BP HBK 76100 00001 PDF
BP HBK 76100 00001 PDF
BP HBK 76100 00001 PDF
Handbook
procedures or recommendations.
1.0 Introduction
7.0 Chain
9.0 Slings
Points
Cranes
Cranes
1.1 Forward
1.2 Acknowledgement
1.3 Scope
1.4 References
1.5 Definitions
1.6 Acronyms
Introduction
1
1.1 Foreword
Maintenance Programs.
and practices.
2
Introduction
1.2 Acknowledgement
Mechanical Equipment
Introduction
3
1.3 Scope
compliance is discretionary.
1.4 References
others:
Caution
B Regulatory Documents
C Industry Standards
Manual (1996)
Cranes
Hoist)
D Other Publications
Unirope Catalogue
1.5 Definitions
OHSA as well.
Basic Lift: A lift where despite the nature of the load being
the Environment.
8
Introduction
Critical Lift: Any lift of an object where due to the nature of the
the lift. Considerations for this include, but are not limited to,
as Factor of Safety.
complexity.
wire rope.
slings.
to the left).
strands and the strands composing the rope are laid in the
same direction.
sling.
Load Path: The route the lift team intends to use to move the
effort.
Critical lifts.
of a crane which pulls out the load line as the hook is lowered.
Engineer. (RSE)
Introduction
11
a rope is bent.
personnel involved.
Strand Laid: Wire rope made with strands laid around a fibre
of the lift.
counterweight.
Tag Line: A light line used to control the position of a load and
takes into account the design factor. Note: Was once called the
no longer used.
Introduction
13
1.6 Acronyms:
AF Angularity Factor
C of G Centre of Gravity
LW Load Weight
CAUTION
Engineering.
Introduction
15
2.1.6 Riggers
2.1.7 Signalers
2.3.1 General
2.3.2 Management
2.3.5 Operator
2.3.7 Signaler
2.3.8 Engineering
2.4.1 General
2.4.2 Control
Program Overview
18
Personnel Requirem ents
months.
OHSA.
requirements
Hoist Operators
Bruce Power
requirements
Bruce Power
requirements
2.1.6 Riggers
Riggers:
a Basic
requirements
b Skilled
requirements
c Master
requirements
2.1.7 Signalers
Maintenance Programs
obtain a qualification.
NOTE
Approval.
22
Personnel Requirem ents
a Vision Tests
corrective lenses
b Hearing Test
months.
themselves or others
equipment to be operated
24
Personnel Requirem ents
2.3.1 General
Management
Supervisor of Equipment
Operator
Rigger
Signaler
Engineering
the lift
2.3.2 Management
Shall:
operation
extinguisher.
26
Personnel Requirem ents
prior to use.
Skilled or Basic).
approval.
maintained.
Engineering.
w Ensure that the operator has more than one safe way
lift.
supervisor
28
Personnel Requirem ents
operation.
Form.
condition.
appropriate tag
adding a counterweight
adequately.
installed correctly
the following:
and hold.
30
Personnel Requirem ents
load.
manufacturers recommendations.
raised.
2.3.5 Operator
the controls
so fitted)
local authority
Inspection Log
fire extinguisher
appropriate
b Know the weight of the load and the crane and hook
capacity.
required.
movements.
Personnel Requirem ents
33
2.3.8 Engineering
lifting events.
2.4.1 General
rigging equipment.
load.
same thing.
should be avoided.
2.4.2 Control
documents.
Control:
40
Personnel Requirem ents
spreader.
required.
may proceed.
land the load. This may indicate that the load has
Lifts.
technique.
42
Personnel Requirem ents
drum.
1 The load is lifted and held for 120 seconds. Once the
height.
come to rest.
path.
to come to rest.
come to rest.
44
Personnel Requirem ents
2.5.1
selected
to be rotated vertically)
lifts that require the use of more than one hoist (i.e.
to drift a load)
structural support
lifts where the sling angle of any sling is less than 45°
energized
contaminated/radioactive loads
of balancing a load)
48
Personnel Requirem ents
Program Overview
2.7.1
2.7.2
Handling Equipment.
50
Personnel Requirem ents
required.
of Influence)
block
other structure
winching
blocks
and is followed
concrete forms
ensured:
knotted
in the area.
adjacent obstructions.
Rigging and Lifting Pra ctices
55
other arrangement.
56
Rigging and Lifting Pra ctices
used.
1 Engineering calculations
manufacturer
sizing rigging.
3 Shipping papers
container
4 Procedures
7 Work Reports
independent verification).
58
Rigging and Lifting Pra ctices
obstruction.
proceed.
NOTE
CAUTION
Approximate Weights
For example:
= 918 lb.
plate.
square foot
= 601 lb.
rectangular shapes.
For example:
circle):
Circumference = Diameter x
= 5 ft x 3.14
= 15.7 ft
= 2,883 lb.
follows:
40 pounds
square foot
= 900 lb.
62
Rigging and Lifting Pra ctices
Width x Thickness).
1,728.
Table 3-1
d
b
a
d D
A = r
A =
A = a b
4
(D
- d
)
2
2
C = 2 r
d
D
d
l
l
V = l w h
V =
4 d
l
2
V =
4
l (D
2
- d
2 )
Cubes/Rectangles
= (4 ft x 3 ft x 2 ft) x 490
Weight = 11760
Steel 490#
2 ft.
per cu. ft.
ft.
3
4 ft
Weight = ((πr1
2 H) ( π r2
r2 = Inside Diameter
Weight = ((πr1
2 H) ( π r2
= (((3.14x 2
2 ) x 10) - ((3.14x 1
2 ) x 10)) x 150
2 ft.
4 ft.
Plain Concrete
4 ft.
2 ft.
150#
10 ft.
10 ft.
64
Rigging and Lifting Pra ctices
Cylinders (solid)
3 ft.
= (π r
2 H) x Material Weight
= (3.14(1.5)
2
x 10) x 530
10 ft.
= 3.14(2.25) x 10 x 530
Round Plates
Weight = (πr
2 H) x Material Weight
= (3.14(3)
2
x 0.166) x 530
Weight = 2,486.31
2 in.
6 ft.
Table 3-2
Volume
Mass
Length
Area
66
Rigging and Lifting Pra ctices
Table 3-3
Asphalt 85 1,360
Riprap 90 1,440
load weight.
Table 3-4
Thickness
Weight
Thickness
Weight
[in]
[lb/sq ft]
[mm]
[kg/sq m]
3/8 15.3
10 78
1/2 20.4
12 94
5/8 25.5
16 125
3/4 30.6
19 148
7/8 35.7
22 172
1 40.8
25 195
1-1/8 45.9
28 218
1-1/4 51.0
32 250
1-3/8 56.1
35 273
1-1/2 61.2
38 296
1-3/4 71.4
45 351
2 81.6
50 390
Table 3-5
Diameter
Sch 80 Pipe Sch 160 Pipe
[in]
[lb/ft] [kg/m] [lb/ft] [kg/m]
1 2 3 4 6
1-1/4 3 4 5 7
1-1/2 4 6 6 9
2 5 7 9 13
2-1/2 8 12 14 21
3 10 15 19 28
3-1/2 13 19
4 15 22 28 42
5 21 31 39 58
6 29 43 53 79
8 43 64 72 107
68
Rigging and Lifting Pra ctices
Table 3-6
1 2.7 4.0
2 10.7 15.9
3 24.0 35.7
load stability
equal.
a sling to be overloaded.
Unstable
Unstable
Stable
C of G is above
Hook is not above C of G and load will
Hook is above
Figure 3-1
Effect of C of G on Lift
70
Rigging and Lifting Pra ctices
Unstable
Stable
Figure 3-2
Position of Attachments
Angle.
B
A
B
Figure 3-3
72
Rigging and Lifting Pra ctices
Figure 3-4
Load Leveled
selecting slings:
shall be known
headroom
74
Rigging and Lifting Pra ctices
rotation.
the C of G.
Figure 3-5
bridle hitch.
sling legs.
sling will share the load equally among its legs, sling
load.
Figure 3-6
76
Rigging and Lifting Pra ctices
may tear.
of gravity.
may be damaged.
Table 3-7
90° 200%
60° 170%
45° 140%
30° 100%
Figure 3-7
supporting it.
78
Rigging and Lifting Pra ctices
Figure 3-8
sling
point
NOTE
Angle of Choke.
Table 3-8
Angle of Choke
Angle of Choke
Percent of Sling Rated Capacity
in Degrees
To be used in a choker hitch
90 - 120 87
60 - 89 74
30 - 59 62
0 - 29 49
80
Rigging and Lifting Pra ctices
Figure 3-9
short
Figure 3-10
the load
choker hitch
Figure 3-11
tightly together
balance loads
sling leg
Figure 3-12
Figure 3-13
Load Turning
Figure 3-14
Figure 3-15
Turning a Load
86
Rigging and Lifting Pra ctices
should be used.
NOTE
Figure 3-16
Long Loads
Rigging and Lifting Pra ctices
87
use of shackles.
performed:
load.
engineered lift.
88
Rigging and Lifting Pra ctices
length.
Halfthe
C of G
length
Load
Length xWidth
Zone ofInfluence
Half the
x
width
Twice the Width
Preffered
load is moved horizontally
direction of
(Bridge, Trolley, Jib)
horizontal
motion
Load may
Highest potential for
rotate
movement is about
load is lifted from the floor/grade
Figure 3-17
Zone of Influence
at a time.
90
Rigging and Lifting Pra ctices
uncontrolled motion.
horizontally
diameter.
line.
point.
hand.
92
Rigging and Lifting Pra ctices
up the building.
hoist.
hoist.
these specs.
c If all rigging does not fit within this area, then one or
Figure 3-18
1-2-4 Formation
94
Rigging and Lifting Pra ctices
4.1 General
Apparatus
4.7.1 Wind
4.7.2 Temperature
4.7.3 Icing
4.8 Communication
4.8.2 Signaler
4.1 General
P Power on
check N, S, E, W
hook/block assembly
96
Genera l Cra ning Considerations
and Maintenance
Crane manufacturer
NOTE
98
Genera l Cra ning Considerations
disconnected.
time to operate.
sheaves.
authorized to do so.
100
Genera l Cra ning Considerations
moved.
acetylene cylinders).
a crane.
not be dragged.
if it is locked out.
operator present.
102
Genera l Cra ning Considerations
Figure 4-1
Rules).
104
Genera l Cra ning Considerations
Electrical Apparatus
apparatus:
hoisted.
moved laterally.
distances.
as a non-conductor).
106
Genera l Cra ning Considerations
following:
operations
operations
charged.
contact protection.
ground probes
ground mats
lead.
108
Genera l Cra ning Considerations
WARNING
crane.
contact.
to do so.
potential).
inspection.
110
Genera l Cra ning Considerations
4.7.1 Wind
deferred.
4.7.2 Temperature
4.7.3 Icing
exposed to the wind. These forces are not factored into load
charts.
112
Genera l Cra ning Considerations
4.8 Communication
particularly important:
else.
4.8.2 Signaler
114
Genera l Cra ning Considerations
Overhead).
crane operators.
completely.
Figure 4-3a
Figure 4-3b
Figure 4-3c
Figure 4-3d
Figure 4-3e
Figure 4-3f
5.1 General
5.1.1 Size
5.1.2 Construction
5.1.4 Core
5.1.5 Lay
5.1.7 Description
5.1.8 Strength
5.3.1 Handling
5.4.1 Application
Wire Rop e
123
5.1 General
combine to determine
of a wire rope. In
smaller wires.
Figure 5-1
Basic Composition of
Wire Rope
(Courtesy ofUnirope)
124
Wire Rop e
5.1.1 Size
Figure 5-2
(Courtesy ofUnirope)
5.1.2 Construction
or wire).
Wire Rop e
125
Seale IWRC
Seale IWRC
die drawn*
Compac® Rotation
Python® Construct 6
Python® super 6R/8V*
Resistant*
(pre-stretched)*
Cable
Aircraft cable
Cable*
Figure 5-3
Courtesy ofUnirope
126
Wire Rop e
d All wire rope used for cranes and hoists shall be the
follows:
strength ropes.
Wire Rop e
127
5.1.4 Core
were originally supplied with fibre core (FC) ropes. Fibre core
CAUTION
5.1.5 Lay
rope centerline.
to the left.
easily.
obtained.
of the rope.
Figure 5-4
Figure 5-5
Wire Rop e
129
5.1.7 Description
c Metric example:
5.1.8 Strength
Table 5-1
Factor ofsafety = 5
Rope dia.
Weight
6x19 Class IWRC
6x37 Class IWRC
[in.]
[lb/ft]
SWL in Pounds
SWL in Pounds
Grade
Grade
Grade
Grade
110/120
120/130
110/120
120/130
IPS
[1]
EIPS
[2]
IPS
[1]
EIPS
[1]
Wire Rop e
131
Table 5-2
Factor ofsafety = 5
Rope dia.
Weight
6x19 Class IWRC
6x37 Class IWRC
[mm]
[kg/m]
SWL in Pounds
SWL in Pounds
Grade
Grade
Grade
Grade
110/120
120/130
110/120
120/130
IPS
[1]
EIPS
[2]
IPS
[1]
EIPS
[1]
132
Wire Rop e
among suppliers).
resistant rope.
Wire Rop e
133
the device they are attached to. Users should look for loose
Wire Rope
134
Wire Rop e
Figure 5-6
Table 5-3.
Table 5-3
Wire Rop e
135
Table 5-4
6x25 wire
Aluminum conduit
Die size for pressing
rope size
or IPS piping
136
Wire Rop e
5.3.1 Handling
placed through the reel and the reel lifted using slings
or jack stands.
should be performed:
Wire Rop e
137
Figure 5-7
so that the turns lie snugly against each other in even layers.
whether the rope leads from the top or bottom of the drum.
Drum):
on the drum.
138
Wire Rop e
Figure 5-8
The fleet angle is the angle between the centre of the first
Figure 5-9
Fleet Angle
140
Wire Rop e
centre line to the flange. When the fleet angle is 2°, the
metric measurements.
Any time the fleet angle exceeds 2°, consult Engineering for
Wire Rop e
141
5.4.1 Application
revision).
the drum
device:
1 lay
142
Wire Rop e
by more than
and including 29 mm
another)
electricity
connector
damaged or broken.
Wire Rop e
143
winding or bending
revision):
144
Wire Rop e
of the wedge
cable
the cable
Wire Rop e
145
load hoist rope, all boom hoist rope, and all trolley
the drum.
crane log.
procedures.
1 Shock Load:
rope
146
Wire Rop e
Figure 5-10
Courtesy OPG
2 Broken Wires:
of a strand
replaced)
Interface
Wire Rop e
147
lay
Figure 5-11)
Figure 5-11
6 Reduction in Rope:
on the drum).
148
Wire Rop e
7 Stretch:
reduction in diameter.
8 Corrosion:
9 Distortion:
Figure 5-12
Table 5-4
Inch mm Inch mm
up to 3/4 19 3/64 1
Wire Rop e
149
10 Insufficient Lubrication:
lines.
12 Accumulation of Defects:
condition.
rope. Always re-reel wire rope from the top of one reel to
on a Drum.
150
Wire Rop e
6.1 General
6.3 Whipping
6.4.5 Half-S
6.4.6 S Bend
6.5.4 Overloading
Degradation
6.5.7 Heat
Fibre Rope
151
6.1 General
larger rigging
152
Fibre Rope
strength of nylon
unaffected by water
Fibre Rope
153
Table 6-1
Plaited 100-115%
Plaited 135%
Plaited n/a
154
Fibre Rope
Table 6-2
Rope
three-strand
Braided
3-stand
Nylon
Polyester
Kernmantle
Dia.
poly-
poly-
nylon
braid
braid
(in)
propylene
propylene
Fibre Rope
155
6.3 Whipping
Figure 6-1
156
Fibre Rope
Fibre rope, unlike wire rope, does not need a permanent end
Note
Fibre Rope
157
Working End
Standing Part
Overhand Loop
Bight
Figure 6-2
Figure 6-3
158
Fibre Rope
Figure 6-4
front
Figure 6-5
Fibre Rope
159
the loop you want. Form an overhand loop in the bight, and
take the free end behind the standing part, and back
through the loop from the top. Adjust the size of the loop to
Figure 6-6
pole, etc.). Take the working end of the rope and make four
overhand loops around both parts of the rope. Pass the free
end through all the loops, and ease the knot tight. This knot
Figure 6-7
Half-S Knot
160
Fibre Rope
This bend is essentially two Half-S knots tied over the two
the two rope ends parallel. Wrap one working end four
times around itself and the other rope. Pass the working end
through the loops and draw tight. Repeat with the other
working end. Pull the two knots together. This knot replaces
Figure 6-8
S-Bend Knot
Fibre Rope
161
New Rope).
unwound counter-clockwise.
162
Fibre Rope
spread wear.
Fibre Rope
163
removed with care, if they are simply pulled out, the rope
6.5.4 Overloading
Rope, allows for a design factor of five. Rope that has been
reduced diameter
164
Fibre Rope
following:
failure.
immediately.
loss of flexibility
local glazing
Fibre Rope
165
6.5.7 Heat
be encountered
may be touched
166
Fibre Rope
7.0 Chain
7.1 General
7.2 Grades
Chain
167
7.1 General
1 Advantages
is easily stored
is flexible
easy to detect
2 Disadvantages
difficult to measure
800° F
168
Chain
shall be specified.
by the manufacturer.
Chain
169
7.2 Grades
7.2.1 Grades
7.2.2 Classifications
classifications:
170
Chain
Figure 7-1
Chain
171
Table 7-1
Factor ofsafety
Nominal
Working load limit
Max. length of 100 links
Approximate
size
[lb]
[in]*
weight of
100ft [lb]
172
Chain
used.
Chain
173
obstacles.
two links.
174
Chain
Chain
175
link before use for the following (refer to Figure 7-2 Chain
Inspection):
weld splatter
severe corrosion or
pitting
discoloration due to
exposure to heat
reduced diameter at
reduction is >10%)
elongated (stretched),
Compare a length of
exceeds 3 percent
Figure 7-2
Chain Inspection
176
Chain
8.1 General
8.2 Hooks
8.2.1 General
8.3.1 General
8.4 Links
8.4.1 General
8.5 Shackles
8.5.1 General
8.6 Eyebolts
8.6.1 General
8.7.1 General
8.8.1 General
Fittings a nd Hardware
177
8.9.1 General
8.10 Swivels
8.10.1 General
178
Fittings and Hardwa re
8.1 General
being discarded;
defective item.
Fittings a nd Hardware
179
not be exceeded.
inspection.
180
Fittings and Hardwa re
8.2 Hooks
8.2.1 General
hook.
NOTE
Figure 8-1
Figure 8-2
Sling Hooking
182
Fittings and Hardwa re
side).
NOTE
Table 8-1
Crosby
WLL Dimensions (inches) Weight
designation
Mg Tons B E
(lbs)
Fittings a nd Hardware
183
Figure 8-3
Sling Hook
Table 8-2
Sling Hook
184
Fittings and Hardwa re
Design factor = 4
Figure 8-4
Grab Hook
Table 8-3
Grab Hook
Fittings a nd Hardware
185
Figure 8-5
Sling Positioning
Attachment).
Figure 8-6
186
Fittings and Hardwa re
Figure 8-7
8.3.1 General
the wear.
Figure 8-8
Table 8-4
per 100
Overall
Inside
Overall
Inside
Width of
(lbs.)
length
length
width
width
score
Fittings a nd Hardware
189
extreme wear
190
Fittings and Hardwa re
8.4 Links
8.4.1 General
Figure 8-9
Links
Fittings a nd Hardware
191
Table 8-6
Design Factor = 6
Stock
Dimensions (in.) Working load Weight
diameter
each
(in.)
Outside length Outside width
lbs. Kg.
(lbs.)
(large end)
192
Fittings and Hardwa re
Table 8-7
Design Factor = 6
Fittings a nd Hardware
193
Table 8-8
included angle or smaller. For included angles greater than 60 degrees, the
A
Working load limit (lbs)* Weight
Dimensions (in.)
size
each
(in.) Based on
Based on
(lbs.) B C D E F
Grade 8
5:1 Design
chain (4:1)
factor
Figure 8-10
Connecting Link
194
Fittings and Hardwa re
Table 8-9
Connecting Link
Design Factor = 4
Each
Load Limit
Load Limit
sling
manufacturers markings
wear)
Fittings a nd Hardware
195
8.5 SHACKLES
8.5.1 General
Only" policy.
For example:
types.
196
Fittings and Hardwa re
Pinching).
Figure 8-11
Fittings a nd Hardware
197
shackle body.
WLL to be used.
Figure 8-12
Figure 8-13
be applied in the
90 degrees
Figure 8-14
Fittings a nd Hardware
199
120°
Maximum
LOAD
Figure 8-15
Courtesy ofCrosby
200
Fittings and Hardwa re
Table 8-11
Design Factor 6
Nominal Size
Working Load Limit Stock Number Weight Each
in inches
Tons Pounds G-209 S-209
in pounds
Fittings a nd Hardware
201
Table 8-12
Round
Working Load Limit Web Slings Stock
Weight
Sling
Tons Pounds Webbing
Eye
Ply
Number
Each
Size
Width
Width
S-281
in
Number
Inches
Inches
pounds
body
inside width at the pin has not increased (if the pin
202
Fittings and Hardwa re
Figure 8-16
Shackle Inspection
Figure 8-17
Shackle Use
Fittings a nd Hardware
203
8.6 Eyebolts
8.6.1 General
Only" policy.
against a load.
be over tightened.
204
Fittings and Hardwa re
Figure 8-18
Eyebolt Installation
eyebolt diameter.
bronze
plastic
Fittings a nd Hardware
205
Figure 8-19
eyebolt failure.
Table 8-13
Eyebolt Shimming
1/4 0.0125
5/16 0.0139
3/8 0.0156
1/2 0.0192
5/8 0.0227
3/4 0.0250
7/8 0.0278
1 0.0312
1-1/4 0.0357
1-1/2 0.0417
For example:
entire assembly.
Fittings a nd Hardware
207
vertical lift but may not have the capacity for a 60°
sling angle.
Rating (Imperial))
WARNING
CAUTION
Improper Attachments).
eyebolts to a hook.
Figure 8-20
Improper Attachments
210
Fittings and Hardwa re
Table 8-14
Eyebolt
Than
Size
Tons Pounds Tons Pounds Tons Pounds
45°
Not Recommended
3/8 x 1-1/4
1/2 x 1-1/2 1.30 2,600 0.85 1,690 0.39 780
Fittings a nd Hardware
211
Table 8-15
Eyebolt
Size
Metric
Kilograms Metric
Kilograms Metric
Kilograms
Than
45°
Tons
Tons
Tons
Not Recommended
212
Fittings and Hardwa re
following:
wear or damage
(after manufactured)
unknown amount.
repair procedure.
Fittings a nd Hardware
213
8.7.1 General
only policy.
ring sizes
shank diameter.
214
Fittings and Hardwa re
bolt requirements:
at Bruce Power.
Figure 8-21
Fittings a nd Hardware
215
Table 8-16
Nominal Size
Working Load Limit Bolt Torque in
Thread Projection
in inches
Tons Pounds
Foot Pounds
Length in Inches
1. WLLs in this table are applicable to Crosby Swivel Host Rings only
2. The star* above indicates a longer bolt shank length for soft
216
Fittings and Hardwa re
Table 8-17
Round
Working Load
Web Sings Torque
Bolt Size
Spool
Thread
Sling
Limit
ft lb
inches
Bolt &
Projection
Size
Nut
Length
Number
Torque
Width
Width
ft lb
Inch
Inch
1. The star* above indicates a longer bolt shank length for soft
Hoist Rings).
Fittings a nd Hardware
217
Figure 8-22
proper torque
8.8.1 General
Nuts).
Fittings a nd Hardware
219
Table 8-18
Design factor = 5
Size
Standard
Tons Pounds
Stock
Each in
Number
Tap Size
Number
Pounds
Inches
thread condition
220
Fittings and Hardwa re
8.9.1 General
Turnbuckle).
turnbuckle.
Fittings a nd Hardware
221
Turnbuckle
thread condition
222
Fittings and Hardwa re
Table 8-19a
Take Up
Working Load
Weight Each Working Load
Weight Each
Limit
Limit
Fittings a nd Hardware
223
Table 8-19b
Take Up
Working
Weight
Working
Weight
Working
Weight
Load Limit
Each
Load Limit
Each
Load Limit
Each
1 x6 10000 20.2 - - - -
1 x 18 15200 28.8 - - - -
1 x 24 15200 27.8 - - - -
2 x 24
2-1/2 x 24
2-3/4 x 24
* use of a hook attachment on a turnbuckle requires engineering approval
224
Fittings and Hardwa re
8.10 Swivels
8.10.1 General
Power.
swivels.
swivels freely
Fittings a nd Hardware
225
Figure 8-24
Swivels
Table 8-20
Swivel Size
Working Load Limit Swivel Weight Each in Pounds
in Inches
Tons Pounds Regular Jaw Chain
226
Fittings and Hardwa re
9.0 Slings
9.1 General
9.4.1 General
9.5.1 General
Slings
227
9.6.1 General
228
Slings
9.1 General
overloading.
used
manufacturers name
diameter
bear:
1 length (reach)
3 a unique identifier
Slings
229
load weight
Centre of Gravity (C of G)
sling tension
230
Slings
synthetic slings.
slings.
by knotting or twisting.
control.
abrasive surfaces.
Slings
231
not be reused.
slippage.
a = available headroom
232
Slings
Figure 9-1
Slings
233
WARNING
CAUTION
sling tension.
each sling.
calculation.
contact engineering.
234
Slings
following:
Example:
Non-Uniform Object)
C of G from B
Slings
235
combined C of G.
C of G from B
0.75 x 20ft = 15 ft
Figure 9-2
Non-Uniform Object
236
Slings
and C of G-2.
Example:
4000 ÷ 10000 x 20 = 8 ft
6000 ÷ 10000 x 20 = 12 ft
Slings
237
Figure 9-3
preferred angle
Figure 9-4
238
Slings
engineering approval.
processes:
Sling Angle).
Slings
239
Figure 9-5
240
Slings
Figure 9-6
Dimensions
sling length = 25
= S ÷ L
S ÷ L = 18 ÷ 25 = 0.72
Slings
241
Table 9-1
this handbook.
Figure 9-7
242
Slings
WARNING
consulted.
Figure 9-8
Horizontal Plane
1 load weight
3 sling tension
Slings
243
= Wt ÷ # legs
= 10,000 lb ÷ 2 = 5,000 lb
Figure 9-9
formula:
4 ft x 10,000 lb ÷ 10 ft = 4,000 lb
6 ft x 10,000 lb ÷ 10 ft = 6,000lb
244
Slings
Figure 9-10
slings (90° sling angle) each sling leg will have 500
Example:
Slings
245
Figure 9-11
246
Slings
Table 9-2
90 1.00
85 1.004
80 1.015
75 1.035
70 1.064
65 1.103
60 1.154
55 1.220
50 1.305
45 1.414
40 1.555
35 1.743
30 2.000
NOTE
Sling Tension
Slings
247
Example:
in Table 9-2)
Figure 9-12
248
Slings
T =
(WL)
N X
V
Where:
ft.
T = Tension in a single leg
L = 12
WL = Weight of load
V = 6 ft.
including hardware
during the lift there may be times that only 2 of the slings
T =
24,000
2 1 X
6
12 6
= 24,000 X 1
T = 24,000
OR
T =
24,000
2 X
12
= 12,000 X 2
T = 24,000
Slings
249
hardware
attachment point
12 ft ÷ 8 ft x 5000lb ÷ 2 = 3750 lb
Figure 9-13
L1 = 6.7 ft
L2 = 5ft
H = 3 ft
D1 = 6 ft
D2 = 4 ft
TD = 10 ft
WT = 10,000 lb
Figure 9-14
L1 Leg:
i D2 x WT ÷ TD = LWD
ii L1 ÷ H = LAM
6.7 ÷ 3 = 2.233
Slings
251
L2 Leg:
i D1 x WT ÷ TD = LWD
ii L2 ÷ H = LAM
5 ÷ 3 = 1.666
Figure 9-15
loading.
Example:
the load will be shared equally (e.g. if the weight of the load
Figure 9-16
of 5.77 tons.
Slings
253
position.
by 100%.
calculated as follows:
Tension = 2 tons.
Tension = 8 tons
254
Slings
Figure 9-17
is calculated as follows:
Sling tension
x Wt x LWD.
Tension in Sling 1
Tension in sling 2
greatest tension.
G location.
Slings
255
TD = 16
D1 = 11
D2 = 5
L1 = 12
L2 = 7
H = 5
WT = 2000 lbs
Figure 9-18
Hoist A:
Hoist B:
(2000 x 11 x 7) ÷ (5 x 16)
256
Slings
Figure 9-19
Step 1
Figure 9-20
Step 2
Slings
257
Tension.
Figure 7-21
Step 3
258
Slings
9.4.1 General
rigging.
diameter or size
identification
considerations:
vibrating location
Slings
259
Due To Bending
wire rope.
strength is reduced.
referenced.
260
Slings
Figure 9-22
rope lay.
(Figure 9-23c).
(Figure 9-23d).
Figure 9-23
262
Slings
Example 1:
D
=
Diameter of Object
=
25
=
25 D/d
25
Example 2:
(1/2 wire rope)
D
=
Diameter of Object
=
8
=
16 D/d
D
Table 9-3
Ratio A
Strength
IWRC and FC Wire Rope Sling
(D/d)
Efficiency
Rated Capacity Multiplier
25 100% 1.00
20 91% 0.91
15 89% 0.89
10 86% 0.86
8 83% 0.83
6 79% 0.79
4 75% 0.75
2 65% 0.65
1 50% 0.50
Note: This table is based on static loads only and applies to 6x19
Slings
263
Table 9-4
Diameter
Vertical Choker Vertical Basket
Construction (inches)
HT MS HT MS HT MS
264
Slings
Table 9-5
1 0.083
2 0.166
3 0.250
4 0.333
5 0.416
6 0.500
7 0.583
8 0.666
9 0.750
10 0.833
11 0.916
12 1.000
Slings
265
into a sling shall not be larger than 1/2 the sling loop
Dimensions.
Table 9-6
1 24 to 26 16 x 8 400 x 200
266
Slings
Flemish Eye)
(IWRC)
wire or greater
Slings
267
Figure 9-24
Flemish Eye
shall be adjusted.
268
Slings
Figure 9-25
Grommet Slings
identification attached.
following:
slings.
Slings
269
perform.
straightening
heat.
sling strength.
270
Slings
rejection.
its strength.
Slings
271
All fabric web slings must have a tag with the basic
Figure 9-26
Edge Loading
an attachment.
Figure 9-27
Slings
273
chain slings.
repair.
factor of five.
274
Slings
sling.
Figure 9-28
protectors.
Slings
275
Figure 9-29
shall be used.
276
Slings
material type.
of the sling
Slings
277
resting on a sling.
following:
broken fittings
9.6.1 General
grade
number of legs
length (reach)
c Links are rated for single leg slings only. Hooks shall
CAUTION
Slings
279
weld splatter
link wear
components
to exposure to heat)
freely
280
Slings
each end.
rope supplier.
Slings
281
Figure 9-30
Four-Legged Sling
NOTE
The slings on the right share the load equally. The slings
282
Slings
Figure 9-31
used.
attachment point.
Figure 9-32
Securing Slings
284
Slings
10.4.1 General
10.5.1 General
10.6.1 General
10.7 Jacks
10.7.1 General
10.8.1 General
10.10 Dynamometers
10.11.1 General
Pre-Use Inspection
10.12 A-Frames
10.12.1 General
10.13.1 General
10.14.1 General
10.15.1 General
10.16.1 General
10.17.1 General
10.18.1 General
286
Rigging Tools and Devices
10.20.1 General
Bruce Power
NOTE
damage.
mating/connecting components.
applicable.
rating.
include:
monorail hoists
tugger hoists
tirfor hoists
abnormal operation
Figure 10-1
290
Rigging Tools and Devices
Lever-Operated
3/4 ton to 6 ton. Lever hoists are often used when rigging
Power.
in the mechanism.
10.4.1 General
operator can control the load. They are not provided with a
level loads.
as follows:
Tension
Tension in Hoist A
= 1,925 lb
Tension in Hoist B
= 12 ÷ 5 x 2,000 x (5 ÷ 16)
= 1,500 lb
Figure 10-2
following:
latch
10.5.1 General
manufacturers name
10.6.1 General
back
298
Rigging Tools and Devices
hoist
Figure 10-3
10.7 Jacks
10.7.1 General
is raised
300
Rigging Tools and Devices
Figure 10-4
Ratchet Jacks
once
engine
hydraulic power
considerations:
periodically.
caused by condensation.
CAUTION
302
Rigging Tools and Devices
Figure 10-5
Hydraulic Jacks
10.8.1 General
or hold a load.
Figure 9-7
10.10 Dynamometers
the following:
instrument.
be recalibrated.
of the load.
306
Rigging Tools and Devices
10.11.1 General
equalizer beam.
on the device.
bending
the RSE.
engineering.
Figure 10-8
Spreader Beam
Beam).
subjected.
308
Rigging Tools and Devices
Figure 10-9
Equalizer Beams
damage
10.12 A-Frames
10.12.1 General
under load.
be checked).
310
Rigging Tools and Devices
Figure 10-10
A-Frame
10.13.1 General
or missing fasteners
312
Rigging Tools and Devices
Figure 10-11
Jib Cranes
(Engine Hoists)
10.14.1 General
problems.
purpose.
boom cranes.
314
Rigging Tools and Devices
following:
hydraulic leaks
Figure 10-12
10.15.1 General
lifting device.
bending, bulging
abrasion damage
Figure 10-13
Monorail
316
Rigging Tools and Devices
10.16.1 General
Beam Clamps):
anchor point
followed.
be properly seated.
not be obtained.
no mechanical damage
smooth operation
Figure 9-14
Beam Clamps
ANSI B31.1.
318
Rigging Tools and Devices
10.17.1 General
electrically driven
applications.
the trolley.
followed.
320
Rigging Tools and Devices
following:
no mechanical damage
Figure 10-15
Beam Trolleys
10.18.1 General
purpose.
light loads
vertical clamp
a load
NOTE
Figure 10-16
Plate Clamps
locking device
324
Rigging Tools and Devices
10.19.1 General
accommodate.
application.
diameter.
line is turned.
Rigging Tools a nd Devices
325
force.
Figure 10-17
Snatch Block
exceeded.
326
Rigging Tools and Devices
Figure 10-18
CAUTION
block.
Table 10-1):
running block
(WLL)
328
Rigging Tools and Devices
Table 10-1
1 0.96 0.98
2 1.87 1.94
3 2.75 2.88
4 3.59 3.81
5 4.39 4.71
6 5.16 5.60
7 5.90 6.47
8 6.60 7.32
9 7.27 8.16
10 7.91 8.98
11 8.52 9.79
12 9.11 10.60
13 9.68 11.40
14 10.20 12.10
15 10.70 12.90
16 11.20 13.60
17 11.70 14.30
18 12.20 15.00
19 12.60 15.70
20 13.00 16.40
bearing block?
330
Rigging Tools and Devices
block?
Factor B
Table 10-2
Compared to WLL
Compared to WLL
hauling system.
departing lines.
block.
sheaves.
332
Rigging Tools and Devices
angle)
Table 10-3
Angularity Factors
Angle Factor
Angle Factor
Angle Factor
0° 2.00
60° 1.73
130° 0.84
10° 1.99
70° 1.64
135° 0.76
20° 1.97
80° 1.53
140° 0.68
30° 1.93
90° 1.41
150° 0.52
40° 1.87
100° 1.29
160° 0.35
45° 1.84
110° 1.15
170° 0.17
50° 1.81
120° 1.00
180° 0.00
10.19.7 Load on Structure
follows:
334
Rigging Tools and Devices
Figure 10-19
wheeling bearings
installation
case
cracking
336
Rigging Tools and Devices
RSE.
storage areas.
338
Rigging Tools and Devices
and Structures
11.1.1 General
11.3.1 General
11.4.1 General
11.5.1 General
11.1.1 General
required.
340
Anchor Points and Non-sta nda rd Lifting Points
points in structures.
= 800 lb ÷ 1
= 800 pounds
= 800 lb + 800 lb
= 1,600 pounds
= 800 lb ÷ 4
= 200 pounds.
= 800 lb + 200 lb
= 1,000 pounds.
342
Anchor Points and Non-sta nda rd Lifting Points
11.3.1 General
following reasons:
angles.
Figure 11-1
Slings
Lifting Practices)
11.4.1 General
Grating.
Lifting Practices).
346
Anchor Points and Non-sta nda rd Lifting Points
following:
Figure 11-2
Lifting Beams
11.5.1 General
engineering signature.
348
Anchor Points and Non-sta nda rd Lifting Points
following:
inspector
signature
350
Anchor Points and Non-sta nda rd Lifting Points
Gantry Cranes
Cranes
Checks
Failure
P Power on
check N, S, E, W
hook/block assembly
Travelling Overhea d Bridge a nd Ga ntry Cra nes
351
used.
Crane).
352
Travelling Overhead Bridge and Ga ntry Cra nes
Figure 12-1
Figure 12-2
Gantry Crane
Figure 12-3
354
Travelling Overhead Bridge and Ga ntry Cra nes
Operation of Cranes
competent operator
Operational Checks
bars, etc.
356
Travelling Overhead Bridge and Ga ntry Cra nes
tag, etc).
problem.
crane availability
log book
(where applicable):
material
crane capacity
operation
crane availability
log book
(where applicable):
material
crane capacity
operation
operation
operation
operation
operation
WARNING
control modes.
power is restored.
put the crane in a safe state (i.e. put the load down
the Lift.
crane will then slip on the rail while the other rolls
364
Travelling Overhead Bridge and Ga ntry Cra nes
crane.
seconds off.
following:
storage position.
366
Travelling Overhead Bridge and Ga ntry Cra nes
exist to affect a safe and effective egress from the crane cab
and Failure
of the following:
capacity)
lack of lubrication
excessive inching
cables or slings
368
Travelling Overhead Bridge and Ga ntry Cra nes
Crawler Cranes
13.1 General
13.3 Setup
13.1 General
Considerations.
370
Roa d Mobile, Rough Terrain and Crawler Cranes
Figure 13-1
372
Roa d Mobile, Rough Terrain and Crawler Cranes
Figure 13-2
13.3 Setup
374
Roa d Mobile, Rough Terrain and Crawler Cranes
shall be known:
angle)
gross load
operating quadrants
Figure 13-3
calculation.
376
Roa d Mobile, Rough Terrain and Crawler Cranes
of the jib.
a Crane Levelling
crane is level.
b Radius
stability.
measured exactly.
load weight.
378
Roa d Mobile, Rough Terrain and Crawler Cranes
Figure 13-4
c Load
stopping, or swinging.
Roa d Mobile, Rough Terrain and Crawler Cranes
379
up to 100%.
load.
d Outriggers
engineering approval.
CAUTION
Values)
followed.
380
Roa d Mobile, Rough Terrain and Crawler Cranes
the float.
e Counterweight
f Gantry Height
boom.
h Boom Stops
backward.
not cross.
j Side Loading
l Pile Driving
observed.
382
Roa d Mobile, Rough Terrain and Crawler Cranes
be damaged.
with a crane.
m Weather Conditions
where available.
serious consequences.
in load charts.
WARNING
used.
not be split
up or released.
loaded.
384
Roa d Mobile, Rough Terrain and Crawler Cranes
the crane
machine weight
stability
hydraulic pressure
follows:
hardware
load ratio
overhead obstructions
limits of approach
386
Roa d Mobile, Rough Terrain and Crawler Cranes
overloaded.
angle
gross load
prepared.
load calculation
crane selection
ground preparation
crane hook up
crane movements
should be used.
Lifting Beam).
NOTE
Figure 13-5
Figure 13-6
Figure 13-7
390
Roa d Mobile, Rough Terrain and Crawler Cranes
maintained as follows:
392
Roa d Mobile, Rough Terrain and Crawler Cranes
be required.
outrigger pads.
50%.
CAUTION
bearing values.
Table 13-1
Sq. Ft.
394
Roa d Mobile, Rough Terrain and Crawler Cranes
following applies:
Bruce Power.
applies:
responsibilities.
of Lift shall:
notify supervisor.
apply.
rigorously enforced.
Mobile Cranes
NOTE
logbook
fuel level
warning lights
parking brake
accelerator
power steering
anti-two-block system
backup alarm
and speed
ground
the crane
hatches
being used
to a complete stop
raised position
following:
404
Roa d Mobile, Rough Terrain and Crawler Cranes
structural support
points
any plane
become energized
contaminated/radioactive loads
408
Critical Hoisting Operations
and Planning
approval.
designation.
items to be moved
load-indicating devices
lifting points
crane orientations
Lift Form.
evaluation.
f All lifting devices used in the lift shall be in date and
reviewed.
concurrence.
the following:
area.
the following:
areas is complete.
are activated.
correctly.
412
Critical Hoisting Operations
the following:
obstructions.
over loading.
be filed.
414 Notes
Notes
415
416 Notes
CS5552r1 Oct 09