximum performance.
1.4 bar (10-20 psi) over maximum pump discharge The impellers must be raised slightly to prevent them
pressure of clean liquid is required. from dragging on the bowls, but not raised too high so
as to adversely affect hydraulic performance.
Pre-lubrication of injection lubricated
pumps The impeller must be down against the bowl seat
As a general rule, the liquid flow is to be started at when starting impeller adjustment. When pumps are
least 15~20 minutes before the pump is started for subjected to suction pressure, the pressure acting
the first time or in the event of pump not being in use against the shaft tends to raise it. Make sure the shaft
for longer duration. is down when starting to adjust the impellers.

Page 38 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

g) Using the cap screw provided, bolt the headshaft


If, after making the impeller adjustment the pump does nut [66] down & lock using lock screw [334] to the
not deliver its rated capacity, the impellers can be motor coupling. See the details of head shaft and
lowered one step at a time until the lowest possible lock screw arrangement under item (h) below.
adjustment is achieved without the impellers dragging.
On the other hand, if the impellers appear to be
dragging after the initial adjustment, the unit should be Always lock headshaft nut by
stopped and the impellers raised one step. Dragging tightening the lock screw [334] before starting driver.
impellers will increase the load significantly and can Failure to do so could result in damage to the pump
usually be heard and felt as increased vibration. A and driver.
sharp rise in motor amperage will occur when
impellers are dragging. h) If a mechanical seal is used, adjust the
mechanical seal at this time.
Impeller adjustment for a hollow shaft
driver Impeller clearance settings
Impeller adjustment when using hollow shaft drivers is Flowserve typical impeller settings based on the
as follows. The driver canopy will have to be removed pump sizes.
before beginning.
a) Install headshaft [10] if not already in place. If the pump size Setting for Setting for semi-
is enclosed open impellers
b) Install driver clutch in accordance with the driver impellers
instruction manual and bolt into place. Size 6 thru size 3~4 mm 0.25 mm to 0.38 mm
c) Check shaft position. Lower shaft until there is a 12 (0.13~0.15 in.) (0.010 in. to 0.015 in.)
definite feel of metal contacting metal. This Size 14 and 6~7 mm 0.63 mm to 0.76 mm
indicates the impellers are "on bottom" and in the above. (0.25~0.27 in.) (0.025 in. to 0.030 in.)
correct starting position for impeller adjustment.
d) Thread headshaft nut [66] down (right hand
threads) except 43 mm (1.7 in.) and larger sizes Shaft elongation varies for each model
that are having left hand threads, until impellers depending upon the size, shaft length, shaft
are just raised off their seat and the shaft will diameter, impeller weight, number of stages. Also,
rotate freely. shafts elongate due to the hydraulic thrust of the
e) Check a separate document that is supplied with pump, and the impeller lift setting may compensate
the pump that provides recommended impeller for this elongation.
setting and running clearance information.
See the pump nameplate, affixed to the discharge
Detail showing head shaft and lock screw head or bowl assembly, for exact impeller setting for
arrangement the specific pump application.

Example of typical pump nameplate.


(334) LOCK SCREW HEAD SHAFT (10)
HEAD SHAFT NUT (66)
DRIVER
COUPLING GIB KEY(335)

If at any time during the life of this pump the


pumping conditions or total pump length changes,
contact the factory for recalculation of the impeller
setting.

f) Tighten the adjusting nut to match impeller setting


recommended by Flowserve. See table 5.3.1.1 &
5.3.1.2.

Page 39 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Head shaft nut adjustment

Head Threads Lateral adjustment


Shaft size per every mm (in.)
mm 25 mm One complete Each face of
(in.) (1 in.) turn of nut will nut
length of result in shaft
the shaft movement of DIAL
INDICATOR #2
1.81 0.30
25 (1.0) 14 DIAL
(0.070) (0.012)
INDICATOR #1
32 (1.25)
2.11 0.35 IF NEEDED
38 (1.50) 12
(0.080) (0.014) INSERT
43 (1.69)
PACKING
43 (1.69) PIECES/WEDGES
50 (1.94) 2.54 0.40 ALL AROUND
10 MECHANICAL
55 (2.19) (0.100) (0.016) TO CENTER
SEAL
62 (2.44) THE SHAFT

68 (2.69) 3.17 0.53


8
75 (2.94) (0.120) (0.020)

Impeller adjustment for a solid shaft · Set the shaft in the center of the maximum
driver and minimum indicator readings both
Impeller adjustment when using solid shaft drivers is directions. If the shaft will not stay in this
accomplished in the adjustable flanged coupling position, use small wooden wedges between
located below the driver. the shaft and seal bolts to hold the shaft.
The indicators can now be removed
Adjusting adjustable flanged coupling
· Alternate method for pump with packing:
a) Assemble coupling on pump shaft and driver
Using an inside micrometer, measure the
shaft (if not installed earlier).
space between the shaft and the packing box
b) Check motor direction of rotation.
bore. Do this both parallel and perpendicular
c) Check and write down Flowserve recommended
to the discharge nozzle
impeller setting for final adjustment.
d) Pump to motor alignment and final coupling
Using the wedges center the shaft so the
· Mount two magnetic indicator bases on the measurements taken at 180 degrees to each other are
discharge head at 90 degrees to each other within 0.10 mm (0.004 in.) of being equal
· Set the indicator tips on the shaft just above (For pumps using jackscrews for motor go to
the seal and at 90 degrees to each other. step f).
(Usually parallel and perpendicular to the
discharge nozzle) push the shaft (parallel to
discharge) back and forth (without bending
shaft)
· Note and record the minimum and maximum
indicator readings. Do the same procedure
at 90 degrees to the discharge nozzle.

Page 40 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Then repeat this step for the set of jackscrews


e) Mount the magnetic base on the drive half located 90 degrees to the first set. Once all
coupling (a band clamp may be necessary to hold readings are within 0.05 mm (0.002 in.) tighten
base due to limited space). Position the tip of the motor bolts and check for any movement in
indicator on the pump shaft just above the seal. readings.
Slowly rotate the driver shaft.
g) Set the impeller setting gap between the
SECURE WITH TWO BOLTS adjusting nut and the driver portion of the
MOTOR HALF
COUPLING
coupling. See impeller setting data supplied
along with the pump. If this information is not
RIGID BRACKET
found, contact Flowserve. Align the match marks
on the pump half coupling with the driver half
DIAL INDICATOR
coupling. On pumps with enclosed impellers the
match marks can be lined up by increasing the
impeller gap until the marks are in line with the
CENTER SHAFT IN STUFFING driver half coupling marks.
STUFFING BOX BOX USING FOUR WOOD OR
EXTENSION METAL WEDGES On pumps with semi-open impellers,
the match marks probably will not be in line when
the gap is set. DO NOT try to align the marking
Note and record the T.I.R. reading. If this reading on the nut with the other markings.
is more than 0.25 mm (0.010 in.) for WA and WSA For pumps with enclosed impellers go to step (h).
couplings or 0.15 mm (0.006 in.) for PA and PSA
couplings, unbolt the drive and reposition the h) Using 2 bolts of the coupling, at 180 degrees to
driver in the direction required to reduce the T.I.R. each other, slowly raise pump half coupling until
to within the allowable limits. impellers are just lifted off the seat (This can be
gauged by trying to turn shaft by hand. At the
point the impellers are lifted the pump will turn).
If a register fit is provided between the Be sure to lift both sides evenly.
driver and discharge head for facilitating the i) Measure the resultant gap between the motor half
approximate position of the driver, the register fit coupling and the adjusting nut.
between the driver and discharge head is not to j) Find the difference between the original gap and
be considered self-aligning as this fit will allow for the new gap. Add this difference to the original
a few thousandths of an inch of movement gap and reset the adjusting nut.
between the driver and discharge head. The k) Bolt the coupling together and tighten bolts by
alignment process must be followed to insure that tightening opposite sides.
the T.I.R. requirements are met. If sufficient l) Remove wooden wedges, if used. Mount
movement is not available for alignment, the male magnetic base on pump and set the tip of indicator
register can be filed to obtain required T.I.R. on the shaft just above the seal. Slowly rotate the
readings (Go to step g). shaft and note the T.I.R. reading.

f) On pumps using jackscrews for motor alignment, Unless otherwise specified, the allowable T.I.R.
mount the dial indicator base on the O.D. of the readings are:
motor half coupling. Set the indicator on the shaft,
position the dial to zero being careful that the · WA and WSA couplings 0.10 mm (0.004 in.)
indicator is in direct line with one of the · PA and PSA couplings 0.05 mm (0.002 in.)
jackscrews. Record this reading then rotate the
motor shaft and indicator 180 degrees. If the reading is larger than the allowable values
specified above, unbolt the pump and rotate the driver
Record this reading being careful to note plus or portion of the coupling to different hole and repeat
minus values. Take the difference of the two steps (h) and (i) until acceptable readings are
readings and using the jackscrews move the obtained.
motor one half of the difference. Repeat this step
until the T.I.R. reading is a maximum of 0.05 mm m) If a mechanical seal is used, adjust the
(0.002 in.). mechanical seal at this time.

Page 41 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Direction of Rotation Pump submergence


Minimum submergence is required to prevent vortex
Ensure the pump is given the same formation.
rotation as specified or as marked on the
pump/driver. Please contact Flowserve Bowl dia
Nom.
representative, if you have any questions before the
startup.

To avoid dry running, the pump must either be filled


with liquid or have the flexible coupling disconnected
before the driver is switched on.

If maintenance work has been carried First


out to the site's electricity supply, the direction of stage imp.
rotation should be re-checked as above in case the eye location.
Min. Liquid Lvl.
supply phasing has been altered.
Guarding
Guarding is supplied fitted to the pump set.
Fasteners for guards must remain captive in the guard
to comply with the Machinery Directive 2006/42/EC.
When releasing guards, the fasteners must be
unscrewed in an appropriate way to ensure that the Min.distance
fasteners remain captive. Whenever guarding is from the sump floor.
removed or disturbed ensure that all the protective
guards are securely refitted prior to start-up The submergence varies in general from 2 to 3 times
the nominal bowl diameter and is always specific to
Priming and Auxiliary Supplies each pump model. The submergence needed for
adequate NPSH to the first stage impeller may be
Ensure electrical, hydraulic, different from the general rule mentioned earlier.
pneumatic, sealant and lubrication systems (as Location of the first stage impeller eye is to be taken
applicable) are connected and operational. into account for minimum priming submergence. It is
also equally important to take note of the minimum
distance to be maintained to the suction bell from the
Ensure the inlet pipe and pump sump floor (with or without strainer). Therefore, refer
casing are completely full of liquid before starting to the Flowserve supplied general assembly drawing
continuous duty operation. on minimum submergence or contact Flowserve
before the pump is started.
Starting the Pump
Pre-starting checks

Before starting the pump, the following checks should


be made.
a) Rotate the pump shaft by hand to make sure the
pump rotates freely and the impellers are
correctly positioned.
b) Ensure that the electric motor has been properly
lubricated in accordance with the instructions
furnished with the driver.
c) Ensure the electric motor has been checked for
proper rotation. The pump must be disconnected
from the driver at the coupling before checking.

Page 42 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

The electric motor must rotate counter-clockwise Typical safety guards


when looking down on the top of the driver.
d) Check all connections to the driver and control.
Do not overfill the grease cavity. Over greasing
can lead to overheating and premature failure of
the thrust bearing.
e) Check that all piping connections are tight.
f) Check all foundation bolts for tightness.
g) Check all bolting connections for tightness
(coupling bolts, mechanical seal gland bolts,
driver bolts etc.).
h) Make sure the mechanical seal is properly GUARDS
adjusted and locked into place. Ensure that all INSTALLED
seal spacers are in the running position prior to
operation.
i) All guards must be secured in position prior to
pump startup to prevent possible contact with
rotating parts.
To ensure proper alignment three items are very
important during installation and they are:
· All machined mating surfaces (such as the
mating faces of the pump and motor) must be
clean and free from burrs and nicks.
These surfaces should be cleaned thoroughly
with a scraper, wire brush and emery cloth if
necessary and all nicks or burrs removed with a
fine file After initial startup, pre-lubrication of
· Exterior strain must not be transmitted to the the mechanical seal will usually not be required as
pump. The most common cause of trouble in this enough liquid will remain in the seal chamber for
respect is forcing the piping to mate with the subsequent startup lubrication.
pump. It is recommended that flexible
connectors be installed in the piping adjacent to
the pump. A screen guard is furnished with all pumps
· All threads should be checked for damage and having a two-piece headshaft or an adjustable
repaired if necessary. If filing is necessary, flanged coupling. This screen must be secured in
remove the part from the pump if possible, or place prior to pump startup to prevent possible
arrange to catch all the filings so they do not fall contact with rotating parts. Typical arrangement is
onto other parts of the pump. Clean all threads shown in section 5.7.1.1.
with a wire brush and approved cleaning solvent,
ends of shafts must be cleaned and any burrs Stuffing box adjustment
removed since alignment depends on the shaft On the initial starting it is very important that the
ends butting squarely. Lubricate all threaded packing not be tightened excessively. New packing
connections with a suitable approved thread must be run in properly to prevent damage to the shaft
lubricant (an approved anti-galling compound and shortening of the packing life.
should be used on stainless mating threads)
j) On pumps equipped with mechanical seals, clean The stuffing box must be allowed to leak for proper
fluid should be put into the seal chamber. With operation. The proper amount of leakage can be
pumps under suction pressure, this can be determined by checking the temperature of the
accomplished by bleeding all air and vapor out of leakage, this should be cool or just lukewarm - NOT
the seal chamber and allowing the fluid to enter. HOT - usually 40 to 60 drops per minute will be
With pumps not under suction pressure, the seal adequate.
chamber should be flushed liberally with clean
fluid to provide initial lubrication. Make sure the
mechanical seal is properly adjusted and locked
into place. Insure that all seal spacers are
removed prior to operation.

Page 43 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Initial Starting
When adjusting the packing gland, bring both nuts
down evenly and in small steps until the leakage is Ensure flushing and/or cooling/
reduced as required. The nuts should only be heating liquid supplies are turned ON before
tightened about one half turn at a time at 20 to 30 starting the pump.
minute intervals to allow the packing to "run-in".
Under proper operation, a packing set will last a long a) If the discharge line has a valve in it, partially
time. Occasionally a new ring of packing will need to open the discharge valve closest to the pump.
be added to keep the box full. The discharge valve is intended to add sufficient
system resistance to the pump. Failure to
After adding two or three rings of packing, or when maintain pump flow rates within the limits of the
proper adjustment cannot be achieved, the stuffing pump and motor could result in severe damage.
box should be cleaned completely of all old packing b) OPEN all inlet valves.
and re-packed. c) Prime the pump & check lubrication system in
operation (check the liquid level).
Open shaft lubrication before startup
Open lineshaft bearings are lubricated by the d) Ensure all vent connections are closed
pumped fluid, and on short-coupled units defined as before starting.
less than 15 m (50 ft) long, pre- or post- lubrication is e) Check the motor connections.
usually not required. All open lineshaft pumps where f) Start pre-lubrication liquid flow on pump if
the static water level is more than 15 m (50 ft) below required.
the discharge head should be adequately pre- g) Start the pump and observe the operation. If
lubricated before startup. Refer to section 5.2. there is any difficulty, excess noise or vibration,
These units should have a non-reverse ratchet on the stop the pump immediately and refer to the
driver to prevent backspin when turning off pump. If Trouble Shooting Chart (section 7.0) to
there is no NRR, post-lubrication is also necessary. determine the probable cause.

Enclosed shaft lubrication before start


Do not run the pump with the outlet
up
valve closed for a period longer than 30 seconds.
Enclosed lineshaft bearings are lubricated by an
extraneous liquid, usually oil or clean water. h) Open vent connections and ensure that the unit
is vented of all trapped vapor before closing the
The oil reservoir must be kept filled with a good vents.
quality of light turbine oil (about 30 cSt (mm2/sec) at
operating temperature) and adjusted to feed 3
Observe extreme
drops/minute for every 30 m (100 ft) of column.
caution when venting and or draining hazardous
liquids. Wear protective clothing in the presence of
Injection systems are designed for each installation.
caustic, corrosive, volatile, flammable or hot liquids.
Injection pressure and quantity of lubricating liquid
Do not breathe toxic vapors. Do not allow sparking,
will vary. Usually 0.45 to 0.90 m 3/h (2 to 4 gpm) at
flames or hot surfaces in the vicinity of the equipment.
0.7 to 0.14 bar (10 to 20 psi) over maximum pump
discharge pressure of clean liquid is required. i) Open the discharge valve as desired to operate
the unit at its design conditions.
For recommended oils for enclosed lineshaft bearing j) Check complete pump and driver for leaks, loose
lubrication under normal operating conditions, please connections, or improper operation.
see tables 5.2.3.1 and 5.2.3.2. If none of the above
If possible, the pump should be left running for
oils are available, oil with the following specifications
approximately one half hour on the initial startup, this
should be obtained. Turbine type oil with rust and
will allow the bearings, packing or seals, and other
oxidation inhibitors added, viscosity 30 cSt (mm2/sec)
parts to "run-in" and reduce the possibility of trouble
to 37 cSt (mm2/sec) at 40 °C (100 °F) with a minimum
on future starts.
viscosity index of 90.

If abrasives or debris are present,


upon startup, the pump should be allowed to run until
the pumpage is clean. Stopping the pump when
handling large amounts of abrasives (as is

Page 44 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

sometimes present on initial starting) may lock the


pump and cause more damage than if the pump is Measurements shall be taken at the
allowed to continue operation. pump/motor interface. Values collected at the top of
the motor will be considered for reference only.
Operating the pump with abrasives in the pumpage
will cause wear. Every effort should be made to keep
abrasives out of lines, sump, etc. so that abrasives Motor start/stop frequency
will not enter the pump. Even though motors are normally suitable for at least
two consecutive starts, it is recommended to restart
Frequency of lubrication only after coasting to rest between starts (minimum
The characteristics of the installation and severity of of 15 minute gaps), with the motor initially at ambient
service will determine the frequency of lubrication. temperature. If more frequent starting is necessary,
Lubricant and pump/motor bearing temperature refer to driver manufacturer’s instructions or contact
analysis is useful in optimizing lubricant change Flowserve with details.
intervals.

The motor bearing temperature limitations should be The number of motor start and stops
considered for its lubrication requirements. Refer to in any given time affects motor life.
the driver manufacturer’s user instructions supplied
with the pump. If documents are not found, contact
Flowserve. & If the motor is expected to experience multi
starts in any given time, please refer to the driver’s
user instructions before the pump is put into
Never mix greases containing different
operation.
bases, thickeners or additives.
Operating the Pump
Normal vibration levels, alarm and trip
Normal operating, alarm, and trip vibration levels are Venting the pump
used to identify and maintain the proper operation of
the pump. Flowserve standard vibration levels are Make sure that the pump is vented to enable
shown below. all trapped air to escape, taking due care with the
Normal allowable field vibration values hazardous or hot liquids. Under normal conditions
for vertical turbines- sump or wet pit or after the pump is fully vented and primed, it should
barrel types be unnecessary to re-vent the pump.
Vibration
Vibration
Motor rating kW (HP) velocity-
mm/sec (in/sec) RMS DISCHARGE VENT LINE
unfiltered
<200 (<268) N 5.1 (0.20) SUCTION VENT LINE
200-750 (268-1000) N 6.1 (0.24)
>750 (>1000) N 7.1 (0.28) SEALING LIQUID
SUCTION
SOURCE

Measurements shall be taken at the


pump/motor interface. Values collected at the top of
the motor will be considered for reference only.

5.7.7.2 Alarm and Trip Values


Alarm and trip values should be established to
monitor for maintenance and operational condition of Pumps fitted with packed glands
the pump assembly. Refer to the latest edition of HI If the pump has a packed gland, there must be some
9.6.5, Guidelines for Condition Monitoring, for leakage from the gland. Gland nuts should initially
establishment of the alarm and trip settings. be finger-tight only. Leakage should take place soon
after the stuffing box is pressurized.

Page 45 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

commissioning stage and after the bearing


The gland must be adjusted evenly to give temperature has stabilized.
visible leakage and concentric alignment of the gland · Record the bearing temperature (t) and the
ring to avoid excess temperature. If no leakage ambient temperature (ta)
takes place, the packing will begin to overheat. · Estimate the likely maximum ambient
temperature (tb)
If overheating takes place, the pump should be · Set the alarm at (t+tb-ta+5) °C [(t+tb-ta+10) °F] and
stopped and allowed to cool before being re-started. the trip at 100 °C (212 °F) for oil lubrication and
When the pump is re-started, check to ensure 105 °C (220 °F) for grease lubrication
leakage is taking place at the packing gland.
It is important, particularly with grease lubrication, to
If hot liquids are being pumped it may be necessary keep a close watch on the bearing temperatures.
to loosen the gland nuts to achieve leakage. After startup the temperature rise should be gradual,
reaching a maximum after approximately 1.5 to 2
The pump should be run for 30 minutes with steady hours. This temperature rise should then remain
leakage and the gland nuts tightened by 10 degrees constant or marginally reduce with time.
at a time until leakage is reduced to an acceptable
level, normally a minimum of 40-60 drops per minute Multiple Can Pump Operation
is required.
Additional procedures may be required in multiple
can pump systems when one or more pump remains
Care must be taken when adjusting the gland
idle. Contact Flowserve for details.
on an operating pump. Safety gloves are essential.
Loose clothing must not be worn to avoid being Stopping and Shutdown
caught by the pump shaft. Shaft guards must be
replaced after the gland adjustment is complete.
a) Close the outlet valve, but ensure that the pump
runs in this condition for no more than a few
Never run gland packing dry, even for seconds.
a short time. b) Stop the pump.
c) Switch off flushing and/or cooling/heating liquid
Pumps fitted with mechanical seal supplies at a time appropriate to the process.
Mechanical seals require no adjustment. Any slight
initial leakage will stop when the seal is run in.
For prolonged shutdowns and
Before pumping dirty liquids, it is advisable, if especially when ambient temperatures are likely to
possible, to run in the pump mechanical seal using drop below freezing point, the pump and any cooling
clean liquid to safeguard the seal face. and flushing arrangements must be drained or
otherwise protected.

External flush or quench should be Hydraulic, mechanical and electrical


started before the pump is run and allowed to flow for duty
a period after the pump has stopped. This product has been supplied to meet the
performance specifications of your purchase order;
however, it is understood that during the life of the
Never run a mechanical seal dry, product, these may change. The following notes may
even for a short time. help the user decide how to evaluate the implications
of any change. If in need of assistance, contact your
Pump and motor bearing temperature nearest Flowserve office.

If the pumps are working in a potentially


explosive atmosphere, temperature or vibration
monitoring at the bearings is recommended.

If pump bearing temperatures (such as thrust


bearings) are to be monitored it is essential that a
benchmark temperature is recorded at the

Page 46 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

6 MAINTENANCE
5.10.1 Specific gravity (SG)
Pump capacity and total head in meters (feet) do not General
change with SG; however, pressure displayed on a
pressure gauge is directly proportional to SG. Power It is the plant operator's responsibility to
absorbed is also directly proportional to SG. It is ensure that all maintenance, inspection and
important to check that any change in SG will not assembly work is carried out by authorized and
overload the pump driver or over-pressurize the qualified personnel who have adequately familiarized
pump. themselves with the subject matter by studying this
manual in detail. (See also section 1.6.)
5.10.2 Viscosity
For a given flow rate the total head reduces with Any work on the machine must be performed when it
increased viscosity and increases with reduced is at a standstill. It is imperative that the procedure
viscosity. Also for a given flow rate the power for shutting down the machine is followed, as
absorbed increases with increased viscosity, and described in section 5.9.
reduces with reduced viscosity. It is important that
checks are made with your nearest Flowserve office Guard fasteners must remain captive during
if changes in viscosity are planned. dismantling of guards as described in section 5.5
5.10.3 Pump speed On completion of work all guards and safety devices
Changing pump speed effects flow, total head, power must be re-installed and made operative again.
absorbed, NPSHR, noise and vibration. Flow varies in
direct proportion to pump speed, head varies as speed Before restarting the machine, the relevant
ratio squared and power varies as speed ratio cubed. instructions listed in section 5, Commissioning, start
The new duty, however, will also be dependent on the up, operation and shut down must be observed.
system curve. If increasing the speed, it is important
therefore to ensure the maximum pump working Oil and grease leaks may make the ground
pressure is not exceeded, the driver is not overloaded, slippery. Machine maintenance must always
NPSHA > NPSHR, and that noise and vibration are begin and finish by cleaning the ground and the
within local requirements and regulations. exterior of the machine.
5.10.4 Net positive suction head (NPSH A) If platforms, stairs and guard rails are required for
NPSH available (NPSHA) is a measure of the head maintenance, they must be placed for easy access to
available in the pumped liquid, above its vapor areas where maintenance and inspection are to be
pressure, at the pump suction branch. carried out. The positioning of these accessories
must not limit access or hinder the lifting of the part to
NPSH required (NPSHR) is a measure of the head be serviced.
required in the pumped liquid, above its vapor pressure,
to prevent the pump from cavitating. It is important that When air or compressed inert gas is used in the
NPSHA > NPSHR. The margin between NPSHA > maintenance process, the operator and anyone in the
NPSHR should be as large as possible. If any change vicinity must be careful and have the appropriate
in NPSHA is proposed, ensure these margins are not protection.
significantly eroded. Refer to the pump performance
curve to determine exact requirements particularly if Do not spray air or compressed inert gas on skin.
flow has changed.
Do not direct an air or gas jet towards other people.
If in of assistance, please consult your nearest
Flowserve office for advice and details of the Never use air or compressed inert gas to clean
minimum allowable margin for your application. clothes.
5.10.5 Pumped flow Before working on the pump, take measures to
Flow must not fall outside the minimum and prevent an uncontrolled start. Put a warning board
maximum continuous safe flow shown on the pump on the starting device with the words:
performance curve and or data sheet. "Machine under repair: do not start".

Page 47 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

With electric drive equipment, lock the main switch Routine inspection (daily/weekly)
open and withdraw any fuses. Put a warning board
on the fuse box or main switch with the words:
The following checks should be
"Machine under repair: do not connect".
made and the appropriate action taken to remedy
any deviations.
Never clean equipment with inflammable solvents or
a) Check operating behavior; ensure noise,
carbon tetrachloride. Protect yourself against toxic
vibration and bearing temperatures are normal.
fumes when using cleaning agents.
b) Check that there are no abnormal fluid or
Maintenance Schedule lubricant leaks (static and dynamic seals) and
that any sealant systems (if fitted) are full and
operating normally.
It is recommended that a maintenance plan c) Check that shaft seal leaks are within acceptable
and schedule is adopted, in line with these User limits.
Instructions, to include the following: d) Check the level and condition of lubrication oil.
a) Any auxiliary systems installed must be On grease lubricated pumps, check running
monitored, if necessary, to ensure they function hours since last recharge of grease or complete
correctly. grease change.
b) Gland packings must be adjusted correctly to e) Check any auxiliary supplies e.g. heating/cooling
give visible leakage and concentric alignment of (if fitted) are operating correctly.
the gland follower to prevent excessive f) Refer to the manuals of any associated
temperature of the packing or follower. equipment if routine checks needed.
c) Check for any leaks from gaskets and seals. The
correct functioning of the shaft seal must be Periodic inspection (every 6 Months)
checked regularly.
d) Check bearing lubricant level, and if the hours
run show a lubricant change is required. a) Check foundation bolts for
e) Check that the duty condition is in the safe security of attachment and corrosion.
operating range for the pump. b) Check pump operation hours to determine if
f) Check vibration, noise level and surface bearing lubricant shall be changed.
temperature at the bearings to confirm c) The coupling should be checked for correct
satisfactory operation. alignment and worn driving elements.
g) Check dirt and dust is removed from areas
around close clearances, bearing housings and
motors.
& Refer to the manuals of any associated
equipment for periodic checks needed.
h) Check coupling alignment and re-align if
necessary. Re-lubrication
Our specialist service personnel can help with Pump lubrication
preventative maintenance records and provide In general, VTPs that are product lubricated will not
condition monitoring for temperature and vibration to require further periodic lubrication. Stuffing box and
identify the onset of potential problems. mechanical seal needs flow of flush. Enclosed line
shaft pumps have to be provided with the required oil
If any problems are found the following sequence of quantity for an oil lubed system and the injection lube
actions should take place: flow at the required pressure for injection lubed
a) Refer to section 8, Faults; causes and remedies, systems.
for fault diagnosis.
b) Ensure equipment complies with the Driver lubrication
recommendations in this manual.
Contact Flowserve if the problem persists. &Refer to driver manufacturer’s User
Instructions supplied with the pump.

Page 48 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Impeller setting re-adjustment PACKING RING SIZES


Ordinarily, impeller settings will not require re- Packing Dimensions
adjustment if properly set at initial installation. Shaft size Packing ring size Outside diameter of
packing
mm (in.) mm (in.) mm (in.)
Any adjustments of the impeller 25 (1.00) 9.65 (0.38) 44.4 (1.75)
setting will change the seal setting; therefore, the 32 (1.25) 9.65 (0.38) 50.8 (2.00)
seal must be loosened from the shaft until the 38 (1.50) 11.17 (0.44) 60.4 (2.38)
adjustment is completed. Then the seal can be 43 (1.69) 12.70 (0.50) 68.3 (2.68)
reset. 49 (1.93) 12.70 (0.50) 74.6 (2.93)
56 (2.20) 12.70 (0.50) 81.0 (3.19)
62 (2.44) 12.70 (0.50) 87.3 (3.43)
Maintenance of the stuffing box
68 (2.68) 12.70 (0.50) 93.7 (3.69)
75 (2.95) 12.70 (0.50) 100.0 (3.93)
General 82 (3.22) 12.70 (0.50) 107.9 (4.24)
Maintenance of the stuffing box will consist of greasing 89 (3.50) 15.74 (0.62) 120.6 (4.74)
the box when required, tightening the packing gland 95 (3.75) 15.74 (0.62) 127.0 (5.00)
occasionally as the leakage becomes excessive, and 102 (4.00) 15.74 (0.62) 133.3 (5.24)
installing new packing rings or sets as required. 114 (4.50) 15.74 (0.62) 146.0 (5.74)

Greasing the stuffing box Startup with new packing


Under ordinary operation, once-a-month greasing of Check to see that the by-pass line (if used) is
the stuffing box will be adequate. A high quality connected and the packing gland is loose. Start
industrial grade # 2 grease is recommended. pump and allow it to run for 20 to 30 minutes. Do not
tighten the gland during this "run-in" period even if
leakage is excessive. Should the new packing cause
Replacing packing excessive heating during "run-in", flush the shaft and
Remove gland and all old packing. If the box contains packing box area with cold water or shut the pump
a lantern ring, remove this and all packing below it down and allow to cool.
using two long threaded machine screws.

Inspect shaft or sleeve for score marks or rough spots. For all repair instructions please call
Be sure by-pass holes (if supplied) are not plugged. Flowserve representative or customer service with
Repair or replace badly worn shaft or sleeve. the order no. and unit details for specific repair
instruction literature.
If wear is minor dress down until smooth and
concentric. Clean box bore. All repair work to be carried out by trained and
authorized personnel only. Flowserve’s written
Oil inside and outside of replacement rings lightly and permission may be required for any
install in box, staggering joints 90 degrees. Be sure to disassembly/repair of the pump that is still under
replace lantern ring in proper position when used. warranty.
Spare Parts
Replace gland and tighten nuts finger tight. The
packing gland must never be tightened to the point Ordering of spares
where leakage from the packing is stopped. Flowserve keep records of all pumps that have been
supplied. When ordering spare parts, we need the
A small amount of leakage is required for packing following information:
lubrication.
1. pump type and pump size
Packing ring sizes vary with the shaft diameter. 2. serial number of the pump
Packing ring size information are as follows. 3. number of the required spare parts
4. reference number and name of the part as listed
in the part list or in the sectional drawing

The pump size and serial number are as shown on


the pump nameplate.

Page 49 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

How to select recommended spares


Other tools may be required depending on
Generally, a list of spare parts supplied along with the the accessories/ special parts used per contract.
pump that shows the parts that are included in each of Flowserve in general is not obligated to ship the tools
the following two classes of recommended spares. If with any pump shipped.
in need of assistance, contact Flowserve for the
spares list.

Class I minimum
Suggested for Domestic Service when pump is
handling clean non-corrosive liquids and where
interruptions in service are not important.

Class II average
Suggested for Domestic Service when pump is
handling abrasive or corrosive liquids and where some
interruptions in continuity of service are not
objectionable.

Please contact Flowserve Sales Representative in


your area to review the spares best suited to meet
your requirements.

Storage of spare parts


Spares should be stored in a clean dry area away
from vibration. Inspection and re-treatment of
metallic surfaces (if necessary) with preservative is
recommended at 6-month intervals.
Recommended Spares and
Consumables
A list of spares and consumables are generally
included along with this User Instructions and other
documents that you have received along with the
pump and is made specifically to your order. In the
event that the list is not found, please contact
Flowserve with pump type and order no.
Tools Required
Standard tools needed to maintain this pump are
follows.
· Open ended spanners / wrenches (standard size
range)
· Socket spanners / wrenches (standard size
range)
· Allen keys/wrenches
· Standard range of screw drivers
· Soft mallet

For drive collet pumps:


· Collet driver
· Sand collar (if not provided on the unit)
· Tie down bolt

Page 50 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Fastener Installation
Fastener Torques
Order specific torque values are located on the “As
Build Cross Sectionals” when provided.

Fastener assemblies including locking


washers should not be torqued to values listed in
table below. Hardware should be tightened just until
locking washers are flattened. Lock washers are not
to be reused.

Fastener torques for pump assembly

Page 51 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Fastener Lubrication
Lubrication is to be used on all fasteners unless
stated otherwise. Lubrication used should be
Setting Impeller Clearance
Please see section 5.3 for specific instructions on
compatible with the pump application. Common
impeller adjustment.
example of lubrication is anti-seize.

Disassembly
Refer to manufacturer specific instructions
for lubrication requirements for all non-pump
manufacture based fasteners. i.e. motor, mechanical Refer to section 1.6, Safety, before
seal, gear drives, thrust pots, etc. dismantling the pump.

Fastener Sequencing Before dismantling the pump for


For proper installation of assembly fasteners, a overhaul, ensure genuine Flowserve replacement
sequencing procedure should be followed. Tighten parts are available.
bolts opposite one another from inside out, ensuring Refer to sectional drawings for part numbers and
an even and equal fastening. See below example. identification.

Please take precaution during


disassembly that there is no risk of explosion due to
the nature of the materials/ tools/ equipment/ method
used. Wherever chemical and hazardous materials
are involved, proper safety rules have to be followed
to prevent any dangers to human lives or livestock.
Contact Flowserve for guidance, or local regulatory
agency for specific safety information.

Pump disassembly instructions


Special Torque Requirements See section 8 for sectional drawings.
a) Disconnect all cables/wires and cooling water
6.6.4.1 Refer to manufacturer specific pipe connections to the driver (if provided).
instructions for torque values for all non- b) Carefully remove the flush or lubricant
pump manufacture based fasteners. i.e. connections and remove any associated piping
motor, mechanical seal, gear drives, thrust that would interfere with the dismantling.
pots, etc. c) Make sure that all the valves are shut completely
to avoid any leaks or spills.
6.6.4.2 Flowserve flanged motor to pump d) Disconnect the coupling halves [471] (the driver
couplings when supplied with Alloy Steel & pump).
fasteners should be torqued to the below e) Disconnect the suction (if used) and discharge
values. pipe connections to the discharge head.
f) Rig the motor to a suitable hoist and keep the
Torques for flanged couplings fasteners lifting mechanism in ready state.
Coupling Flange diameter N-m
size # mm (in) (lbf-ft) g) Remove the motor to discharge head [304]
1&2 111 or 137 122 bolting and remove the motor from the discharge
(4.4 or 5.4) (90) head and place it on a safe and appropriate
3-5 156, 187 213 237 location.
(6.0, 7.4, 8.4) (175)
6 250 424
h) If the pump is of shorter length (with or without
(10.0) (313) can) rig the discharge head along with the entire
Torque values are for standard fasteners lubricated with a high pump assembly (see section 2.3 for lifting) using
stress lubricant (such as, graphite and oil, moly-disulphite, white lead a suitable hoist (check the building height
etc.).
clearance before the lifting is attempted)
i) Use eye bolts and hooks as necessary and get
the lifting mechanism in ready state.

Page 52 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

straightened by supporting on two blocks straddling


j) Lifting of short set pumps the crooked section and applying pressure to the high
· Remove the fasteners at the discharge side to deflect the shaft in the opposite direction. If the
head/foundation/soleplate shaft has a sharp crook (dog-leg), it is recommended
· Lift the entire pump assembly by clamping at that the shaft be replaced since the shaft will not
the discharge head [304] (See section 2.3) always remain straight, even if satisfactorily
k) Lifting of deep set pumps straightened.
· Remove the fasteners at the foundation plate
or soleplate DIAL INDICATOR
· Remove stuffing box/Mechanical seal [349]
completely. Protect the shaft against damage
while lifting the discharge head [304]
· Lift the pump just enough to access the first ROLLERS
column pipe flange connection
· Support the entire pump just below the first
column pipe joint [101]
· Disconnect the discharge head [304] and lift
· Now lift the pump again by using column pipe
flange and disconnect the first section of
column piping SHAFT
· Remove the bearing retainers [307] and shaft
couplings [70] and repeat the process until all
column piping is disassembled
· Last step is to lift and remove the bowl
assembly Even if the shaft is new or has been
previously straightened, it is recommended that the
See section 2.3, 4.1.2 and 4.1.3 for related shaft be re-checked at this point to ensure damage
information. has not occurred in transit or handling.
Examination of Parts
Examination of bearings
Used parts must be inspected before Check all bearings for total clearance over the shaft.
assembly to ensure the pump will subsequently run It is recommended that all bearings indicating visual
properly. In particular, fault diagnosis is essential to wear be replaced. In addition, any bearings whose
enhance pump and plant reliability. running clearance exceeds "As New" tolerances by
more than 50% should be replaced (see table 6.8.2.1).
Before proceeding with assembly, thoroughly clean
all bolts, nuts, threaded connections and mating
Rubber bearings should always be replaced
faces. Clean up any burrs with a file or emery cloth.
when servicing a pump.

Cleanliness and proper lubrication are


required to guarantee ease of re-assembly and
proper pump operation.

Examination of shaft/s
Check the shafts for straightness, pitting and wear.
Remove all burrs or nicks. Shaft damage is usually
best corrected by replacing the shaft.

The shaft must be straight to within 0.127 mm


(0.005 in.) total indicator reading. The detail below
shows the recommended method for checking shaft
straightness. If the shaft is not straight, it must be
straightened or replaced. If the deflection is gradual
over a considerable length, the shaft can usually be

Page 53 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Shaft/bearing clearance
Shaft Shaft Bearing When attempting to rework any part,
Size Diameter/Tolerance Clearance extreme care must be taken to maintain alignment of
mm Min Dia- Max Dia (Max/Min)
(in) mm mm
mating parts and ensure “as new” tolerances.
(in) (in)
25.40 25.35 25.40 0.28/0.13 The inspection, disassembly of bowl assembly
(1.000) (0.998) (1.000) (0.011/0.005) requires expertise and tools to perform the job
31.75 31.70 31.75 0.35/0.15 correctly. It is recommended to seek the services of
(1.250) (1.248) (1.250) (0.012/0.006)
38.10 38.05 38.10 0.33/0.18
Flowserve trained technicians to inspect and repair
(1.500) (1.498) (1.500) (0.013/0.007) bowl assemblies.
42.86 42.81 42.86 0.36/0.18
(1.690) (1.685) (1.687) (0.014/0.007) Inspection of enclosed impellers
49.21 49.16 49.21 0.38/0.23 a) Clear all passageways and check for signs of
(1.940) (1.935) (1.937) (0.015/0.008)
55.56 55.51 55.56 0.41/0.23
damage from abrasion or corrosion. Replace an
(2.190) (2.185) (2.187) (0.016/0.009) impeller that shows signs of excessive wear.
61.91 61.86 61.91 0.41/0.23
(2.440) (2.435) (2.437) (0.016/0.009) b) Check impeller running clearances against “as
68.26 68.21 68.26 0.43/0.23 new” tolerances listed in the section 0. If the
(2.690) (2.685) (2.687) (0.017/0.009) clearances exceed the maximum tolerances
74.61 74.56 74.61 0.43/0.23 shown by more than 50%, the new wear rings
(2.940) (2.935) (2.937) (0.017/0.009) should be installed to obtain correct tolerances.
82.55 82.47 82.55 0.46/0.25
(3.250) (3.247) (3.250) (0.018/0.010) c) If the original unit was furnished with bowl and
88.90 88.82 88.90 0.48/0.28 impeller wear rings, they may be pressed or
(3.500) (3.497) (3.500) (0.019/0.011)
95.25 95.17 95.25 0.53/0.35 machined off.
(3.750) (3.747) (3.750) (0.021/0.012)
101.60 101.58 101.60 0.56/0.33 Please note that certain repairs may require special
(4.000) (3.997) (4.000) (0.022/0.013) skills and it is recommended to contact Flowserve
114.30 114.22 114.30 0.58/0.35 authorized service center before attempting any such
(4.500) (4.497) (4.500) (0.023/0.014)
127.00 126.92 127.00 0.61/0.38 repairs.
(5.000) (4.997) (5.000) (0.024/0.015)
See wear ring tolerance chart in section 0.
Bronze, epoxy, carbon and hard-backed rubber
bearings are pressed into their respective bores. They Inspection of semi-open impellers
can either be pressed out or machined on the inside a) Clear all passageways and check for signs of
diameter until the wall is thin enough to collapse. damage from abrasion or corrosion.
b) Replace any impeller, which shows signs of
Some rubber bearings are the snap-in or glue-in type. excessive wear. If the bowl faces or impellers
These can be removed by prying inward on the are worn slightly (grooves in either impeller or
outside of the bearing to collapse it. bowl under 0.79 mm (1/32 in.)), they can be
corrected by re-facing the impeller and bowl.
If the bearing bore of the housing is heavily scarred or 0.79 mm (1/32 in.) is the maximum that can be
corroded, the part should be replaced or reworked to machined off without harm to the hydraulic
provide a true bore for the bearing. performance of the pump.
c) The machining must match the face angle and
Replacement bearings are designed to be pressed should be re-faced by an authorized Flowserve
into housings so bores will shrink to "as new" repair facility or replaced.
tolerances. Measure the bore of bearings after
pressing and ream as necessary to assure "as new" If the impeller has a balance ring on the topside (side
tolerances. opposite pumping vanes) running clearances must
be checked.
Inspection of bowl assembly
Please see section 6.9.4 for wearing ring tolerance
When repairing a bowl assembly that has chart for enclosed impellers.
been in service for several years, the physical
condition or strength of all parts such as cap screws,
bowls and bowl threads must be carefully checked.

Page 54 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Wearing ring tolerance chart for enclosed impellers

Bowl ring Clearance between bowl


internal and impeller wear rings Bowl ring Impeller ring
diameter. interference fit interference fit
Nominal Standard Galled
mm (in)
mm (in)
50.8-76.2 0.330/0.229 0.533/0.432 0.101/0.050 0.076/0.025
(2-3) (0.013/0.009) (0.021/0.017) (0.004/0.002) (0.003/0.001)
76.2-101.6 0.356/0.229 0.635/0.483 0.127/0.050 0.102/0.025
(3-4) (0.014/0.009) (0.025/0.019) (0.005/0.002) (0.004/0.001)
101.6-127.0 0.381/0.279 0.635/0.533 0.152/0.076 0.127/0.038
(4-5) (0.015/0.011) (0.025/0.021) (0.006/0.003) (0.005/0.002)
127.0-152.4 0.406/0.305 0.660/0.559 0.178/0.076 0.127/0.038
(5-6) (0.016/0.012) (0.026/0.022) (0.007/0.003) (0.005/0.002)
152.4-177.8 0.406/0.305 0.686/0.584 0.178/0.076 0.127/0.038
(6-7) (0.016/0.012) (0.027/0.023) (0.007/0.003) (0.005/0.002)
177.8-203.2 0.432/0.330 0.711/0.610 0.203/0.076 0.152/0.051
(7-8) (0.017/0.013) (0.028/0.024) (0.008/0.003) (0.006/0.002)
203.2-228.2 0.457/0.356 0.737/0.635 0.254/0.102 0.178/0.051
(8-9) (0.018/0.014) (0.029/0.025) (0.010/0.004) (0.007/0.002)
228.2-254.0 0.457/0.356 0.762/0.660 0.254/0.102 0.229/0.051
(9-10) (0.018/0.014) (0.030/0.026) (0.010/0.004) (0.009/0.002)
254.0-279.4 0.457/0.356 0.788/0.686 0.254/0.102 0.229/0.076
(10-11) (0.018/0.014) (0.031/0.027) (0.010/0.004) (0.009/0.003)
279.4-304.8 0.457/0.356 0.813/0.711 0.280/0.102 0.229/0.076
(11-12) (0.018/0.014) (0.032/0.028) (0.011/0.004) (0.009/0.003)
304.8-330.2 0.508/0.356 0.890/0.737 0.280/0.102 0.229/0.076
(12-13) (0.020/0.014) (0.035/0.029) (0.011/0.004) (0.009/0.003)
330.2-355.6 0.508/0.356 0.914/0.762 0.305/0.102 0.254/0.102
(13-14) (0.020/0.014) (0.036/0.030) (0.012/0.004) (0.010/0.004)
355.6-381.0 0.508/0.356 0.940/0.788 0.305/0.127 0.254/0.102
(14-15) (0.020/0.014) (0.037/0.031) (0.012/0.005) (0.010/0.004)
381.0-406.4 0.559/0.406 0.965/0.813 0.305/0.127 0.254/0.102
(15-16) (0.022/0.016) (0.038/0.032) (0.012/0.005) (0.010/0.004)
406.4-431.8 0.559/0.406 0.990/0.838 0.305/0.127 0.254/0.102
(16-17) (0.022/0.016) (0.039/0.033) (0.012/0.005) (0.010/0.004)
431.8-457.2 0.610/0.457 1.010/0.864 0.305/0.127 0.254/0.102
(17-18) (0.024/0.018) (0.040/0.034) (0.012/0.005) (0.010/0.004)
457.2-482.6 0.610/0.457 1.041/0.889 0.330/0.406 0.279/0.127
(18-19) (0.024/0.018) (0.041/0.035) (0.013/0.016) (0.011/0.005)
482.6-508.0 0.610/0.457 1.070/0.914 0.330/0.406 0.279/0.127
(19-20) (0.024/0.018) (0.042/0.036) (0.013/0.016) (0.011/0.005)
508.0-533.4 0.660/0.508 1.092/0.934 0.356/0.152 0.305/0.127
(20-21) (0.026/0.020) (0.043/0.037) (0.014/0.006) (0.012/0.005)
533.4-558.8 0.660/0.508 1.118/0.965 0.356/0.152 0.304/0.127
(21-22) (0.026/0.020) (0.044/0.038) (0.014/0.006) (0.012/0.005)
558.8-584.2 0.660/0.508 1.143/0.990 0.356/0.152 0.304/0.127
(22-23) (0.026/0.020) (0.045/0.039) (0.014/0.006) (0.012/0.005)
584.2-609.6 0.660/0.508 1.168/1.020 0.381/0.179 0.330/0.152
(23-24) (0.026/0.020) (0.046/0.040) (0.015/0.007) (0.013/0.006)
609.6-635.0 0.660/0.508 1.194/1.041 0.406/0.179 0.330/0.152
(24-25) (0.026/0.020) (0.047/0.041) (0.016/0.007) (0.013/0.006)
635.0-660.4 0.660/0.508 1.220/1.066 0.406/0.203 0.356/0.179
(25-26) (0.026/0.020) (0.048/0.042) (0.016/0.008) (0.014/0.007)
660.4-685.8 0.660/0.508 1.244/1.092 0.406/0.203 0.356/0.179
(26-27) (0.026/0.020) (0.049/0.043) (0.016/0.008) (0.014/0.007)

Page 55 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Assembly
To assemble the pump assembly, consult the typical
sectional drawings or the “as built cross sectional”
when provided.

The pump that has been purchased may


have order specific assembly and parts
configurations. Specific cross sectional drawings that
reflect the exact pump/parts details can be purchased
from Flowserve. Contact Flowserve for drawings
purchase and cost information.

It is recommended to call for trained Flowserve


technicians for all your assembly needs.

&Refer to seal manufacturer’s instructions for


disassembly and re-assembly of mechanical seals.

Please take precaution during


assembly process such that there is no risk of
explosion due to the nature of the materials/ tools/
equipment/ methods used. Wherever chemicals and
hazardous materials are involved, proper safety rules
must be followed to prevent any dangers to human
lives or livestock. Refer to applicable local regulatory
agency requirements for specific safety information.

Page 56 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

7 FAULTS; CAUSES AND REMEDIES


FAULT SYMPTOM
Pump overheats and seizes
ß Bearings have short life

ß Pump vibrates or is noisy

ß Mechanical seal has short life

ß Mechanical seal leaks excessivel y

ß Pump requires excessive power

ß Pump loses prime after starting

ß Insufficient pressure developed

ß Insufficient capacity delivered

ß Pump does not deliver liquid


ß POSSIBLE CAUSES POSSIBLE REMEDIES
A. SYSTEM PROBLEMS
l l l Pump not submerged. Check requirements/liquid level. Vent and/or prime.

l l l l Impeller not adjusted or loose on shaft. See PART/2-Section A7 for proper impeller adjustment.
l l l Suction lift too high or level too low.
Check NPSHa>NPSHr, proper submergence, losses at
Insufficient margin between suction strainers/fittings.
l l l l
pressure and vapor pressure.
l l l Excessive amount of air or gas in liquid. Check and purge pipes and system.
l Line check valve backward/stuck. Reverse chuck valve /free the valve.
l Unit running backwards. See start up instruction. Check motor phase/wiring
l l l Air or vapor pocket in suction line. Check suction line design for vapor pockets.
l l Air leaks into suction line. Check suction pipe is airtight.
l l l l Intake strainer or impeller plugged or pump Start and stop several times or use line pressure if
in mud or sand. available to back flush or pull pump to clean.
l l l Inlet of suction pipe insufficiently
Check out system design.
submerged.
l l l Speed too low. Consult Flowserve.
l l Speed too high. Consult Flowserve.
Total head of system higher than differential
l l l
head of pump.
Check system losses or consult Flowserve.
Total system head is lower than pump
l
design head.
l l Specific gravity of liquid different from Check and consult Flowserve.
design.
Check the pump design for the type of liquid to be
l l l l Viscosity of liquid differs from the designed. handled. Consult Flowserve.

l l Operation at very low capacity. Measure. Check minimum permitted. Consult Flowserve.
Measure value and check maximum permitted. Consult
l l l l Operation at high capacity.
Flowserve.
B. MECHANICAL PROBLEMS
Check the flange connections and eliminate strains using
l l l l l l Misalignment due to pipe strain.
elastic couplings or a method permitted.
Improperly designed foundation and/or Check setting of base plate. Tighten, adjust, grout base as
l
loose fasteners. required. Check fasteners and torque.

l l l l l Shaft bent. Check shaft run outs. Consult Flowserve.


l l l l l Rotating part rubbing on stationary part. Check. Consult Flowserve, if necessary.
l l l l l Bearings worn. Replace bearings.
l l l Wearing ring surfaces worn. Replace worn wear ring/surfaces.

Page 57 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

FAULT SYMPTOM
Pump overheats and seizes
ß Bearings have short life

ß Pump vibrates or is noisy

ß Mechanical seal has short life

ß Mechanical seal leaks excessivel y

ß Pump requires excessive power

ß Pump loses prime after starting

ß Insufficient pressure developed

ß Insufficient capacity delivered

ß Pump does not deliver liquid


ß POSSIBLE CAUSES POSSIBLE REMEDIES
l l l Impeller damaged or eroded. Replace. or consult Flowserve for an upgrade.
l Leakage under sleeve due to joint failure. Replace joint and check for damage.
Shaft sleeve worn, scored, or running off
l l Check and renew defective parts.
center.
l l l Mechanical seal improperly installed. Check alignment of faces/damaged parts/assembly
l l l Incorrect type of mechanical seal. Consult Flowserve.
Shaft running off center because of worn Check misalignment and correct if necessary. If alignment
l l l l
bearings or misalignment. satisfactory check bearings for excessive wear.
l l l l Impeller out of balance resulting in
vibration.
l l l l Solids/Abrasive particles in liquid pumped. Check. Consult Flowserve for problem resolution ideas.
Internal misalignment of parts preventing
l l
seal ring and seat from mating properly.

l l Mechanical seal was run dry. Check mechanical seal/flush supply/pump and repair.
Check method of assembly, possible damage or state of
l l l Internal misalignment due to improper
cleanliness during assembly. Check and consult
repairs causing impeller to rub.
Flowserve, if necessary.
Excessive thrust caused by a mechanical Check wear condition of impeller, its clearances and liquid
l l l
failure inside the pump. passages.
l l Excessive grease in ball bearings. Check method of re-greasing.
Check hours run since last change of lubricant, the
l l Lack of lubrication for bearings.
schedule and its basis.
Improper installation of bearings (damage Check method of assembly, possible damage or state of
l l
during assembly, incorrect assembly, wrong cleanliness during assembly and type of bearing used.
type of bearing etc.). Remedy and consult Flowserve, if necessary.

l l Damaged bearings due to contamination. Check contamination source and replace bearings.
C. MOTOR/ELECTRICAL PROBLEMS
l l l l l Wrong direction of rotation. Reverse 2 phases at motor terminal box.
l Check nameplate for voltage and current rating.
Motor Protector open.
Replace faulty motor protectors.
l Line voltage not correct/faulty control
Check wiring diagram.
box/wiring/low voltage.
l Blown fuse/breaker open/dead motor/short
Check/repair or replace fuses/breakers.
or loose connection.
l l Motor running on 2 phases only. Check supply and fuses.
l l l Motor running too slow. Check motor terminal box connections and voltage.

Page 58 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

8 DRAWINGS AND PARTS LISTS

Please refer to appendix for Europump


part number equivalents.

Cross Section: Product Lubricated VTP


Typical wet pit pump

See sections 8.1.1 and 8.1.2 for parts details

All the sectional drawings provided in this


section are typical representations of the most
common pump types and are provided for the
purposes of basic understanding of the equipment.
The details shown may not reflect the specifics of the
pump that has been purchased. Order-specific “as
built cross sectional drawings” and “parts list” can
be purchased from Flowserve separately. Contact
Flowserve for ordering and pricing information on
such drawings and documentation.
SEE
SECTION
8.1.1
FOR PART
DETAILS

SEE
SECTION
8.1.2
FOR PART
DETAILS

Page 59 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Parts identification: Discharge head and column assembly


Typical wet pit/sump type design-product lubricated VTP
ELECTRIC MOTOR

(ASSEMBLY)
REF. NO. 471

314
425
424
304
349
131
354
418
355
417
347
326A
416
327A
117
416
348

431
327
307
326
39
14
366
12A
325
327
101
307
39
14
366

Parts list-Discharge head and column 327 NUT-HEX


assembly 327A NUT-HEX
Ref no. Description 347 O-RING-STUFFING BOX
12A SHAFT-TOP 348 HOUSING-THROTTLE BUSHING
14 SLEEVE-LINESHAFT 349 SEAL-MECHANICAL
39 BEARING-SLEEVE-LINESHAFT 354 STUD-THREADED
101 COLUMN-PIPE-REG 355 NUT-HEX
117 BEARING-SLEEVE-THROTTLE BUSHING 366 SCREW-SET
131 GUARD-COUPLING 416 PLUG-PIPE
304 HEAD-DISCHARGE 417 SCREW-CAP-HEX HEAD
307 RETAINER-BEARING 418 WASHER
314 SPACER-FLANGED 424 NAMEPLATE-FLS
325 SCREW-CAP-HEX HEAD 425 DRIVE SCREW FOR SERIAL PLATE
326 STUD-THREADED 431 O-RING
326A STUD-THREADED 471 ASSEMBLY, MOTOR TO PUMP COUPLING

Page 60 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Parts identification: Bowl assembly Parts list-Bowl assembly


Typical wet pit/sump type design-product Ref no. Description
lubricated VTP 2 IMPELLER
6 SHAFT-PUMP
55 BELL-SUCTION
64 COLLAR-PROTECTIVE
70 COUPLING-SHAFT-THREADED
101 COLUMN-PIPE-REG
125 PLUG-GREASE
309 CASE-DISCHARGE
310 BOWL
311 COLLET-DRIVE
101 316 STRAINER
70 6 320 BEARING-THREADED-DISCHARGE CASE
361 320 321 BEARING-SLEEVE-DISCHARGE CASE
323 BEARING-SLEEVE-BELL
360
328 SCREW-SET
309 337 PLUG-PIPE
321 337 356 SCREW-CAP-HEX HEAD
357 NUT-HEX
357
358 SCREW-CAP-HEX HEAD
356 360 SCREW-CAP-HEX HEAD
310 361 NUT-HEX
311 369 RING-FLOW
422 SCREW-CAP-HEX HEAD
369
2

310
358

311

310
358

311

2
55

358

64 422
328
323 316
125

Page 61 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Cross Section: Enclosed Tube VTP


Typical enclosed tube/oil lubricated VTP

See sections 8.2.1 and 8.2.2 for parts details.

All the sectional drawings provided in this


section are typical representations of the most
common pump types and are provided for the
SEE SECTION 8.2.1 FOR
purposes of basic understanding of the equipment.
PARTS DETIALS The details shown may not reflect the specifics of the
pump that has been purchased. Order-specific “as
built cross sectional drawings” and “parts list” can
be purchased from Flowserve separately. Contact
Flowserve for ordering and pricing information on
such drawings and documentation.

SEE SECTION 8.2.2 FOR


PARTS DETAILS

Page 62 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Parts identification: Typical enclosed shaft and oil lube connections


Typical enclosed tube/oil lubricated VTP

(ASSEMBLY)
382
384 ELECTRIC MOTOR
383 469
381
77
79 (ASSEMBLY)
REF. NO. 471
386
385

304
343
341
425
131 418 424
342 417 301
89
39

388 (ASSEMBLY)
414
387
389 397
396 13
(ASSEMBLY)
REF. NO. 344 354
302

12A
85

103

374
327 431
326
307
85

103

85

Parts list-Enclosed shaft and oil lube connections


Ref no. Description 374 O-RING-BARREL
12A SHAFT-TOP 381 SCREW-CAP-HEX HEAD
13 PACKING SET 382 NUT-HEX
39 BEARING-SLEEVE-LINESHAFT 383 CAP
77 OIL TANK 384 BAND
79 BRACKET 385 STOVE BOLT
85 ENCLOSING TUBE 386 NUT-HEX
89 SEAL-OIL 387 LUBRICATION LINE
103 BEARING-THREADED-LINE SHAFT 388 FITTING-ELBOW
131 GUARD-COUPLING 389 FITTING-ADAPTER
301 ENCLOSING TUBE NUT 396 CLIP-SAFETY
302 TUBE-TENSION 397 SCREW-CAP-HEX HEAD
304 HEAD-DISCHARGE 414 PLUG-PIPE
307 RETAINER-BEARING 417 SCREW-CAP-HEX HEAD
326 STUD-THREADED 418 WASHER
327 NUT-HEX SERIAL PLATE-FLOWSERVE
424
341 VALVE-SHUTOFF TANEYTOWN
342 REGULATOR-SIGHT FEED 425 DRIVE SCREW FOR SERIAL PLATE
343 ELBOW-VENT 431 O-RING
354 STUD-THREADED 469 SCREW-CAP-HEX HEAD

Page 63 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Parts identification: Bowl and enclosing tube assembly


Typical enclosed tube/oil lubricated VTP

103
101

103
85
431
361 309
354 89
427

357
321 430
354 310
426 369
6
312
2
(ASSEMBLY) 26
32
REF. NO. 492 430
8
357 310
(ASSEMBLY)
358A 429
REF. NO. 491
426 319
322 428
312
26
2
(ASSEMBLY) 430
32
REF. NO. 492 55
8 (ASSEMBLY)
429
357 REF. NO. 493
319
358A
428
426
64
328 422
323 316
125

Parts list-Bowl and enclosing tube


assembly.
Ref no. Description 316 STRAINER
2 IMPELLER 319 RING-WEAR-BOWL
6 SHAFT-PUMP 319* RING-WEAR-BOWL
8 RING-WEAR-IMPELLER 321 BEARING-SLEEVE-DISCHARGE CASE
26 SCREW-CAP SOCKET HEAD 322 BEARING-SLEEVE-BOWL
32 KEY-STRAIGHT 323 BEARING-SLEEVE-BELL
39 BEARING-SLEEVE-LINESHAFT 328 SCREW-SET
55 BELL-SUCTION 354 STUD-THREADED
64 COLLAR-PROTECTIVE 357 NUT-HEX
85 ENCLOSING TUBE 358A STUD-THREADED
89 SEAL-OIL 361 NUT-HEX
101 COLUMN-PIPE-REG 369 RING-FLOW
103 BEARING-THREADED-LINE SHAFT 422 SCREW-CAP-HEX HEAD
125 PLUG-GREASE 426 SCREW-CAP-HEX HEAD
309 CASE-DISCHARGE 427 SCREW-CAP-HEX HEAD (JACKING LUG)
310 BOWL 428 PIN-ROLL
311 COLLET-DRIVE 429 PIN-ROLL
312 RING-THRUST-SPLIT-IMPELLER 430 O-RING
312* RING-THRUST-SPLIT-COUPLING 431 O-RING

Page 64 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Cross Section: Suction Barrel VTP


Typical

See sections 8.3.1 and 8.3.2 for parts details

All the sectional drawings provided in this


section are typical representations of the most
common pump types and are provided for the
purposes of basic understanding of the equipment.
The details shown may not reflect the specifics of the
SEE
SECTION pump that has been purchased. Order-specific “as
8.3.1 built cross sectional drawings” and “parts list” list
FOR PART can be purchased from Flowserve separately.
DETAILS Contact Flowserve for ordering and pricing
information on such drawings and documentation.

SEE
SECTION
8.3.2
FOR PART
DETAILS

Page 65 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Parts identification: Discharge head/column/suction barrel


Typical product lubricated VTP with a suction barrel

ELECTRIC MOTOR

382
(ASSEMBLY)
REF. NO. 471
381

304
131 425
418 424
417 349
326A
354
327A
355
347
416
117
348

372
412
373
413
374
23

327 431
326 307
39
101

Parts list-Discharge head/column/suction barrel


Ref no. Description 354 STUD-THREADED
23 PLATE-SOLE 355 NUT-HEX
39 BEARING-SLEEVE-LINESHAFT 372 STUD-THREADED
101 COLUMN-PIPE-REG 373 NUT-HEX
117 BEARING-SLEEVE-THROTTLE BUSHING 374 O-RING-BARREL
131 GUARD-COUPLING 381 SCREW-CAP-HEX HEAD
304 HEAD-DISCHARGE 382 NUT-HEX
307 RETAINER-BEARING 412 STUD-THREADED
326 STUD-THREADED 413 NUT-HEX
326A STUD-THREADED 416 PLUG-PIPE
327 NUT-HEX 417 SCREW-CAP-HEX HEAD
327A NUT-HEX 418 WASHER
347 O-RING-STUFFING BOX 424 DISPLAY NAMEPLATE-FLS
348 HOUSING-THROTTLE BUSHING 425 DRIVE SCREW FOR SERIAL PLATE
349 SEAL-MECHANICAL 431 O-RING

Page 66 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Parts identification: Column and bowl assembly


Typical product lubricated VTP with the suction barrel

327
326
354 430
355 309
426 6
430
428 310
8* (ASSEMBLY)
REF. NO. 491
*
319
(ASSEMBLY)
2 429
REF. NO. 492
32
8 430
355 310
354 429
426 (ASSEMBLY)
319
REF. NO. 491
322 428
428 *
319
8* 429

(ASSEMBLY)
2
REF. NO. 492 430
32
310
8 (ASSEMBLY)
429
355 REF. NO. 491
319
354
428
426
322
312 26
2 430
(ASSEMBLY) 55
32
REF. NO. 492 (ASSEMBLY)
8 429
REF. NO. 493
355 319
354 428
426

323

26
315 *
312 312

THRUST RING DETAIL


F/ THRUST BALANCED IMPELLER

Page 67 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Parts list- Column and bowl assembly


Ref no. Description 10 OTHER RELEVANT
2 IMPELLER
6 SHAFT-PUMP DOCUMENTATION AND MANUALS
8 RING-WEAR-IMPELLER
26 SCREW-CAP SOCKET HEAD Supplementary User Instructions
32 KEY-STRAIGHT Supplementary instructions determined from the
39 BEARING-SLEEVE-LINESHAFT contract requirements for inclusion into user
55 BELL-SUCTION Instructions such as for a driver, instrumentation,
309 CASE-DISCHARGE
310 BOWL
controller, sub-driver, seals, sealant system,
312 RING-THRUST-SPLIT-IMPELLER mounting component, etc.… are included in the Final
312* RING-THRUST-SPLIT-COUPLING Data Book. If further copies of these are required
315 BARREL they should be obtained from the supplier for
319* RING-WEAR-BOWL retention with these user instructions.
322 BEARING-SLEEVE-BOWL
323 BEARING-SLEEVE-BELL
326 STUD-THREADED Where any pre-printed set of user instructions are
327 NUT-HEX used, and satisfactory quality can be maintained only
354 STUD-THREADED by avoiding copying these, they are included at the
355 NUT-HEX end of these user instructions such as within a
426 SCREW-CAP-HEX HEAD
standard clear polymer software protection envelope.
428 PIN-ROLL
429 PIN-ROLL
430 O-RING
Change Notes
491 ASSEMBLY, BOWL If any changes, agreed with Flowserve Pump
492 ASSEMBLY, WEARING RING Division, are made to the product after its supply, a
493 ASSEMBLY, SUCTION BELL & WEAR RING record of the details should be maintained with these
User Instructions.
General Arrangement Drawing
The typical general arrangement drawing and any .
specific drawings required by the contract will be sent
to the Purchaser separately unless the contract
specifically calls for these to be included into the User
Instructions. If these drawings are supplied
separately, the purchaser should retain those with the
User Instructions.

9 CERTIFICATION
Certificates determined from the Contract
requirements are provided with these instructions
where applicable. Examples are certificates for CE
marking and ATEX markings etc. If required, copies
of other certificates sent separately to the Purchaser
to be retained along with these User instructions.

Page 68 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

11 APPENDIX
Bill of Materials Reference Numbers
Europump
Current system Hydraulic institute
Ref. # Ref. # terminology 1995 Ref. #
description 2000 description
description
2 Impeller 2200 Impeller 2 Impeller / propeller
2 Impeller 2210 Impeller, suction stage 2 Impeller / propeller
6 Shaft pump 2110 Pump shaft 6 Shaft, pump
8 Ring wear impeller 2300 Impeller wear ring 8 Ring, impeller
10 Shaft head 2130 Top shaft / head shaft 10 Shaft, head
Intermediate shaft, drive
12 Shaft line 2120 12 Shaft, line
shaft
12 Shaft top (12a) 2130 Top shaft / head shaft 12 Shaft, line
13 Packing 4130 Packing 13 Packing
14 Sleeve lineshaft 3400 Bearing sleeve
17 Gland packing split 4120 Stuffing box gland 17 Gland
23 Plate base 6110 Base plate 129 Sole plate
24 Nut collet
Screw cap socket/head f/imp.
26 6579.# Socket head cap screw
Thrust ring
29 Ring lantern 4134 Lantern ring 29 Ring, lantern
32 Key impeller 6700.# Key 32 Key, impeller
39 Bearing sleeve f/tube nut 4132 Stuffing box bushing 39 Bushing, bearing
39 Bearing sleeve lineshaft 3300.# Bearing, bushing 39 Bushing, bearing
42 Coupling half driver 7200.1 Coupling half (driver) 42 Coupling half, driver
44 Coupling half driven 7200.2 Coupling half (driven) 44 Coupling half, pump
Key assembly driven coupling
46 6700.# Key 46 Key, coupling
half
46 Key driver coupling half 6700.# Key
55 Bell suction 1310 Suction bell 55 Bell, suction
Sand guard protection
64 Collar protective 2922 64 Collar, protecting
collar
66 Nut adjusting 2909 Adjusting nut 66 Nut, shaft, adjusting
66 Nut head shaft 2909 Adjusting nut 66 Nut, shaft, adjusting
70 Coupling shaft (threaded) 7119 Screwed coupling 70 Coupling, shaft
70 Coupling shaft (keyed) 7020 Shaft coupling 70 Coupling, shaft
71 Stand driver 3160 Driver pedestal
73 Gasket top column 4590.# Gasket
73 Oring top column (73a) 4610.# O-ring
77 Tank oil 3800 Lubricator 77 Lubricator
79 Bracket oil tank 3831 Lubricator bracket
83 Box stuffing 4110 Stuffing box housing 83 Box, stuffing
85 Tube enclosing 1917.# Shaft enclosing tube 85 Tube, shaft enclosing
Oring f/oil lube discharge
89 4610.# O-ring
case
89 Seal oil 4305 Shaft seal ring

Page 69 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

Housing bearing threaded


99 3240 Bearing carrier
lineshaft
101 Column pipe 1350 Column pipe 101 Pipe, column
Bearing, line
103 Bearing threaded lineshaft 3050.# Connector bearing 103
shaft,enclosing
Bearing sleeve
117 4132 Stuffing box bushing 63 Bushing, stuffing box
throttle/bushing
125 Plug pipe grease plug 6578.# Threaded plug
131 Guard coupling 7450 Coupling guard
171 Bushing auxiliary throttle 4140 Auxiliary seal
191 Coupling column threaded 6850 Pipe coupling 191 Coupling, column pipe
301 Nut enclosing tube 4110 Stuffing box housing
301 Nut packing injection/lube 4110 Stuffing box housing
302 Plate tube tension 1220 Cover 185 Plate, tube, tension
304 Head discharge 1370 Discharge head 187 Head, surface discharge
304 Plate surface 1370 Discharge head 105 Elbow, discharge
305 Flange top column 189 Flange, top column
Coupling column threaded
306 6850 Pipe coupling 191 Coupling, column pipe
(duplicate to 191)
Retainer, bearing, open
307 Retainer bearing 3250 Bearing support 193
line shaft
308 Tube enclosing top 1917.# Shaft enclosing tube
309 Case discharge 1140 Discharge casing 197 Case, discharge
309 Spool discharge 1140 Discharge casing
310 Bowl 1170.1 Pump bowl 199 Bowl, intermediate
Clamping ring impeller
311 Collet drive 2484 84 Collet, impeller lock
bushing
311 Collet threaded
312 Ring thrust split coupling 7410 Coupling ring 86 Ring, thrust, split
Ring thrust split coupling
312 2531 Split retaining ring
clamp (312b)
Loose (shaft) collar
312 Ring thrust split impeller 2520 82 Ring, thrust, retainer
shoulder ring
313 Case suction 1130 Suction casing 203 Case, suction
314 Spacer flanged 88 Spacer, coupling
315 Barrel 1100 Casing 205 Barrel or can, suction
316 Strainer suction 6531 Suction strainer 209 Strainer
319 Ring wear bowl 1500 Casing wear ring 213 Ring, bowl
Bearing threaded discharge Bearing, line
320 3050.# Connector bearing 103
case shaft,enclosing
Bearing sleeve discharge
321 3300.# Bearing, bushing 39 Bushing, bearing
case
322 Bearing sleeve bowl 3300.# Bearing, bushing 39 Bushing, bearing
323 Bearing sleeve suction 3300.# Bearing, bushing 39 Bushing, bearing
Screw cap hex/head column
325 6570.# Screw
to column
Screw cap hex/head column
326 6570.# Screw
to head
Stud threaded column to
326 6572.# Stud
head
326 Stud threaded packing gland 6572.# Stud

Page 70 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

326 Stud threaded seal housing 6572.# Stud


327 Nut hex column to column 6581.# Hexagon nut
327 Nut hex column to head 6581.# Hexagon nut
327 Nut hex packing gland 6581.# Hexagon nut
327 Nut hex seal housing 6581.# Hexagon nut
328 Screw set protective collar 6814.# Grub screw
328 Screw set stuffing box sleeve 6814.# Grub screw
330 Liner tube stabilizer
334 Screw lock adjusting nut 6570.# Screw
335 Key gib 6700.# Key
336 Stand driver f/m head
Plug pipe hex/socket
337 6578.# Threaded plug
f/discharge case
340 Housing packing
Valve shut/off f/tank oiler
341
assy.
Regulator sight feed f/tank
342
oiler assy.
Elbow vent f/enclosing tube
343
nut
Lubrication line w/fittings
344
f/tank oiler assy.
345 Grease zerk stuffing box 3853 Grease nipple
346 Slinger 2540 Oil flinger / oil deflector 40 Deflector
Oring stuffing box/throttle
347 4610.# O-ring
bush. Hsg.
348 Housing throttle/bushing 4210 Mechanical seal housing 83 Box, stuffing
349 Housing seal 4212 Seal plate 83 Box, stuffing
350 Stabilizer tube
Screw cap hex/head driver
351 6570.# Screw
adapter
Screw cap hex/head driver
352 6570.# Screw
stand
353 Nut hex driver stand 6581.# Hexagon nut
Stud threaded throttle
354 6572.# Stud
bushing housing
Nut hex throttle bushing
355 6581.# Hexagon nut
housing
Screw cap hex/head bowl to
356 6570.# Screw
discharge case
Nut hex bowl to discharge
357 6581.# Hexagon nut
case
Screw cap hex/head bowl to
358 6570.# Screw
bowl
359 Pin lock threaded/bowl 2923.# Pin
Screw cap hex/head column
360 6570.# Screw
to discharge case
Nut hex column to discharge
361 6581.# Hexagon nut
case
363 Nut hex flanged coupling 6581.# Hexagon nut
Screw cap socket/head
364 6579.# Socket head cap screw
flanged coupling
366 Screw set lineshaft sleeve 6814.# Grub screw

Page 71 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

369 Ring flow


370 Sleeve stuffing box 2450 Shaft sleeve
371 Oring stuffing box sleeve 4610.# O-ring
372 Stud threaded barrel 6572.# Stud
373 Nut hex barrel 6581.# Hexagon nut
374 Oring barrel 4610.# O-ring
Gasket suction f/adapter
377 4590.# Gasket
column
378 Gasket discharge 4590.# Gasket
Screw cap hex/head
379 6570.# Screw
discharge
380 Nut hex discharge 6581.# Hexagon nut
381 Screw cap hex/head motor 6570.# Screw
382 Nut hex motor 6581.# Hexagon nut
383 Cap lubricator tank
384 Band lubricator tank
385 Bolt stove f/tank oiler assy.
386 Nut hex f/tank oiler assy. 6581.# Hexagon nut
Lubrication line f/tank oiler
387 3840 Lubrication line
assy.
Fitting compression elbow
388
f/tank oiler assy.
Fitting compression straight
389
f/tank oiler assy.
390 Bearing assembly (ag)
392 Nipple pipe pre-lube
393 Valve gate pre-lube
394 Pin lifting f/head 2923.# Pin
395 Ring retaining f/head
396 Clip safety f/tube nut
397 Screw cap hex/head tube nut 6570.# Screw
Adapter column flanged to
399 1140 Discharge casing
flanged
Screw cap hex/head adapter
400 6570.# Screw
column
401 Nut hex adapter column 6581.# Hexagon nut
Bearing rubber cutless
402 3300.# Bearing, bushing
discharge case
Adapter column flanged to
403 1140 Discharge casing
threaded
405 Oring ingerseal 4610.# O-ring
409 Adapter driver f/m head
412 Stud threaded base plate 6572.# Stud
413 Nut hex base plate 6581.# Hexagon nut
414 Plug pipe head pre-lube 6578.# Threaded plug
Plug pipe head inspection
415 6578.# Threaded plug
hole
416 Plug pipe head pressure tap 6578.# Threaded plug
Screw cap hex/head coupling
417 6570.# Screw
guard

Page 72 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

418 Washer flat coupling guard


Plug pipe stuffing box relief
419 6578.# Threaded plug
line
420 Washer flat column
421 Clip strainer
422 Screw cap hex/head strainer 6570.# Screw
Screw mach submersible
422 6570.# Screw
strainer
424 Plate serial
425 Screw drive 6570.# Screw
426 Jackscrew bowl to bowl 6575.# Jack screw
Jackscrew discharge case to
427 6575.# Jack screw
column
428 Pin impeller wear ring 2923.# Pin
429 Pin bowl wear ring 2923.# Pin
430 Oring bowl 4610.# O-ring
431 Oring column 4610.# O-ring
Oring f/oil lube discharge
432 4610.# O-ring
case
433 Key keyed/coupling 6700.# Key
434 Ring retaining keyed/coupling 2530 Retaining ring
435 Stud thrust keyed/coupling 6572.# Stud
Oring reinforcing tube to
436 4610.# O-ring
suction case
437 Tube reinforcing
438 Oring reinforcing tube 4610.# O-ring
439 Ring reinforcing
Oring top injection tube to
440 4610.# O-ring
housing
Coupling column threaded
441 6850 Pipe coupling
f/suction
442 Housing bearing stand
443 Retainer oil
444 Bearing ball 3010 Anti-friction bearing
445 Spacer bearing
446 Bearing ball top
447 Stem bearing
Pin non-reverse f/4b-100 &
448
100
449 Spring compression f/4b-100
450 Cap bearing stem
451 Plate lube instructions
Screw drive lube instruction
452 6570.# Screw
plate
453 Nipple pipe level indicator
454 Tee pipe level indicator
455 Plug pipe level indicator 6578.# Threaded plug
456 Gauge oil level
457 Cap pipe level indicator

Page 73 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

458 Guard bearing stand


459 Sleeve seal 2445 Shaft sleeve
Seal, mech. Stationary/
460 Seal mechanical 4200 Mechanical seal 65/80
rotating elements
461 Collar drive
462 Guard cable f/submersible 8361 Cable guard
463 Plug upthrust (submersible)
464 Screw set upthrust plug 6814.# Grub screw
Stud threaded submersible
465 6572.# Stud
dr. Adapter to suct. Case
Nut hex submersible dr.
466 6581.# Hexagon nut
Adapter to suct. Case
467 Coupling motor submersible 7010 Drive coupling 70 Coupling, shaft
Key submersible motor
468 6700.# Key
coupling
469 Jackscrew motor 6575.# Jack screw
470 Washer flat tail water strainer
471 Coupling flanged assembly 7113 Rigid coupling
472 Cone diffusion
473 Jackscrew stuffing box 6575.# Jack screw
474 Clamp coupling guard
475 Valve check f/submersible 6301 Non-return valve
476 Thrust stand driver/stand 3160 Driver pedestal
Thrust stand coupling flg
477 7112 Flexible coupling
flexible
478 Thrust stand cap upper 3260.2 Bearing cover
Thrust stand screw cap
479 6570.# Screw
hex/hd upper/cap
480 Thrust stand grease zerk cap 3853 Grease nipple
Thrust stand fitng pipe plug
481 6578.# Threaded plug
upper/cap
Thrust stand oil/sleeve or
482 2470 Centring sleeve
thrust/sleeve
483 Thrust stand cap lower 3260.1 Bearing cover
Thrust stand screw cap
484 6570.# Screw
hex/hd lower/cap
Thrust stand fitng pipe plug
485 6578.# Threaded plug
lower/cap
487 Thrust stand key driver 6700.# Key
488 Thrust stand key pump shaft 6700.# Key
Thrust stand key thrust
489 6700.# Key
sleeve
490 Ring retaining teflon bearings
491 Bowl w/wr 1170.2 Pump bowl 199 Bowl, intermediate
492 Impeller w/wr 2200 Impeller 2 Impeller / propeller
Bell suction w/wr & case Suction bell / suction
493 1310/1130 55 Bell, suction
suction w/wr casing
Stud threaded bowl to
494 6572.# Stud
bowl/bell
495 Nut hex bowl to bowl/bell 6581.# Hexagon nut
496 Thrust stand vent plug 6521 Vent plug

Page 74 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

497 Thrust stand sight glass 8221 Sight glass


498 Thrust stand fitng pipe plug 6578.# Threaded plug
Thrust stand fitng pipe plug
499 6578.# Threaded plug
bush redcr
500 Thrust stand bearing housing 3200 Bearing housing
Thrust stand o-ring f/bearing
501 4610.# O-ring
housing
Thrust stand screw cap
502 6570.# Screw
hex/hd dr/stand to brg/hsg
Thrust stand fitng pipe plug
503 6578.# Threaded plug
hex/sckt flush seal side
Thrust stand fitng pipe plug
504 6578.# Threaded plug
hex/sckt flush seal top
505 Thrust stand bearing spindle 2471 Bearing adapter sleeve
506 Thrust stand lockwasher 6541 Lock washer
507 Thrust stand locknut 6580 Nut
508 Thrust stand oil impeller 4223 Pumping ring
Thrust stand o-ring f/bearing
509 4610.# O-ring
housing cap
510 Thrust stand seal labyrinth 4305 Shaft seal ring
Thrust stand screw cap
511 6579.# Socket head cap screw
sockt/hd adjusting nut

Page 75 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

NOTES:

Page 76 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19

FLOWSERVE REGIONAL
Your Flowserve factory contacts: SALES OFFICES:

USA and Canada


Flowserve Corporation
5215 North O’Connor Blvd.,
Suite 2300
Irving, Texas 75039-5421 USA
Telephone +1 937 890 5839

Europe, Middle East, Africa


Flowserve Corporation
Parallelweg 13
4878 AH Etten-Leur
The Netherlands
Telephone +31 76 502 8100

Latin America
Flowserve Corporation
Martin Rodriguez 4460
B1644CGN-Victoria-San
Fernando
Telephone +54 11 4006 8700

Asia Pacific
Flowserve Pte. Ltd
Your local Flowserve representative:
10 Tuas Loop
Singapore 637345
Telephone +65 6771 0600

To find your local Flowserve representative please


use the Sales Support Locator System found at
www.flowserve.com

Page 77 of 77 flowserve.com

You might also like