Safe Lifting and Slinging
Safe Lifting and Slinging
Safe Lifting and Slinging
The material in this presentation will concentrate on the following: Working in accordance with LOLER Methods of ensuring safe lifting and slinging Equipment to help prepare and position pipework
LOLER requirements
It should be ensured that all lifting equipment is: sufficiently strong, stable and suitable for the proposed use positioned or installed to prevent the risk of injury visibly marked with any appropriate information to be taken into account for its safe use
Chain slings
Chain slings are generally the most versatile type of sling, as well as the most robust. General purpose chain slings can have either one, two, three or four legs
Shortening clutches
Shortening clutches enabling a multi legged sling to have different length legs to adjust the loads are available for chains. Clutches must be correctly fitted to avoid failure or shortening of the chain life
Note: the allowable lifting weight is reduced when all the legs of a chain sling are not being used
End fittings
The end fittings on chain slings will generally be either sling hooks ) or C hooks. Both of these are designed to minimise the risk of the load slipping out of the hook. Of the two, the C hook is designed not to catch on obstructions; it is more robust and does not have a easily damaged safety catch. Special purpose fittings such as shackles are also used for lifting pipes.
Two-legged slings
For two-legged slings the angle between the legs of the sling determines its safe working load (SWL):
A two-legged sling will be marked with its SWL at 90, and this applies to all sling angles from 0-90 The sling may also be marked with its SWL at 120, and this will apply for angles between 90 and 120 These SWL assume that both legs are equally loaded, and that each leg is straight Never us any two-legged sling not marked with the SWL for the angle being used, or for any angles greater than 120
Three-legged slings
For three-legged slings, the maximum angle between the legs of the sling and the vertical will determine the safe working load (SWL):
A three-legged sling will be marked with its SWL at 45 and this applies for all angles from 0 - 45 The SWL for a three-legged sling assumes that all legs are equally loaded, and that each leg is at the same angle Never use any three-legged sling not marked with the SWL for the angle being used, or for angles greater than 45
Four-legged slings
For four-legged slings, the maximum angle between opposite legs of the sling will determine its safe working load (SWL):
A four-legged sling will be marked with its SWL at 90 and will apply for all angles from 0 - 90 It may also be marked with its SWL at 120 which will apply for angles between 90 and 120 The SWL for a four-legged sling assumes that all legs are equally loaded and that each leg is straight Never use any four-legged sling not marked with the SWL for the angle being used, or for angles greater than 120
Methods of Slinging
SWL factors also apply according to the type of sling and how it is used. The same principles also apply to multi-legged slings Examples for various types of single legged slings are shown in the following slide
Types of Slings
SLING MATERIAL
1 1 1 1 N/A
1 1 N/A 1 N/A
N/A 1 1 1 1
Sling hooks
When slinging, hooks must always face outwards from the lifting point.
Choke hitch
Do not batter down slings to increase the grip, allow the angle to form naturally. The maximum permitted angle is 120.
Webbing slings
Wide webbing slings cannot be used at a sideways angle where the sling would not be equally loaded across its width.
Palletised loads
An example of a frequently lifted load that requires special equipment is a pallet of fittings/accessories. When covered by safety netting, the mesh size should be smaller than the smallest item to be lifted.
Beams
Use double wrapped slings when sling legs can slide together. SWL for chain slings used in this way is 0.8.
Columns
Columns should be lifted using purpose designed lifting points or brackets.
Stillages/fitting bins
Wrap slings round corner posts and do not attempt to lift double stacked stillages. Beware of overloading scaffold boards if landing loaded stillages on a scaffold. SWL factor for chain slings used in this way is 0.8.
Rubbish skips
Typical arrangement of special sling is with steel box sections under skip, and steel tube spreaders to keep sling legs vertical. Keyhole plates on skip lugs are for location purposes not for lifting. Skips with specially adapted lifting points are acceptable providing thorough examination is undertaken at 6 month intervals. Beware of rusted skip bottoms, as these can fall out when the skip is lifted.
The Lift
Before lifting the following must be considered:
Are the slings undamaged and properly attached to the load? Is the crane hoist rope vertical? Is the load free to be lifted i.e. not fixed to anything else? Are the legs of a multi-legged sling equally loaded? Are the slings free of knots, tangles etc Are all spare legs of the sling hooked up to the master link on the lifting hook? Is the safety catch on the lifting hook closed Are there any obstructions above the load preventing a straight lift Is the master link on the lifting hook free and in the centre of the bowl of the hook? Are all personnel clear of the load?
Signalling
If radios are chosen, the following method of use should be followed:
All instructions must be repeated continuously for example Lower, Lower, Lower. until the movement is complete If the instructions stop getting through to the crane operator the load should be brought to a halt immediately This will help guard against failure of the radio system
Signalling continued
If hand signals are used, the following signals should be employed ensuring that:
There is always a line of sight between the signaller and the crane operator The signaller faces the crane operator whenever signalling Visiting crane operators understood the standard hand signals as detailed in the following slides
Signalling continued
Signalling continued
Signalling continued
Signalling continued
Signalling continued