Performance Improvement of Pulverized Coal Fired Thermal Power Plant: A Retrofitting Option
Performance Improvement of Pulverized Coal Fired Thermal Power Plant: A Retrofitting Option
Performance Improvement of Pulverized Coal Fired Thermal Power Plant: A Retrofitting Option
ABSTRACT - The present study deals with the possibilities of renovation and modernization (R&M) options in
an existing 210 MW pulverized coal fired thermal power plant. Three different options along with its cost
implications have been discussed based on the performance and levelised cost of generation. The performance of
the unit for all the three options is examined under the consideration of increasing the availability of the unit
with continuous capabilities to generate power maintaining normal operating parameters over an extended life
of at least 15 years. The results revels that with the R&M approach the unit availability can be increase to more
than 85%, with a capacity enhancement of 215 MW and the heat rate of the unit will be approximately 2544
kcal/kWh.
Keywords - Coal fired power plant, Energy audit, Life extension, Moving electrostatic precipitator, Renovation
and modernization, Techno-economic
I. INTRODUCTION
For many decades, most countries have their electricity generation based on fossil fuel power plants.
Fossil fuel-fired power plants, especially coal-fired ones, will keep playing a major role in global power
generation. The majorities of these plants are still in operation and holds a major share in energy production.
Consequently, taking into consideration for fulfillment of different government regulations, high cost
involvement and other uncertainties in setting up a new unit, the option for need based improvement and
upgrading the operation and efficiency of these old units is much more lucrative option to get the benefits from
these old units within a short period.
The Government of India has embarked upon an ambitious plan to add 78,700 MW during the 11th
plan and 94431 MW during the 12th plan. The central Electricity Authority (CEA) in consultation with state
power utilities and other stake holders have prepared a national perspective plan for R&M and Life Extension
(LE) of thermal power stations up to the year 2016-2017 [1]. However, in view of high investment requirement
in the green field power station, resource constraints and environmental concern, there is an urgent need for
optimal utilization of existing generating capacity as well. In this context R&M and LE [2-5] of existing old
power plants is considered an economical option.
In India major part of the electricity generation is dependent on coal fired power plants. Coal is the
main natural resource in the country. However, the quality and the heating value are low, mainly due to high
levels of ash and moisture contained in the fuel. Most of the existing power plants of 210 MW are old units that
have been in commercial operation for 2 to 3 decades. The low efficiency of these plants due to exhausted life
causes important economic losses and environmental pollutions. Instead of replacing the old power plants before
or at the end of their expected life, retrofitting of these units under LE & energy efficient R & M scheme seems
to be the most economically viable solution [6, 7]. The retrofitting option is an alternative way, not only to
increasing the life of the plant, but also for increasing the total energy output of the plant. The main benefits of
R&M are:
To increase unit availability and reliability.
Restoration / up-rating of generation capacity.
Achieving rated or better efficiency of the unit.
To achieving an extended competitive plant-life of another 15 to 20 years.
To meet current environmental norms.
Li et al. [6] in his study did an investigation of over 100 large power plants in China to determine their
potential for a retrofit with CO2 capture, transport and storage. Korkmaz et al.[7] discussed retrofitting of
existing coal fired power plants with a Carbon dioxide capture. The study deals with the integration of an amine-
based flue gas scrubber within a coal-fired power plant including compression of CO 2 and the resulting effects
of the integration on the power plant’s operation. Xu G, et al.[8] in his work carried out process simulations,
5
Performance Improvement of Pulverized Coal Fired Thermal…
characteristic analysis, and system integration of CO2 capture based on an existing typical coal-fired power plant
in China with supercritical parameters. The main constraints encountered in decarburized retrofitting of the
existing power plants using mono-ethanolamine solution are analyzed. Heyena and Kalitventzeff [9] in their
study discussed three parallel proposals and compared on the basis of exergy efficiency for up gradation of
existing power plants. Yan et al.,[10] did an analysis in a 600 MW tangentially coal fired boiler to develop an
effective retrofit scheme to settle the problem of reheat steam under heating, excessive de-superheater water,
and temperature deviation at the furnace outlet. Ayodhi [4] in his paper describes the salient details of R&M of a
plant commissioned in the sixties. Srivastava and Sharna [5] in his study describes the RLA based R&M of a
steam turbine. Gerbelová, et al. [11] assesses the retrofit potential of existing Portuguese fossil fuel power plants
with post-combustion CO2 capture and storage (CCS) technology. The Integrated Environmental Control Model
(IECM) was used to provide a systematic techno-economic analysis of the cost of emission control equipment,
the reduction in greenhouse gas emissions, and other key parameters. Escosa and Romeo [12] presented
different repowering alternatives and a methodology for evaluating their integration within existing power plants
with the aim of reducing its CO2 emissions at minimum cost. As per the study the repowering as a suitable
technology to reduce 10–30% of CO2 emissions in existing power plants with cost well below 20 €/tCO2. Dalia
et al.[13] use an options-based analysis to determine the optimal capital investment for owners of an existing
pulverized coal power plant to make today, given their beliefs about the future values of key variables that affect
the investment outcomes.
In the present work we discuss the possibilities of renovation options in an existing 210 MW
pulverized coal fired thermal power plant. The objective is to estimate the potential performance and cost
implications of retrofitting in the existing fossil fuel power plant with improving the capacity of pulverizer and
modification in ESP along with replacement of the some of the existing systems to improve the availability and
plant life. Moving electrostatic precipitator (MEEP) technology have been introduced for the modification of
ESP as this does not required any lay out changes and can reduce the emission level less than 50 mg/Nm3. Three
possible options have been discussed along with the cost of implementation of each option. Also
thermodynamic simulation studies of the unit have been carried out to evaluate the current performance and best
achievable performance by renovation options.
6
Performance Improvement of Pulverized Coal Fired Thermal…
The boiler adopts pressurized direct firing system with 6 numbers of XRP 763 Bowl mills (5 working +
1 stand-by) with pulverizing capacity of 31.4 t/h each. Volumetric coal feeders are provided to feed raw coal to
the pulverizes. 2 x 100 % capacity seal air (SA) fan, having suction from primary air (PA) fan discharge header,
supplies the sealing air to the mills and coal feeders. The unit is having 4 oil fire elevations (1 for light diesel oil
& 3 for heavy fuel oil), having a capacity of 7.85 t/h per elevation (4 guns), are located amidst of coal elevations
for initial warm-up and support for low loading of the steam generator. Flame scanners are provided at every
firing elevation. Burner tilting, primarily to control reheat steam temperature, is also provided in the system.
III. METHODOLOGY
The R&M measures suggested in this study are based on hot and cold walk down survey [14, 15] of the
plant and energy audit measure taken during the course of the study. Need for the R&M of the unit was
discussed and various options for improvement in energy efficiency and replacement of existing
obsolete technology were indentified. The results of the analysis were verified using the Ebsilon(R) Professional
[7, 16] simulation model. Figure 2 indicates the step wise methodology for taking R&M measure.
Figure 3. Variation of plant load factor and unit cost Figure 4. Variation of GCV of coal
Based on condition and age, it is necessary to study the renovation possibilities if the unit is to
be continued in service. Variation of gross calorific value (GCV) of coal feed in the boiler for a period of 2009
to 2013 is shown in Figure 4. The coal GCV varies from 3300 to 3700 kcal/kg against the design GCV of 5000
kcal/kg. Based on the data collected and model simulation variation of boiler efficiency performance at a test
run of 1 hour period is shown in Figure 5. The average boiler efficiency was found to be 84.88 %.
7
Performance Improvement of Pulverized Coal Fired Thermal…
Figure 6 indicates the variation of turbine efficiency during the test run period. The average efficiency
of high pressure turbine (HPT), intermediate pressure turbine (LPT) and low pressure turbine (LPT) is found to
be 81.59%, 87.31% and 78.36 % respectively.
In Figure 7 variations of TG heat rate and unit heat rate is shown and the average TG heat rate is found
to be 2468.56 kcal/kWh and the average unit heat rate found to be 2905.28 kcal/kWh. Figure 8 shows that stack
emissions were above the prescribed norm of 150 mg/Nm3. The highest suspended particle matter (SPM) level
in the stack emission was recorded as 387 mg/Nm3 in 2012 and the second highest was recorded as 320 mg/Nm3
during 2011.
Figure 7. TG heat rate and gross unit heat rate Figure 8. Variation of SPM level
8
Performance Improvement of Pulverized Coal Fired Thermal…
The following important developments are included as part of R&M measures in the unit:
Improvement in fuel preparation/handling and firing system towards, uniformity of the flue gas
temperature distribution.
Uprating/modifying the milling system to grind low quality fuel (low calorific value and more % of
ash) available for the next 20 years. Proper grinding of coal to desired size together with the
appropriate air-fuel mixing should contribute to achieving complete combustion and the reduction of
the unburnt in the bottom and fly ash
Modification of combustion system to fire more amount of low grade coal and generate the rated
capacity steam at desired operating parameters to ensure the rated output
Implementation of techniques for low NOx burners & staged combustion for reduction of thermal NOx
emissions
Improvement of the air distribution system through modified Secondary Air Damper Control (SADC)
& wind box arrangement to maintain the desired air fuel ratio for each burner group in operation
Introduction of FSSS (Furnace safeguard and supervisory system) and BMS (Burner management
system)
Replacement, rearrangement or modification of heat exchange surfaces to match the distribution of heat
in different zones of the furnace.
Optimization of soot blower operation
Supplementary heat exchange surfaces within the existing furnace volume for further uniform heat
distribution of flue gas thermal energy
Improvement of the air preheating system with replacement for new basket and improved sealing
system.
Improved metallurgy for boiler pressure parts and heat exchanger components, which permit trouble
free operations and longer life (as also recommended by latest code for Indian Boiler Regulation)
Steam turbine retrofitting(blades with new design and improvement of the labyrinths operation and
turbine control system)
Distributed Control System (DCS).
Energy efficient auxiliaries such as improved control of BFP within the operating range, advanced
microprocessor based ESP controls, Vapor absorption system for HVAC system etc.
Enhanced safety features and environmental improvements using, effluent treatment plant,
modified fire fighting system, online pollution monitoring, dry ash utilization etc.
Since the unit is firing with poor grade coal of GCV around 3500 kcal/kg, the flue gas volume is on
higher side compared to the design and the ESP is incapable to handle this higher volume. Thus the ESP
performance deteriorated drastically with heavy SPM level at outlet exceeding 200 mg/Nm3 which seems to be
high compared to the current norms of 50 mg/Nm3 as per MOEF guidelines. To address the above situation, it is
proposed to retrofit the ESP with MEEP [17] technology. This technology can be applied to the last field of the
ESP without any requirement of extra space, so that the issue of the layout which is a common problem for the
older units can be addressed without any major layout modification. Moreover, this technology shall bring down
9
Performance Improvement of Pulverized Coal Fired Thermal…
the emission level less than 50 mg/Nm3 resulting reduction in pollution. Also the unit was originally designed
with four mills in service and two standbys. In current condition due to deterioration in coal quality and the
aging factor, the unit is not able to generate 210 MW on a sustainable basis with all 6 mills in service without no
standby. The consequences will be on generation in case of breakdown of a single mill. Thus keeping in view of
the station requirements to achieve 210 MW, it is being proposed that the existing mills are up rated from XRP
763 to six numbers of new XRP 803 mills of 39.8 t/h each to increase the throughput. With the above
modifications, with the current coal quality the unit shall be able to achieve full load condition with four mills in
service and other two in standby for emergency operation.
The energy audit and RLA studies have indicated the measures to be undertaken to restore the unit at a
minimum to its original design conditions and extend its life by 15-20 years. This has been considered as the
base case of the study. Each of these naturally requires additional investments. However, there are returns in
terms of improved efficiency, output, availability and plant load factor, which can pay back the investments.
The combination of measures in each option is the result of recommendations arising out of the energy
audit and the practical possibilities based on proven technology currently available. Based on the above, three
options have been considered for techno-economic study as shown in Table 1.
Levelised heat rate = (X+50)*1.06, where X is the Heat rate measured as per PGT procedure and 50 kcal/kWh is
the variation of operation correction from design parameters and 6% allowance as per CERC norms [18]. The
estimated costs of different options have been calculated taking into account the measures recommended
for the particular option.
10
Performance Improvement of Pulverized Coal Fired Thermal…
The levelised cost of generation (COG) is calculated for all the three options. The quantum of
generation loss during the shutdown of the plant is taken as a cost and taken into account as the short term price
of power to be procured at Rs. 5.30/kWh, being the costliest power available for purchase by the Utility for the
short term. Summary of results of financial analysis is presented in Table 2.
The benefits anticipated as a result of implementation of the preferred option for this project, as noted
in the report, could briefly be the following:
Life of the unit will be extended for 15-20 years.
Rated capacity/ designed capacity of 210 MW will be restored and will be improved further with
additional measures.
Forced outages will be reduced.
Environmental improvement measures taken will enable plant to meet Pollution Control Board norms.
Higher safety will be ensured for operational personnel and equipment.
Savings in maintenance expenditure, fuel oil consumption and auxiliary power consumption.
11
Performance Improvement of Pulverized Coal Fired Thermal…
On the basis of the financial analysis, the operational benefits include percentage reduction in auxiliary
consumption, increase PLF, reduction in station heat rate with resultant savings in coal and oil consumption and
availability of incremental saleable energy. The economic benefits accruing (1st year) after implementation of R&M
program under each option as a result of improved operational performance of the plant over the position as existed prior
thereto (Business As Usual) are summarized in Table 3.
Table 3. Economic benefits (1st Year) after R&M (in INR Million)
BCR is higher under option C followed by options B and then A. R&M capital cost compared to the capital cost
for new capacity addition under different options is shown Table 4. The R&M capital cost compared to capital cost of
new capacity addition is considered to be more economical resulting in savings to the utility both in terms of capital cost
and the cost per MW. Benefit-Cost-Ratio (BCR) as worked out in the financial analysis in the report for option A, B and C
are 1.13, 1.34 and 1.37 respectively as shown in Table 5.
R&M of the units will result in additional generation and use of beneficiated coal will result in savings in coal and
fuel oil consumption. The incremental saleable energy becoming available after implementation of R&M program will
minimize dependence on power purchase from outside the State. In monetary terms, this is also expected to result in
appreciable savings in power purchase cost. Sensitivity analysis considering the impact of variation due to adverse
implementation scenarios such impact of change in capital cost, change in power tariff & increase in shutdown duration, it is
observed that the project would be able to sustain the variation and will remain financially viable with different marginal
considerations. Given the considerations to the economic and financial benefits as well as the risk factors under the various
options as have been brought, option C is considered as the best option based on the comfort ability margin, and the BCR. It
is also the best suited technical solution as regards sustainability to risk factors.
12
Performance Improvement of Pulverized Coal Fired Thermal…
REFERENCES
[1] CEA, “National Perspective Plan for Renovation & Modernization and Life Extension of Thermal Power Stations (up to 2016-17),”
2009.
[2] N. AYODHI and M. PAL, “Renovation, Up-gradation and Modernization of Durgapur Projects Power Station: Life Extension
Program First of its kind in INDIA,” in PowerGen, Delhi, 2000.
[3] N. AYODHI, “Life assessment and Life extension of Thermal Power Plants employing NDT technique - a case study,” in EPRI
Conference, 2002.
[4] N. Ayodhi, “Renovation and Modernisation of Thermal Power Plants,” OMMI, vol. 1, no. 2, 2002.
[5] A. Srivastava and V. Sharan, “Residual Life Assessment (RLA) based Renovation & Modernization (R&M) of steam turbines,” in
International Conference & Exhibition India Thermal Power-4, 2007.
[6] J. Li, J. Gibbins, T. Cockerill, H. Chalmers, M. Lucquiaud and X. Liang, “An assessment of the potential for retrofitting existing
coal fired power plants in China,” Energy Procedia 4, pp. 1805-1811, 2011.
[7] Ö. Korkmaz, G. Oeljeklaus and K. Görner, “Analysis of retrofitting coal-fired power plants with carbon dioxide capture,” Energy
Procedia 1, pp. 1289-1295, 2009.
[8] G. Xu, Y.-p. Yang, J. Ding, S. Li, W. Liu and K. Zhang, “Analysis and optimization of CO2 capture in an existing coal-fired power
plant in China,” Energy, 2013.
[9] G. Heyena and B. Kalitventze, “A comparison of advanced thermal cycles suiTable for upgrading existing power plant,” Appl
Thermal Eng, vol. 19, p. 227–37, 1999.
[10] Y. Linbo, H. Boshu, P. Xiaohui, W. Chaojun, Y. Min and S. Jingge, “Research on Retrofit Schemes for Reheat Steam
Underheating and Excessive Desuperheater Spray for a 600 MW Tangentially Coal-Fired Boiler,” Energy Fuels, vol. 26, pp. 5804-
5820, 2012.
[11] H. Gerbelová, P. Versteeg, S. Christos, Ioakimidis and P. Ferrão, “The effect of retrofitting Portuguese fossil fuel power plants with
CCS,” Applied Energy , vol. 101, p. 280–287, 2013.
[12] J. M. Escosa and L. M. Romeo, “Optimizing CO2 avoided cost by means of repowering,” Applied Energy, vol. 86, p. 2351–2358,
2009.
[13] D. P. Echeverri, B. Morel, J. Apt and C. Chen, “Should a Coal-Fired Power Plant be Replaced or Retrofitted?,” Environ. Sci.
Technol., vol. 41, p. 7980–7986, 2007.
[14] ASME, “PTC 102 Operating Walkdowns, Draft Report,” ASME PTC-101 – Outage Inspections, 2011.
[15] E. B. Woodruff, H. B. Lammers and T. F. Lammers, Steam Plant operation, New York: McGraw Hill, Inc., NY Sixth Edition,
1992.
[16] “https://www.steag-systemtechnologies.com/ebsilon_professional+M54a708de802.html,” Steag. [Online].
[17] T. Kojo, “Optimal Solution For Blue Skies MEEP for Retrofit Application,” in CEA-JCOAL Workshop , New Delhi, 2012.
[18] CERC, “Recommendations on Operation Norms for Thermal Power Stations for Tariff Period beginning 1st April 2009,” 2008.
[19] Ministry of Power, “Tariff Policy published by authority Ministry of Power,” 2006. [Online]. Available:
http://powermin.nic.in/whats_new/pdf/Tariff_Policy.pdf.
[20] CERC,“http://www.npti.in/Download/Distribution/CERC- (Terms%20&%20Conditions%20of%20Tariff)%20FY%202009-
14.pdf,” CERC, 2009. [Online].
[21] CERC, “http://www.cercind.gov.in/,” 2009. [Online]. Available: http://cercind.gov.in/2009/February09/SOR-regulations-on-T&C-
of-tariff-05022009.pdf.
13