Series 7000 - Tolerances, Testing and Quality Control

Download as pdf or txt
Download as pdf or txt
You are on page 1of 25

GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

SERIES 7000
TOLERANCES, TESTING AND
QUALITY CONTROL

SECTION PAGE
7100 TESTING OF MATERIALS AND
WORKMANSHIP 7000-2
7200 QUALITY CONTROL 7000-12
7300 SETTING OUT AND TOLERANCES 7000-17
7400 RECTIFICATION OF EARTHWORKS AND
PAVEMENT LAYERS OUTSIDE
PERMITTED GEOMETRIC TOLERANCES 7000-19
7500 SPECIFICATIONS AND TEST METHODS 7000-20

CONTENTS OF THE GENERAL SPECIFICATIONS:


SERIES 1000 GENERAL
SERIES 2000 DRAINAGE
SERIES 3000 EARTHWORKS AND PAVEMENT LAYERS OF GRAVEL OR CRUSHED STONE
SERIES 4000 BITUMINOUS LAYERS AND SEALS
SERIES 5000 ANCILLARY ROADWORKS
SERIES 6000 STRUCTURES
SERIES 7000 TOLERANCES, TESTING AND QUALITY CONTROL

APPENDICES

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 1
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

SERIES 7000: TOLERANCES, TESTING AND 7103 GENERAL SPECIFICATIONS


QUALITY CONTROL Where in the Specifications tests on materials, tests on
completed Works and construction control tests are
called for or implied, they shall be carried out according
SECTION 7100: TESTING OF to the test methods listed in Section 7502 (a), unless
the test in question is not covered within this Section.
MATERIALS AND When a particular test is not covered by the referred
standard, then the method shall be to an equivalent
WORKMANSHIP standard called for in the contract documents or as
directed by the Engineer.
CONTENTS:
Materials shall comply with, the requirements of the
CLAUSE PAGE current edition of Specifications issued by the Uganda
7101 SCOPE 7000-2 National Bureau of Standards (US), American
7102 MATERIALS GENERALLY 7000-2 Association of State Highway and Transportation
7103 GENERAL SPECIFICATIONS 7000-2 Officials (AASHTO) or American Society for Testing
7104 MATERIALS TESTING AND ACCEPTANCE 7000-2 Materials (ASTM) or British Standard (BS), or European
7105 LABORATORY FOR THE ENGINEER 7000-3 Standards (BS EN) or where applicable, an equivalent
7106 TESTING BY THE CONTRACTOR 7000-3 Specification called for in the contract documents or as
7107 ACCEPTANCE STANDARDS OR directed by the Engineer.
MATERIALS 7000-3
7108 THE COST OF TESTING 7000-3 Other equivalent national standard specifications may
7109 TAKING AND SUBMITTING SAMPLES 7000-3 only be substituted for the above at the sole discretion
7110 TESTING METHODS 7000-3 of the Engineer.
7111 TESTING CEMENTITIOUS BINDERS AND
CONCRETE 7000-4
7112 TESTING SOILS, GRAVELS AND CRUSHED 7104 MATERIALS TESTING AND
AGGREGATE FOR EARTHWORKS AND
ACCEPTANCE
PAVEMENT LAYERS 7000-5
As soon as possible after the Contract has been
7113 TESTING BITUMINOUS BINDERS AND awarded, the Contractor shall submit to the Engineer
MIXES 7000-5 complete statements as to the origin, composition and
7114 FIELD DENSITY TESTING 7000-6
manufacture of all materials to be used in the Works
7115 TESTS OF SURFACE REGULARITY, together with a list of the suppliers from whom he
LEVELS AND LAYER THICKNESS 7000-7 proposes to purchase these materials.
7116 LABORATORY TRIALS AND SITE TRIALS 7000-8
7117 TESTS ON STRUCTURES 7000-10 Prior to delivery of materials to the job site, the
7118 MEASUREMENT AND PAYMENT 7000-11 Contractor shall submit certified test reports and
samples to the Engineer of all materials proposed for
use in the Works, whether from an outside supplier or
whether supplied by the Contractor from his own
7101 SCOPE resources. The certification(s) shall show the
This SECTION covers the tests and methods of testing appropriate test(s) for each material, the test results,
which are required for the selection and control of the and a statement that the material meets the
materials and for control of workmanship, trials and specification requirement. The Engineer's approval
construction control testing. shall be received prior to any materials being delivered
in bulk to the works.
During the progress of the Work tests shall be
conducted on materials and workmanship to ensure The Engineer may request further samples for testing,
compliance with the requirements of the Specifications. prior to and during construction to verify the quality of
the materials and to ensure conformance with the
The Contractor's attention is drawn to the provisions of applicable specifications. The Contractor shall provide
Clause 1205 in regard to his/her obligations to conduct all samples free of charge.
tests on regular basis for check of compliance with
specification requirements. The intensity of control and All equipment to be used in testing shall be calibrated at
of tests to be conducted by the Contractor is not the start of the project, and at regular intervals
specified but shall be adequate to ensure that proper throughout the project period as approved by the
control is being exercised. This process-control shall be Engineer.
detailed in a quality control management system to be
prepared by the Contractor. The Contractor shall test samples as specified from
each quarry location and borrow pit proposed for use in
the Works. The particular tests to be carried out will be
7102 MATERIALS GENERALLY determined by the function for which the Contractor
All materials shall conform to the requirements of the proposes to use the material in the Works, as
Contract, the Drawings and the Specifications. necessary to show compliance to these Specifications.
The results of these tests shall be submitted to the
All materials shall be of approved manufacture and Engineer for approval at least 14 days before the quarry
origin and the best quality of their respective kinds. or borrow pit is required for use. Should any quarry or
Unless otherwise specified such materials shall be new borrow pit prove to be unsuitable, the Contractor shall
(as compared to used or reprocessed). investigate further sites until suitable materials are
found and approved.
No materials of any description shall be used without
the prior sanction of the Engineer and any materials The Contractor’s programme shall allow sufficient time
condemned as unsuitable for use in the Works shall be for materials testing and no claim for delays or extra
removed immediately from the Site by and without costs arising out of this will be accepted.
recompense to the Contractor.
All materials supplied for use in the Works shall
conform within specified tolerances, to the quality of the

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 2
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

approved samples, which will be retained at the (c) Testing materials and products covered by
Engineer’s office until the completion of the Contract. certificates
The Engineer shall be entitled to take samples of, and
Where a material has been specified by a order tests to be made on, products and materials in
manufacturer’s trade name, the product of another respect of which certificates of compliance may be
manufacturer will be accepted provided that, in the required. The Contractor shall only be paid at the
opinion of the Engineer, it is in all respects of an appropriate rates if the costs of such tests are itemised
equivalent or higher quality. in the Bill of Quantities.

7105 LABORATORY FOR THE ENGINEER 7109 TAKING AND SUBMITTING SAMPLES
The Contractor shall facilitate independent testing by
the Engineer as he may deem necessary in accordance (a) General
with SECTION 1410. Where the Contractor is required in these Specifications
to submit samples of materials or mixtures to the
Engineer for approval prior to their being used in the
7106 TESTING BY THE CONTRACTOR Works, the use of these materials or mixtures without
The Contractor shall provide, use and maintain on the the Engineer’s written approval shall constitute default
site throughout the period of execution of the works a on the part of the Contractor, who shall be liable for the
suitable laboratory and adequate equipment operated consequence of such default. All samples shall be
by competent staff for carrying out tests required for the submitted in sufficient time for proper testing.
selection and control of the quality of materials and for
the control of workmanship in accordance with this The Engineer’s approval of any materials or mixtures
specification, in accordance with SECTION 1410. The shall in no way relieve the Contractor of his obligation to
contractor shall assume that tests will be required on all provide materials, mixtures and workmanship which
materials used in the works and on all finished work. comply with the Specifications.

The Contractor shall carry out all necessary tests and All samples for testing shall be taken from the road after
shall report to the Engineer the results of such tests completion of work on the particular layer to be tested
before submitting materials and finished work to the except as specified elsewhere in these Specifications.
Engineer for approval. In appropriate circumstances, Where specified or required by the Engineer, stratified
tests may be carried out at the place of manufacture. random sampling methods, as defined in SUBCLAUSES
7203(b) and 7204(b), shall be followed. For the testing
of layer work stratified random sampling methods shall
be used for obtaining all the sample portions and for
7107 ACCEPTANCE STANDARDS OR
determining the locations of in situ test sites.
MATERIALS
All materials used in or upon the works shall comply The method of taking samples shall be as specified in
with this Specification and the Special Specification and the appropriate sampling and testing methods listed in
shall be acceptable to the Engineer. Where so SECTION 7502 (a) or similar approved by the Engineer.
specified, the material shall comply with the US
specification named or with an alternative national The Engineer shall have full access to the Works for the
specification on the approval of the Engineer. purpose of taking samples. The Contractor shall render
any assistance necessary for taking the samples and
Similarly, where a material has been specified by shall be responsible for the reinstatement of pavement
manufacturer’s trade name, the product of another layers or other structures at the positions where the
manufacturer will be acceptable provided it is in all samples have been taken. Full compensation for
respects of equivalent or higher quality and provided rendering assistance with sampling and for
that the Engineer’s approval has been obtained. reinstatement where samples have been taken shall be
included in the rates tendered for the various items of
Samples of all materials proposed to be used shall be work tested, and no additional payment will be made in
submitted to the Engineer and shall, where required, be this respect.
tested prior to the material being delivered in bulk upon
the works. (b) Sampling frequency
Samples shall be taken for laboratory testing for each
new material encountered, or when there is a significant
7108 THE COST OF TESTING change in material properties in the opinion of the
Engineer.
(a) Process control
The cost of testing undertaken by the Contractor in The minimum sampling frequencies shall be as given in
terms of his obligations under CLAUSE 1205 for TABLE 7109/1. Samples for tests that are not mentioned
purposes of process control, including the taking of in TABLE 7109/1, but for which there are material
samples, reinstating where samples have been taken, requirements in these Specifications, shall be taken as
and all testing equipment, labour, materials, etc, shall required in the opinion of the Engineer.
be included in the rates bid for the various items of work
supplied and will not be paid for separately.
7110 TESTING METHODS
(b) Producing certificates All tests shall be conducted in accordance with the
Where the properties of materials or manufactured standard methods specified in the Specifications. Other
products are required in these Specifications to comply equivalent national standard specifications may only
with specified specifications published by a Standards substitute the prescribed test method at the sole
Authority approved by the Engineer, the Contractor discretion of the Engineer.
shall produce, when called upon to do so, certificates
from the manufacturer confirming that the materials or Where in the Specifications tests on materials, tests on
products supplied comply with the relevant completed Works and construction control tests are
specifications. All costs of providing such certificates called for or implied, they shall be carried out according
shall be borne by the Contractor. to test methods listed in SECTION 7502 (a), unless the
test in question is not covered within this Section. When

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 3
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

a particular test is not listed in SECTION 7502 (a), then is made to one of the above standards in the
the method shall be an equivalent standard called for in Specification.
the contract documents or as directed by the Engineer.
In addition to the above standard methods of testing, The Contractor shall have on the Site all the relevant
equivalent standard specifications or test methods of standards required for the work he is to undertake
other bodies may be used in these specifications if under the Contract. The Engineer shall be provided a
approved by the Engineer. copy of such standards.

In all cases the latest amendment or revision current at


the closing date of the tender is implied when reference

TABLE 7109/1
SAMPLING FREQUENCIES

Layer and nominal class of material Tests to be carried out Sampling frequency, minimum
1)
Roadbed CBR 1 sample per 10000 m2
MDD, PI, grading 1 sample per 5000 m2
Earthworks fill using soils: (G3) CBR, PI, grading 1 sample per 2000 m3
MDD 1 sample per 1000 m3
Backfill to culverts and structures CBR, PI, grading 1 sample per 500 m3
MDD 1 sample per 200 m3
Improved subgrade (G7, G15) or CBR, PI, grading 1 sample per 10000 m2
Gravel wearing course (GW)
MDD 1 sample per 5000 m2
Subbase: (G30, G45) CBR, incl. swell, grading 1 sample per 5000 m2
MDD, PI, LL, LS 1 sample per 5000 m2
Subbase: (CM, C0.7, C1.0) UCS, PI 1 sample per 5000 m2
MDD 1 sample per 5000 m2
Base course: (G60, G80) CBR, PI, grading 1 sample per 5000 m2
MDD 1 sample per 2500 m2
Base course: (C1.0, C1.5) UCS, PI 1 sample per 5000 m2
MDD 1 sample per 2500 m2
Base course using crushed aggregate: (CRS) LS, grading 1 sample per 5000 m2
MDD 1 sample per 2500 m2
Base course using crushed aggregate: (CRR) LL, LS, grading, flakiness 1 sample per 5000 m2
MDD, TFV, CBR 1 sample per 10000 m2
Base course of a bituminous mix or asphalt concrete Extraction, grading 1 sample per 10000 m2
surfacing Marshall test / Gyratory 1 sample per 5000 m2
Compaction Test
Surface treatments TFV 1 sample per 20000 m2
Grading, flakiness 1 sample per 5000 m2
Tray Test 2 1 sampler per 500 m²
The referred tests shall be carried out in accordance with standards test methods indicated in the special specifications or
other standards approved by the Engineer. Tray test shall be performed for both bitumen spraying rate and chipping
spreading rate.

It is emphasised that the Atterberg limits of soil fines 7111 TESTING CEMENTITIOUS BINDERS AND
shall be measured according to the British Standard
CONCRETE
(BS) procedures and utilise BS equipment. Other
laboratory test procedures and equipment do not give
(a) Testing aggregates for concrete
comparable results and shall not be used unless proper
Aggregates shall be regularly tested by the Contractor
correlation to BS has been carried out to the
at a frequency to the satisfaction of the Engineer as part
satisfaction of the Engineer.
of the Contractor’s process control as they are being
manufactured or brought onto the site and used or
All CBR testing shall be carried out using the three point
taken to stockpile.
method as described in SECTION 7502 (a) or other
approved at the discretion of the Engineer. All CBR
The appropriate test methods shall be those included
tests relate to material compacted to the dry density
under the respective CLAUSES of the Specifications, or
obtained using the compaction test as specified in the
any other relevant tests prescribed by the Engineer.
respective CLAUSES for material requirements. The
CBR testing shall be carried out at moisture content as
Accelerated tests shall be carried out to determine the
specified in the respective Clauses for material
potential alkali reactivity of aggregates where this is
requirements.
considered appropriate by the Engineer.

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 4
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

(b) Test for cementitious- binder content (ii) Stiff Concrete


The test method used for determining the cementitious The same procedure is followed, except that the
binder content of soils, gravels or crushed stone mixed mould is filled in three to four steps instead of in
with a chemical stabilising agent shall be determined by two. The vibration is stopped for each layer when a
the Engineer and may be any test method currently wet sheen appears.
recognised by the Engineer as being acceptable.
(g) Consistency
Where the cementitious binder content is determined, The test method described in shall apply in regard to
due allowance shall be made for the presence in the the slump test.
un-stabilised material of naturally occurring MgO or
CaO which affects the result of such tests. If the (h) Air content
standard deviation of the natural CaO plus MgO content The air content of the freshly mixed concrete shall be
of the untreated material exceeds 0.35% any tested by the method given in BS 1881, Part 106 or
determination of the cementitious- binder content shall equivalent. Air content tests shall be conducted on the
be ignored. same samples of concrete from which cubes were
made for the 28 – day compressive strength tests.
Sample holes shall be randomly (as defined in
SUBCLAUSES 7203(b) and 7204(b)) spaced transversely (i) Drilling and testing the cores
as well as longitudinally over the area to be tested, or Where sections of concrete which have failed to comply
as directed by the Engineer, and if the material is road – with the Specifications are required to be further
mixed, samples shall be taken from the top and bottom investigated by extracting and testing concrete cores,
of each hole. The minimum number of samples per test 100 mm or 150 mm cores shall be drilled and tested.
shall be 10. The sampling and testing procedure to be followed shall
be in accordance with the publication Concrete Core
(c) Canvas patch test for the spreading rate of Testing for Strength – Concrete Society Technical
cementitious binder Report No.11, published by the Concrete Society of
The following method shall be used for determining the Great Britain.
spreading rate of a chemical stabilising agent where
bulk distributors are used. The instructions of this report shall be followed for
determining the “estimated potential strength”, which
At least 10 clean canvas patches, each measuring 1.0 shall be compared with the 28 days cube strength
m x 1.0 m shall be placed flat on the road in selected specified for each type of concrete. Corrections to the
positions in relation to the bulk distributor’s track. After actual core strength to allow for excess voids, included
the stabilising agent has been spread by the bulk steel and the length :diameter ratio of cores shall be as
distributor, the canvas patches shall be carefully lifted stated in this publication, and the correction for curing
and all the material on the patches transferred to a shall be determined by the Engineer in accordance with
container and weighed. The total mass of stabilising this publication and such other information as he may
agent on each patch is then recorded and the average deem to be appropriate.
rate of application determined. Instead of canvas
patches, flat metal trays may be used for collecting the The Engineer’s decision regarding the degree to which
stabilising agent. the concrete, which is represented by the cores tested
as described above, complies with the requirements
(d) Test for mix uniformity in chemically stabilised and also regarding the properties and suitability of the
layers concrete, shall be final and binding.
Where required by the Engineer, the Contractor shall
determine the mix uniformity in chemically stabilised
layers by means of unconfined compressive strength 7112 TESTING SOILS, GRAVEL AND
tests, using an approved method.
CRUSHED AGGREGATE FOR
The Contractor shall without delay make the necessary EARTHWORKS AND PAVEMENT
arrangements to take samples in accordance with the LAYERS
requirements in the method used. Specimens of soils, gravel and crushed stone materials
in earthworks and pavement layers shall be taken in
(e) Test for initial consumption of lime accordance with CLAUSE 7104, and subjected to tests
The objective of the gravel ICL test is the control of the as prescribed for each respective layer in the relevant
pH in lime and cement stabilised soil in order to allow sections of SERIES 3000.
the possible formation of cement minerals, calcium
silica hydrate in particular, and for proper modification
to take place. It is recommended that the stabiliser to be 7113 TESTING BITUMINOUS BINDERS AND
used during construction (or the nearest equivalent)
MIXES
should be used to carry out this test.
Specimens of soils, gravel and crushed stone materials
in earthworks and pavement layers shall be taken in
(f) Determining the compressive strength
accordance with SECTION 7105. And subjected to tests
The procedure for sampling and manufacturing, storing,
as prescribed for each respective layer in the relevant
curing and testing test cubes shall be in accordance
sections of SERIES 4000.
with appropriate tests in SECTION 7502 (a).
The Engineer shall be entitled to order the Contractor to
Where specified in the Special Specifications, the
have material tested by an approved laboratory for
compaction of concrete specimens in the moulds by
compliance with all of the requirements specified, and
means of a vibrating table shall be obligatory. In such
the results of such tests shall be submitted direct to the
case the method of compaction shall be as follows:
Engineer by the testing laboratory with copies, if
requested, to the Contractor.
(i) Plastic concrete
Fill the mould halfway and vibrate it and spade it on
The cost of such tests shall be borne as specified in
all four sides with a suitable trowel to remove air
CLAUSE 7108.
bubbles. Stop the vibration as soon as a wet sheen
appears on the surface. Fill the mould and repeat
the procedure, but stop when again a wet sheet
appears on the surface.

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 5
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

7114 FIELD DENSITY TESTING same time accepting or rejecting the section or layer
concerned.
(a) General
All earthwork and pavement layers and backfill to Work on layers shall in no circumstances commence
drainage works and structures will be subject to until the preceding layer has been approved and
construction control testing by the Engineer, and the accepted by the Engineer in writing. The Contractor is
Contractor must allow for any disturbance or delays to wholly responsible for protecting and maintaining the
the sequence of his operations occasioned by such condition of the work which has been submitted for
control testing. approval.

The contractor shall request, in writing, the Engineer’s Should any layer be left unprotected for more than 24
approval for each layer of each section of earthworks hours subsequent to approval the Contractor shall
and pavement construction and backfill to drainage request re-approval of the layer and the layer will again
works and structures. Such requests shall be made only be subject to proof rolling, construction control testing,
when the Contractor is fully satisfied that the section of and tolerance checks in accordance with this
the work concerned is in the condition required by this Specification.
Specification. Such requests shall be accompanied by
the test results required in accordance with this Notwithstanding the Engineer’s approval of a layer, the
Specification. Contractor shall be responsible for making good any
subsequent damage doe to traffic, ingress of water or
The Engineer shall thereupon without undue delay any other reason and should any damage occur the
inspect the section for any visible wet spots, layer will again be subject to proof rolling, construction
laminations, heaving material (visible during compaction control testing and tolerance checks in accordance with
or on proof rolling), segregation, and for the uniformity this Specification.
of the mixing and compaction. Providing the visual
aspects are satisfactory, the Engineer shall test the (b) Testing frequency
section of the works submitted and inform the The minimum testing frequencies shall be as given in
Contractor in writing of the results of the tests at the TABLE 7114/1.

TABLE 7114/1
TESTING FREQUENCIES FOR FIELD DENSITY TESTING

Layer and nominal class of material Frequency, minimum Absolute minimum

3 tests per section and


Roadbed 1 test per 1000 m2
1 test per 50m

Earthworks fill using soils: (G3) 1 test per 200 m3 3 per section per layer

tests
Backfill to culverts and structures 2 10 m3 2 per section
per
Fill or improved subgrade layers using dump rock: (DR)
Method specification
Improved subgrade layers using gravel/soils: (G7, G15)
1 test per 1000 m2 4 per section per layer
Gravel wearing course used on gravel roads: (GW)
1 test per 1000 m2 4 per section

Subbase: (G30, G45, CM, C 0.7, C 1.0) 1 test per 750 m2 5 per section

Base course: (G60, G80, CRS, CRR) 1 test per 500 m2 6 per section
Base course of bituminous mix: (BEMIX, FBMIX, DBM40,
DBM30, 37.5, 25.0 Nominal mixes) 1 test per 500 m2 6 per section
Asphalt concrete surfacing
(AC20, AC14, AC10, 19.0, 12.5, 9.5 Nominal mixes) 1 test per 400 m2 6 per section

(c) Testing methods manufacturer’s guidelines or as required by the


If a nuclear method is used for determining density and Engineer to establish a moisture correction and any
moisture content, tests will be done at least at the same correction of density required. Check tests will be used
frequency required when using the sand replacement to update the initial calibration of the nuclear density
method but at each nuclear densometer test location, testing equipment.
the average of two readings taken at positions rotated
by 180° shall be used. A check/comparison test using (d) Field density requirements
the sand replacement method shall be carried out as The required field densities for each material type shall
required by the Engineer. be as shown in TABLE 7114/2. The values shown are
nominal values to which an assessment of the results
Initial calibration of the nuclear testing equipment shall shall be applied in accordance with SECTION 7200.
be done by carrying out at least fifty tests in parallel with
the sand replacement method for each different
material encountered.

When starting to use a new material source, or


whenever there is a change of material type, a
calibration shall be carried out in accordance with the

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 6
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

7115 TESTS OF SURFACE REGULARITY, directed by the Engineer. Measurements shall be


carried out by measuring the largest deviation from
LEVELS AND LAYER THICKNESS
true surface along the straightedge.
(a) General
Using the rolling straight edge for measuring
surface irregularities, the apparatus and testing
(i) Straight edge measurements, normal conditions
method for this shall be in accordance with testing
Measurements of surface regularity shall be carried
Method ST3 of TMH6 of South Africa.
out with a 3 m straight edge having sharp right
.
angled corners at the bottom, and shall be placed
on the road at any angle to the centreline as

TABLE 7114/2
MINIMUM FIELD DENSITY, NOMINAL VALUES

Layer and nominal class of material Field density, Lower Specification Limit

Depends on the depth below formation, reference is made to


Roadbed (after removal of topsoil etc.)
TABLE 3606/1
To be the same as adjacent layers at the same level, not less
Backfill to culverts and structures
than 93% BS-Heavy

Fill or improved subgrade layers using dump rock: (DR) Method specification

Earthworks fill using soils: (G3) (more than 300mm below


90% of BS-Heavy
formation level)

Lower improved subgrade layers using gravel/soils: (G7) 93% of BS-Heavy

Upper improved subgrade layers using gravel/soils: (G15) 95% of BS-Heavy

Gravel wearing course used on gravel roads: (GW) 95% of BS-Heavy

Subbase of natural gravel: (G30, G45) 95% of BS-Heavy

Subbase of cemented material: (CM, C0.7, C1.0) 95% of BS-Heavy

Base course of natural gravel: (G60, G80) 98% of BS-Heavy

Base course of cemented material: (C1.0, C1.5) 97% of BS-Heavy

Base course of crushed aggregate: CRS 98% of BS-Heavy

Base course of crushed aggregate: CRR 102% of BS-Heavy

96% of Marshall density, or


Base course of cold bituminous mix: (BEMIX, FBMIX)
method specifications 1)

Base course of hot bituminous mix: (DBM40, DBM30) Method specification) 1)

Base course of hot bituminous mix: (37.5, 25.0 Nominal


> 93.5 % of Max. Theoretical Density G mm
mixes)
Asphalt concrete surfacing: (AC20, AC14, AC10, 19.0, 12.5,
96% of Marshall density
9.5 Nominal mixes)

Asphalt concrete surfacing: (19.0, 12.5, 9.5 Nominal mixes) > 93.5 % of Max. Theoretical Density G mm
1) Marshall density cannot be used on coarse bituminous material types, i.e. with nominal aggregate size 30 mm or larger.
Whether or not Marshall compaction can be applied for a specific type of cold bituminous mix shall be decided by the
Engineer.

intervals shall be engraved on the sloping face and


(ii) Straight edge measurements, severe conditions numbered to indicate the positions where the
Where surface irregularities are measured on a wedge is 1.0 mm, 2.0 mm, etc, thick.
surface with a coarse surface texture in the opinion
of the Engineer, such as grooved concrete (iii) Horizontal tolerances
pavements, crushed aggregate pavement layers, At no point shall the distance between the centre-
natural gravel base course, asphalt with rolled in line and the edge of the top of a layer be less than
such chipping, seals and other like surface, the that detailed or more than 150 mm in excess of that
following procedure shall be followed: detailed.

A metal wedge of 100 mm in length and 50 mm in (iv) Shoulders


width shall be constructed with a taper of 7.5 Shoulders shall be constructed to the same
horizontal to 1.0 vertical and tapering to a feather thickness, level, crossfall and surface regularity
edge (50 mm wide). Parallel lines spaced at 7.5 mm requirements as for the adjacent pavement layers,

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 7
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

except otherwise as stated in the other contract TABLE 7115/1


documents. SURFACE REGULARITY, MEASUREMENTS WITH 3 METRE
STRAIGHT EDGE
(b) Surface regularity, straight edge measurements
The required surface regularity, measured with a 3 m Layer Maximum straight
straight edge at any angle in relation to the centreline, edge deviation (mm)
shall be within the limits shown in TABLE 7115/1.
Bituminous wearing 6
(c) Surface levels course
The maximum deviation in levels shall be as shown in Bituminous binder 7
TABLE 7115/2. course
Base course (not PM 7
materials)
Gravel wearing course 15

Subbase 30

TABLE 7115/2
SURFACE LEVELS

Layer and material class Maximum deviation in levels (mm)

High (+) Low (-)

H90 value 1) Absolute max Hmax H90 value 1) Absolute max Hmax
value value
Base course, when 10 15 10 15
followed by a seal only
Base course, when NIL NIL 10 20
followed by AC surfacing
Subbase NIL NIL 25 35

Formation NIL NIL 50 75

Gravel wearing course 15 30 15 20

1) H90 is the limit within which 90% of the measurements shall fall when assessing 50 or more measurements against the
specified level at the respective locations the measurements were taken.

(d) Surface crossfall at intervals not less frequent than 25 metres and a lot
The maximum deviation in longitudinal slope or crossfall size shall be at least 20 measurements.
shall be as shown in TABLE 7115/3. The values shown
are nominal values to which an assessment of the
results shall be applied in accordance with SECTION 7116 LABORATORY TRIALS AND SITE TRIALS
7200.
(a) Laboratory trials
Laboratory trials shall be carried out by the Contractor
TABLE 7115/3 and the Engineer on earthwork and pavement materials
SURFACE CROSSFALL which are to be used in the works in their natural state
to establish a relationship between their specified end
Maximum crossfall product requirements and properties which can be
Layer
deviation + (%) readily determined in the field for construction control
Bituminous wearing purposes.
0.25
course
Laboratory trial mixes and site trials for bituminous
Base course (not PM
0.25 mixes shall be carried out in accordance with the
materials)
requirements of SERIES 4000 of this Specification.
Subbase 0.50
For mixed materials the composition which meets the
specified requirements and is accepted by the Engineer
Formation 0.50 shall then be used in the site trials to establish that all
specified requirements of the completed pavement
Gravel wearing course 0.50 course can be achieved.

The Laboratory trials on mixed materials shall be


(e) Layer thickness undertaken, and the Contractor’s proposals based
The final compacted layer thickness measured by thereon submitted to the Engineer, at least two weeks
excavating trial pits or core drilling shall not deviate before the Contractor proposes to use the mixed
more from the specified thickness than the maximum material in the site trials.
deviations shown in TABLE 7115/4. The measurements
shall be taken at locations as directed by the Engineer

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 8
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

TABLE 7115/4 Contractor proposing to commence full scale work on


LAYER THICKNESS that layer.

Layer Maximum deviation in layer The Contractor shall compact each section of trial over
thickness (mm) the range of compactive effort the Contractor is
proposing and if appropriate, the following data shall be
T90 value 1) Absolute max recorded for each level of compactive effort at each site
Tmax value trial:
Bituminous wearing 5 10 (i) The composition and grading of the material before
course the site trial.
Bituminous base 10 15
course (not PM (ii) The composition and grading of the material
materials) including the cement, lime or bitumen content.
Base course, 10 20 (iii) The moisture content at the time of compaction and
aggregate or natural the optimum moisture content for the specified
gravel compaction.
Subbase 15 25
(iv) The type, size, tyre pressure, frequency of vibration
and the number of passes of the compaction
Improved subgrade 20 35 equipment.
layers
Gravel wearing 15 25 (v) The maximum dry density or target density as
course appropriate measured on a sample before and at
1) T90 is the value with which 90% of the intervals through the site trials.
measurements shall comply when assessing 20 or
more measurements against the specified layer (vi) The density achieved.
thickness.
(vii) The compacted thickness of the layer.
(b) Site trials
(viii) Any other relevant information as directed by the
The Contractor shall prepare a Trial Section
Engineer.
Programme for the approval of the Engineer detailing all
sequences of the proposed trial section. In addition to
At least eight sets of tests shall be made by the
the items listed further below, at least the following,
Contractor and the Engineer on each 100 metres of trial
where appropriate, shall be included:
for each level of compactive effort and provided all eight
- date and time, location, sketch of location and type
sets of results over the range of compactive effort
of layer to be placed;
proposed by the Contractor meet the specified
- preparation of surface;
requirements for the material the site trial shall be
- rate of application;
deemed successful. The above data recorded in the
- frequency of testing (test trays, cores, density
trial shall become the agreed basis on which the
measurements, gradation, etc);
particular material shall be provided and processed to
- type and number of equipment to be used;
achieve the specified requirements.
- roller pattern;
- joint construction methods.
The Contractor shall not proceed with the placing of the
layer tried in the trial section until the methods,
The plan for the proposed trial section shall be
materials and procedures established in the trials have
forwarded to the Engineer for approval not less than
been approved. Such approval shall be based on a
two working days before the planned trial. Attention
detailed trial section report prepared by the Contractor
shall be given to joint construction methods, limitation of
including all observations and test results. Should the
longitudinal and transversal joints and handling of
trial fail, the Contractor shall perform additional trials at
materials.
his own cost until a trial and the trial section report has
been approved by the Engineer.
Full scale laying and compaction site trials shall be
carried out by the Contractor on all earthwork and
If during the execution of the works, the construction
pavement materials proposed for the works using the
control tests indicate that the requirements for a
constructional plant and methods proposed by the
material are not being consistently achieved, then work
Contractor for constructing the works. The trials shall be on that layer shall stop until the cause is investigated by
carried out with the agreement, and in the presence of
the Contractor. Such investigation may include, effect of
the Engineer.
using other compaction methods, further laboratory and
site trials on the material to determine a revised set of
The trials shall be carried out to enable the Contractor
data as above which, when agreed, shall be the basis
to demonstrate the suitability of his mixing and
on which all subsequent material will be provided and
compaction equipment to provide and compact the
processed to achieve the specified requirements.
material to the specified density and to confirm that the
other specified requirements of the completed
Agreement by the Engineer to a set of data recorded in
earthwork or pavement layer can be achieved.
a site trial shall not relieve the Contractor of any
responsibility to comply with the requirements of this
Each trial area shall be at least 100 metres long and to
Specification and the Special Specification.
the full construction width and shall be laid to the
specified depth for the material. It may form part of the
works provided it complies with this Specification. Any
areas which do not comply with this Specification shall 7117 TESTS ON STRUCTURES
be removed and a new trial shall be laid.
(a) Test on elastomeric bearings
The Contractor shall allow in his programme for Tests on elastomeric bearings shall be conducted in
conducting site trials and for carrying out the accordance with BS 5400 Part 9.2: 1983 and the
appropriate tests on them. The trial on each pavement bearings shall comply with the test requirements
layer shall be undertaken at least 21 days ahead of the specified in the said specification.

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 9
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

(b) Prestressed concrete (c) Load test on foundation piles


The head of the test pile shall be exposed for checking
(i) General position and slope. Where necessary, the head shall be
Where so directed by the Engineer the contractor cut further back so as to expose a full bond length of
shall make arrangements for samples of the main reinforcing steel, and a suitable pile head slab for
materials he intends to use in the Works to be applying an axial load to the pile shall be cast. As an
tested by an Independent testing authority. The cost alternative, the head may be cut at right angles and the
of testing prestressing steel, anchorage assemblies load applied directly to the pile.
and couplings shall be included in his rates.
The test load shall be applied to the top of the pile with
Material represented by samples which do not a hydraulic jack. Where more than one jack is used for
comply with the specified requirements shall be applying the load, all the jacks in the circuit shall be
removed and replaced with suitable material. activated by the same pumping unit. The jack (s) shall
be placed so as to ensure that the load is applied
(ii) Anchorage’s and couplers axially.
Anchorage’s and couplers shall be tested in
accordance with the requirements of CLAUSE 6503. The applied load shall be calculated in accordance with
The anchorages and couplers shall be assembled the hydraulic pressure which is being monitored by two
in accordance with their practical application on the pressure meters in the circuit. The pressure meter shall
site where all components necessary for anchoring be calibrated in divisions not exceeding 2% of the
shall be used, but excluding the ducts. maximum pressure applied, and the range of the
metres shall not exceed 150% of the maximum
(iii) Prestressing steel pressure. The jack(s) and meters shall be calibrated by
Prestressing steel shall be tested in accordance an approved testing laboratory not more than four
with the requirements of CLAUSE 6503. Should any weeks before the test will commence.
test piece fail to comply with the requirements
specified for the prestressing steel, the material The deflection of the pile head shall be measured with
represented by that sample shall be replaced with two scale rulers and two dial extensometers. The scale
materials conforming to the specifications if further rulers shall be fixed to the pile and placed on both sides
testing confirms that they do not comply with the of the pile on a diameter line and the dial
specifications. extensometers shall be similarly placed but on a
diameter line at right angles to that in which the scale
(iv) Grout rulers have been mounted.
The fluidity of grout shall be measured with a flow
cone, immersion apparatus or viscometer. The Level measurements shall be taken on the scale rulers
instrument shall be accurately calibrated in a and reduced as a level mark to a similar scale ruler
laboratory so that the specified viscosity of grout placed at a distance from the test pile. All three scale
can be controlled satisfactorily. rulers shall be calibrated in millimetres and the level –
indicating instrument shall be capable of taking
The readings obtained during grouting shall be readings to 0.5 mm, and approximate readings of up to
compared with the times determined in the laboratory 0.1 mm.
for grouts of the specified viscosities.
The dial extensometers shall have a range of 50 mm
The bleeding of grout shall be measured in a metal or and shall be marked in 0.1 mm divisions to enable
glass container with an internal diameter of measurements to 0.05 mm to be taken. The plungers of
approximately 100 mm and a height of approximately the extensometer shall rest on a machined metal or
120 mm. The grout and water levels in the container glass surface.
shall be controlled with a metal bridge into which two
adjustable studs A and B are secured. The extensometer shall be supported by one or more
beams kept in the shade. The supports for the beams
The procedure for determining the bleeding of grout shall be so placed as to limit the effect of earth
shall be as follows: movements around the test pile on the deflection
readings.
Studs A and B in the metal bridge shall be adjusted and
locked so that the distance from the lower tips of studs The test load shall be applied in increments of 20% of
to the bottom of the container will be approximately 100 the specified working load to a maximum test load
mm and 107 mm respectively. The volume Va and Vb equal to twice the specified working load or the ultimate
for the container at the respective levels of the stud test load whichever is the smaller.
settings shall then be determined to the nearest
millilitre. A load increment may not be applied before the
subsidence or the rate has stabilised at a rate of not
The container shall be filled with freshly mixed grout to more than 0.10 mm in 20 minutes under the load
a level where the grout will just touch the tip of stud A applied.
which points downwards. The bridge shall then be
removed and the container tightly sealed to prevent After the load loading has been completed, the
evaporation. The container shall then be stored at 20°C maximum test load shall be maintained until the
and kept free from vibrations for the entire duration of movement is less than 0.2 mm within a period of 24
the test. hours. The load shall be removed in decrements of 20%
of the specified working load at intervals of not less than
Three hours after the grout has been mixed, the 20 minutes.
container shall be opened and the free (bleed) water
poured off. The bridge shall be placed over the After the loading has been removed, the readings on
container with tip of stud B pointing downwards and both meters registering the movement of the pile shall
water poured onto the grout with measuring apparatus be recorded accurately to 0.1 mm at intervals of 5.10
until the water level touches the tip of stud B. The and 20 minutes and then every 30 minutes until the
volume of water added shall be determined to the load is changed. The final recovery shall be recorded
nearest millilitre. 24 hours after the maximum test load has been
removed.

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 10
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

During the test, the pile shall be loaded with up to 100% REQUESTED BY THE ENGINEER
of the specified working load and the load shall then be (a) TESTS PROVISIONAL
removed. It shall then be loaded to the maximum test SUM
load after which the test load shall be removed. (b) CONTRACTOR’S OVERHEAD AND %
PROFIT

7118 MEASUREMENT AND PAYMENT The actual costs of special tests requested by the
Engineer shall be reimbursed from the provisional sum
Payment for the Engineer’s laboratory shall be in entered in the Bill of Quantities for such tests. The
accordance with SECTION 1400. Contractor’s overhead and profit associated with
arranging and paying for the tests shall be covered by a
percentage on the actual costs.
ITEM UNIT
71.01 SPECIAL TESTS
SERIES 7000: TOLERANCES, TESTING AND signs of poor workmanship, and similar considerations
which constitute sufficient grounds for rejecting the work
QUALITY CONTROL
without any further testing in the opinion of the
Engineer.
SECTION 7200: QUALITY The Engineer shall be entitled to assess separately any
CONTROL specified portion of a lot if, in his opinion, it exhibits
significant deviations as compared with the remainder
of the lot.
CONTENTS:
CLAUSE PAGE
7201 SCOPE 7000-12
7203 DEFINITIONS
The limit values will depend on the sample sizes and
7202 JUDGEMENT PLANS: GENERAL 7000-12
7203 DEFINITIONS 7000-12 may be a lower limit L, an upper limit or double limits.
For the purposes of this SECTION the following words
7204 GENERAL REQUIREMENTS 7000-12
and symbols shall have the following meanings:
7205 PROCEDURES 7000-13
7206 CONDITIONAL ACCEPTANCE 7000-14
(a) Lot
7207 ROUTINE TESTS AND INSPECTION BY
A lot is a sizeable portion of work or quantity of material
THE ENGINEER. 7000-15
7208 PROCESS CONTROL BY THE which is assessed as a unit for the purpose of quality
control, and selected to represent material or work
CONTRACTOR 7000-15
produced by essentially the same process and from
7209 MEASUREMENT AND PAYMENT 7000-15
essentially the same materials.

(b) Random Sample


Random samples are test measurements at separate
7201 SCOPE test positions or on separate sample portions obtained
This Section describes the scheme used for from the lot in an unbiased manner.
determining, by means of tests and measurements and
by applying statistical judgement plans, whether certain (c) Nominal value or specification limit
specified requirements in regard to the properties of This is the limit value of the property of any material
materials and workmanship are being complied with. outside which not more than a specified percentage of
the population of values representing an acceptable
It also covers the requirements in regard to the control material is allowed to lie. The nominal value may be a
to be exercised by the Contractor for monitoring the single lower limit or a single upper limit or a double limit
quality of his work and materials and the routine tests consisting of a lower limit and an upper limit.
and inspections to be carried out by the Engineer.
(d) Acceptance limit for sample mean
This is the limit value of a product property within which
7202 JUDGEMENT PLANS: GENERAL the sample mean shall lie for a product to be
Certain requirements and nominal limit values are laid acceptable.
down in the Specifications in regard to the properties of
materials and workmanship to be supplied. Tests shall (e) Acceptance limits for individual test values
be conducted and measurements taken for controlling These are the limit values of a product property within
the relevant properties of the workmanship and which the sample values representing a product shall lie
materials supplied, and the results of such tests and for the product to be acceptable.
measurements shall be assessed on the basis of the
prescribed criteria for compliance with the specified (f) Conditional acceptance
requirements. This is the acceptance of a lot at conditions that specific
rectification measures are taken and carried through to
Wherever possible, acceptance criteria shall be completion to the satisfaction of the Engineer before the
determined by way of statistical principles described in lot can be approved in the permanent Works and
this Section. Wherever statistical acceptance criteria certified for payment. Conditional acceptance shall be
are deemed inappropriate in the opinion of the subject to the provisions of CLAUSE 7202.
Engineer, a specified minimum requirement shall be
fully complied with. (g) Outliers
Where, in a sample, one or more test results differ
Despite acceptance of those properties judged by these significantly from the other values obtained, this
statistical methods, the materials or work submitted will difference could be ascribed to an assignable cause if
be rejected when other properties (which are not so deemed by the Engineer, in which case such test
controlled by statistical methods) fail to comply with the result shall be regarded as an outlier and disregarded
requirements of the Specifications, or where there are when assessing the lot.
other causes for rejection such as obviously defective
workmanship or excessively variable properties, visible

THE REPUBLIC OF U GANDA, MINISTRY OF W ORKS, H OUSING AND COMMUNICATIONS PAGE 7000 - 11
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

7204 GENERAL REQUIREMENTS Where Xn and Sn are the arithmetic mean and the
sample standard deviation respectively, and Xo is the
(a) Determining the lot size value of the test differing most from the mean.

(i) Road-construction layers Compare the value of To with the value of T for the
The lot size shall be a section compacted in one applicable value of n from TABLE 7204/1.
process where essentially the same materials and
construction equipment have been used. If To is greater than T, then Xo is an outlier.

Where production is on a continuous basis, a lot Every outlier shall be disregarded and replaced by
shall normally mean the product of one day’s work another random test value. The sample mean and the
and shall not exceed the product of two full days’ sample standard deviation shall then be recalculated. If
work. However, a lot of any smaller size may be an outlier cannot be replaced, the sample mean and the
ordered by the Engineer where: standard deviation shall be calculated using the
remaining test results. The final number of test results
(1) The properties under investigation exhibit used in the assessment, after the elimination of outliers,
abnormal local variation within the normal lot shall never be less than three.
size.
(2) An area is obviously of a different quality than (e) Resubmission
the rest; Where a lot has been accepted conditionally, or has
(3) The rate of production is very high. been rejected, the Engineer may agree to its
resubmission for approval if it has been rectified to the
(ii) Concrete satisfaction of the Engineer. In such case a fresh
The lot size shall be determined by the Engineer, sample shall be taken, and a fresh (second) set of test
with due regard being given to the size and the type values determined.
of structure in which the concrete is placed, the
specific portion of the structure, and the total The first and second sets of test values shall then be
quantity of concrete placed in a day. The lot sizes in compared with each other to determine whether their
concrete structures could therefore vary properties differ significantly.
considerably, and, particularly in the case of small
structures, it could be necessary to combine Where in the opinion of the Engineer a significant
samples of the same grade of concrete from difference does occur, the submission of the lot shall be
different structures at the discretion of the Engineer, regarded as a first submission and assessed as such,
provided that the concrete has been obtained from and only the second set of test values shall then be
the same concrete plant and has been cast in the used for this purpose.
same period.

(iii) Other TABLE 7204/1


In certain cases, as for example in material VALUES OF T FOR DIFFERENT SAMPLE SIZES
stockpiles, others where the definition of a lot in
accordance with this Section does not apply directly Number of observations n Critical value T
in the opinion of the Engineer, the Engineer will 1
determine lot sizes in accordance with
circumstances pertaining to each case. 2
3
(b) Random sampling
4 1.46
When any lot is tested, whether a normally sized lot or
an isolated section that clearly exhibits an abnormal 5 1.67
variation of the properties under consideration, all 6 1.82
samples shall be taken in a random pattern.
7 1.94
For this purpose use shall be made of tables of random 8 2.03
numbers according to standard instructions approved
9 2.11
by the Engineer.
10 2.18
(c) Sample Sizes 11 2.23
For purposes of acceptance control, the Engineer will
determine sample size, i.e. the number of values to be 12 2.29
assessed in a lot. 13 2.33
14 2.37
(d) Outliers
Test results shall be scanned for possible outliers. 15 2.41
Where there is reason to believe that a test result may 16 2.44
be erroneous, it shall, if possible, be re-examined by
further testing, and, if there is reasonable evidence to 17 2.47
suggest that the test result is erroneous, it shall be 18 2.5
regarded as an outlier, rejected and replaced with a 19 2.53
fresh result.
20 2.56
Where reinvestigation of a test result is not possible, the
procedure described below shall be used for identifying
outliers:
7205 PROCEDURES
Calculate the value of To from
(a) General
The statistical judgement procedures described below
abs  Xo  Xn  shall apply to the corresponding product properties for
To 
Sn the purpose of acceptance control. Outliers shall be

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 12
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

identified, disregarded, and, if possible, replaced at the


discretion of the Engineer. After outliers have been examined and replaced as
directed by the Engineer, compliance with the specified
(b) Straight edge measurements density requirements shall be determined by the
Six straightedge measurements shall be taken in the statistical method specified below unless a fixed
longitudinal direction and six measurements shall be minimum average value and/or absolute minimum value
taken in the transversal direction every 25 m along the has been specified for the compaction elsewhere in
road or as otherwise directed by the Engineer. The these Specifications.
measurements shall be taken at offsets as agreed with
the Engineer. All measurements taken shall fall within The lot will be considered to comply with the
the limits given in TABLE 7115/1 including the requirements for field density if the following conditions
requirement for surface dressing. are fulfilled:

(c) Surface levels (1) For a lower limit specification, LLs


At least 5 points across road shall be taken every 25 m.
The levels shall be taken at the centreline, at the edge Xn > LLs + Sn*K
of the carriageway and at the edge of the shoulders or
as directed by the Engineer. The levels may be taken at Accept the lot if the sample mean satisfies the
shorter intervals than 25 m, see CLAUSE 7303. expression, otherwise reject the lot.

At least 50, but preferably more, levels shall be (2) For an upper limit specification, ULs
determined for each lot of completed work The lot will
be considered to comply with the requirements in Xn < ULs - Sn*K
respect of surface levels if, before any repair work is
undertaken, at least 90% of the level measurements Accept the lot if the sample mean satisfies the
show a deviation from the specified levels which is expression, otherwise reject the lot.
smaller than the tolerance specified in TABLE 7115/2 (3) For a double limit specification, LLs and ULs
and no measurements fall outside the maximum
allowed deviation Hmax. LLs + Sn*K < Xn < ULs - Sn*K

Isolated spots, where the surface levels deviate by Accept the lot if the sample mean satisfies the
more than the appropriate tolerance of the specified expression, otherwise reject the lot.
levels shall be repaired to bring the deviation to within
the tolerance. where

(d) Crossfall and longitudinal slope Xn is the arithmetic mean of a set of n test results
All measurements of crossfall and longitudinal slope as constituting the sample.
directed by the Engineer shall fall within the limits given
in TABLE 7115/3. Sn is the sample standard deviation defined by:
0.5
 (X - X n )2 
Isolated spots, where the crossfall and longitudinal Sn =  

slope deviate by more than the appropriate tolerance of n-1
the specified crossfall shall be repaired to bring the  
deviation to within the tolerance.
where
(e) Layer thickness
At least 20, but preferably more, layer thickness shall X is the value of an individual sample portion, i.e.
be determined in accordance with a stratified random an individual test result or measurement.
pattern (as defined in SUBCLAUSES 7203(b) and
7204(b)) for each lot of completed layer work. Layer n is the number of sample portions, i.e. the number
thickness may not be determined by means of level of individual test results or measurements.
measurements, but shall be measured by core drilling
of excavation of sample pits at locations approved by K is a statistical constant defined by
the Engineer. t
K
The lot will be considered to comply with the n
requirements for layer thickness if both the following
conditions are fulfilled: where
 at least 90% of all the thickness measurements
taken before any thickness repairs are made are t is the Student's t.
equal to or greater than the specified nominal
thickness, minus the T90 tolerance specified in The value of K is dependent on the number of sample
TABLE 7115/4. portions in the sample and the acceptance criteria. The
 the mean layer thickness of the lot is not less than acceptance criteria normally used where statistical
the specified nominal thickness control of materials and workmanship are applied is that
the specification limit, Ls, is satisfied for more than 90%
(f) Relative compaction of earthworks and of the lot and that the risk of accepting a lot that does
pavement layers not satisfy the specified requirement is less than 10%.
At least the following number of relative density
determinations shall be taken in a random pattern (as The value of K determined according to the above
defined in SUBCLAUSES 7203(b) and 7204(b)) on each criteria is given in TABLE 7205/1.
section or as directed by the Engineer and assessed as
a lot: (g) Cementitious binder content of cemented layers
 Roadbed, fill: 3 tests
 Improved subgrade layers, (i) Method
gravel wearing course: 4 tests
 Subbase 5 tests (1) Take 50 samples according to a random pattern
 Base course, surfacing: 6 tests (as defined in SUBCLAUSES 7203(b) and

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 13
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

7204(b)) and determine their cementitious


binder content.
(2) Examine the results for outliers and replace
them if any in the opinion of the Engineer.

(ii) Analysis
The lot will be considered to comply with the
requirements for cementitious binder content if the
following conditions are both fulfilled:

(1) The mean cementitious-binder content shall be


not less than 91% of the specified binder
content.
(2) The cementitious binder content in not more
than 12 of the 50 samples may be lower than
70% of the specified binder content.

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 14
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

TABLE 7205/1: 7204(b)) and make test cubes. Test them for cube
VALUES OF STUDENT’S-T AND K FOR DIFFERENT SAMPLE compressive strength after 28 days.
SIZES

TABLE 7205/3
t
n Student's-t K MINIMUM NUMBER OF TESTS OF STRUCTURAL CONCRETE
FOR COMPRESSION STRENGTH
n
3 1.89 1.09 Volume of lot (m3) Minimum number of
4 1.64 0.82 tests in lot 1)
5 1.53 0.68 0 – 20 4
6 1.48 0.60 21 – 40 6

7 1.44 0.54 41 – 70 9

8 1.42 0.50 71 – 100 12

9 1.40 0.47 101 – 150 14

10 1.38 0.44 > 150 16

11 1.37 0.41 1) Each test consists of the average value of a set of


three cubes.
12 1.36 0.39
13 1.36 0.38 (ii) Analysis
Examine the results for outliers and disregard as
14 1.35 0.36 required in the opinion of the Engineer. The results
15 1.34 0.35 are then assessed according to the criteria set out
below. A lot will comply with the requirements for
16 1.34 0.34 the characteristic strength denoted X, if it meets the
17 1.34 0.32 following requirements by using the acceptance
factors A and B given in TABLE 7205/4:
18 1.33 0.31
19 1.33 0.31  Mean value: minimum ( X + A )
 Single test value: minimum ( X - B )
(h) Binder content of bituminous mixes
TABLE 7205/4
(i) Method ACCEPTANCE FACTORS FOR STRENGTH OF STRUCTURAL
(1) Take at least four specimens of bituminous mix CONCRETE
in a random pattern (as defined in SUBCLAUSES
7203(b) and 7204(b)) and determine the binder Number of Acceptance factors for strength of
content. tests in lot structural concrete
(2) Examine the results and replace any outliers as A B
directed by the Engineer. Determine the sample (MPa) (MPa)
mean and assess the lot by using the following 3 2.7 3.9
criteria. 4 2.7 4.2

(ii) Analysis 5 2.6 4.5


The binder content of bituminous mixes shall 6 2.5 4.7
not deviate from the specified binder content by 7 2.4 4.9
more than the values given in Table 7205/2 or
according to the Special Specifications. 8 2.3 5.0
9 2.2 5.2
10 2.1 5.3
TABLE 7205/2
ACCEPTANCE LIMITS FOR BITUMINOUS BINDER CONTENT 11 1.9 5.4
IN MIXES 12 1.7 5.5
13 1.4 5.6
Number of Maximum deviation from the
tests in lot specified binder content 14 1.1 5.7
(% of binder) 15 0.5 5.8
Sample mean Single values
2 0.37 0.54 (j) Relative compaction of SuperpaveTM Layers
3 0.33 0.58
The relative compaction (U) of SuperpaveTM layers shall
4 0.30 0.60 be determined by employing the following equation:
5 0.28 0.62
6 0.27 0.64 t *s
7 0.26 0.65 U x
8 or more 0.25 0.66
n
Where:
(i) Concrete cube compressive strength, 28-day
x is the sample mean
(i) Method
Take at least the minimum number of samples as t is the Student’s t (refer to Table 7205/1)
given in Table 7205/3 according to a random
s is the standard deviation
pattern (as defined in SUBCLAUSES 7203(b) and
n is the number of samples

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 15
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

7207 ROUTINE TESTS AND INSPECTION BY


7206 CONDITIONAL ACCEPTANCE THE ENGINEER
The Engineer will at regular intervals inspect and test
(a) General materials and completed work for compliance with the
Where a lot is rejected under a statistical judgement, specified requirements, and, where applicable the
plan described in this Section, but the test results are various specified judgement plans will be applied. The
such that the lot complies with the requirements for testing frequencies and sample and lot sizes for routine
conditional acceptance specified in this Clause, the testing shall be at the Engineer’s discretion.
Engineer may accept the lot conditionally. The Engineer
may then apply a number of conditions for rectification All sections of completed work shall be submitted to the
of the layer at his own discretion for the product to be Engineer for routine inspection and testing, and the
approved and certified for payment. Conditional Contractor shall not cover up or construct any work on
acceptance shall be the sole discretion of the Engineer top of sections of completed work before being advised
and is not an option which may be exercised by the by the Engineer of the outcome of his tests and
Contractor or a right he may claim. inspection. The Contractor shall arrange the submission
of work for testing in a manner as will afford the
The Contractor shall have the option to remove and Engineer reasonable opportunity for inspecting and
reinstate completely at his own cost conditionally testing.
accepted work with work which complies with the
requirements.
7208 PROCESS CONTROL BY THE
(b) Application
Conditional acceptance may be applied in respect of CONTRACTOR
the properties of structures as shown in TABLE 7206/1. The requirements of Clause 1205 shall apply in respect
of the Contractor's obligation to institute and implement
(c) Criteria a control system for monitoring the quality of the work
When properties to which conditional acceptance may and materials supplied.
apply are assessed in accordance with this Section, two
requirements shall always apply, viz one in relation to For continuous concrete and asphalt-production
the sample mean and one in relation to individual tests processes, the Engineer may order the Contractor to
value. A lot may be conditionally accepted when it augment the above control system by introducing a
complies with one of the two requirements for process-control system for monitoring the various
acceptance, but not with the second requirement properties to be controlled. The specific system to be
provided that it complies with the requirements for applied shall be subject to the Engineer's approval, and
conditional acceptance in relation to the second the attention of the Contractor is drawn to the systems
requirement. described in TRH5, which will normally be regarded as
suitable.

TABLE 7206/1 The Contractor shall take immediate steps to rectify any
PROPERTIES TO WHICH CONDITIONAL ACCEPTANCE MAY deviation from the specified requirements indicated by
APPLY his process-control system, and the Engineer shall have
the right to inspect and be given all details of tests and
Property Structure testing procedures in order to satisfy himself that the
Contractor is implementing adequate process-control
system.
Relative  Bituminous base course or
compaction surfacing
 Cemented layers 7209 MEASUREMENT AND PAYMENT
 Plant mixed, paver laid layers No separate measurement or payments apply to this
Bituminous Layers of bituminous mixes Section.
binder content
Cementitious Cemented layers
binder content
28-day cube All structural concrete (excepting
strength concrete pavements
Levels Earthworks and pavement layers

Layer Earthworks and pavement layers


thickness

(d) Resubmission
Where a lot has been accepted conditionally or has
been rejected, the Engineer may agree to its
resubmission for approval if it has been reworked and
the Engineer is satisfied that a proper attempt was
made to improve the properties which were
unacceptable. A fresh sample shall be taken, and a
fresh (second) set of test values determined. The first
and second sets of test values shall then be compared
with each other to determine whether their properties
differ significantly. Where in the opinion of the Engineer
a significant difference does occur, the submission of
the lot shall be regarded as a first submission and
assessed as such, and only the second set of test
values shall then be used for this purpose.

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 16
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

SERIES 7000: TOLERANCES, TESTING AND After completion of the setting out and site clearance
the Contractor shall take ground cross sections at
QUALITY CONTROL
intervals of 25 m along the road centreline and along
the centreline of all culverts and structures. These shall
SECTION 7300: SETTING OUT be plotted to a natural scale of 1:100 on a stable
transparent material or other approved material and a
AND TOLERANCES copy of the plot submitted to the Engineer for
agreement. If the Contractor fails to take requisite
levels, levels determined by the Engineer shall be taken
CONTENTS: as correct.
CLAUSE PAGE
The Contractor shall programme for a period of 30 days
7301 SCOPE 7000-17 between submitting the ground cross sections and
7302 GENERAL 7000-17 being issued with final road, culvert and structure levels.
7303 DETAILED SETTING OUT 7000-17
A minimum 5 km section of road shall be submitted, but
7304 TOLERANCES 7000-17 where the Contractor submits cross sections for more
7305 MEASUREMENT AND PAYMENT 7000-18 than 10 km of road within the same 30 day period the
initial 30 days shall be extended by 30 days for each
additional 10 km or part thereof. Final road, culvert or
structure levels will be determined by the Engineer and
7301 SCOPE may be different from the levels shown on the
This Section covers the procedures for setting out and Drawings.
gives the limits for geometric tolerances for earthworks
and layer work. On receipt of the final road levels the Contractor shall
mark up the details on the transparencies and the
original and one print of the cross-sections shall be
7302 GENERAL provided free of charge by the Contractor for the
The Engineer will provide sufficient basic survey Engineer.
information to enable the contractor to set out the works
and the Contractor shall be responsible for setting out On completion of the earthworks but before starting
all necessary reference points and for the maintenance formation or pavement layers the Contractor shall
thereof. establish steel pins at a constant offset to the edges of
the carriageway shoulders. The offset may however
The Contractor shall satisfy himself as to the accuracy vary between sections in cut and those in fill. The steel
in line, level and dimension of the basic survey and pins will be clearly and indelibly marked with all the
setting out details provided and should the Contractor relevant information necessary to directly establish the
discover any error in the information provided by the centreline and level at any point across the carriageway
Engineer, he should at once notify the Engineer. If the by using either boning rods or a string line.
information is confirmed to be in error the Engineer will
issue amended drawings or instructions regarding the The interval between pins shall not be more that 12.5 m
correction of the error. and the pins shall be maintained by the Contractor for
as long as they are needed by the Engineer to check
Prior to commencing construction, the Contractor shall the work.
establish the road reserve boundary posts, or if no
boundary posts are instructed, then the Contractor shall
establish reference points to define the road reserve at 7304 TOLERANCES
100 m intervals on both sides.
(a) General
The Contractor shall establish temporary benchmarks In addition to the requirements set out in this Clause
along the road at intervals not exceeding 200 m and attention is drawn to the requirements of CLAUSE 7115
shall provide the Engineer with a schedule of their which shall all be fulfilled.
levels and locations.
(b) Horizontal alignments
The Contractor shall not remove, damage, alter or Horizontal alignments shall be determined from the
destroy in any way plot beacons or survey beacons. centreline of the pavement surface as constructed, and
Should the Contractor consider that any beacon will be all other parallel alignments shall be corrected within a
interfered with by the works he shall notify the Engineer tolerance of ±13 mm therefrom.
who, if he considers necessary, will make arrangements
for the removal and replacement of the beacon. (c) Thickness of pavement layers
The thickness of any pavement layer as specified or
If the Contractor removes or disturbs a beacon without ordered by the Engineer, measured at five points in any
permission of the Engineer, he shall be liable for the full length of 100 m, shall meet the requirements given in
cost of its replacement and any legal consequences TABLE 7115/4.
thereof.
(d) Surface levels of payment layers and formation
The level measured at any point on the surface of a
7303 DETAILED SETTING OUT pavement layer or the formation level shall not deviate
The Contractor shall set out the line and level of the from the corresponding level calculated from the
works at intervals of not more than 25 m or such lesser Drawings by more than the tolerances shown in TABLE
intervals as are required to construct the Works to the 7115/2.
tolerances specified in this Specification. Reference
pegs and batter rails clearly and indelibly marked with For checking compliance with TABLE 7115/2
all the relevant information shall be provided clear of the measurements of surface levels will be taken at points
road and at right angles to it from which the centreline, to be selected by the Engineer at 12.5 m centres
level and batter slope can be directly established at any longitudinally and at 2 m centres transversely. At
time. These shall be maintained by the Contractor for junctions, the grid point spacing shall be determined by
as long as they are needed to check the work. the Engineer.

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 17
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

(e) Surface regularity


The surface regularity of pavement layers and the
formation shall be tested at points decided by the
Engineer with a rigid, steel straightedge 3 m long
placed at any angle to the centreline of the road. The
maximum allowable deviation of the surface below the
straightedge shall be as given in TABLE 7115/1.

In addition the longitudinal slope or transverse crossfall


shall not deviate from that shown on the Drawings by
more than the tolerances given in TABLE 7115/3.

(f) Shoulders
Shoulders shall be constructed to the same thickness,
level and surface regularity requirements as for the
adjacent pavement layers.

(g) Cutting and embankment slopes


In the final trimmed slope of cuttings a tolerance of
+0.25 will be permitted, i.e. if a slope of 1 in 2 is
specified, the acceptable slope shall be not steeper
than 1 in 2 or slacker than 1 in 2.25

In the final trimmed slopes of embankments, a


tolerance of +0.25 will be permitted, i.e. if the specified
slope is 1 in 2, the acceptable slope shall be not
steeper than 1 in 2 or slacker than 1 in 2.25.

(h) Width of cuttings and embankments


The tolerance permitted in the width of the bottom of
cuttings shall be 200 mm between the centreline of the
road and the toe of the cutting slope.

The width of embankments measured as the horizontal


distance from the centreline of the road to the top of the
embankment shall not be less than that shown on the
Drawing or more than that shown on the Drawings plus
0.25 m.

(i) Depth of side drains


The depth of side drains measured as the vertical
height difference from the centreline of the finished
pavement and the invert of the side drain shall not be
less than that shown on the Drawings nor more than
that shown on the Drawings plus 0.15 m.

(j) Construction control testing


Unless otherwise directed values given in this
Specification are minimum values and the workmanship
will only be considered as satisfactory if all tests, taken
at the frequency specified in SECTION 7100 of this
Specification are at least equal to that specified in the
relevant section.

7305 MEASUREMENT AND PAYMENT


No separate payment shall be made for work described
in this Section.

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 18
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

SERIES 7000: TOLERANCES, TESTING AND wide or such area to be determined by the Engineer as
necessary to obtain compliance with this Specification.
QUALITY CONTROL
Where the results of the construction control tests are
SECTION 7400: RECTIFICATION less than that specified the full depth of the layer shall
be reworked to specification. The area treated shall be
OF EARTHWORKS AND the whole section submitted for approval or following a
retest a length of at least 50 m both sides of each test
PAVEMENT LAYERS OUTSIDE and retest, failure.
PERMITTED GEOMETRIC (c) Base course and subbase
TOLERANCES Where the levels or widths are out of tolerance and the
courses consist of unbound (i.e. natural or graded
stone) material, the full depth of the material shall be
CONTENTS: reworked to specification. The area treated shall be at
CLAUSE PAGE least 30 m long and 3 m wide or such area to the
determined by the Engineer as necessary to obtain
7401 SCOPE 7000-19 compliance with this Specification.
7402 RECTIFICATION MEASURES 7000-19
7403 MEASUREMENT AND PAYMENT 7000-19 Where the courses consist of cement or lime treated
material or lean concrete the full depth of the layer shall
be removed from the pavement and replaced to
specification. The area treated shall be at least 5m long
7401 SCOPE and the full width of the paving laid in one operation. If
This Section sets out the methods for rectification of areas are corrected within 7 days of laying no
earthworks and pavement layers constructed outside construction traffic or compaction plant shall use the
permitted geometric tolerances. Where any tolerances surrounding satisfactory areas during that period.
in SECTION 7300 are exceeded, the Contractor shall
determine the full extent of the area which is out of For bituminous bases the full depth of layer shall be
tolerance and shall make good the surface of the removed and replaced with fresh material laid and
pavement course, earthworks or formation in the compacted to specification. Any area so treated shall be
manner described below. at least 5 m long and the full width of the paving laid in
one operation.

7402 RECTIFICATION MEASURES Where the results of the construction control tests for
any of the base or subbase materials are less than that
(a) Earthworks excluding improved subgrade specified, the full depth of the layer shall be reworked to
layers specification in case of unbound material and removed
Where a cutting slope is steeper, and an embankment and replaced to specification in case of cemented and
slope is slacker, than the specified slope then the slope bituminous materials. The area treated shall be the
shall be trimmed to the specified slope. Where a cutting whole section submitted for approval or, following a
slope in slacker, and an embankment slope is steeper, retest, such area to be determined by the Engineer as
than the specified slope then the slope shall be necessary to obtain compliance with the Specification.
benched and fill material placed and compacted and the
slope shall be trimmed all in accordance with (d) Asphalt concrete surfacing
requirements of SERIES 3000 and any other relevant Where the levels or widths are out of tolerance the full
part of this Specification. depth of the layer shall be removed and replaced with
fresh material laid and compacted to specification. The
Where the width of a cutting is less than, and the width area rectified shall be the full width of the paving laid in
of an embankment more than, the specified width then one operation and at least 15 m long.
the cutting or embankment shall be trimmed to the
specified width. Where the width of a cutting is more Where the results of the construction control tests for
than, and the width of an embankment is less than, the the wearing course are less than that specified the full
specified width then the embankment or cutting shall be depth of the layer shall be removed and replaced to
benched and fill material placed and compacted and the specification. The area treated shall be the whole
slopes shall be trimmed all in accordance with the section submitted for approval or, following a retest,
requirements of this Specification. such area to be determined by the Engineer as
necessary to obtain compliance with the Specification.
Where the depth of a side drain is less than that
specified the side drain shall be trimmed to the
specified depth. Where the depth of a side drain is more 7403 MEASUREMENT AND PAYMENT
than specified the side drain shall be backfilled with fill The Contractor shall be deemed to have allowed in his
material compacted to a dry density of at least 90% general rates and prices for the cost of complying with
MDD of BS-Heavy up to the specified depth. the requirements in this Section and no additional
payment will be made.
Where the results of the construction control tests are
less than that specified the full depth of the layer shall
be reworked to specification. The area treated shall be
the whole section submitted for approval or, following a
retest, a length of at least 50 m both sides of each test
and retest failure or such area to be determined by the
Engineer as necessary to obtain compliance with this
Specification.

(b) Improved subgrade layers


Where the levels or widths are out of tolerance then the
full depth of the layer shall be reworked to specification.
The area treated shall be at least 12.5 m long and 3 m

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 19
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

SERIES 7000: TOLERANCES, TESTING AND 7501 INSTITUTIONS


QUALITY CONTROL  Central Materials Laboratory (CML) of Ministry of
Works, Housing and Communications, Uganda.
 Uganda National Bureau of Standards (UNBS)
SECTION 7500: SPECIFICATIONS  American Association of State Highway and
Transport Officials (AASHTO)
AND TEST METHODS  American Society for Testing and Materials (ASTM)
 British Standards Institute (BS)
CONTENTS:  European Standards (BS EN)
CLAUSE PAGE  Standard Coordination Specification (CKS)
 Deutshe Ingineur Norme (DIN)
7501 INSTITUTIONS 7000-20  South African Bureau of Standards (SABS)
7502 STANDARDS AND TEST METHODS 7000-20  Southern African Bitumen and Tar Association
7503 ADDRESSES 7000-24 (SABITA)
 Swedish Standard (SIS)
 Technical Methods for Highways (TMH)
 Technical Recommendations for Highways (TRH)
 International Standards Organisation (ISO)

7502 STANDARDS AND TEST METHODS


(a) Test methods

(i) Tests on Soils and Gravel:

Name of Test Standard Test Method

Moisture Content BS 1377: Part 2: 1990


Liquid Limit (Cone Penetrometer) BS 1377: Part 2: 1990
Plastic Limit & Plasticity Index BS 1377: Part 2: 1990
Linear Shrinkage BS 1377: Part 2: 1990
Particle Density Determination – Pycnometer BS 1377: Part 2: 1990
Particle Density Determination BS 7755-5.3/ISO 11508
Bulk Density for undisturbed samples BS 1377: Part 2: 1990
Determination of dry bulk density ISO 11272: 1998
Particle Size Distribution BS 1377: Part 2: 1990
Particle Size Distribution - Hydrometer Method BS 1377: Part 2: 1990
Compaction Test - BS Light and BS Heavy BS 1377: Part 4: 1990
Unsoaked CBR Test - One Point Method BS 1377: Part 4: 1990
Unsoaked CBR Test - Three Point Method BS 1377: Part 4: 1990
Soaked CBR Test - One point method BS 1377: Part 4: 1990
Soaked CBR Test - Three Point Method BS 1377: Part 4: 1990
Consolidation Test - Oedometer BS 1377: Part 5: 1990
Triaxial Test BS 1377: Part 7: 1990
Shear Box Test BS 1377: Part 7: 1990
Permeability Test - Constant Head BS 1377: Part 5: 1990
Organic Content - Ignition Loss Method BS 1377: Part 3: 1990
Crumb Test BS 1377: Part 5: 1990
pH Value (pH meter) BS 1377: Part 3: 1990
Sulphate carbonate content BS 1377: Part 3
Chloride content BS 1377: Part 2
Durability test BS 1377: Part 5
Field density BS 1377: Part 9
In situ tests: sand replacement, CBR testing, vane shear strength, cone penetrometer BS 1377: Part 9
and plate bearing test
Determination of water retention characteristics BS 7755-5.5
Sampling, sample preparation and tests on materials before stabilisation BS 1924: Part 1
Preparation of Stabilised Samples for UCS BS1924:Part 2:1990
Compaction Test and UCS of Stabilised Materials BS1924:Part 2:1990
Initial Consumption of Lime - ICL US 288:2001 or BS 1924:Part 2:1990
Quicklime, hydrated lime and natural calcium carbonate-methods of physical testing BS 6463 : Part 103

(ii) Tests on Aggregates

Name of Test Standard Test Method

Guide to sampling and testing aggregates BS 812: Part 101 and BS 5835
Methods of sampling US 145:2000 or BS 812: Part 102
Determination of physical properties US 146:2000
Moisture content of aggregates BS 812: Part 109:1990 and BS 5835
Relative density BS EN 1097-3: Part 3: 1998

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 20
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

Name of Test Standard Test Method

Determination of loose bulk density and air voids BS EN 1097-3: Part 3: 1998
Water absorption BS EN 1097-3: Part 3: 1998
Determination of voids of dry compacted filler BS EN 1097-4: Part 4: 1999
Determination of resistance to wear by abrasion from studded tyres – Nordic test BS EN 1097-9: Part 9: 1999
Sieve tests on aggregates BS 812: Part 103.1: 1985
Flakiness Index (FI) BS EN 933-3: 1997
Elongation Index BS 812: Section 105.2:1990
Average Least Dimension (ALD) US 144:2000 or BS EN 933-3: 1997
Particle Shape Index US 144:2000 or BS EN 933-4: Part 4
Aggregate Crushing Value (ACV) BS 812: Part 110: 1990
Ten Percent Fines Value (TFV) BS 812: Part 111: 1990
Aggregate Impact Value (AIV) - Standard BS 812: Part 112: 1990
Aggregate Impact Value (AIV) - Modified BS 812: Part 112: 1990
Los Angeles Abrasion Test (LAA) ASTM C535-89 and BS 812: Part 113
Polished Stone Value BS 812: Part 114
Determination of percentage of crushed & broken surfaces in coarse aggregate BS EN 933-5: Part 5: 1998
particles
Determination of shell content - percentage shells in coarse aggregate BS EN 933-7: Part 7
Assessment of fines – Grading of fillers (Airjet filing) BS EN 933-10: 2001
Determination of grading requirements BS 882
Determination of resistance to wear (mico-Deval) BS EN 1097-1: Part 1: 1998
Determination of resistance to fragmentation BS EN 1097-2: Part 2: 1998
Sodium Soundness Test (SSS) ASTM C88-90
Sulphate Content BS 812: Part 118
Magnesium Sulphate test BS EN 1367-2: Part 2
“Sonnenbrand” boiling test BS EN 1367-3: Part 3
Determination of Drying and Shrinkage BS EN 1367-4: Part 4
Aggregate Soundness BS 812: Part 121
Alkali-Silica Reactivity BS 812: Part 123: 1999
Tests for filler aggregates used in bituminous mixes – Delta ring and ball BS EN 13179-1: Part 1: 2000
Tests for filler aggregates used in bituminous mixes – Bitumen number BS EN 13179-1: Part 2: 2000

(ii) Tests on Concrete

Name of Test Standard Test Method

TESTING CEMENT
Determination of strength US 100-1/ EAS 148-1: Part 1
Chemical analysis of cement US 100-2 / EAS 148-2: Part 2
Determination of standard consistency, setting time and soundness US 100-3 / EAS 148-3: Part 3
Determination of chloride, carbon dioxide and alkali content US 100-4 / EAS 148-8: Part 4
Pozzolanicity test for pozzolanic cements soundness US 100-5:2001 / EAS 148-5: Part 5
Determination of fineness US 100-6:2001 / EAS 148-6: Part 6
Methods of taking and preparing samples of cement US 100-7:2001 / EAS 148-7

TESTING FRESH CONCRETE


Sampling BS EN 12350-1: Part 1: 2000
Slump Test BS 1881: Part 102: 1983
Vebe test BS EN 12350-3: Part 3
Making of Concrete Test Cubes BS 1881: Part 108: 1983
Concrete Cube Strength BS 1881: Part 116: 1983
Degree of Compactibility BS EN 12350-4: Part 4: 2000
Flow Table test BS EN 12350-5: Part 5
Determination of density BS EN 12350-6: Part 6: 2000
Air Content BS 1881: Part 106: 1983
Measuring fibre content in fresh glass fibre reinforced concrete BS EN 1170-2: Part 2

TESTING HARDENED CONCRETE


Shape, dimensions and other requirements for specimens and moulds BS EN 12390-1: Part 1: 2000
Making and curing specimens for strength tests BS EN 12390-2: Part 2: 2000
Compressive strength of test specimens BS EN 12390-3: Part 3: 2002
BS 1881: Part 116: 1983
Flexural strength of test specimens BS EN 12390-5: Part 5: 2000
Tensile splitting strength of test specimens BS EN 12390-6: Part 6: 2000
Density of hardened concrete BS EN 12390-7: Part 7: 2000
Depth of penetration of water under pressure BS EN 12390-8: Part 8: 2000
Cored specimens – taking, examining and testing in compression BS EN 12504-1: Part 2: 2000
Method of normal curing of test specimens BS 1881: Part 111: 1983
Method for testing cement in a reference concrete BS 1881: Part 131: 1983

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 21
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

(iv) Tests on Asphalt and Bituminous Materials

Name of Test Standard Test Method

Sampling Bituminous mixes BS 598: Part 100


Preconditioning of bitumen samples prior to mixing or testing NPRA 014 Test 14.511
Density of Bituminous Binders ASTM D70-97
Flash and Fire Point by Cleveland Open Cup ASTM D92-90
Thin-Film Oven Test (TFOT) ASTM D1754-87
Rotating Thin-Film Oven Test (RTFOT) AASHTO T 240
Penetration of Bituminous Materials ASTM D5-86 or BS 2000: Part 49
Softening Point Test ASTM D36-70 or BS 2000: Part 58
Ductility ASTM D113-86
Viscosity Determination using the Brookfield Thermosel Apparatus ASTM D4402-91 or BS 2000: Part 72
Kinematic Viscosity of Asphalts AASHTO T 201 or ASTM D 2170
Viscosity of Asphalts by Vacuum capillary Viscometer AASHTO T 202 or ASTM D 2171
Density and Water Absorption of Aggregates Retrieved on a 4.75 mm Sieve ASTM C127-88
Density and Water Absorption of Aggregates Passing the 4.75 mm Sieve ASTM C128-88
Calibration of Glass Pycnometers (0.5-1 litre) NPRA 014 Test 14.5922
Mixing of Test Specimens; Hot Bituminous Mixes NPRA 014 Test 14.5532
Determination of Maximum Theoretical Density of Asphalt Mixes ASTM D2041-95 and D4469-85
and Absorption of Binder into Aggregates
Bulk Density of Saturated Surface Dry Asphalt Mix Samples ASTM D2726-96
Bulk Density of Paraffin-Coated Asphalt Mix Samples ASTM D1188-89
Bulk Density of Asphalt Mix Samples, Calliper Measurements NPRA 014 test 14.5622
Calculation of Void Content in Bituminous Mixes ASTM D3203 and AASHTO pp19-93
Marshall Test ASTM D1559-89
Marshall Mix Design ASTM D1559-89
TRL Overseas Road Note 31,
Refusal Density Mix Design
Appendix D: 1990
Methods of test of the design of wearing course asphalt BS 598: Part 107
Methods for the determination of the condition of binder on coated chippings and for the
BS 598: Part 108
measurement of the rate of spread of coated chippings
Methods for the measurement of temperature of bituminous mixtures BS 598: Part 109
Temperature Measurement BS EN 12697 – 13: Part 13: 2000
Methods of test for the determination of density and compaction BS 598: Part 104
ASTM D3967 and NPRA 014 Test
Indirect Tensile Strength Test
14.554
Determination of Binder Content and Aggregate Grading by Extraction ASTM D2172-88, Method B
BS EN 12697 – 1: Part 1: 2000
Bitumen Recovery : rotary evaporator soluble binder content BS EN 12697 – 3: Part 3: 2000
Bitumen Recovery : fractionating column BS EN 12697 – 4: 2000
Water Content BS EN 12697 – 27: Part 14: 2000
Sampling BS EN 12697 – 27: Part 27: 2001
Distillation of cut back asphalt (bituminous) products BS 2000: Part 27
Frass breaking point of bitumen BS 2000: Part 80
Methods of testing plastics BS 2782: Part 3
Resin compositions-method for preparation of test specimens BS 6319: Part 1
Raw and vulcanised rubber-chemical tests BS 7164: Various dates
Plastics/rubber – Polymer dispersions and rubber lattices- Determination of residual
monomers and other organic components by capillary chromatography BS ISO 13741: 1998
Plastics and Liquid epoxy resins- Determination of tendency to crystallise BS ISO 4895: 1997
Effect of Water on Bituminous Coated Aggregates, Boiling Test ASTM D3625-96

(b) Uganda National Bureau of Standards (UNBS) US 401: 1993 Reflective sheeting materials for
US 100 Cement - methods of testing traffic control signs
US 101: 2000 Aggregates from natural sources
for concrete (c) American Association of State Highway and
US 104: 1993 Pozzolanas for use with lime Transport Officials (AASHTO)
US 144: 2000 Aggregates-particle size and M – 85 Ordinary Portland cement
particle shape determination M – 140 Bituminous prime coat
US 145: 2000 Aggregates-methods of sampling M – 153 Joint filler
US 146: 2000 Aggregates-determination of M – 154 Air entraining agents.
physical properties M – 173 Thermoplastic hot poured sealant
US 288: 2001 Lime for soil stabilisation M – 194 Concrete Admixtures
US 290: 2001 Glossary terms used in lime M – 213 Joint filler
products M – 216 Road lime
US 310: 2001 Compositions, specifications, M – 240 Portland blast furnace cement
conformity criteria and evaluation T – 87 Atterberg limits test method
for common cements T – 89 Atterberg limits test method
US 320: 2001 Cement-Definition of terminologies T – 90 Atterberg limits test method
T – 132 Sealant tests

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 22
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

T – 180 Maximum dry density test method BS – 6089 Concrete strength in existing structures
BS – 6543 Recycling
(d) American Society for Testing and Materials BS – 6572 Specification for High Density
(ASTM) Polyethylene (HDPE) pipes
A – 252-68 Pile castings BS – 6588 Portland pulverised fuel ash cements
C – 156 Curing agents BS – 6610 Pozzolanic pulverised fuel ash cement
C – 260 Air entraining agents BS – 6677 Clay and calcium silicate paver for
C – 309 Curing agents flexible pavements
C – 494 Concrete admixtures BS – 6699 Ground granulated blast-furnace slag
C – 719 Sealant tests for use with Portland cement
C – 920 Thermosetting chemically cured sealant BS – 6717 Precast concrete paving blocks
C – 227-90 Test method for alkali reactivity of BS – 7263 Precast concrete kerbs, edgings,
aggregates channels and quadrants
D – 36 Bitumen tests (Softening point) Bs – 7373 Preparation of specifications
D – 244 Bitumen tests (binder content test) BS – 7533 Pavement design-clay or concrete
D – 1557 Maximum dry density tests pavers
D – 4402 Bitumen tests (dynamic viscosity) BS – 7583 Portland and Limestone cement
BS – 7755 Soil quality
(e) British Standards Institute (BS) BS – 7850 Total Quality Management
BS – 7903 Selection and use of gully trops and
BS – 4 Structural steel hot rolled sections manholes
BS – 63 Road aggregates BS – 8000 Code of practice for concrete work
BS – 76 Tars BS – 8004 Code of practice for foundations
BS – 162 Working under power lines BS – 8006 Strengthened / reinforced soils and
BS – 146 Portland blast furnace cement with other fills
strength properties outside the scope of BS – 8110 Structural use of concrete
BS EN 197
BS – 410 Test sieves for particle analysis (f) Standard Coordination Specification (CKS)
Bs – 434 Bitumen road emulsions CKS – 82 Steel sections
BS – 594 Hot rolled asphalt CKS – 176 Corrugated metal culverts
BS – 470 Aluminium plate CKS – 191 Retro-reflective materials
BS – 709 Welding CKS – 192 Retro-reflective road marking paint
BS – 812 Fillers for asphalt CKS – 388 Natural rubber water stops
BS – 873 Traffic signs, road studs and bollards CKS – 389 PVC rubber water stops
BS – 881 VEBE test BS - 915 High alumina CKS – 437 Corrugated metal culverts
cement CKS – 564 Bonding liquid for concrete surfaces
BS – 970 Stainless steel CKS – 592 Barbed tape concertina wire
BS – 1134 Stainless steel plate
BS – 1154 Natural rubber (g) Deutshe Ingineur Norme (DIN)
BS – 1474 Aluminium sections DIN – 52013 Bitumen tests (ductility and elastic
BS – 1707 Hot binder distributors for road surface recovery)
dressing
BS – 1721 Fire extinguishers (h) South African Bureau of Standards (SABS)
BS – 1780 Pressure gauges SABS – 044 Welding procedures
BS – 2499 Hot applied joint sealants SABS – 064 Abrasive blasting
BS – 2752 Synthetic rubber SABS – 094 Holes for friction grip fasteners
BS – 2994 Cold rolled steel sections SABS – 0100 Concrete cores
BS – 3262 Hot applied thermoplastic road marking SABS – 0142 Electrical installations
materials SABS – 0162 Design of work/codes of practice
BS – 3662 Plastic road marking paint SABS – 05 Timber treatment
BS – 3690 Specification of bitumens for road SABS – 82 Steel reinforcing bars
purposes SABS – 92 Roofing felt (bridge bearings)
BS – 3837 Joint filler (rigid foams) SABS – 113 pH test (Water)
BS – 3892 Pulverised fuel ash SABS – 134 Paint
BS – 3921 Clay bricks SABS – 135 Bolts and nuts
BS – 4246 Low heat Portland blast-furnace cement SABS – 136 Bolts and nuts
BS – 4254 Joint sealant SABS – 141 Paint thickness test
BS – 4360 Structural steel SABS – 202 Chloride content (Water)
BS – 4447 Anchorages and couplers SABS – 212 Sulphate content (Water)
BS – 4486 High tensile alloy steel bars SABS – 213 Total dissolved solids (Water)
BS – 4840 Joint filler (rigid foams) SABS – 227 Bricks
BS – 4987 Coated macadams for roads and other SABS – 307 Penetration grade bitumen
paved areas SABS – 308 Prime
BS – 5047 Polymised types of butadiene rubber SABS – 309 Bitumen emulsion
(BR) SABS – 435 Rivets
BS – 5075 Concrete admixtures SABS – 455 Welding electrodes
BS – 5268 Timber SABS – 457 Timber Posts
BS – 5135 Welding SABS – 471 Ordinary Portland Cement
BS – 5212 Cold applied joint sealants SABS – 533 Pipes
BS – 5328 Specifying concrete SABS – 538 Timber treatment
Bs – 5273 Dense tar surfacing SABS – 539 Timber treatment
BS – 5400 Bridge bearings SABS – 548 Bitumen emulsion
BS – 5750 Quality systems SABS – 558 Manhole covers
BS – 5896 Steel wire SABS – 626 Portland blast-furnace cement
BS – 5911 Precast concrete pipes SABS – 630 Finishing coats (paint)
BS – 5930 Site investigation SABS – 634 Finishing coats (paint)
BS – 6031 Earthworks SABS – 657 Steel tubes
BS – 6044 Rubber lattices SABS – 673 Timber treatment
BS – 6088 Glass beads SABS – 675 Wire

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 23
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

SABS – 677 Pipes (k) European Standards


SABS – 679 Primer (paint)
SABS – 681 Undercoat (paint) BS EN 124 Concrete-Specification,
SABS – 684 Finishing coats (paint) performance, production and
SABS – 723 Primer (paint) conformity
SABS – 731 Road marking paint BS EN 125 Gully and manhole tops-loading,
SABS – 741 Sulphate content (cementitious binders) design and dimensions
SABS – 748 Prime BS EN 197 Cement-Composition,
SABS – 1519 Paint specifications, conformity criteria
SABS – 1555 Delineation signs and conformity evaluation
SABS – 1580 Wire mesh BS EN 206 Concrete-guidance to
SABS – 749 Prime specifier/specification for the
SABS – 754 Timber posts constituent materials and concrete
SABS – 763 Galvanishing BS EN 410-2 Test sieves
SABS – 772 Abrasive blasting BS EN 512 Fibre-cement products, pressure
SABS – 783 Finishing coats (paint) pipes and joints
SABS – 791 Pipes BS EN 1423 Road marking materials-glass
SABS – 801 Epoxy tar paint beads, antiskid aggregates and
SABS – 802 Finishing coats (paint) mixtures of the two
SABS – 821 Road Lime BS EN 1424 Road marking performance for
SABS – 831 Rapid hardening cement (OPC15) road users and premix glass beads
SABS – 836 Aggregate test BS EN 1456-1 UPVC pipes
SABS – 837 Sugar Content (Water) BS EN 1463 Road marking materials - Retro
SABS – 838 Sand equivalent test reflective road studs
SABS – 841 Alkali carbonates and bicarbonates BS EN 1824 Road trials
(water) BS EN 1871 Physical properties for paint,
SABS – 844 Relative density tests thermoplastic and cold plastic
SABS – 845 Compacted bulk density EN – 10113 Structural steel
SABS – 848 Polished stone value tests EN – 10155 Structural steel
SABS – 850 Sulphate content (aggregates) BS EN 1916 Precast concrete pipes
SABS – 855 Free water content (aggregates) BS EN 12271 Surface dressing
SABS – 856 Bulking of fine aggregates BS EN 12591 Specification for pavement grade
SABS – 862 Slump (concrete) bitumens
SABS – 864 Flexure strength test (concrete) BS EN 12597 Bitumen and bituminous binders-
SABS – 865 Compression strength (Concrete cores) terminology
SABS – 878 Ready mix concrete BS EN 12889 Trench less construction and
SABS – 912 Primer (paint) testing of drains and sewers
SABS – 920 Steel reinforcing bars BS EN 13055-1 Lightweight aggregates for
SABS – 921 Pipes concrete
SABS – 926 Zinc rich epoxy BS EN 13249 Geotextiles-characteristics required
SABS – 927 Kerbing fro use in construction of roads and
SABS – 934 Galvanising other trafficked areas
SABS – 967 Rubber joints for pipes BS EN 13251 Geotextiles-characteristics required
SABS – 986 Culverts for use in earthworks, foundations
SABS – 1024 Welded steel fabric and retaining structures
SABS – 1058 Paving blocks BS EN 13252 Geotextiles-characteristics required
SABS – 1077 Joint sealant for use in drainage systems
SABS – 1083 Aggregate BS EN ISO 10320 Geotextiles-Identification on site
SABS – 1085 Sand
SABS – 1091 Paint
SABS – 1143 Steel bolts and nuts 7503 ADDRESSES
SABS – 1149 Washers The Ugandan, AASHTO, ASTM, BS, BS EN, ISO, CKS,
SABS – 1223 Pipes DIN, SABS, SIS and US Federal specification and test
SABS – 1260 Prime method documents referred to in this document can be
SABS – 1282 Friction grip nuts and bolts obtained from the following sources:
SABS – 1350 Guardrails
SABS – 1373 Diamond mesh Central Materials Laboratory, Ministry of Works,
SABS – 1391 Galvanising Housing and Communications
SABS – 1413 Finishing coats (paint) P.O.Box 7188
SABS – 1431 Structure steel Kampala
SABS – 1442 Road Studs Uganda
SABS – 1500 Electrical installations Phone: +256 41 28 57 12
Fax: +256 41 28 60 56
(i) Technical Methods for Highways (TMH), South
Africa Uganda National Bureau of Standards
TMH – 1 Standard methods of testing road P. O. Box 6329
construction material Kampala
TMH – 5 Sampling methods for road construction Uganda
materials Tel +256 41 22 23 67/50 59 95
TMH – 6 Special methods for testing roads Fax +256 41 28 61 23
(j) International Standards Organisation South African Bureau of Standards
Private Bag x 191
ISO / R – 161 Specification for High Density Pretoria
Polyethylene (HDPE) pipes 0001
BS ISO 8349 Road vehicles-measurement of Tel +27 12 428 6925
road friction by direct liquid Fax +27 12 428 6928
injection method

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 24
GENERAL SPECIFICATIONS FOR ROAD AND BRIDGE W ORKS SERIES 7000 - TOLERANCES, TESTING AND QUALITY CONTROL

The SABITA specification and test method documents


can be obtained from:
SABITA
P. O. Box 6946
Roggebaai
South Africa
8012
Tel +27 21 421 2577
Fax +27 21 425 1279

The TMH and TRH documents can be obtained from:


Department of Transport (Publications Department)
P.O. Box 415
Pretoria
South Africa
0001
Tel +27 12 309 3310
Fax +27 12 328 5102

Comite Européen de Normalisation


36, rue de Stassart
B-1050 Brussels
Tel +32 2550 08 11
Fax +32 2550 08 19

International Organisation for Standardisation (ISO)


1, rue de Varembe, Case Postale 56
CH-1211 Geneve 20, Switzerland
Tel +41 22 749 011
Fax+41 22 733 34 30

THE REPUBLIC OF UGANDA, MINISTRY OF W ORKS, HOUSING AND COMMUNICATIONS PAGE 7000 - 25

You might also like