VTP-VPC Manual 71569224 01-2019 (G) A4
VTP-VPC Manual 71569224 01-2019 (G) A4
VTP-VPC Manual 71569224 01-2019 (G) A4
CONTENTS
PAGE PAGE
1 INTRODUCTION AND SAFETY ....................... 4 6 MAINTENANCE ............................................... 47
General ............................................................ 4 General .......................................................... 47
CE Marking and Approvals .............................. 4 Maintenance Schedule .................................. 48
Disclaimer ........................................................ 4 Spare Parts .................................................... 49
Copyright ......................................................... 4 Recommended Spares and Consumables .... 50
Duty Conditions ............................................... 4 Tools Required ............................................... 50
Safety .............................................................. 5 Fastener Installation ....................................... 51
Safety Labels Summary .................................. 8 Setting Impeller Clearance............................. 52
Specific Machine Performance........................ 8 Disassembly ................................................... 52
Noise Level ...................................................... 8 Examination of Parts ...................................... 53
Specific machine performance ................ 9 Assembly ...................................................... 56
2 TRANSPORT AND STORAGE ....................... 10 7 FAULTS; CAUSES AND REMEDIES ............. 57
Consignment receipt and unpacking ............. 10
8 DRAWINGS AND PARTS LISTS .................... 59
Handling ........................................................ 10
Cross Section: Product Lubricated VTP ........ 59
Lifting ............................................................. 10
Cross Section: Enclosed Tube VTP ............... 62
Storage .......................................................... 14
Cross Section: Suction Barrel VTP ................ 65
Recycling and End of Product Life ................ 14
General Arrangement Drawing ...................... 68
3 DESCRIPTION ................................................ 14
9 CERTIFICATION .............................................. 68
Configuration ................................................. 14
Nomenclature ................................................ 15 10 OTHER RELEVANT DOCUMENTATION AND
Design of Major Parts .................................... 17 MANUALS........................................................ 68
Performance and Operation Limits................ 21 Supplementary User Instructions ........... 68
Change Notes ........................................ 68
4 INSTALLATION ............................................... 21
Location ......................................................... 21 11 APPENDIX ....................................................... 69
Preparation .................................................... 21 Bill of Materials Reference Numbers ..... 69
Foundation/Anchor Bolts ............................... 21
Grouting ......................................................... 24
Lifting and Assembly ..................................... 24
Initial Alignment ............................................. 30
Piping ............................................................. 31
Electrical Connections ................................... 34
Final Shaft Alignment Check ......................... 34
Protection Systems ...................................... 34
5 COMMISSIONING, STARTUP, OPERATION
AND SHUTDOWN ........................................... 35
Pre-commissioning Procedure ...................... 35
Pump Lubricants............................................ 35
Impeller Adjustment ....................................... 38
Direction of Rotation ...................................... 42
Guarding ........................................................ 42
Priming and Auxiliary Supplies ...................... 42
Starting the Pump .......................................... 42
Operating the Pump ...................................... 45
Stopping and Shutdown ................................ 46
Hydraulic, mechanical and electrical duty .... 46
Page 2 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
INDEX
PAGE PAGE
Page 3 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 4 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Personnel qualification and training Before applying heat ensure any residual hazardous
All personnel involved in the operation, installation, liquid trapped between the impeller and pump shaft is
inspection and maintenance of the unit must be thoroughly drained out through the impeller keyway
qualified to carry out the work involved. If the to prevent an explosion or emission of toxic vapor.
personnel in question do not already possess the This must be carried out with the shaft in the vertical
necessary knowledge and skill, appropriate training position. On some pump sizes a cavity exists in the
and instruction must be provided. If required, the impeller bore so on occasions a significant volume of
operator may commission the manufacturer/supplier liquid may drain out.
to provide applicable training.
THERMAL SHOCK
Rapid changes in the temperature of the liquid within
Always coordinate repair activity with operations and
the pump can cause thermal shock, which can result
health and safety personnel, and follow all plant
in damage or breakage of components and should be
safety requirements and applicable safety and health
avoided.
laws and regulations.
HOT (and cold) PARTS
Safety action If hot or freezing components or auxiliary heating
This is a summary of conditions and actions to
supplies can present a danger to operators and
prevent injury to personnel and damage to the
persons entering the immediate area action must be
environment and to equipment. For products
Page 5 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
taken to avoid accidental contact. If complete the motor and cause cavitation. Low flow rates may
protection is not possible, the machine access must cause a reduction in pump/bearing life, overheating of
be limited to maintenance staff only, with clear visual the pump, instability and cavitation/vibration.
warnings and indicators to those entering the
immediate area. Note: bearing housings must not be Products used in potentially explosive
insulated and drive motors and bearings may be hot. atmospheres
If the temperature is greater than 80 ºC (175 ºF) or Measures are required to:
below -5 ºC (23 ºF) in a restricted zone, or exceeds · Avoid excess temperature
local regulations, action as above shall be taken. · Prevent build up of explosive mixtures
· Prevent the generation of sparks
HAZARDOUS LIQUIDS · Prevent leakages
When the pump is handling hazardous liquids care · Maintain the pump to avoid hazard
must be taken to avoid exposure to the liquid by
appropriate siting of the pump, limiting personnel The following instructions for pumps and pump units
access and by operator training. If the liquid is when installed in potentially explosive atmospheres
flammable and/or explosive, strict safety procedures must be followed to help ensure explosion protection.
must be applied. For ATEX, both electrical and non-electrical
equipment must meet the requirements of European
Gland packing must not be used when pumping Directive 94/9/EC. Always observe the regional legal
hazardous liquids. Ex requirements e.g. Ex electrical items outside the
EU may be required certified to other than ATEX e.g.
PREVENT EXCESSIVE EXTERNAL IECEx, UL.
PIPE LOAD
Do not use pump as a support for piping. Do not Scope of compliance
mount expansion joints, unless allowed by Flowserve
in writing, so that their force, due to internal pressure, Use equipment only in the zone for which it is
acts on the pump flange. appropriate. Always check that the driver, drive
coupling assembly, seal and pump equipment are
ENSURE CORRECT LUBRICATION
suitably rated and/or certified for the classification of the
(See section 5, Commissioning, startup, operation
specific atmosphere in which they are to be installed.
and shutdown.)
START THE PUMP WITH OUTLET Where Flowserve has supplied only the bare shaft
VALVE PARTLY OPENED pump, the Ex rating applies only to the pump. The
(Unless otherwise instructed at a specific point in the party responsible for assembling the ATEX pump set
User Instructions.) shall select the coupling, driver and any additional
This is recommended to minimize the risk of equipment, with the necessary CE Certificate/
overloading and damaging the pump motor at full or Declaration of Conformity establishing it is suitable for
zero flow. Pumps may be started with the valve the area in which it is to be installed.
further open only on installations where this situation
cannot occur. The pump outlet control valve may The output from a variable frequency drive (VFD) can
need to be adjusted to comply with the duty following cause additional heating affects in the motor and so, for
the run-up process. (See section 5, Commissioning pumps sets with a VFD, the ATEX Certification for the
start-up, operation and shutdown.) motor must state that it is covers the situation where
electrical supply is from the VFD. This particular
NEVER RUN THE PUMP DRY requirement still applies even if the VFD is in a safe area.
Page 6 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 7 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Preventing leakage
Page 8 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
The usual approach is to control the exposure time to Typical vertical motor noise data
the noise or to enclose the machine to reduce (Hollow and Solid shafts)
emitted sound. You may have already specified a
Motor RPM Sound Sound
limiting noise level when the equipment was ordered, Frame Pressure Power
however if no noise requirements were defined, then Size. (dBA) (dBA)
attention is drawn to the following table to give an NEMA (WP- I (WP- I
enclosure) enclosure
indication of equipment noise level so that you can 180 3600 70.0 78.0
take the appropriate action in your plant. 1800 60.0 68.0
1200 & slower 55.0 63.0
Pump noise level is dependent on a number of 210 3600 70.0 78.2
operational factors, flow rate, pipework design and 1800 60.0 68.2
1200 & slower 55.0 63.2
acoustic characteristics of the building, and so the
250 3600 75.0 83.4
values given are subject to a 3 dBA tolerance and 1800 70.0 78.4
cannot be guaranteed. 1200 & slower 60.0 68.4
280 3600 75.0 83.8
Similarly, the motor noise assumed in the “pump and 1800 70.0 78.8
motor” noise is that typically expected from standard 1200 & slower 60.0 68.8
320 3600 75.0 84.0
and high efficiency motors when on load directly driving 1800 65.0 74.0
the pump. Note that a motor driven by an inverter may 1200 & slower 65.0 74.0
show an increased noise at some speeds. 360 3600 75.0 84.2
1800 65.0 74.2
If a pump unit only has been purchased for use with 1200 & slower 65.0 74.2
400 3600 80.0 89.5
customer driver, then the “pump only” noise levels in the 1800 70.0 79.5
table should be combined with the level for the driver 1200 & slower 65.0 74.5
obtained from the supplier. Consult a noise specialist if 440 3600 80.0 90.0
assistance is required in combining the values. 1800 70.0 80.0
1200 & slower 70.0 80.0
449 1800 85.0 97.8
It is recommended that where exposure approaches
1200 & slower 80.0 92.8
the prescribed limit, then site noise measurements 5000 3600 90.0 102.8
should be made. 1800 85.0 97.8
1200 & slower 80.0 92.8
The values are in sound pressure level, LpA, at 1 m 5800 3600 90.0 103.7
(3.3 ft) from the machine for “free field conditions 1800 90.0 103.7
1200 & slower 80.0 93.7
over a reflecting plane”. 6800 1800 90.0 103.9
1200 & slower 85.0 98.8
For estimating sound power level, LWA (re 1pW), add 8000 1800 90.0 104.7
17 dBA to the sound pressure value. 1200 & slower 85.0 99.7
Page 9 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 10 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Lifting of cast discharge head with Typical lift pin sizes of fabricated discharge heads.
complete/partial pump assembly Fabricated heads with discharge size mm (in.)
Cast discharge heads with attached pump 100-200 250-600 700-900
(4-8) (10-24) (28-36)
components are recommended to be lifted using lift
Pin
pins sized in accordance with the pump weights Dia. 32 (1.25) 38 (1.50) 44 (1.75)
provided on the general arrangement and/or
Weight <2300 (5000) <4500 (10000) <6800 (15000)
nameplate. Alternative lift method would be to use
minimum of two straps on the cast discharge head,
placing each strap around two ribs on the head. Pins shall be sized in accordance with the pump
weights provided on the general arrangement and/or
Typical lift pin sizes of cast discharge heads. nameplate.
Cast heads with discharge size mm (in.)
100 150 200 250 300 Fabricated discharge head with lift holes
(4) (6) (8) (10) (12) in lugs.
Pin 25 32 32 32 38
Dia. (1) (1.25) (1.25) (1.25) (1.5)
Page 11 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 12 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Two (2)
cranes are
required
Examples shown here are for illustration only. See section 2.3 1~2.3.6 for specific lifting
instructions based on design variations.
Page 13 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Storage
Make sure that hazardous substances or
Store the pump in a clean, dry toxic fluids are disposed of safely and that the correct
location away from vibration. Leave protective personal protective equipment is used. The safety
covers in place to keep dirt and other foreign material specifications must be in accordance with the current
out of pump assembly. Turn the pump at frequent regulations.
intervals to prevent brinelling of the bearings and
sticking of the seal faces, if supplied. 3 Description
When contacting Flowserve pump division for
Inspection before storage assistance, the pump and driver serial numbers will
a) Inspect the preservative coating/painted surfaces be required. Both pump and driver have unique
on the various parts. Touch up the areas as serial numbers, and these serial numbers are located
needed. on the corresponding nameplates. The pump
b) Inspect all protective covers over pump openings nameplate is affixed to the discharge head or bowl
and piping connections. If damaged, remove the assembly, and motor nameplate is affixed to the
covers and inspect interiors of the opening for any motor housing. These serial numbers must be
deposits of foreign materials or water. referenced for all product correspondences.
c) If necessary, clean and preserve the interior parts
as noted above to restore the parts to the "as
shipped" condition. Replace covers and fasten Configuration
securely. VTPs, are engineered pumps typically configured as:
d) Exercise caution with pumps exposed to weather. a) Wet pit or b) suction barrel (can) pumps. Most
Containers are not leak proof. Parts may be pumps are built with customer specific features and
coated with a residual amount of protective for applications such as water pumping stations,
coating, which will wash away if exposed to deep wells, storm water service, industrial and
elements. cryogenic applications. The pumps vary in hydraulic
type and size, and can be of open shaft or enclosed
Short term storage (up to 6 months) shaft designs depending on the application.
Follow the steps given in section 2.4.1. Select a
storage space so that the unit will not be subjected to See 3.1.1 and 3.1.2 for typical configuration
vibration, excess moisture, extreme weather representations.
conditions, corrosive fumes, or other harmful
conditions.
Some units will not require a column
Refer to the driver manufacturer’s instructions for assembly. In such cases, the bowl assembly is
proper short term procedure for the driver. connected directly to the discharge head. Vertical
turbine pumps can have single or multiple stages.
Long term or extended storage
If long-term storage is required, (more than 6
months), please contact Flowserve for special
storage instructions and warranty related information.
Page 14 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
DRIVER
DRIVER
DISCHARGE
HEAD
ASSEMBLY
DISCHARGE
HEAD
ASSEMBLY
COLUMN
ASSEMBLY
COLUMN
ASSEMBLY
BOWL
SUCTION
ASSEMBLY BARREL
(CAN)
BOWL
ASSEMBLY
Nomenclature
Pump assemblies are designated by pump models
which are specific to the hydraulics utilized for the
bowl assembly. Common bowl models are EB, EG,
EH, EJ, EK, EL, EM, EN, EP, EQ, SK, SL, SN, SP,
SR, ST, & AV. The pump size is expressed in terms
of nominal bowl diameter in inches, and those sizes
could vary from 150mm (6 in) to 1300 mm (52 in.).
Page 15 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
12 E J H-3
No. of Stages
10 HF 20
c) LF/LFL/LFH type fabricated discharge head
(Typical representation with a circular base
flange)
Nominal driver base diameter in inches
Page 16 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Drivers
A variety of drivers may be used; however, electric
d) TF type fabricated discharge head motors are most common. For the purposes of this
(Typical representation with a circular base manual, all types of drivers can be grouped into two
flange) categories.
e) UF type fabricated discharge head The shaft sealing arrangement is located in the
(Typical representation with square base plate) discharge head which contains the pumpage at the
point where the shaft exits from the liquid chamber.
Column assembly
The column assembly consists of the column pipe,
bearing, bearing retainer, and shaft assembly. The
column pipe connects the bowl assembly to the
discharge head and directs the pumped fluid to the
discharge head. Typical column assemblies are:
Page 17 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Suction strainers
a) Flanged column assembly: VTPs can also be fitted with strainers [316] to prevent
foreign particles from entering the pump. The type of
strainers and the mesh size depends on the
application. Examples are shown below. Strainers
are fastened [422] directly to the suction bell [55] or
attached using clips [421]. Cone shaped strainers
are provided with internal or external threads to
attach it to the main assembly.
a) Slip-on strainer
b) Clip-on strainer
SUCTION BELL (55)
CLIP
(421)
Bowl assemblies
The bowl assembly consists of impellers rigidly
mounted on the pump shaft coupled to an electric
motor. Impellers are cast wheels with multiple diffuser
vanes and are generally coated to meet the hydraulic
requirements. See section 8.0 for cross sectional and
part details.
Page 18 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Impellers
VTP’s are supplied with enclosed, or semi open Low pressure stuffing box
impeller types. Impellers are low, medium and high This type of packing box is fitted on to an open
capacity type designed for maximum coverage of all lineshaft for pressures less than 6.5 bar (100 psi) and
VTP applications. Impellers are cast and machined used only on W-type discharge heads (see Section
to match each order and to provide required surface 3.2.2.1 to see for W type discharge head detail).
finish to achieve hydraulic characteristics. Impellers
are dynamically balanced and held in position on the
shaft by a tapered lock collet or split ring and key. SLINGER (346)
PRESSURE
REDUCING
BUSHING (117)
Page 19 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 20 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Accessories
Accessories may be fitted when specified by the Preparation
customer. The pump should be located to allow room for access,
ventilation, maintenance and inspection with ample
Performance and Operation Limits headroom for lifting and should be as close as
This product has been selected to meet the practicable to the supply of liquid to be pumped.
specifications of the purchase order. See section 1.5.
Refer to the general arrangement drawing for the pump
The following data is included as additional information to dimensions and details.
help with the installation. It is typical and factors such as
temperature, materials and seal type may influence this General installation check-list
data. If required, a definitive statement for your particular The following checks should be made before starting
application can be obtained from Flowserve. actual installation.
Operating limits a) Make sure that motor nameplate ratings and the
power supply system match correctly.
Pumped liquid temperature 5 ºC (40 ºF) to +80 ºC (176 ºF) b) Check the sump depth and pump length match-
limits* up.
Maximum ambient Up to +40 ºC (104 ºF) c) Check the liquid level in the sump.
temperature*
Maximum pump speed refer to the nameplate
d) Check the installation equipment to be sure that it
will safely handle the pump weight and size.
*Subject to written agreement from Flowserve. e) Check all pump connections (bolts, nuts etc.) for
Special designs and materials may be available for any shipping and handling related problems.
pumps operating above and below these specified
limits. Contact Flowserve for upgrade options
available for your specific application. Always support shafting in at least
three places when lifting or installing. No installation
should be attempted without adequate equipment
4 INSTALLATION necessary for a successful installation.
Equipment operated in hazardous locations
must comply with the relevant explosion protection
regulations. See section 1.6.4, Products used in · On hollow shaft drivers, check the clutch size
potentially explosive atmospheres. against the shaft size, which must go through the
Location clutch
When equipment has been in storage for greater than 6 · On solid shaft drivers, check the motor shaft size
months, a complete inspection should be conducted in against the coupling bore size
accordance with section 2.4.3. The pump should be
located to allow room for access, ventilation,
maintenance and inspection with ample headroom for Apply thread lubricant sparingly to
lifting and should be as close as practicable to the male shaft threads only at the time of making up
supply of liquid to be pumped. Refer to the general shaft connection. Excess lubricant should be
arrangement drawing for the pump set. avoided.
Page 21 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
provision of correct foundation and installation may Grout is poured under the mounting plate and
lead to failure of the pump and, as such, would be allowed to cure per the manufacturer’s instructions
outside the terms of the warranty. before the foundation bolts are fully torqued or any
further work is done on the pump.
The foundation must consist of material that will afford
rigid support to the discharge head and will absorb Example of a typical discharge head with the
expected stresses that may be encountered in service. mounting plate
Page 22 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 23 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Leveling of the grouted soleplate with If leveling nuts are used to level the
the suction barrel assembled to the base, they must be backed off as far as possible prior
soleplate to grouting.
The suction barrel is lowered into the sump, and the
suction barrel mounting flange is installed on the
soleplate. The soleplate with the assembled suction Lifting and Assembly
barrel is shimmed to achieve the required levelness Motors may be supplied separately from the pumps.
of no greater than 0.051 mm (0.002 in.) between any It is the responsibility of the installer to ensure that
two points taken on the top surface of the suction the motor is assembled to the pump and aligned as
barrel mounting plate, and the levelness is measured detailed in section 4.5. Discharge head column
by using a precision machinist’s level. The data is to piping and the pump assembly are supplied either
be recorded for future reference. Anchor bolt nuts separately or as fully assembled depending upon the
[373] are tightened sufficient enough to hold the pump size and weight. If the parts are shipped
suction barrel with assembled suction barrel in place. separately, it is the customer’s responsibility to install
and align the pump with driver to the satisfaction of
Grout is poured under the soleplate and allowed to Flowserve’s installation instructions.
cure per the manufacturer’s instructions before the
foundation bolts are fully torqued and the pump is Installation of pumps that are shipped
installed in the suction barrel. unassembled
Page 24 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 25 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
instructions). Be sure, not to bend the shaft. b) Flush the pump inside and outside with clean
Fasten the top column flange and alignment ring if water.
supplied to bottom of head. (W heads do not have c) Clean all machined surfaces. Remove any rust
an alignment ring at the top column flange). spots found on the machined surfaces with fine
d) Use shims or wedges between the pump and emery cloth.
foundation to level the pump. The shaft must be d) Clean all threaded connections and any accessory
centered in the discharge head. equipment.
See section 4.4.4 for coupling installation on solid
shaft drivers and section 4.2.1~4.2.4 for pump leveling Installing the fully assembled pump
details. If a base plate is used, level the plate to 0.16 mm per
m (0.002 in. per ft), grout and anchor in place.
Installation of pumps that are shipped
fully assembled See sections 4.2.1~4.2.4 for pump leveling details.
Page 26 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 27 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 28 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 29 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
e) Check driver manufacturer's instructions for two line leads. To change direction of rotation on
special instructions including lubrication a two-phase motor, interchange the leads of
instructions and follow all "startup" instructions. either phase.
f) Electric drivers should be checked for rotation at f) See impeller adjustment instructions (section 5.3
this time. Make electrical connections "bump" before bolting the pump and driver half of the
motor (momentarily start, then stop) to check coupling together.
rotation. DRIVER MUST ROTATE
COUNTERCLOCKWISE when looking down at Initial Alignment
top end of motor. To change the direction of
rotation on a three-phase motor, interchange any Thermal expansion
two line leads. To change direction of rotation on
a two-phase motor, interchange the leads of either
phase. The pump and motor will normally
g) See impeller adjustment instructions (section 5.3) have to be aligned at ambient temperature and
before bolting the pump and driver half of the should be corrected to allow for thermal expansion at
coupling together. operating temperature. In pump installations
involving high liquid temperatures greater than 300°F,
Installation of solid shaft driver with the unit should be run at the actual operating
jacking screws temperature, shut down and the alignment checked
immediately.
a) Clean driver mounting flange on discharge head
and check for burrs or nicks on the register and Preparation before alignment
mounting face. Oil lightly. To ensure proper alignment the following items are
b) Center motor over pump and rotate to align very important.
mounting holes.
Electric motors: Rotate junction box into a) All machined mating surfaces (such as the
desired position. mating flanges of pump and motor) must be
Gear Drives: Rotate input shaft into desired clean and free of burrs and nicks.
position. b) Exterior strain must not be transmitted to the
c) Lower driver carefully into place. Mount the dial pump. The most common cause of trouble is
indicator base on the O.D. of the motor half forcing the piping to mate with the pump. It is
coupling. Set the indicator on the pump shaft, recommended that flexible connectors be installed
position the dial to zero being careful that the in the piping adjacent to the pump.
indicator is in direct line with one of the c) All threads should be checked for damage and
jackscrews. Record this reading then rotate the repaired if necessary. Lubricate all threaded
motor shaft and indicator 180 degrees. Record connections with a suitable thread lubricant (an
this reading being careful to note plus or minus anti-galling compound).
values. Take the difference of the two readings
and using the jackscrews move the motor one- Alignment methods
half of the difference. Repeat this step until the
Ensure pump and driver are isolated
T.I.R. reading is a maximum of 0.051mm
electrically and the half couplings are disconnected.
(0.002in.). Then repeat this step for the set of
jack screws located 90 degrees to the first set.
Once all readings are within 0.051mm (0.002in.),
The alignment MUST be checked.
tighten motor bolts and check for any movement
Although the pump will have been aligned at the
in readings.
factory it is most likely that this alignment will have
d) Check driver manufacturer's instructions for
been disturbed during transportation or handling.
special instructions including lubrication
If necessary, align the motor to the pump, not the
instructions and follow all "startup" instructions.
pump to the motor.
e) Electric drivers should be checked for rotation at
this time. Make electrical connections and
"bump" motor (momentarily start, then stop) to The motor assembly may also have to be
check rotation. DRIVER MUST ROTATE adjusted in the horizontal direction to line up the
COUNTER-CLOCKWISE when looking down at driver and shaft centers. Alignment screws are
top end of motor. To change the direction of provided to lock the motor assembly in its final
rotation on a three-phase motor, interchange any aligned position.
Page 30 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Axial offset
Angular offset
&Refer to the motor User Instructions for details.
b)
If the motor does not run in its
magnetic center the resultant additional axial force
may overload the pump thrust bearing.
c)
If the pump is handling hot liquid, the alignment must
be rechecked in warm condition of the unit. The
Parallel offset alignment of the unit shall be checked again after 200
service hours.
a) Angular Offset: The median lines of shaft Piping
intersect halfway between the ends of the two
shafts.
b) Axial Offset: Another offset is the displacement Protective covers are fitted to the pipe
of one or both of the shafts. A typical example is connections to prevent foreign particles or objects
thermal expansion. entering the pump during transportation and
c) Parallel Offset: The median lines run parallel. installation. Ensure that these covers are removed
The maximum allowable parallel offset depends from the pump before connecting pipes.
on the size of coupling and is indicated in the
instruction manual of manufacturer of coupling. Pipe work velocities
In order to minimize friction losses and hydraulic
For couplings with narrow flanges use a dial indicator noise in the pipe work it is good practice to choose
as shown in the detail to check both parallel and pipe work that is one or two sizes larger than the
angular alignment. pump suction and discharge.
Page 31 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
DISCHARGE
SUCTION
Page 32 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Typical forces and moments allowed on VTP pump flanges for Standard Applications
1.07 1.60 2.27 2.94 3.34 3.56 4.23 4.90 5.34 6.01 7.12 8.46
Fx (240) (360) (510) (660) (750) (800) (950) (1100) (1200) (1350) (1600) (1900)
1.34 2.00 2.94 3.65 4.00 4.45 5.12 5.79 6.23 7.12 8.46 9.79
Fy (300) (450) (660) (820) (900) (1000) (1150) (1300) (1400) (1600) (1900) (2200)
0.89 1.36 1.87 2.45 2.67 2.89 3.34 4.00 4.45 4.90 5.56 6.23
HF Fz (200) (300) (420) (550) (600) (650) (750) (900) (1000) (1100) (1250) (1400)
&
1.00 1.49 2.11 2.75 3.05 3.18 3.66 4.06 4.47 5.42 6.50 7.60
LF Mx (740) (1100) (1560) (2030) (2250) (2350) (2700) (3000) (3300) (4000) (4800) (5600)
0.51 0.77 1.06 1.34 1.49 1.56 1.83 2.03 2.51 2.71 3.25 3.80
My (380) (570) (780) (990) (1100) (1150) (1350) (1500) (1850) (2000) (2400) (2800)
0.75 1.15 1.54 2.09 2.30 2.37 2.71 3.05 3.39 4.07 4.88 5.70
Mz (550) (850) (1140) (1540) (1700) (1750) (2000) (2250) (2500) (3000) (3600) (4200)
1.07 1.60 2.27 2.94 3.34 3.56 4.23 4.90 5.34 6.00 7.12
Fx (240) (360) (510) (660) (750) (800) (950) (1100) (1200) (1350) (1600)
1.34 2.00 2.94 3.65 4.00 4.45 5.12 5.79 6.23 7.12 8.46
Fy (300) (450) (660) (820) (900) (1000) (1150) (1300) (1400) (1600) (1900)
0.89 1.34 1.87 2.45 2.67 2.89 3.34 4.00 4.45 4.90 5.56
Fz (200) (300) (420) (550) (600) (650) (750) (900) (1000) (1100) (1250)
(1)
TF
1.00 1.49 2.11 2.75 3.05 3.18 3.66 4.07 4.47 5.42 6.50
Mx (740) (1100) (1560) (2030) (2250) (2350) (2700) (3000) (3300) (4000) (4800)
0.51 0.77 1.06 1.34 1.49 1.56 1.83 2.03 2.51 2.71 3.25
My (380) (570) (780) (990) (1100) (1150) (1350) (1500) (1850) (2000) (2400)
0.75 1.15 1.54 2.09 2.30 2.37 2.71 3.05 3.39 4.07 4.88
Mz (550) (850) (1140) (1540) (1700) (1750) (2000) (2250) (2500) (3000) (3600)
Fx
CONTACT FLOWSERVE CUSTOMER SERVICE
Fy
Fz
UF
Mx
CONTACT FLOWSERVE CUSTOMER SERVICE
My
Mz
Units: Force (F) in kN (lbf); Moments (M) in kN-m (lbf-ft)
1. Forces and moments used for the TF head should correspond to the specific flange size. I.e. the discharge flange loads should be
based on the discharge flange size and the suction flange loads should be based on the suction flange size.
Order specific loads are located on the General Arrangement drawing for the order. Loads shown above
are maximum allowable for a typical application.
Page 33 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Pumps fitted with mechanical seals See section 5.4, Direction of rotation
Auxiliary piping to circulate the flushing liquid back before connecting the motor to the electrical supply.
into the suction is required. In case of external clean
Final Shaft Alignment Check
source requirements for pump applications such as
After connecting piping to the pump, rotate the shaft
high temperature service, contaminated fluids,
several times by hand to ensure there is no binding
oxidizing fluids, a special piping plan to carry the
and all parts are free. Recheck the coupling
clean liquid into the seal chamber with adequate
alignment, as previously described, to ensure no pipe
pressure is required and several piping plans are
strain. If pipe strain exists, correct piping.
available to suit the specific pump application.
Protection Systems
See section 5.4 for Direction of
rotation before connecting motor to the power supply. The following protection systems are
recommended particularly if the pump is installed in a
Final checks potentially explosive area or is handling a hazardous
After connecting the piping to the pump, rotate the liquid. If in doubt, consult Flowserve.
shaft several times by hand to ensure no pipe strain.
If pipe strain exists, correct piping. If there is any possibility of the system allowing the
pump to run against a closed valve or below
Electrical Connections minimum continuous safe flow a protection device
should be installed to ensure the temperature of the
Electrical connections must be made
liquid does not rise to an unsafe level.
by a qualified Electrician in accordance with relevant
local national and international regulations.
If there are any circumstances in which the system
It is important to be aware of the EUROPEAN can allow the pump to run dry, or start up empty, a
DIRECTIVE on potentially explosive areas where power monitor should be fitted to stop the pump or
compliance with IEC60079-14 is an additional prevent it from being started. This is particularly
requirement for making electrical connections. relevant if the pump is handling a flammable liquid.
It is important to be aware of the EUROPEAN If leakage of product from the pump or its associated
DIRECTIVE on electromagnetic compatibility when sealing system can cause a hazard it is
wiring up and installing equipment on site. Attention recommended that an appropriate leakage detection
must be paid to ensure that the techniques used system is installed.
during wiring/installation do not increase To prevent excessive surface temperatures at the
electromagnetic emissions or decrease the bearings, it is recommended that temperature and/or
electromagnetic immunity of the equipment, wiring or vibration monitoring is done on a regular basis.
Page 34 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
5 COMMISSIONING, STARTUP,
Pump Lubricants
OPERATION AND SHUTDOWN Other than the stuffing box lubrication, mechanical
seal and/or lineshaft lubrication, the pump will not
These operations must be carried out require further periodic lubrication. On water pumps,
by fully qualified personnel. Turn off power supply for the suction bearing on the bowl assembly should be
safety while pump commissioning is in progress. repacked when required. Pumps that pump
hydrocarbons or have carbon, rubber, epoxy or
Pre-commissioning Procedure Teflon suction bearings do not have the suction
bearings packed. If the pump will be started after a
The gland is to be filled with grease, and flush supply longer storage period, the bearings should be first
to be in place. Flush piping is to be checked for flushed and cleaned by using a suitable cleaning
leaks. Mechanical seals are to be checked for leaks, agent. It is not necessary to remove the oil sprayed
flush flow, and pressure. for short or long-term storage as this will mix up
thoroughly with the lubrication oil.
a) Pumps with the enclosing tubes and oil-lubed
bearings must be filled with the proper lubricant to
avoid running dry and to guarantee acceptable Re-checking the motor lubrication should
performance of the pump. A separate oil tank is be in accordance with the motor manufacturer’s user
attached to the pump (see detail in section 5.2.2). instructions supplied separately with the pump.
b) For can pumps check all vent connections for
complete filling of the pump. The venting Open lineshaft lubrication
procedure can take from 10 minutes up to 2 hours, Open lineshaft bearings are lubricated by the pumping
depending on the kind of fluid. fluid; however, when the static water level is greater
c) Check the direction of rotation of the pump (pump than 15 m (50 ft) below the discharge head, the
rotor uncoupled). Rotation should be counter lineshaft bearings will require pre or post-lubrication.
clockwise when viewed from the driver end. Care is to be taken to ensure that the gland or seal is
d) The pump rotor and the shaft seal must be in supplied with the required flush flow.
correct axial position.
e) Check the readiness of all auxiliary systems (seal All open lineshaft pumps where the static water level is
system, lubrication system etc.,) for startup. more than 15 m (50 ft) below the discharge head
f) All pipe work, including the internal and the should be adequately pre-lubricated before starting the
auxiliary pipe work, must be connected correctly pump.
and must be absolutely tight. Check the tightness
of all connections of the auxiliary pipe work. The Pre-lubrication duration
suction valve must be in the open position. The Allow clean flush water to flow down the shaft for
discharge valve shall be in the closed or partially sufficient time to completely wet the bearings prior to
open position as required. operation. When provided, the fittings for pre-lube
g) Turn the pump by hand, if required with the help of are located at the discharge head.
a lever, to check the free rotation of the rotor. The
rotor must turn uniformly and noiselessly. Some Typical pre-lube pipe connection
resistance may be felt due to the friction in the (examples (a) thru (d))
bearings and seals. In general, all W type cast discharge heads are
h) Check the readiness of the driver for startup. Refer provided with a standard size pipe fitting for pre-lube
to the manual for the driver to be sure that all connection. Fabricated discharge heads are not
precautions are in place to energize the motor. fitted with a special piping arrangement to allow pre-
lube liquid flow onto the shaft. This is an optional
feature for the fabricated discharge head.
Page 35 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Example (a)
TANK
PIPING MUST BE
KEPT TO LENGTH AS
MINIMUM
POSSIBLE
GATE VALVE SHOULD
WITHSTAND
MAX. DISCHARGE
PRESSURE
1" MIN PIPE
LINE
PRESSURE
GAGE
Pre-lubrication recommended tank volume for pumps started at rated RPM’s for all cases of pre-lubrication
methods suggested in this section
Depth to water level Pre-Lubrication tank size
(at the time of starting the m3 (US gal)
pump) m (ft)
More than Up to
0 9 (30) 0
9 (30) 30 (100) 0.19 (50)
30 (100) 60 (200) 0.38 (100)
60 (200) 150 (500) 0.75 (200)
Example (b)
VENT LUBRICATION
TANK
LEVEL
MAX GAUGE
LEVEL
STARTUP
LEVEL
Page 36 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Example (c)
VENT LEVEL
SWITCH
MAX
LEVEL
LUBRICATION
TANK
STARTUP
LEVEL
VENT LEVEL
GAUGE
TIME DELAY RELAY
MAX
LEVEL
LUBRICATION
TANK
STARTUP
LEVEL
Page 37 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 38 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 39 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Impeller adjustment for a solid shaft · Set the shaft in the center of the maximum
driver and minimum indicator readings both
Impeller adjustment when using solid shaft drivers is directions. If the shaft will not stay in this
accomplished in the adjustable flanged coupling position, use small wooden wedges between
located below the driver. the shaft and seal bolts to hold the shaft.
The indicators can now be removed
Adjusting adjustable flanged coupling
· Alternate method for pump with packing:
a) Assemble coupling on pump shaft and driver
Using an inside micrometer, measure the
shaft (if not installed earlier).
space between the shaft and the packing box
b) Check motor direction of rotation.
bore. Do this both parallel and perpendicular
c) Check and write down Flowserve recommended
to the discharge nozzle
impeller setting for final adjustment.
d) Pump to motor alignment and final coupling
Using the wedges center the shaft so the
· Mount two magnetic indicator bases on the measurements taken at 180 degrees to each other are
discharge head at 90 degrees to each other within 0.10 mm (0.004 in.) of being equal
· Set the indicator tips on the shaft just above (For pumps using jackscrews for motor go to
the seal and at 90 degrees to each other. step f).
(Usually parallel and perpendicular to the
discharge nozzle) push the shaft (parallel to
discharge) back and forth (without bending
shaft)
· Note and record the minimum and maximum
indicator readings. Do the same procedure
at 90 degrees to the discharge nozzle.
Page 40 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
f) On pumps using jackscrews for motor alignment, Unless otherwise specified, the allowable T.I.R.
mount the dial indicator base on the O.D. of the readings are:
motor half coupling. Set the indicator on the shaft,
position the dial to zero being careful that the · WA and WSA couplings 0.10 mm (0.004 in.)
indicator is in direct line with one of the · PA and PSA couplings 0.05 mm (0.002 in.)
jackscrews. Record this reading then rotate the
motor shaft and indicator 180 degrees. If the reading is larger than the allowable values
specified above, unbolt the pump and rotate the driver
Record this reading being careful to note plus or portion of the coupling to different hole and repeat
minus values. Take the difference of the two steps (h) and (i) until acceptable readings are
readings and using the jackscrews move the obtained.
motor one half of the difference. Repeat this step
until the T.I.R. reading is a maximum of 0.05 mm m) If a mechanical seal is used, adjust the
(0.002 in.). mechanical seal at this time.
Page 41 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 42 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 43 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Initial Starting
When adjusting the packing gland, bring both nuts
down evenly and in small steps until the leakage is Ensure flushing and/or cooling/
reduced as required. The nuts should only be heating liquid supplies are turned ON before
tightened about one half turn at a time at 20 to 30 starting the pump.
minute intervals to allow the packing to "run-in".
Under proper operation, a packing set will last a long a) If the discharge line has a valve in it, partially
time. Occasionally a new ring of packing will need to open the discharge valve closest to the pump.
be added to keep the box full. The discharge valve is intended to add sufficient
system resistance to the pump. Failure to
After adding two or three rings of packing, or when maintain pump flow rates within the limits of the
proper adjustment cannot be achieved, the stuffing pump and motor could result in severe damage.
box should be cleaned completely of all old packing b) OPEN all inlet valves.
and re-packed. c) Prime the pump & check lubrication system in
operation (check the liquid level).
Open shaft lubrication before startup
Open lineshaft bearings are lubricated by the d) Ensure all vent connections are closed
pumped fluid, and on short-coupled units defined as before starting.
less than 15 m (50 ft) long, pre- or post- lubrication is e) Check the motor connections.
usually not required. All open lineshaft pumps where f) Start pre-lubrication liquid flow on pump if
the static water level is more than 15 m (50 ft) below required.
the discharge head should be adequately pre- g) Start the pump and observe the operation. If
lubricated before startup. Refer to section 5.2. there is any difficulty, excess noise or vibration,
These units should have a non-reverse ratchet on the stop the pump immediately and refer to the
driver to prevent backspin when turning off pump. If Trouble Shooting Chart (section 7.0) to
there is no NRR, post-lubrication is also necessary. determine the probable cause.
Page 44 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
The motor bearing temperature limitations should be The number of motor start and stops
considered for its lubrication requirements. Refer to in any given time affects motor life.
the driver manufacturer’s user instructions supplied
with the pump. If documents are not found, contact
Flowserve. & If the motor is expected to experience multi
starts in any given time, please refer to the driver’s
user instructions before the pump is put into
Never mix greases containing different
operation.
bases, thickeners or additives.
Operating the Pump
Normal vibration levels, alarm and trip
Normal operating, alarm, and trip vibration levels are Venting the pump
used to identify and maintain the proper operation of
the pump. Flowserve standard vibration levels are Make sure that the pump is vented to enable
shown below. all trapped air to escape, taking due care with the
Normal allowable field vibration values hazardous or hot liquids. Under normal conditions
for vertical turbines- sump or wet pit or after the pump is fully vented and primed, it should
barrel types be unnecessary to re-vent the pump.
Vibration
Vibration
Motor rating kW (HP) velocity-
mm/sec (in/sec) RMS DISCHARGE VENT LINE
unfiltered
<200 (<268) N 5.1 (0.20) SUCTION VENT LINE
200-750 (268-1000) N 6.1 (0.24)
>750 (>1000) N 7.1 (0.28) SEALING LIQUID
SUCTION
SOURCE
Page 45 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 46 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
6 MAINTENANCE
5.10.1 Specific gravity (SG)
Pump capacity and total head in meters (feet) do not General
change with SG; however, pressure displayed on a
pressure gauge is directly proportional to SG. Power It is the plant operator's responsibility to
absorbed is also directly proportional to SG. It is ensure that all maintenance, inspection and
important to check that any change in SG will not assembly work is carried out by authorized and
overload the pump driver or over-pressurize the qualified personnel who have adequately familiarized
pump. themselves with the subject matter by studying this
manual in detail. (See also section 1.6.)
5.10.2 Viscosity
For a given flow rate the total head reduces with Any work on the machine must be performed when it
increased viscosity and increases with reduced is at a standstill. It is imperative that the procedure
viscosity. Also for a given flow rate the power for shutting down the machine is followed, as
absorbed increases with increased viscosity, and described in section 5.9.
reduces with reduced viscosity. It is important that
checks are made with your nearest Flowserve office Guard fasteners must remain captive during
if changes in viscosity are planned. dismantling of guards as described in section 5.5
5.10.3 Pump speed On completion of work all guards and safety devices
Changing pump speed effects flow, total head, power must be re-installed and made operative again.
absorbed, NPSHR, noise and vibration. Flow varies in
direct proportion to pump speed, head varies as speed Before restarting the machine, the relevant
ratio squared and power varies as speed ratio cubed. instructions listed in section 5, Commissioning, start
The new duty, however, will also be dependent on the up, operation and shut down must be observed.
system curve. If increasing the speed, it is important
therefore to ensure the maximum pump working Oil and grease leaks may make the ground
pressure is not exceeded, the driver is not overloaded, slippery. Machine maintenance must always
NPSHA > NPSHR, and that noise and vibration are begin and finish by cleaning the ground and the
within local requirements and regulations. exterior of the machine.
5.10.4 Net positive suction head (NPSH A) If platforms, stairs and guard rails are required for
NPSH available (NPSHA) is a measure of the head maintenance, they must be placed for easy access to
available in the pumped liquid, above its vapor areas where maintenance and inspection are to be
pressure, at the pump suction branch. carried out. The positioning of these accessories
must not limit access or hinder the lifting of the part to
NPSH required (NPSHR) is a measure of the head be serviced.
required in the pumped liquid, above its vapor pressure,
to prevent the pump from cavitating. It is important that When air or compressed inert gas is used in the
NPSHA > NPSHR. The margin between NPSHA > maintenance process, the operator and anyone in the
NPSHR should be as large as possible. If any change vicinity must be careful and have the appropriate
in NPSHA is proposed, ensure these margins are not protection.
significantly eroded. Refer to the pump performance
curve to determine exact requirements particularly if Do not spray air or compressed inert gas on skin.
flow has changed.
Do not direct an air or gas jet towards other people.
If in of assistance, please consult your nearest
Flowserve office for advice and details of the Never use air or compressed inert gas to clean
minimum allowable margin for your application. clothes.
5.10.5 Pumped flow Before working on the pump, take measures to
Flow must not fall outside the minimum and prevent an uncontrolled start. Put a warning board
maximum continuous safe flow shown on the pump on the starting device with the words:
performance curve and or data sheet. "Machine under repair: do not start".
Page 47 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
With electric drive equipment, lock the main switch Routine inspection (daily/weekly)
open and withdraw any fuses. Put a warning board
on the fuse box or main switch with the words:
The following checks should be
"Machine under repair: do not connect".
made and the appropriate action taken to remedy
any deviations.
Never clean equipment with inflammable solvents or
a) Check operating behavior; ensure noise,
carbon tetrachloride. Protect yourself against toxic
vibration and bearing temperatures are normal.
fumes when using cleaning agents.
b) Check that there are no abnormal fluid or
Maintenance Schedule lubricant leaks (static and dynamic seals) and
that any sealant systems (if fitted) are full and
operating normally.
It is recommended that a maintenance plan c) Check that shaft seal leaks are within acceptable
and schedule is adopted, in line with these User limits.
Instructions, to include the following: d) Check the level and condition of lubrication oil.
a) Any auxiliary systems installed must be On grease lubricated pumps, check running
monitored, if necessary, to ensure they function hours since last recharge of grease or complete
correctly. grease change.
b) Gland packings must be adjusted correctly to e) Check any auxiliary supplies e.g. heating/cooling
give visible leakage and concentric alignment of (if fitted) are operating correctly.
the gland follower to prevent excessive f) Refer to the manuals of any associated
temperature of the packing or follower. equipment if routine checks needed.
c) Check for any leaks from gaskets and seals. The
correct functioning of the shaft seal must be Periodic inspection (every 6 Months)
checked regularly.
d) Check bearing lubricant level, and if the hours
run show a lubricant change is required. a) Check foundation bolts for
e) Check that the duty condition is in the safe security of attachment and corrosion.
operating range for the pump. b) Check pump operation hours to determine if
f) Check vibration, noise level and surface bearing lubricant shall be changed.
temperature at the bearings to confirm c) The coupling should be checked for correct
satisfactory operation. alignment and worn driving elements.
g) Check dirt and dust is removed from areas
around close clearances, bearing housings and
motors.
& Refer to the manuals of any associated
equipment for periodic checks needed.
h) Check coupling alignment and re-align if
necessary. Re-lubrication
Our specialist service personnel can help with Pump lubrication
preventative maintenance records and provide In general, VTPs that are product lubricated will not
condition monitoring for temperature and vibration to require further periodic lubrication. Stuffing box and
identify the onset of potential problems. mechanical seal needs flow of flush. Enclosed line
shaft pumps have to be provided with the required oil
If any problems are found the following sequence of quantity for an oil lubed system and the injection lube
actions should take place: flow at the required pressure for injection lubed
a) Refer to section 8, Faults; causes and remedies, systems.
for fault diagnosis.
b) Ensure equipment complies with the Driver lubrication
recommendations in this manual.
Contact Flowserve if the problem persists. &Refer to driver manufacturer’s User
Instructions supplied with the pump.
Page 48 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Inspect shaft or sleeve for score marks or rough spots. For all repair instructions please call
Be sure by-pass holes (if supplied) are not plugged. Flowserve representative or customer service with
Repair or replace badly worn shaft or sleeve. the order no. and unit details for specific repair
instruction literature.
If wear is minor dress down until smooth and
concentric. Clean box bore. All repair work to be carried out by trained and
authorized personnel only. Flowserve’s written
Oil inside and outside of replacement rings lightly and permission may be required for any
install in box, staggering joints 90 degrees. Be sure to disassembly/repair of the pump that is still under
replace lantern ring in proper position when used. warranty.
Spare Parts
Replace gland and tighten nuts finger tight. The
packing gland must never be tightened to the point Ordering of spares
where leakage from the packing is stopped. Flowserve keep records of all pumps that have been
supplied. When ordering spare parts, we need the
A small amount of leakage is required for packing following information:
lubrication.
1. pump type and pump size
Packing ring sizes vary with the shaft diameter. 2. serial number of the pump
Packing ring size information are as follows. 3. number of the required spare parts
4. reference number and name of the part as listed
in the part list or in the sectional drawing
Page 49 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Class I minimum
Suggested for Domestic Service when pump is
handling clean non-corrosive liquids and where
interruptions in service are not important.
Class II average
Suggested for Domestic Service when pump is
handling abrasive or corrosive liquids and where some
interruptions in continuity of service are not
objectionable.
Page 50 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Fastener Installation
Fastener Torques
Order specific torque values are located on the “As
Build Cross Sectionals” when provided.
Page 51 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Fastener Lubrication
Lubrication is to be used on all fasteners unless
stated otherwise. Lubrication used should be
Setting Impeller Clearance
Please see section 5.3 for specific instructions on
compatible with the pump application. Common
impeller adjustment.
example of lubrication is anti-seize.
Disassembly
Refer to manufacturer specific instructions
for lubrication requirements for all non-pump
manufacture based fasteners. i.e. motor, mechanical Refer to section 1.6, Safety, before
seal, gear drives, thrust pots, etc. dismantling the pump.
Page 52 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Examination of shaft/s
Check the shafts for straightness, pitting and wear.
Remove all burrs or nicks. Shaft damage is usually
best corrected by replacing the shaft.
Page 53 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Shaft/bearing clearance
Shaft Shaft Bearing When attempting to rework any part,
Size Diameter/Tolerance Clearance extreme care must be taken to maintain alignment of
mm Min Dia- Max Dia (Max/Min)
(in) mm mm
mating parts and ensure “as new” tolerances.
(in) (in)
25.40 25.35 25.40 0.28/0.13 The inspection, disassembly of bowl assembly
(1.000) (0.998) (1.000) (0.011/0.005) requires expertise and tools to perform the job
31.75 31.70 31.75 0.35/0.15 correctly. It is recommended to seek the services of
(1.250) (1.248) (1.250) (0.012/0.006)
38.10 38.05 38.10 0.33/0.18
Flowserve trained technicians to inspect and repair
(1.500) (1.498) (1.500) (0.013/0.007) bowl assemblies.
42.86 42.81 42.86 0.36/0.18
(1.690) (1.685) (1.687) (0.014/0.007) Inspection of enclosed impellers
49.21 49.16 49.21 0.38/0.23 a) Clear all passageways and check for signs of
(1.940) (1.935) (1.937) (0.015/0.008)
55.56 55.51 55.56 0.41/0.23
damage from abrasion or corrosion. Replace an
(2.190) (2.185) (2.187) (0.016/0.009) impeller that shows signs of excessive wear.
61.91 61.86 61.91 0.41/0.23
(2.440) (2.435) (2.437) (0.016/0.009) b) Check impeller running clearances against “as
68.26 68.21 68.26 0.43/0.23 new” tolerances listed in the section 0. If the
(2.690) (2.685) (2.687) (0.017/0.009) clearances exceed the maximum tolerances
74.61 74.56 74.61 0.43/0.23 shown by more than 50%, the new wear rings
(2.940) (2.935) (2.937) (0.017/0.009) should be installed to obtain correct tolerances.
82.55 82.47 82.55 0.46/0.25
(3.250) (3.247) (3.250) (0.018/0.010) c) If the original unit was furnished with bowl and
88.90 88.82 88.90 0.48/0.28 impeller wear rings, they may be pressed or
(3.500) (3.497) (3.500) (0.019/0.011)
95.25 95.17 95.25 0.53/0.35 machined off.
(3.750) (3.747) (3.750) (0.021/0.012)
101.60 101.58 101.60 0.56/0.33 Please note that certain repairs may require special
(4.000) (3.997) (4.000) (0.022/0.013) skills and it is recommended to contact Flowserve
114.30 114.22 114.30 0.58/0.35 authorized service center before attempting any such
(4.500) (4.497) (4.500) (0.023/0.014)
127.00 126.92 127.00 0.61/0.38 repairs.
(5.000) (4.997) (5.000) (0.024/0.015)
See wear ring tolerance chart in section 0.
Bronze, epoxy, carbon and hard-backed rubber
bearings are pressed into their respective bores. They Inspection of semi-open impellers
can either be pressed out or machined on the inside a) Clear all passageways and check for signs of
diameter until the wall is thin enough to collapse. damage from abrasion or corrosion.
b) Replace any impeller, which shows signs of
Some rubber bearings are the snap-in or glue-in type. excessive wear. If the bowl faces or impellers
These can be removed by prying inward on the are worn slightly (grooves in either impeller or
outside of the bearing to collapse it. bowl under 0.79 mm (1/32 in.)), they can be
corrected by re-facing the impeller and bowl.
If the bearing bore of the housing is heavily scarred or 0.79 mm (1/32 in.) is the maximum that can be
corroded, the part should be replaced or reworked to machined off without harm to the hydraulic
provide a true bore for the bearing. performance of the pump.
c) The machining must match the face angle and
Replacement bearings are designed to be pressed should be re-faced by an authorized Flowserve
into housings so bores will shrink to "as new" repair facility or replaced.
tolerances. Measure the bore of bearings after
pressing and ream as necessary to assure "as new" If the impeller has a balance ring on the topside (side
tolerances. opposite pumping vanes) running clearances must
be checked.
Inspection of bowl assembly
Please see section 6.9.4 for wearing ring tolerance
When repairing a bowl assembly that has chart for enclosed impellers.
been in service for several years, the physical
condition or strength of all parts such as cap screws,
bowls and bowl threads must be carefully checked.
Page 54 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 55 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Assembly
To assemble the pump assembly, consult the typical
sectional drawings or the “as built cross sectional”
when provided.
Page 56 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
l l l l Impeller not adjusted or loose on shaft. See PART/2-Section A7 for proper impeller adjustment.
l l l Suction lift too high or level too low.
Check NPSHa>NPSHr, proper submergence, losses at
Insufficient margin between suction strainers/fittings.
l l l l
pressure and vapor pressure.
l l l Excessive amount of air or gas in liquid. Check and purge pipes and system.
l Line check valve backward/stuck. Reverse chuck valve /free the valve.
l Unit running backwards. See start up instruction. Check motor phase/wiring
l l l Air or vapor pocket in suction line. Check suction line design for vapor pockets.
l l Air leaks into suction line. Check suction pipe is airtight.
l l l l Intake strainer or impeller plugged or pump Start and stop several times or use line pressure if
in mud or sand. available to back flush or pull pump to clean.
l l l Inlet of suction pipe insufficiently
Check out system design.
submerged.
l l l Speed too low. Consult Flowserve.
l l Speed too high. Consult Flowserve.
Total head of system higher than differential
l l l
head of pump.
Check system losses or consult Flowserve.
Total system head is lower than pump
l
design head.
l l Specific gravity of liquid different from Check and consult Flowserve.
design.
Check the pump design for the type of liquid to be
l l l l Viscosity of liquid differs from the designed. handled. Consult Flowserve.
l l Operation at very low capacity. Measure. Check minimum permitted. Consult Flowserve.
Measure value and check maximum permitted. Consult
l l l l Operation at high capacity.
Flowserve.
B. MECHANICAL PROBLEMS
Check the flange connections and eliminate strains using
l l l l l l Misalignment due to pipe strain.
elastic couplings or a method permitted.
Improperly designed foundation and/or Check setting of base plate. Tighten, adjust, grout base as
l
loose fasteners. required. Check fasteners and torque.
Page 57 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
FAULT SYMPTOM
Pump overheats and seizes
ß Bearings have short life
l l Mechanical seal was run dry. Check mechanical seal/flush supply/pump and repair.
Check method of assembly, possible damage or state of
l l l Internal misalignment due to improper
cleanliness during assembly. Check and consult
repairs causing impeller to rub.
Flowserve, if necessary.
Excessive thrust caused by a mechanical Check wear condition of impeller, its clearances and liquid
l l l
failure inside the pump. passages.
l l Excessive grease in ball bearings. Check method of re-greasing.
Check hours run since last change of lubricant, the
l l Lack of lubrication for bearings.
schedule and its basis.
Improper installation of bearings (damage Check method of assembly, possible damage or state of
l l
during assembly, incorrect assembly, wrong cleanliness during assembly and type of bearing used.
type of bearing etc.). Remedy and consult Flowserve, if necessary.
l l Damaged bearings due to contamination. Check contamination source and replace bearings.
C. MOTOR/ELECTRICAL PROBLEMS
l l l l l Wrong direction of rotation. Reverse 2 phases at motor terminal box.
l Check nameplate for voltage and current rating.
Motor Protector open.
Replace faulty motor protectors.
l Line voltage not correct/faulty control
Check wiring diagram.
box/wiring/low voltage.
l Blown fuse/breaker open/dead motor/short
Check/repair or replace fuses/breakers.
or loose connection.
l l Motor running on 2 phases only. Check supply and fuses.
l l l Motor running too slow. Check motor terminal box connections and voltage.
Page 58 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
SEE
SECTION
8.1.2
FOR PART
DETAILS
Page 59 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
(ASSEMBLY)
REF. NO. 471
314
425
424
304
349
131
354
418
355
417
347
326A
416
327A
117
416
348
431
327
307
326
39
14
366
12A
325
327
101
307
39
14
366
Page 60 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
310
358
311
310
358
311
2
55
358
64 422
328
323 316
125
Page 61 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 62 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
(ASSEMBLY)
382
384 ELECTRIC MOTOR
383 469
381
77
79 (ASSEMBLY)
REF. NO. 471
386
385
304
343
341
425
131 418 424
342 417 301
89
39
388 (ASSEMBLY)
414
387
389 397
396 13
(ASSEMBLY)
REF. NO. 344 354
302
12A
85
103
374
327 431
326
307
85
103
85
Page 63 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
103
101
103
85
431
361 309
354 89
427
357
321 430
354 310
426 369
6
312
2
(ASSEMBLY) 26
32
REF. NO. 492 430
8
357 310
(ASSEMBLY)
358A 429
REF. NO. 491
426 319
322 428
312
26
2
(ASSEMBLY) 430
32
REF. NO. 492 55
8 (ASSEMBLY)
429
357 REF. NO. 493
319
358A
428
426
64
328 422
323 316
125
Page 64 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
SEE
SECTION
8.3.2
FOR PART
DETAILS
Page 65 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
ELECTRIC MOTOR
382
(ASSEMBLY)
REF. NO. 471
381
304
131 425
418 424
417 349
326A
354
327A
355
347
416
117
348
372
412
373
413
374
23
327 431
326 307
39
101
Page 66 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
327
326
354 430
355 309
426 6
430
428 310
8* (ASSEMBLY)
REF. NO. 491
*
319
(ASSEMBLY)
2 429
REF. NO. 492
32
8 430
355 310
354 429
426 (ASSEMBLY)
319
REF. NO. 491
322 428
428 *
319
8* 429
(ASSEMBLY)
2
REF. NO. 492 430
32
310
8 (ASSEMBLY)
429
355 REF. NO. 491
319
354
428
426
322
312 26
2 430
(ASSEMBLY) 55
32
REF. NO. 492 (ASSEMBLY)
8 429
REF. NO. 493
355 319
354 428
426
323
26
315 *
312 312
Page 67 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
9 CERTIFICATION
Certificates determined from the Contract
requirements are provided with these instructions
where applicable. Examples are certificates for CE
marking and ATEX markings etc. If required, copies
of other certificates sent separately to the Purchaser
to be retained along with these User instructions.
Page 68 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
11 APPENDIX
Bill of Materials Reference Numbers
Europump
Current system Hydraulic institute
Ref. # Ref. # terminology 1995 Ref. #
description 2000 description
description
2 Impeller 2200 Impeller 2 Impeller / propeller
2 Impeller 2210 Impeller, suction stage 2 Impeller / propeller
6 Shaft pump 2110 Pump shaft 6 Shaft, pump
8 Ring wear impeller 2300 Impeller wear ring 8 Ring, impeller
10 Shaft head 2130 Top shaft / head shaft 10 Shaft, head
Intermediate shaft, drive
12 Shaft line 2120 12 Shaft, line
shaft
12 Shaft top (12a) 2130 Top shaft / head shaft 12 Shaft, line
13 Packing 4130 Packing 13 Packing
14 Sleeve lineshaft 3400 Bearing sleeve
17 Gland packing split 4120 Stuffing box gland 17 Gland
23 Plate base 6110 Base plate 129 Sole plate
24 Nut collet
Screw cap socket/head f/imp.
26 6579.# Socket head cap screw
Thrust ring
29 Ring lantern 4134 Lantern ring 29 Ring, lantern
32 Key impeller 6700.# Key 32 Key, impeller
39 Bearing sleeve f/tube nut 4132 Stuffing box bushing 39 Bushing, bearing
39 Bearing sleeve lineshaft 3300.# Bearing, bushing 39 Bushing, bearing
42 Coupling half driver 7200.1 Coupling half (driver) 42 Coupling half, driver
44 Coupling half driven 7200.2 Coupling half (driven) 44 Coupling half, pump
Key assembly driven coupling
46 6700.# Key 46 Key, coupling
half
46 Key driver coupling half 6700.# Key
55 Bell suction 1310 Suction bell 55 Bell, suction
Sand guard protection
64 Collar protective 2922 64 Collar, protecting
collar
66 Nut adjusting 2909 Adjusting nut 66 Nut, shaft, adjusting
66 Nut head shaft 2909 Adjusting nut 66 Nut, shaft, adjusting
70 Coupling shaft (threaded) 7119 Screwed coupling 70 Coupling, shaft
70 Coupling shaft (keyed) 7020 Shaft coupling 70 Coupling, shaft
71 Stand driver 3160 Driver pedestal
73 Gasket top column 4590.# Gasket
73 Oring top column (73a) 4610.# O-ring
77 Tank oil 3800 Lubricator 77 Lubricator
79 Bracket oil tank 3831 Lubricator bracket
83 Box stuffing 4110 Stuffing box housing 83 Box, stuffing
85 Tube enclosing 1917.# Shaft enclosing tube 85 Tube, shaft enclosing
Oring f/oil lube discharge
89 4610.# O-ring
case
89 Seal oil 4305 Shaft seal ring
Page 69 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 70 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 71 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 72 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 73 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 74 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
Page 75 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
NOTES:
Page 76 of 77 flowserve.com
VERTICAL TURBINE PUMPS (VTPs) CENTRIFUGAL PUMPS ENGLISH 71569224 – 01-19
FLOWSERVE REGIONAL
Your Flowserve factory contacts: SALES OFFICES:
Latin America
Flowserve Corporation
Martin Rodriguez 4460
B1644CGN-Victoria-San
Fernando
Telephone +54 11 4006 8700
Asia Pacific
Flowserve Pte. Ltd
Your local Flowserve representative:
10 Tuas Loop
Singapore 637345
Telephone +65 6771 0600
Page 77 of 77 flowserve.com