Hoisting & Rigging Handbook - AEDC PDF
Hoisting & Rigging Handbook - AEDC PDF
Hoisting & Rigging Handbook - AEDC PDF
An Annex to:
AEDC Safety Health & Environmental Standard
D5, Hoisting Devices
AEDC
HOISTING
&
RIGGING
HANDBOOK
AEDC Operations
Record of Review/Revision
Date/POC Description
July 2013 7th Edition. Incorporated Change #1, Jan 2011. Added definitions and modified duty
June 2014 position titles throughout document for clarity and consistency with OSHA and ASME,
and as a result of in depth crane program review. Corrected exhibit numbers throughout
C. Bidmead document to reflect unique number for each exhibit. Added Rigger, Signal Person and
E. Dedicated Spotter training and qualification changes to Chapter 6 and changed operating
Robinson near power line requirements to be consistent with latest OSHA 1926 Subpart CC
mandatory requirements. Incorporated changes requested by AEDC Crane System
Engineer. Deleted chapter 15 to reduce redundancy with chapter 9. Reformatted entire
document for consistency and e-document use. Reduced number of entries on Table of
Contents and added hyperlinks for easier e-document navigation. Corrected errors and
made minor clerical changes throughout.
May 2013 6th Ed.: Added stability analysis and explosives handling information to critical lift
requirements. Added definition of Stability Equilibrium, Changed/added: Paragraphs
R. Roosa 2.1.1.2; 2.1.1.7; 2.1.1.2. 8; 2.2.1.2.1; 2.2.1.2.3.9; Exhibit 2.1; Exhibit 2.2; added new
Exhibit 2.6 Stability Analysis Methodology.
Oct 2010 5th Ed.: Updated to reflect new OSHA requirements for mobile crane operations.
R.Eichel
Table of Contents
10.5 OPERATIONS.............................................................................................................................................191
In 2002, AEDC established a crane safety committee to develop an AEDC Hoisting and Rigging
Program. The Committee reviewed existing hoisting and rigging codes, standards, and regulations, such
as the Occupational Safety and Health Administration (OSHA) 29 CFR 1910, the American Society of
Mechanical Engineers (ASME) B-30 series, and others. The Committee determined that these
documents, while adequate as minimum general industry standards, did not contain the details for the
unique hoisting and rigging operations being performed at AEDC. Due to the risky operations at AEDC,
it was determined that an AEDC Hoisting and Rigging (H&R) handbook was necessary.
Preliminary work on the handbook was begun in June 2002. The first handbook developed incorporated
the minimum requirements of OSHA, ASME, similar documents and included additional requirements to
control hoisting and rigging work processes at AEDC. The handbook was reviewed by AF and base
operating contractor personnel. A final draft was completed in December 2002 and implemented in May
2003.
This handbook is a safety, not a design, document and is intended for use by safety professionals,
managers, supervisors, riggers, and operators. In keeping with this philosophy, only those portions of
standards and regulations dealing with safety have been included. In that, the target audience for this
document is safety professionals, managers and supervisors, riggers, and operators rather than hoisting
and rigging equipment designers, the design references cited within Chapter 17 of this handbook
(References) should be consulted for specific design, fabrication, and other performance criteria. Readers
are strongly encouraged to review each of them to have a full description of the subject area covered.
This Handbook supports the objectives of AEDC by controlling hoisting and rigging activities in a safe
and cost-effective manner. It is intended to be a users guide to requirements, codes, laws, regulations,
standards, and practices that apply to AEDC operations. This Handbook, or any part of this Handbook, is
applicable to all contractors and subcontractors (offsite or onsite) performing work at/for AEDC.
This Handbook is generally invoked via contract. All contractors performing work involving critical lifts
shall follow this Handbook. As a minimum, acceptability of equipment and rigging should be verified by
the AEDC Crane System Engineer and critical lift procedures shall be reviewed and approved by Person-
In-charge (PIC) or another qualified person designated by the PIC.
This is the seventh edition. This revision incorporates the recent OSHA and ANSI B-30 changes.
ACKNOWLEDGMENTS
AEDC acknowledges the many organizations whose documents provided important source material for
the handbook. They include:
Permission to reprint specific figures and illustrations was obtained from CSA and SAE.
Applicable sections of 29 CFR 1910, "Occupational Safety and Health Standards for General Industry,"
and 29 CFR 1926, "Occupational Safety and Health Regulations for Construction," have been
paraphrased or reproduced verbatim throughout. The contributions of AEDC's Hoisting and Rigging
Committee are also recognized. Without their time and talent, which has been provided gratuitously,
there would be no handbook.
INTRODUCTION
The AEDC Hoisting and Rigging Handbook is intended as a reference document for use by supervisors,
line managers, safety personnel, equipment operators, and any other personnel responsible for hoisting
and rigging operations at AEDC sites. The handbook quotes verbatim or paraphrases (with minor
editorial changes for consistency) the requirements of the OSHA and the ASME. It also encompasses
hoisting and rigging requirements, codes, standards, and regulations, eliminating the need to maintain
extensive (and often incomplete) libraries of hoisting and rigging standards throughout AEDC.
The word shall denotes a mandatory action and should denotes a recommended action in keeping with
best management practices. To permit use of each chapter as a standalone document, there is some
repetition from chapter to chapter.
This handbook addresses the following items that are not covered in detail in the general industry
standards:
To propose improvements to this handbook, please provide suggested text changes and supporting
technical documentation to the AEDC Crane System Engineer.
The following are specialized terms commonly used when discussing hoisting and rigging operations.
Many may not be used in this handbook, but are included for general information. Terms are arranged
alphabetically. Illustrations are included for clarity.
ABRASION: the mechanical wearing of a surface resulting from frictional contact with other materials
or objects.
ALTERNATE LAY: Lay of wire rope in which the strands are alternately regular and lang lay.
AREA LIFT MANAGER: A term use by the base operating contractor. For the purpose of this
document see DESIGNATED LEADER.
AREA, METALLIC: Sum of the cross-sectional areas of individual wires in a wire rope or strand.
ASSET OWNER: A person assigned the role of managing the life cycle of an asset. The Asset Owner
ensures the capability, capacity, and configuration of assets. For the purpose of this document the
title Asset Owner is synonymous with the ASME B30 role of site supervisor- a person who
exercises supervisory control over the work site on which the hoisting equipment is being used
and over the work that is being performed on that site.
ATTACHMENT: A device other than conventional forks or load backrest extension, mounted
removable or permanently on the elevating mechanism of a truck for handling the load. Popular
types are fork extension clamps, rotating devices, side shifters, load stabilizers, rams, and booms.
AUXILIARY HOIST: Supplemental hoisting unit usually of lower load rating and higher speed than
the main hoist.
BACK STAY: Guy used to support a boom or mast or that section of a main cable, as on a suspension
bridge, or cableway, and the like, leading from the tower to the anchorage.
BASE OPERATING CONTRACTOR: The contractor directly accountable to the Air Force for the
AEDC mission.
BASKET OR SOCKET: The conical portion of a socket into which a splayed rope end is inserted and
secured with zinc.
BATTERY-ELECTRIC TRUCK: An electric truck in which the power source is a storage battery.
BECKET LOOP: A loop of small rope or a strand of rope fastened to the end of a large wire rope to
facilitate installation.
BENDING STRESS: Stress on wires of a wire rope imposed by bending. This stress need not be added
to direct load stresses. When sheaves and drums are of suitable size, bending stress does not
affect normal life of the wire rope.
BIRDCAGE: A colloquialism describing the appearance of a wire rope that is forced into compression.
The outer strands form a cage and at times displace the core.
BIRDCAGING: The twisting of fiber or wire rope in an isolated area in the opposite direction of the
rope lay, causing it to take on the appearance of a birdcage.
BOOM (Crane): A member hinged to the rotating superstructure and used for supporting the hoisting
tackle.
BOOM LINE: A wire rope for supporting or operating the boom on derricks, cranes, draglines, shovels,
etc.
BRAKE: A device used for slowing or stopping motion by fiction or electromagnetic means.
BRAKE, DRAG: A brake that provides stopping force without external control.
BRAKE, HOLDING: A brake that sets automatically and that prevents motion when power is off.
BRAKING, COUNTER TORQUE: A method of controlling speed by reversing the motor line voltage
polarity or phase sequence to develop torque in the direction opposite to the rotation of the motor.
BRAKING, DYNAMIC: a method of controlling speed by using the motor as a generator, with the
energy being dissipated in resistors.
BRAKING, REGENERATIVE: A form of dynamic braking in which the electrical energy generated is
fed back into the power system.
BREAKING STRENGTH: The measured load required to break a wire rope or chain.
BRIDGE: The part of a crane, consisting of girders, walkways, railings, trucks, and drive mechanisms,
that carries the trolley or trolleys.
BRIDGE TRAVEL: Horizontal travel of the crane parallel with runway rails.
BRIDLE SLING: A sling composed of multiple legs (branches), the top ends of which terminate in a
fitting that latches onto the lifting hook.
BULL RING: The main large ring of a sling to which sling legs are attached.
BUMPER (BUFFER): a device for reducing impact when a moving crane or trolley reaches the end of
its permitted travel, or when two moving cranes or trolleys come into contact. This device may
be attached to the bridge, trolley, or runway stop
CABLE: A term loosely applied to wire ropes, wire strands, manila ropes, and electrical conductors.
CABLE-LAID WIRE ROPE: A type of wire rope consisting of several independent wire ropes laid
into a single wire rope.
CABLE CROWD ROPE: A wire rope used to force the bucket of a power shovel into the material
being handled.
CARRIAGE: A support structure for forks or attachments, generally roller-mounted, traveling vertically
within the mast of a cantilever truck.
CENTER: A single wire or fiber in the center of a strand around which the wires are laid.
CENTER CONTROL: The position near the center of a truck cab from which the operator controls
movement of the truck.
CHOKER ROPE: A short wire-rope sling used to form a slip noose around
the object to be moved or lifted (see Figure 1-1).
CLOSING LINE: Wire rope that closes a clamshell or orange-peel bucket and then operates as a
hoisting rope.
COLLECTOR: Contacting device mounted on a bridge or trolley and used to collect current from the
conductor system.
COME-ALONG: A portable, hand-operated device consisting of housing, length of chain or wire rope,
two hooks, and a ratcheting lever, that is used for miscellaneous pulling.
CONDUCTOR: Wire, angles, bars, tees, or special sections mounted to transmit current to the
collectors.
CONSTRUCTION (WIRE ROPE): Refers to the design of wire rope, including number of strands,
number of wires per strand, and arrangement of wires in each strand.
CONTINUOUS BEND: Reeving of wire rope over sheaves and drums so that it bends in one direction
(as opposed to reverse bend).
CONTROLLER: An operators device for regulating the power delivered to a motor or other
equipment.
CONTROLLER, SPRING RETURN: A controller that, when released, will return automatically to a
neutral position.
CORE: The center member of a wire rope around which the strands are laid. It may be fiber, a wire
strand, or an independent wire rope.
CORING LINE: Wire rope used to operate the coring tool for taking core samples during the drilling of
a well.
CORRUGATED: A term used to describe the grooves of a sheave or drum when worn to show the
impression of a wire rope.
CRANE: A machine used for lifting and lowering a load vertically and moving it horizontally and that
has a hoisting mechanism as an integral part of it. A crane has three (3) axis of movement, any
less see Hoist.
Cab-Operated Crane: a crane whose movements are controlled by an operator through the use
of controllers located in a cab that is attached to the crane.
Cantilever Gantry Crane: A gantry or semigantry crane in which the bridge girders or trusses
extend transversely beyond the crane runway on one or both sides.
Floor-Operated Crane: A crane whose operation is controlled by use of a pendant in the hands
of an operator on the floor or on an independent platform.
Gantry Crane: A crane similar to an overhead crane, except that the bridge for carrying the
trolley or trolleys is rigidly supported on two or more legs running on fixed rails or other
runway.
Jib Crane: A fixed crane with a vertical rotating member supported at the bottom (also at top in
some types) from which an arm extends to carry the hoist trolley. Jib cranes are most
commonly mounted on a vertical column, supplied as part of the jib crane, or on existing
structural members (e.g., a wall-mounted jib crane). Note: For the purpose of this
document and training requirements, a Jib Crane is considered a Hoist.
Mobile Crane: Mobile cranes are defined as wheel-mounted cranes, truck cranes, and crawler
cranes.
A wheel-mounted crane consists of a rotating structure with power plant, operating machinery,
and boom, mounted on a base or platform equipped with axles and rubber-tired wheels
for travel. The base is usually propelled by an engine in the superstructure, but it may be
equipped with a separate engine controlled from the superstructure (see ASME B30.5-
2007 for examples).
A truck-mounted crane consists of a rotating superstructure with power plant that operates
machinery and boom, mounted on an automotive truck equipped with a power plant for
travel. Commercial truck-mounted cranes are included in this category (see ASME
B30.5-2007 for examples).
A crawler crane consists of a rotating superstructure with power plant, operating machinery, and
boom mounted on a base equipped with crawler treads for travel (see ASME B30.5-2007
for examples).
Overhead Traveling Crane: A crane with a movable bridge carrying a movable or fixed
hoisting mechanism and traveling on an overhead fixed-runway structure.
Pulpit-Operated Crane: a crane whose movements are controlled by an operator through the
use of controllers located in a control room or a fixed or movable cab or platform that is
independent of the crane..
Remote-Operated Crane: A crane whose movements are controlled by an operator through the
use of controllers contained in a portable operating station not attached to the crane.
Semigantry Crane: A gantry crane with one end of the bridge rigidly supported on one or more
legs running on a fixed rail or runway, the other end of the bridge being supported by a
truck running on an elevated rail or runway.
Shop Crane: A Portable Automotive Lifting Device (PALD), self-contained hydraulic and
pneumatic-hydraulic crane characterized by a pair of laterally spaced legs, an upright
mast, a pivoting boom with a boom extension and hook, and a hydraulic unit. The
hydraulic unit moves the boom up and down at a pivot point for the purpose of raising,
removing, transporting in the lowered position, and replacing automotive engines,
transmissions and other components. Shop cranes have a capacity of 4 tons (8000
pounds) or less.
Wall-Mounted Crane: A crane having a jib, with or without a trolley, supported from a sidewall
or line of columns of a building. It is a traveling-type crane and operates on a runway
attached to the sidewall or line of columns.
CRITICAL DIAMETER: Diameter of the smallest bend for a given wire rope that permits the wires
and strands to adjust themselves by relative movement while remaining in their normal positions.
DECELERATION STRESS: Additional stress imposed on a wire rope due to decreasing the load
velocity.
DEDICATED SPOTTER (Power Lines): A person assigned to monitor the separation between the
power line and the equipment, load line and load (including rigging and lifting accessories), and
ensure through communication with the crane operator that the required minimum approach
distance is not breached. The assigned persons sole responsibility is to be the dedicated spotter.
The assigned person must meet the same training and qualification criteria as the Qualified Signal
Person.
DEFLECTION: Sag of a rope in a span, usually measured at midspan as the depth from a chord joining
the tops of the two supports. Any deviation from a straight line.
DESIGN FACTOR: Ratio of ultimate strength of a material to the design working (unit) stress, unless
defined otherwise in the text of this volume, for specific applications.
DESIGNATED LEADER: A qualified person who directly oversees the work being performed by a
crane and the associated crew. This person remains at the job site throughout the lift.
DIAMETER: Distance measured across the center of a circle circumscribing the wires of a strand or the
strands of a wire rope.
DIESEL-ELECTRIC TRUCK: An electric truck in which the power source is a generator driven by a
diesel engine.
DOCKBOARD: A portable or fixed device for spanning the gap or compensating for the difference in
level between loading platforms and carriers.
DOG-LEG: Permanent short bend or kink in a wire rope caused by improper use.
DRIVE: Motor, coupling, brake and gear case, or gear cases used to propel bridge, trolley, or hoist.
DRIVE GIRDER: A girder on which is mounted the bridge drive, cross shaft, walk, railing, and
operators cab.
DRUM: A cylindrical-flanged barrel of uniform (cylindrical drum) or tapering (conical drum) diameter
on which a wire rope is wound for operation or storage. It may be smooth or grooved.
ELASTIC LIMIT: Limit of stress beyond which a permanent deformation takes place within the
material. This limit is approximately 55-65% of breaking strength of steel-wire ropes.
ELECTRIC TRUCK: A truck in which the principal energy is transmitted from power source to
motor(s) in the form of electricity.
END CONTROL: An operator-control position that is located at the end opposite the load end of the
truck.
EQUALIZER: A device that compensates for unequal length or stretch of a hoist rope or chain.
EQUALIZING THIMBLES: A special type of fitting used as a component part of some wire-rope
slings.
EYE OR EYE SPLICE: A loop with or without a thimble formed in the end of a wire rope.
FAIL-SAFE: A provision designed to automatically stop or safely control any motion in which a
malfunction could occur.
FIBER CENTERS: Cords or rope made of vegetable fiber used in the center of a strand.
FIBER CORES: Cords or rope made of vegetable fiber used in the core of a wire rope.
FIRST POINT: The first setting on the operators controller that starts crane motion (slowly) in each
direction.
FLAT ROPE: Wire rope made of parallel alternating right-lay and left-lay ropes sewn together by
relatively soft wires.
FLATTENED STRAND ROPE: A wire rope with either oval or triangular strands that present a
flattened rope surface.
FLEET ANGLE: Angle between the position of a rope at the extreme end wrap on a drum and a line
drawn perpendicular to the axis of the drum through the center of the nearest fixed sheave.
FORKS: Horizontal tine-like projections, normally suspended from the carriage, used to engage and
support loads.
FORK HEIGHT: The vertical distance from the floor to the load-carrying surface adjacent to the heel
of the forks with the mast vertical, and in the case of reach trucks, with the forks extended.
FORKLIFT TRUCK: A high-lift self-loading truck equipped with load carriage and forks for
transporting and tiering loads (see Figure 10-3).
GAS-ELECTRIC TRUCK: An electric truck in which the power source is a generator driven by an LP-
gas or gasoline engine.
GROMMET: A seven-strand wire-rope sling made from one continuous length of strand or an endless
synthetic-web sling.
GROOVED DRUM: Drum with grooved outer surface to accommodate and guide a rope.
GROOVES: Depressions in the outer surface of a sheave or drum for positioning and supporting a rope.
GUY LINE: Strand or rope, usually galvanized, for holding a structure in position.
HIGH-LIFT TRUCK: A self-loading truck equipped with an elevating mechanism designed to permit
tiering. Popular types are high-lift platform trucks (see Exhibit 10.1).
HOIST: A device used to lift or lower items. A hoist can have no more than two axis of movement
otherwise see Crane. Note: For the purpose of this document and training requirements, a Jib
Crane is considered a Hoist.
HOIST, LEVER OPERATED: A lever-operated manual device used to lift, lower, or pull a load and to
apply or release tension.
HOLDING LINE: Wire rope on a clamshell or orange-peel bucket that holds the bucket while the
closing line is released to dump the load.
HOOK LOAD: The total live weight supported by the hook of a crane, derrick, or other hoisting equip-
ment, including the load, slings, spreader bars, and other tackle not part of the load, but supported
by the hook and required for the handling of the load.
INDEPENDENT WIRE ROPE CORE: Wire rope used as the core of a larger rope.
INSULATED LINK: A connecting device placed between the load hook and the platform rigging, which
electrically isolates them. Normally used when working near electrically energized circuits or
when electric welding operations are to be performed from the platform.
INTERNAL-COMBUSTION ENGINE TRUCK: A truck in which the power source is a gas or diesel
engine.
INTERNALLY LUBRICATED: Wire rope or strand having all wires coated with lubricant.
KINK: Permanent distortion of wires and strands resulting from sharp bends.
LANG-LAY ROPE: Wire rope in which the wires in the strands and the strands in the rope are laid in
the same direction.
LIFT: Maximum safe vertical distance through which a hook can travel. The hoisting of a load.
LIFT DIRECTOR: A title used by OSHA and ASME to mean a person who directly oversees the work
being performed by the hoisting equipment and the associated crew. This person remains at the
job site during the lifting operation. For the purpose of this document see DESIGNATED
LEADER.
LIFT, NON-STANDARD: The load to be lifted is between 50% and 85% of the rated capacity of the
mobile crane operating on a rubber surface (Pick and carry).
LIFT, PLANNED ENGINEERED: Any lift in excess of the manufacturers rated load capacity of the
crane (Fixed Cranes). Planned engineered lifts will always be classified as a Critical Lift. No
such lift shall be made without the authorization of the AEDC Crane System Engineer. This
authorization will only be granted after the AEDC Structural Engineer has reviewed the design of
the crane-supporting structure, has inspected the structure as required by ASME B 30 standards
and has approved its use for the intended lift.
LOAD BLOCK: The assembly of hook or shackle, swivel, bearing, sheaves, pins, and frame suspended
by the hoisting ropes or load chain. This shall include any appurtenances reeved in the hoisting
rope or load chain
LOAD-BACKREST EXTENSION: A device extending vertically from the fork carriage frame.
LOAD-BEARING PARTS: Any part of a material-handling device in which the induced stress is
influenced by the hook load. A primary load-bearing part is a part the failure of which could
result in dropping, upset, or uncontrolled motion of the load. Load-bearing parts, which, if failed,
would result in no more than stoppage of the equipment without causing dropping, upset, or loss
of control of the load are not considered to be primary load-bearing parts.
LOAD CENTER (FORKLIFTS): The horizontal longitudinal distance from the intersection of the
horizontal load-carrying surfaces and vertical load engaging faces of the forks (or equivalent
load-positioning structure) to the center of gravity of the load.
LOW-LIFT TRUCK: A self-loading truck equipped with an elevating mechanism designed to raise the
load only sufficiently to permit horizontal movement (see Exhibit 10.1).
MAGNET: An electromagnetic device carried on a crane hook and used to pick up loads.
MAIN HOIST: The primary hoist mechanism provided for lifting and lowering the maximum-rated
load.
MESSENGER STRAND: Galvanized strand or bronze strand used to support telephone and electrical
cables.
MODULUS OF ELASTICITY: Mathematical quantity giving the ratio, within the elastic limit,
between a definite range of unit stress on a wire rope and the corresponding elongation.
MOUSING: A method of bridging the throat opening of a hook to prevent the release of load lines and
slings, under service or slack conditions, by wrapping with soft wire, rope, heavy tape, or similar
materials.
NARROW-AISLE TRUCK: A self-loading truck intended primarily for right angle stacking in aisles
narrower than required by counterbalanced trucks of the same capacity (see Exhibit 10.1).
OPEN SOCKET: A wire-rope fitting consisting of a basket and two ears with a pin.
OVERHEAD GUARD: A framework fitted to a truck over the head of a riding operator.
PALLET TRUCK: A self-loading, non-motorized or motorized low-lift truck equipped with wheeled
forks of dimensions sized to go between the top and bottom boards of a double-faced pallet, the
wheels fitting into spaces between the bottom boards, to raise the pallet. (see Exhibit 10.2).
PEENING: Permanent distortion of the outside wire, in a wire rope, caused by pounding.
PERSON-IN-CHARGE (PIC): The manager or other responsible person (other than the equipment
operator) known to be qualified and appointed to be responsible for the safe handling of critical
loads.
POWERED INDUSTRIAL TRUCK: A mobile, power-driven vehicle used to carry, push, pull, lift,
stack, or tier material.
PREFORMED WIRE ROPE: Wire rope in which the strands are permanently shaped, before being
fabricated into the rope, to the helical form they assume in the wire rope.
PREFORMED STRAND: Strand in which the wires are permanently shaped, before being fabricated
into the strands, to the helical form they assume in the strand.
PRE-STRESSING: Stressing a wire rope or strand before use under such a tension and for such a time
that stretch that would otherwise occur once the load is picked up is largely nonexistent.
PROOF TEST: A nondestructive tension (load) test performed to verify construction and workmanship
of slings or rigging accessories.
QUALIFIED INSPECTOR: One whose competence is recognized by the responsible manager and
whose qualification to perform specific inspection activities has been determined, verified, and
attested to in writing.
QUALIFIED OPERATOR: One who has had appropriate and approved training, including satisfactory
completion of both written and operational tests to demonstrate knowledge, competence, and
skill, in the safe operation of the equipment to be used.
QUALIFIED RIGGER: One who meets the definition of a qualified person as it applies to the
assigned rigging tasks. Employers must determine whether a person is qualified to perform
specific rigging tasks. Each qualified rigger may have different credentials or experience. The
person designated as the qualified rigger must have the ability to properly rig the load for a
particular job. This does not mean that a rigger must be qualified to do every type of rigging job.
QUALIFIED SIGNAL PERSON: A qualified person who has met the requirements of 29 CFR
1926.1428 and has successfully passed the required oral or written test and a practical evaluation.
NOTE: The term rigger or qualified rigger in this handbook refers to the function performed, and in
no way relates to the workers classification in any union or bargaining unit.
RATED CAPACITY: The maximum hook load that a piece of hoisting equipment is designed to carry
the maximum load that an industrial truck or a sling, hook, shackle, or other rigging tackle is
designed to carry.
NOTE: At the option of the user, a rated capacity can be assigned that is less than the design-rated
capacity.
REACH TRUCK: A self-loading truck, generally high-lift, having load-engaging means mounted so it
can be extended forward under control to permit a load to be picked up and deposited in the
extended position and transported in the retracted position (see Exhibit 10.1).
REEL: The flanged spool on which wire rope or strand is wound for storage or shipment.
REEVING: A system in which a rope or chain travels around drums, sprockets, or sheaves.
REGULAR-LAY ROPE: Wire rope in which the wires in the strands and the strands in the rope are laid
in opposite directions.
REVERSE BEND: Reeving of a wire rope over sheaves and drums so that it bends in opposite
directions.
RIGGING: The hardware or equipment used to safely attach a load to a lifting device. The art or
process of safely attaching a load to a hook by means of adequately rated and properly applied
slings and related hardware.
ROLLERS: Relatively small-diameter cylinders or wide-faced sheaves used for supporting or guiding
ropes.
ROTATION-RESISTANT WIRE ROPE: Wire rope consisting of a left-lay, lang-lay inner rope
covered by right-lay, regular-lay outer strands.
RUNNING SHEAVE: A sheave that rotates as the load block is raised or lowered.
RUNWAY: Assembly of rails, girders, brackets, and framework on which a crane operates.
SAFE WORKING LOAD: Load that a rope may carry economically and safely.
SEALE: A strand construction having one size of cover wires with the same number of one size of wires
in the inner layer and each layer having the same length and direction of lay. Most common
construction is one center wire, nine inner wires, and nine cover wires.
SEIZE: To securely bind the end of a wire rope or strand with seizing wire or strand.
SEIZING STRAND: Small strand, usually of seven wires, made of soft-annealed-iron wire.
SELF-LOADER: A truck with tires that can fit between the top and bottom boards of a double-faced
pallet.
SERVE: To cover the surface of a wire rope or strand with a wrapping of wire.
SHEAVE: A grooved wheel or pulley used with a rope to change direction and point of application of a
pulling force.
SHEAVE, NON-RUNNING (EQUALIZER): A sheave used to equalize the tension in opposite parts
of a rope, called non-running because of its slight movement.
SPIRAL GROOVE: Groove that follows the path of a helix around a drum, similar to a screw.
SPLICING: Interweaving of two ends of rope to make a continuous or endless length without
appreciable increasing the diameter. Also refers to making a loop or eye in the end of a rope by
tucking the ends of the strands.
SPLICE, HAND TUCKED: A loop or eye formed in the end of a rope by tucking the end of the strands
back into the main body of the rope in a prescribed manner.
SPLICE, MECHANICAL: A loop or eye formed in the end of a wire rope by pressing or swaging one
or more metal sleeve over the wire rope junction.
STAINLESS-STEEL ROPE: Wire rope made of chrome-nickel steel wires having great resistance to
corrosion.
STEEL-CLAD ROPE: Rope with individual strands spirally wrapped with flat steel wire.
STRAND: An arrangement of wires helically laid about an axis or another wire or fiber center to
produce a symmetrical section.
A suspect item is one in which visual inspection, testing, or other means indicate it may not conform to
established Government or industry-accepted specifications or to national consensus standards.
SWITCH, ELECTRIC: A device for making, breaking, or changing Figure 1-5. Thimble
the connections in an electrical circuit.
SWITCH, EMERGENCY STOP: A manually or automatically operated electric switch to cut off
electric power independently of the regular operating controls.
SWITCH, LIMIT: A switch that is operated by some part or motion of a power-driven machine or
equipment to alter the electrical circuit associated with the machine or equipment.
SWITCH, MAIN: A switch controlling the entire power supply to a crane or other equipment, often
called the disconnect switch.
TAPERING AND WELDING: Reducing the diameter of the end of a wire rope and welding it to
facilitate reeving.
THIMBLE: Grooved metal fitting to protect the eye of a wire rope (Figure 1-5).
TROLLEY: A unit consisting of frame, trucks, trolley drive, and hoisting mechanism moving on the
bridge rails in a direction at right angles to the crane runway.
TROLLEY GIRTS: Structural members that are supported on the trolley trucks and that contain the
upper sheave assemblies.
TROLLEY TRUCK: An assembly consisting of wheels, bearings, axles, and structural-supporting hoist
mechanism and load girts.
TRUCK, POWERED INDUSTRIAL: A mobile, power-propelled truck used to carry, push, pull, lift,
stack, or tier material (see Figure 10-3).
TURNBUCKLE: A device attached to wire rope for making limited adjustments in length. It consists
of a barrel and right- and left-hand threaded bolts.
TWO-BLOCKING: The act of continued hoisting in which the load-block and head-block assemblies
are brought into physical contact, thereby preventing further movement of the load block and
creating shock loads to the rope and reeving system.
WEDGE SOCKET: Wire-rope fitting in which the rope end is secured by a wedge.
WHEEL BASE: Distance between centers of outermost wheels for bridge and trolley trucks.
WHEEL LOAD: The load on any wheel with the trolley and lifted load (rated load) positioned on the
bridge to give maximum-loading conditions.
WIRE (ROUND): Single continuous length of metal, cold drawn from a rod.
WIRE (SHAPED): A single continuous length of metal either cold drawn or cold rolled from a rod.
This chapter provides guidelines for critical / non-standard / ordinary lift determination and
requirements for planning and performing each classification of lift safely and judiciously. A
qualified and competent person shall classify each lift critical, non-standard, or ordinary prior to
planning the lift, based on the following criteria.
2.1.1 A lift shall be designated CRITICAL if any of the following conditions are met:
2.1.1.1 Any lift that involves the lifting of people. (Chapter 4 has been devoted to the subject, and is to be
referred to for guidance and documentation requirements.)
2.1.1.2 The lift involves lifting or movement of explosives. Written procedures and operations must be
validated/verified using an inert prototype for all first time lifts involving explosives.
Documented validation/verification obtained from the test customer will satisfy this requirement.
2.1.1.3 The lift involves the use of two cranes to lift a common load, when the load exceeds 50% of either
cranes rated capacity.
2.1.1.4 The item being lifted contains radioactive or other hazardous materials or chemicals, which if
dropped or upset could result in a release/spill that meets State or Federal reporting criteria.
2.1.1.5 Additional requirements specific to FIXED CRANES.
2.1.1.5.1 Any planned engineered lift.
2.1.1.5.2 Any lift that exceeds 95% of the rated load capacity.
2.1.1.6 Additional requirements specific to MOBILE CRANES.
2.1.1.6.1 Lifts in vicinity of overhead power lines. The minimum clearance under most conditions is 20
feet. This means, if any part of the equipment, load line or load, if operated up to the equipment's
maximum working radius in the work zone, could get closer than 20 feet to a power line. (See
paragraph 9.6)
2.1.1.6.2 The lift involves lifting in excess of 85% of the cranes rated capacity, as shown on the
applicable crane manufacturers load charts for the configuration to be used.
2.1.1.6.3 Use of a crane or lifting device in any application, which deviates from the manufacturers
recommendations, including but not limited to:
Boom configuration not per boom make-up chart.
Moving a crane with longer boom than recommended.
Exceeding capacities or restrictions shown on the load chart.
2.1.1.6.4 Operations, which require traveling the crane while carrying a load of 85% of the crane
manufacturers rated pick and carry capacity.
2.1.1.7 Any lift deemed critical by management, AEDC Crane System Engineer or the base operating
contractors safety office. Some additional conditions that should be taken into consideration that
do not automatically classify the lift as critical are as follows:
2.1.1.7.1 The cost to replace or repair the load item, or the delay in operations of having the load item
damaged would have a negative impact on facility, organizational, or AEDC budgets to the extent
that it would affect program commitments.
2.1.1.7.2 The load item is unique and, if damaged, would be irreplaceable or not repairable and is vital to
a system, facility, or project operation.
2.1.1.7.3 Lifts that are made where the load or crane could fall on pipelines or storage vessels containing
flammable gases or liquids.
2.1.1.7.4 Lifts where the crane or load is in a confined space.
2.1.1.7.5 Lifts over active work areas, office buildings, or public access ways.
2.1.1.7.6 Lifts using rigs over 150-ton capacity and/or 200 feet of boom.
2.1.1.7.7 Lifts with attachment points at or below CG.
2.1.1.7.8 Further site-specific criteria may be developed to supplement those cited above and may include
loads which require exceptional care in handling because of size, weight, close-tolerance
installation or high susceptibility to damage as well as lifts using multiple pieces of lifting
equipment.
2.1.2 A lift shall be designated NON-STANDARD if the following condition is met:
2.1.2.1 The load to be lifted is between 50% and 85% of the rated capacity of the mobile crane.
2.1.3 A lift shall be designated ORDINARY if the lift is not designated as a critical lift or non-standard
lift.
2.2 CRITICAL / NON STANDARD / ORDINARY LIFT REQUIREMENTS
2.2.1 Lifts classified as CRITICAL shall be performed in accordance with the following requirements
before initiating the lift:
2.2.1.1 The operating organization conducting the lift shall appoint a Person-in-Charge (PIC), along with
sufficient numbers of employees to ensure the lift can be completed safely, for the entire
operation. The PIC shall meet the definitions of appointed, designated, and qualified as described
in Chapter 1 and shall be present at the lift site during the entire lifting operation.
2.2.1.2 The PIC shall ensure that a Critical Lift Plan is prepared that defines the operation and includes
the following:
2.2.1.2.1 Identification of the items to be moved, the weight, dimensions, and center of gravity of the
load, stability analysis, and any hazardous or toxic materials that are present.
2.2.1.2.2Identification of operating equipment to be used by type and rated capacity.
2.2.1.2.3 Rigging sketches that include (as applicable):
Identification and rated capacity of slings, lifting bars, rigging accessories, and below-the-
hook lifting devices.
Load-indicating devices.
Load vectors.
Lifting points.
Sling angles.
Boom and swing angles.
Methods of attachment.
Crane orientations.
Stability Analysis.
Other factors affecting equipment capacity.
2.2.1.2.4 Operating procedures and special instructions to operators including rigging precautions and
safety measures to be followed as applicable.
2.2.1.3 Experienced operators who have been trained and qualified to operate the specific equipment to be
used shall be approved by the PIC before being assigned the task.
2.2.1.4 Only one qualified signal person at a time shall give signals to the operator. However, the
operator shall obey a STOP or Emergency Stop signal at all times, no matter who gives the
signal.
2.2.1.5 The procedure and rigging sketches shall be reviewed and approved by the AEDC Crane System
Engineer (or designee) and the responsible oversight organization (such as safety, quality
assurance, or quality control) before the lift is made.
2.2.1.6 A pre-lift meeting(s) involving participating personnel shall be conducted and documented prior to
making a critical lift. The critical lift plan/procedure shall be reviewed and questions shall be
resolved.
2.2.1.7 If required by the critical lift procedure, a practice lift shall be performed before the critical lift.
Conditions for a practice lift should closely simulate actual conditions involving: weight, rigging
selection and configuration, load movement path, and other relevant factors. The same assigned
craftsmen shall perform the practice lift and the actual lift, using the same lifting equipment
during each lift.
2.2.2 Lifts classified as NON-STANDARD shall require a pre-lift meeting(s), involving participating
personnel, to be conducted and documented prior to making the non-standard lift. The non-
standard lift plan / procedure shall be reviewed and questions shall be resolved.
2.2.3 Lifts classified as ORDINARY shall be performed in accordance with the requirements for ordinary
lifts specified in each section of this handbook for each particular equipment category.
Lift
No
Follow Appropriate
Ordinary rqmts in H&R Hndbk
Lift
A. IDENTIFICATION
Job Number: Location:
1. Operator Certifications
2. Capacity Certificates & Inspection Reports for Crane and All Lifting Equipment
4. Rigging Diagram
6. Stability Analysis
7. JSA/Hazard Analysis
8. Engineering structural analysis and inspection documentation of support structure, if lift is a planned
engineered lift.
9. Stability Analysis for PIC Training
(Initials)
Pre-Lift Checklist to be completed by the PIC
Yes No
Have the cribbing mats/blocks/dunnage used under for outrigger floats been
10.
inspected and approved?
Are all required approvals signed including outside oversight, when required as
17.
directed by OGM?
(Print/Sign)
Weight Verified By:
E. SIZING OF SLINGS
1. Sling Selection
a. Type of Arrangement
b. Number of Slings to Hook
c. Sling Size Inch
d. Sling Length Ft.
e. Rated Capacity Lbs.
E. SIZING OF SLINGS
1. Sling Selection
a. Type of Arrangement
b. Number of Slings to Hook
c. Sling Size Inch
d. Sling Length Ft.
e. Rated Capacity Lbs.
B. LOAD CALCULATIONS
Main Crane
Main Hoist Auxiliary Hoist
1. Net Equipment Weight Lbs. 1. Net Equipment Weight Lbs.
2. Weight of Lifting Beam Lbs. 2. Weight of Lifting Beam Lbs.
3. Weight of Slings and Shackles Lbs. 3. Weight of Slings and Shackles Lbs.
4. Other Lbs. 4. Other Lbs.
3. Weight of Slings and Shackles Lbs. 3. Weight of Slings and Shackles Lbs.
Method of Communications.
Pre-Lift Inspection of Area.
Pre-Lift Operational Check of Crane
Discussion of Responsibilities:
Site Manager/Project Manager
PIC
Crane Operator(s)
Rigger(s)
Crane System Engineer (if applicable)
Site Safety Representative
As can be seen Sling 2 carries 1.9 times the load of Sling 1 (74,211/39,474 = 1.9)
1. The crane operator(s) and PIC are to discuss and understand the method of
communications, hand signals or radio. For fixed cranes, if not indicated on crane, it
should be understood between the operator and PIC the intended east, west, etc.
directions
NOTE: Steps 2 through 8 are intended to serve as pre-lift crane checkouts. If during the checkouts any
anomalies are found, STOP the operation and notify the PIC or engineering. If at any step this procedure
has to be stopped for repair or anomalies, steps 1 thru 5 shall be repeated in order as listed.
CAUTION: All persons involved in the critical lift pre-checks shall have hard hats, safety glasses, safety
shoes, gloves, and any other PPE that would further contribute to the safety of this operation.
2. Using the same method of calls established in step No. 1 the PIC is to direct the operator
to execute the following operations. If during these operations any anomalies are found,
STOP the operation and notify the coach or engineering.
a. Lower the crane hook to within 2 ft of the operational surface or its lower limit.
b. Observe the extended cables for any broken strands, kinks, or abnormal wear.
c. Inspect the hook for cracks, distortions or abnormal wear.
d. If the hook has swivel features verify that it can be freely rotated by hand.
e. Verify that the safety latch on the hook is in good order.
f. Verify that the cable spools properly on the drum while raising the hook from the ground
to near its upper limit.
g. Raise the hook to NEAR its upper limit. Verify that the cable spools properly on the
drum while raising the hook from the ground to near its' upper limit.
h. Verify that the hooks movement is smooth while raising the hook and no abnormal
noises are observed.
i. Bump the upper limit device/anti two-block to assure that it is working properly.
3. If two hooks or cranes are to be used in the operation, repeat step 2.
4. Swing the boom or move the trolley to near the travel limits in both directions
and observe the movement for hesitations, jerking or abnormal noises. STOP the
movement while traveling in each direction to verify that the brakes operate
satisfactorily.
5. Raise and lower the boom or move the bridge in both directions to points in its travel
limits that are beyond the points that the forth-coming critical lift will employ. Stop the
boom or bridge movement in both directions to verify that the brakes are in good order.
Observe the movement for any hesitations, jerking or abnormal noises.
6. For mobile cranes only: Assure outriggers are extended to manufacturers specifications,
are resting on proper load bearing surfaces, and crane is within 1 percent grade. Note:
Outrigger pads are required for all picks at AEDC.
7. Prior to committing to the critical lift, all of the required rigging is to be
inspected by the PIC or his designated personnel or agency and verified to have been
proof tested and to be in good order.
a. All shackles and pins are to be inspected to be free from distortions or excessive wear.
The pins should have free engagement of the threads or the correct restraining pins in
place.
b. All chokers are to be certified and free from broken strands, kinks, distorted lay,
excessive wear or other anomalies. Verify that the swaged fittings securing the choker
eyes to the main strand are in good order. If the chokers are required to be a matched set,
check the length and substitute as required.
c. Any come-a-longs to be used in the lift are to be specified by engineering. They are to be
inspected by the PIC to be in good order and in compliance with engineering
specifications.
d. Verify that any special brackets to be used in the lift show no distortions, cracks, or
broken welds and that the lifting eyes and bolt holes align properly.
e. Verify that all equipment supplied by the customer is in good order and is ready to
commit to the forth-coming critical lift.
f. Verify that any other special equipment that is to be used in the forth-coming lift is noted
below and is in good order.
_______________________________________________________________________
8. The PIC is to verify that the lift areas are free from equipment or objects which would
create hazards in the lifting operation.
Exhibit 2.6 Description and Analysis Methodology for Hoisting Equilibrium Stability
The characteristic of a positively stable equilibrium configuration for a lift is defined as: if the
slightest force acts momentarily to produce a small displacement from equilibrium, the system will return
to the original equilibrium condition as soon as the disturbing force is removed.
The characteristic of a negatively stable ( un-stable) equilibrium configuration for a lift is defined
as: if the slightest force acts momentarily to produce a small displacement from equilibrium, the system
will move away from the original equilibrium condition even after the disturbing force is removed.
The characteristic of a neutrally stable equilibrium configuration for a lift is defined as: if the
slightest force acts momentarily to produce a small displacement from equilibrium, the system neither
returns to the original equilibrium nor to a position further away from the original configuration.
Examples of the unstable and stable equilibrium cases are illustrated below.
Unstable Configuration: The condition of equilibrium exists for a ball placed on the highest
point of the convex curve in Figure A1a and is indicative of an unstable equilibrium. The condition of
equilibrium is due to the reactive force normal to the surface which is vertical and equals the gravity force
acting through the ball center of gravity. All forces and moments are summed to zero. The slightest force
applied horizontally to disturb the ball starts a motion downward along the convex surface continually
moving away from the original equilibrium condition.
Stable Configuration: In A1b, the ball is placed at a low position of the concave curve and the position
is stable. A small force that displaces the ball from equilibrium position creates a force normal the
surface that causes the ball to return to the original position. This is considered a stable restoring force.
For an unstable position of equilibrium of the ball, as in Fig. A1a, the vertical position decreases
for any small (virtual) positive or negative horizontal displacement, while in the case of a stable position
of equilibrium, as in Fig. A1b, the vertical displacement increases on any small (virtual) positive or
negative horizontal displacement. It can be stated that for an unstable position of equilibrium the vertical
position of the ball is a (local) maximum and for a stable position of equilibrium it is a (local) minimum.
The same kind of reasoning can be applied in the general case of a hoisting configuration.
In classical mechanics the method to find local maxima and minima is to consider the second
derivative. For consideration in lifting configurations this is done by calculating the vertical (Y direction)
displacement of the load CG for a small (virtual) displacement of the CG in the positive x ( axial) or z (
lateral ) direction.
The change in the vertical CG for a change in the x or z direction is approximately equal to the
first derivative ( for small value of displacement).
The second derivative is approximated by taking the change in the first derivative for a small
change in the x or z direction. If the approximated second derivative is positive the configuration is
stable. If the approximated second derivative is zero the configuration is neutrally stable. If approximated
second derivative is negative, the configuration is unstable.
For our case in Figure A1a and A1b we can display notionally the first and second derivative
approximations as shown in Figure A3a,b. The second derivative of vertical displacement relative to
horizontal displacement is required to assess equilibrium stability. A stable lifting configuration may still
tilt in order to move the CG into equilibrium position, resulting in a condition where the CG is under the
system line of suspension.
For analyzing lifting configurations, the rotation about the longitudinal and lateral axes must be
considered for lifting stability. Forces about the yy ( yaw about vertical) axis are generally not generated
by the lift itself, but by external forces such as wind.
If the CG is below the attachment points, static equilibrium stability in the axes of rotation is
assured. This is always the preferred lifting configuration.
If the CG is at or above the attachment point, the CG moves away from stable static equilibrium
and towards unstable. The configuration is not necessarily unstable, but stability must be assessed. This is
an un-preferred configuration.
If the CG of the load is at or above the attachment point of the rigging, the stability of the
configuration must be analyzed and approved as part of the lift plan.
Graphic illustration of stable and unstable equilibrium for lifts is shown below for a 2 point lift to an apex
attachment at the crane hook.
In the unstable configuration, Fig A4a, the CG moves away from equilibrium without restorative
forces generated. For the stable configuration Fig A4b, the CG moves toward the equilibrium condition
with the line of suspension below the hook.
3.1 GENERAL
It is recognized that lifts, in excess of the rated load capacity of an overhead crane may be required
from time to time on a limited basis for specific purposes such as new construction or major
repairs. This chapter specifies the requirements for when it becomes necessary to perform such a
lift. When a Planned Engineered Lift becomes necessary, the following applies:
3.1.1 Every lift, exceeding the rated load capacity of an overhead crane, shall be treated as a special and
separate event. Limitations and planned requirements shall be applicable, as follows:
3.1.1.1 Planned engineered lifts shall be limited to powered cranes having a load rating of 5 tons and
above.
3.1.1.2 When planned engineered lifts are made, the load shall not exceed 125% of the crane load rating,
except as provided in Paragraph .3.1.1.6.
3.1.1.3 Planned engineered lifts shall be limited to two occurrences on any crane within any continuous
12 month period, except as provided in Paragraph 3.1.1.6 If greater lift frequency is desired,
consideration shall be given to rerating or replacing the crane.
3.1.1.4 Each planned engineered lift shall comply with the following requirements.
3.1.1.4.1 A written review of the crane service history shall be prepared, including reference to previous
planned engineered lifts, structural repairs, and modifications of original design
3.1.1.4.2 The design of the structural, mechanical, electrical, pneumatic, and hydraulic components of the
crane shall be reviewed, by means of applicable calculations for the load to be lifted, and
approved by the crane manufacturer or a qualified person, in accordance with accepted crane
design standards if the load to be lifted exceeds 125% of rated load, or if the frequency of planned
engineered lifts exceeds two during a continuous 12-month period
3.1.1.4.3 The design of the crane-supporting structure shall be reviewed and approved by a qualified
person for conformance to applicable design criteria. The crane support shall be inspected and
any deterioration or damage shall be taken into consideration in design calculations for the load to
be lifted.
3.1.1.4.4 The crane shall be inspected in accordance with Paragraph 7.2. just prior to making the lift.
3.1.1.4.5 The lift shall be made under controlled conditions under the direction of a designated person in
accordance with a previously prepared lift plan. All persons in the area of the crane shall be
alerted that the lift is being made.
3.1.1.4.6 The operator shall test the crane at the planned engineered load by lifting the load a short
distance and setting the brakes. The lift shall only be continued if the brakes stop and hold the
load. Any failure to hold the load shall be corrected before proceeding with the lift.
3.1.1.4.7 The crane shall be inspected in accordance with Paragraph 7.2. after the lift is completed and
prior to being used for the lifting of any other load.
3.1.1.4.8 A record of the planned engineered lift, including calculations, inspections, and all distances
moved, shall be placed on file for availability to appointed personnel.
3.1.1.5 The rated load test specified in Paragraph 7.3.2 is not applicable to planned engineered lift
provisions.
3.1.1.6 The crane manufacturer shall be consulted if the planned engineered lift exceeds 125% of rated
load or if the frequency of planned engineered lifts exceeds two during a continuous 12-month
period.
4.1 GENERAL
Note: The requirements of this chapter are not intended to direct emergency response actions
performed by appropriately trained and/or qualified rescue personnel or first responders.
This chapter specifies the operation, design, testing, and inspection requirements for the use of
personnel lift platforms or baskets suspended from mobile or overhead cranes. This chapter
implements the requirements of 29 CFR 1926.1431 Cranes and Derricks and ASME B30.23.
4.1.1.1 The use of a crane to hoist employees on a personnel lift platform is prohibited, except when the
erection, use, and dismantling of conventional means of reaching the worksite, such as a
personnel hoist, ladder, stairway, aerial lift, elevating work platform, or scaffold, would be more
hazardous or is not possible because of structural design or worksite conditions. Riding the load,
headache ball, hook, etc., is always prohibited.
4.1.1.2 The Asset Owner responsible for the overall work function to be performed shall determine that
the erection, use, and dismantling of conventional means of reaching the work site (i.e., scaffold,
ladder, stairway, aerial lift, or elevating work platform) would be more hazardous or is not
possible because of structural design or worksite conditions.
4.1.1.3 For each personnel lifting procedure, Asset Owner, with for the task shall authorize the use of a
crane-suspended work platform and attest to the need for the operation through a written
justification. (See Exhibit 4.1, Section D.) A statement describing the operation and its period
shall be included. The statement, after being approved by the authorizer, shall be retained at the
job site.
4.1.1.4 The Asset Owner responsible for the overall work function shall not allow or require any operator
to lift personnel under the following circumstances:
4.1.1.4.1 The operator does not feel physically or mentally fit to perform the operation.
4.1.1.4.2 The operator has been working for more than 10 hours prior to the start of the lift or the lift will
not be completed before the operator has been working for 12 hours.
4.1.1.4.3 The operator did not have at least eight hours off, immediately prior to the work shift containing
the person.
4.1.2.1 The Asset Owner shall appoint a Designated Leader for the entire personnel lifting operation.
The PIC must
4.1.2.2 The Designated Leader shall ensure that a pre-job plan is prepared that defines the operation. The
Designated Leader shall ensure:
4.1.2.2.1 At each new job site prior to hoisting personnel, the personnel lift platform, rigging, and hook
block shall be proof-tested by a qualified inspector to 125% of the personnel platforms rated
capacity by holding it suspended for 5 minutes with the test load suitably distributed on the
personnel platform.
4.1.2.2.2 The record of the most recent proof testing shall be maintained at the job site.
4.1.2.2.3 A meeting, with the qualified operator, signaler, persons to be lifted (when available), and the
person responsible for overall worksite safety is held prior to the trial lift to review the procedure.
4.1.2.2.4 The procedures for entering and leaving the personnel platform and the points at which persons
will enter and leave the device shall be reviewed. This meeting shall be held at each new work
location, and shall be repeated for any employees newly assigned to the operation.
4.1.2.2.5 A personnel lifting critical lift plan is developed and followed per this chapter.
4.1.2.3 The Designated Leader and the crane operator shall determine that:
4.1.2.3.1 The crane is uniformly level within 1% of level grade and firm footing exist under both crawler
tracks or under each outrigger. Cribbing mats / dunnage / blocks under outrigger floats are used
as necessary to provide a firm and substantial footing.
4.1.2.3.2 Cranes equipped with outriggers have outriggers extended in accordance with the
manufacturers instructions.
4.1.2.3.3 Crane systems, controls, operator aids, and safety devices are activated and functioning
properly.
4.1.2.3.4 Area has been inspected for potential hazards, such as but not limited to excessive load and/or
radius, overhead obstructions and electrical transmission lines, hazardous locations, inadequate
surface and support to withstand all forces imposed, wind, weather, unstable conditions, and any
other potentially hazardous conditions.
4.1.2.3.5 The total weight of the loaded personnel lift platform (including personnel) and related rigging
does not exceed 50% of the crane rating under the planned conditions of use.
4.1.2.3.6 The personnel lift platform is not loaded in excess of its rated load capacity.
4.1.2.3.7 The number of employees occupying the platform does not exceed the number required for the
work being performed.
4.1.3.1 Each shift, before personnel initially enter the personnel lift platform, the operator and signaler
shall conduct a trial lift. The trial lift shall include:
4.1.3.1.1 Loading the unoccupied personnel platform to at least the maximum anticipated load. Materials
and tools to be used during the actual lift, if secured to prevent displacement, can be in the
platform for the trial lift.
4.1.3.1.2 Making the trial lift from the location where personnel will enter the platform to each location
where the platform will be hoisted and positioned. It is acceptable to perform a single trial lift on
each shift for all locations to be reached from a single setup position.
4.1.3.2.1 A mobile crane is moved and set up in a new location or returned to a previously used location.
4.1.3.2.2 When the lift route is changed, unless the operator determines that the safety of the hoisted
personnel is not affected.
4.1.4.1.1 A meeting attended by the Designated Leader, crane operator, signal person, riggers handling
the tag lines and person(s) to be lifted shall be held each shift to plan and review procedures to be
followed, including:
The Pre-Lift Inspection shall be performed after the trial lift but prior to lifting personnel:
4.1.4.2.1 A visual (non-documented) inspection of the crane, rigging, and personnel lift platform shall be
conducted by a qualified inspector. Any defects found that create a safety hazard shall be
corrected prior to hoisting personnel. See Exhibit 4.3.
4.1.4.2.2 The platform shall be lifted a few inches and inspected to ensure that it is secure and properly
balanced.
No hazardous conditions exist with the platform and its associated rigging.
The hoist line is not wrapped around any part of the platform.
Hoist ropes are free of kinks.
Remain in continuous sight of, and in direct communication with, the operator or signaler. In
situations where direct visual contact with the operator is not possible, and the use of a
signaler would create a hazard for that person, direct communication alone (such as a two-
way radio) may be used.
Keep all parts of their bodies inside the suspended personnel lift platform during raising,
lowering, and positioning to avoid pinch points.
Wear body harnesses with lanyards attached to the lower load block or overhaul ball, or to a
structural member within the platform that is capable of supporting a fall impact.
Not stand on or work from the top rail, midrail, or toe board of the suspended personnel
platform.
When working above water, the requirements of 29 CFR 1926.106 shall also apply.
When welding is being performed from the personnel lift platform, the electrode holders shall
be protected from contact with metal components of the personnel platform.
Have materials and equipment evenly distributed and secured while the platform is lifted, and
shall not pull the platform out of plumb with the hoisting equipment
4.1.4.3.3 Operators of cranes hoisting personnel in a personnel lift platform shall:
Before commencing or continuing the lift, consult with the Designated Leader whenever
there is any doubt as to the safety of the lift.
Remain at the controls when the personnel lift platform is occupied.
Operate the crane so that lowering will be power-controlled (no free-fall).
Ensure movement of the personnel lift platform is performed in a slow, controlled, cautious
manner with no sudden movements of the crane or the platform. The lifting or lowering
speed shall not exceed 100 ft/min (30 m/min).
After the personnel lift platform is positioned, set all brakes and locks on the lift crane before
personnel perform any work.
If the personnel lift platform cannot be landed, ensure it is tied to the structure before
personnel enter or exit.
Ensure no other loads are lifted on any other load lines while conducting a personnel lift.
4.1.4.3.4 Suspended personnel lift platforms shall be used only for personnel, their tools, and sufficient
materials to do their work. They shall not be used for transporting bulk materials.
4.1.4.3.5 Personnel lift platforms shall not be used in winds greater than 20 mph (32.2 km/hr), electric
storms, snow, ice, sleet, or other adverse weather conditions that could affect the safety of
personnel.
4.1.4.3.6 Use tag lines to control motion of occupied personnel lift platforms unless their use creates an
unsafe condition.
4.1.4.3.7 Cranes shall not travel while personnel are in the platform. Exceptions to this provision shall be
approved by the manager specifically responsible for the overall work function and precautions to
be taken documented in the personnel lift plan.
4.1.5.1 For additional safety of personnel and equipment, an insulating link shall be used whenever
electrical welding is to be performed from a personal lift platform.
4.1.5.2 The platform shall not be used as a ground return for an electric welder. Ground return leads shall
be insulated from the platform.
4.1.5.3 All work from a platform will cease and employees will take cover whenever lightning is within
10 miles of the job site.
Mobile cranes are designed and intended for handling materials, not personnel. In addition to the
general requirements in paragraph 4.1, the following requirements shall be met when lifting
personnel with a mobile crane:
4.2.1.1 A personnel lift platform that is supported from the cranes hook, which meets the requirements of
paragraph 4.4.
4.2.1.2 A personnel basket attached directly to the boom, which is approved by the crane manufacturer.
4.2.2 Cranes with variable-angle booms shall be equipped with a boom-angle indicator that is readily
visible to the operator.
4.2.3 Cranes with telescoping booms shall be equipped with a device to indicate clearly to the operator, at
all times, the booms extended length, or an accurate determination of the load radius to be used
during the lift shall be made prior to hoisting personnel.
4.2.4 A positive-acting device shall be used that prevents contact between the load block or overhaul ball
and the boom tip (anti-two-blocking device), or a system shall be used that deactivates the
hoisting action before damage occurs in the event of a two-blocking situation (two-block damage-
prevention feature).
4.2.5 Cranes having booms in which lowering is controlled by a brake without aid from other devices,
which slow the lowering speeds, is prohibited.
4.2.6 Crane load lines shall be capable of supporting, without failure, at least seven times the maximum
intended load, except where rotation resistant rope is used, the lines shall be capable of
supporting without failure, at least ten times the maximum intended load.
4.2.7 Hydraulic cranes shall have check valves or other devices that will prevent uncontrolled movement
in the event of system failure, engine failure, or hose rupture.
4.2.8 Cranes shall have a means to prevent retraction of hydraulically or pneumatically activated
outriggers or stabilizers in the event a hydraulic or pneumatic line fails.
4.2.9 Pendant supported, jib type, boom extensions without positive stops are prohibited for personnel
lifting.
4.2.10 Hooks on overhaul ball assemblies, lower load blocks, or other attachment assemblies shall be of
the type that can be closed and locked, eliminating the hook throat opening. (See Figure 4-1).
Alternatively, an alloy anchor type shackle with a bolt, nut,
and retaining pin may be used
structural design and familiar with national consensus standards governing personnel platform
design.
4.4.1.3 All welding of the platform shall be performed by a qualified welder in accordance with
ANSI/AWS D1.1. Where special steels or other materials are used, the manufacturer shall
provide welding procedures. Welds shall be inspected by a qualified inspector.
4.4.1.4.2 A plate specifying its empty weight and its rated load capacity or maximum intended load.
4.4.1.4.3 Perimeter protection consisting of a top rail approximately 45 in. (10 cm) high, and a midrail
approximately halfway between the top rail and the toe board.
4.4.1.4.4 A grab rail inside the personnel lift platform to minimize hand exposure.
4.4.1.4.5 Anchorage points within the platform for attaching personnel fall protection lanyards.
4.4.1.4.6 The sides of the platform enclosed from the toe board to the midrail with solid construction or
expanded metal having openings no greater than in. (1.27 cm).
4.4.1.4.7 Platform access gates, including sliding or folding types, if installed, shall have a positive acting
device to restrain the gate from accidental opening. Swinging type access gates shall open only
to the interior of the personnel lift platform.
4.4.1.4.8 Rough edges exposed to contact by employees surfaced (ground smooth) to prevent injury.
4.4.1.5 In addition to wearing hard hats, personnel shall be protected by overhead protection on the
personnel lift platform when there is an overhead hazard. Sufficient headroom shall be provided
to allow employees to stand upright in the platform.
4.4.2.1 Wire rope, shackles, rings master links, and other rigging hardware must be capable of supporting,
without failure, at least five (5X) times the maximum intended load applied or transmitted to that
component and guided by the following:
4.4.2.1.2 Two- or more leg system design factor of five (5) for each leg with only two legs under stress.
4.4.2.2 Sling suspension systems shall utilize a master link or safety type shackle to connect the personnel
lift platform to the load line to ensure that the load is evenly divided among the suspension
system legs.
4.4.2.3 The suspension system shall be designed to minimize tipping of the platform due to movement of
employees occupying the platform.
4.4.2.4 The sling suspension system attaching the personnel lift platform to the hoist line shall not be used
for any other purpose when not hoisting personnel.
4.4.2.5 Shackles used in any part of the suspension system shall be a safety type (bolt-type shackle with
nut and cotter pin).
4.4.2.6 All eyes in wire rope slings shall be fabricated with thimbles.
4.4.2.7 Wire rope clips, wedge sockets, or knots shall not be used in suspension system sling assemblies.
4.4.2.8 Synthetic webbing, natural or synthetic fiber rope shall not be used for the suspension systems.
4.4.2.9 Chain sling suspension systems shall use a minimum of grade 80 chain.
4.5 INSPECTIONS
All equipment used in the lifting of personnel shall be inspected, tested, and maintained to protect
against failure during lifting operation.
4.5.1.1 General
The platform manufacturer shall furnish complete inspection criteria for the platform users. The
criteria shall address all inspection frequency classifications and shall cover:
4.5.1.1.3 Fasteners
4.5.1.2.1 Prior to initial use, and at each new job, the platform shall be inspected by a qualified inspector
in accordance with the instructions provided by the manufacturer.
4.5.1.2.2 The platform, suspension system, attachment points, and any motion controls shall be inspected
at least each day, before use, by a designated person. The inspection is to identify conditions that
have been specifically indicated by the platform manufacturer, or a qualified person, as
potentially creating a hazardous operating condition. Visually inspect items such as the
following:
o Perimeter protection; top rail, midrail, toe board, and barrier from toe board to
midrail.
o Fall protection device anchorage points.
o Gate locking mechanisms.
o Platform flooring.
o Suspension attachment points.
Attachment mechanisms: Master links, shackles, slings, bolt-ups, etc.
Special purpose items:
o Overhead protection
o Platform controls
4.5.1.2.3 For frequent inspections, dated records for the hoisting equipment and personnel lift platform
shall be made and kept by the platform user for the duration of the personnel lift operation.
4.5.2.1.1 At least once every 12 months, or as required by the personnel lift platform manufacturer, a
periodic inspection of the platform shall be performed by a qualified inspector in accordance with
the instructions provided by the manufacturer.
4.5.2.1.2 Platforms, which have been out of service for 12 or more consecutive months, shall receive a
periodic inspection prior to use.
4.5.2.1.3 Dated inspections records for the platform shall be made. The last periodic inspection records
shall kept by the platform user in the platforms historical file and available for review.
4.6 TESTING
4.6.1.1.4 When the complete production platform is not supplied by one manufacturer, the manufacturers
platform test shall be conducted at final assembly by the platform assembler or a qualified
inspector. Dated records of the test(s) shall be made and filed in the platforms historical file.
4.6.1.2 Slings (wire rope or chain) shall receive an initial load test before installation by applying a test
load to each individual leg equal to twice the rated load of the leg. If a master link or safety
shackle is used in the suspension system, it shall be tested to at least the weight of the platform
plus the platform rating.
4.6.1.2.2 Any components showing damage shall be replaced and the test procedure repeated.
4.6.2.1 At each new job site, prior to hoisting people in the personnel platform, the platform and rigging
shall be proof tested to 125% of the platforms rated capacity.
4.6.2.2 With the proof test load evenly distributed in the platform, the platform shall be hoisted and held
in a suspended position for 5 minutes.
4.6.2.3 When feasible the proof testing may be done concurrently with the trial lift.
4.6.2.4 After proof testing, the platform shall be inspected by a qualified person. Any damage or
deficiencies revealed during the inspection, or by the proof test, shall be corrected and another
proof-test conducted.
4.6.2.5 After any structural repair or modification to a personnel lift platform, the platform shall be proof
tested to 150% of the platforms rating.
4.6.2.6 Suspended platforms shall be tested by raising the platform to a height, then lowering it at a speed
of not less than 100 ft/min. Once a lowering speed of 100 ft/min or more is reached, the platform
descent shall be halted by applying the hoisting equipment brakes and then the platform allowed
to hang for a period of not less than 5 min. After this test and hanging period, the platform shall
be inspected by a qualified person. Any damage revealed by the inspection shall be corrected and
another proof test conducted.
4.6.2.7 When feasible, the hoisting equipment to be used for lifting personnel should be the equipment
used to perform the proof test at the job site.
4.6.2.8 The record of the most recent proof testing shall be maintained at the job site.
Paragraph 9.5.2 outlines the requirements for crane operations near power lines.
4.7.1 If possible, when lifting personnel near electrical power lines, the lift shall be performed to
eliminate possibility of the crane, load line, or personnel platform becoming a conductive path.
4.7.2 Cranes shall not lift any personnel under electrical power lines if any combination of boom,
personnel platform, load line, or machine components will enter the prohibited zone (Figure 4-3).
4.7.3 Lifting personnel near electrical power lines shall not be allowed unless there is no less hazardous
way to perform the job. Conditions specified in 4.7.2 must be considered when lifting personnel
near electrical power lines.
A. GENERAL INFORMATION
2.
3.
Designated Leader or Person-In-Charge (PIC):
Is the total intended load weight equal to or less than 50% of the
4.
cranes capacity as configured?
Has a trial lift in accordance with AEDC H&R Handbook Chap 4
5.
been done?
Has a pre-lift inspection been done after the trial lift in
6. accordance with AEDC H&R Handbook Chap 4, and all defects
corrected?
Has the Crane Operator, Signal Person, Personnel to go in basket
7. and Designated Leader (or Person-In-Charge) of task conducted a
pre-lift safety meeting?
Has a proof test been conducted in accordance with AEDC H&R
8.
Handbook Chapter 4
13. Is the working area of the lift clear of all power lines?
If all of the above questions are answered yes or N/A, you may proceed.
Changes in the crane location, configuration and lift route will require another checklist.
I acknowledge that all requirements have been met and all conditions are satisfactory for this
operation.
Date: Location:
Crane Operator:
Persons to be Hoisted: / /
REVIEW
Pre-Lift Checklist
Communication Method(s)
Emergency Procedures
UNSAT SAT
2. Markings
Platform (All Information Legible)
Suspension System
3. Structure
Load Supporting Welds/Bolts
Load Supporting Members
Barrier From Toe Board to Intermediate Rail
Hand Rail
Fall Protection Device Anchorage Points
Gate Locking Mechanisms
Platform Flooring
Suspension Attachment Points
4. Attachment Mechanisms
Pins/Ears/Bolt-Ups/Eyes (Circle)
Wire Rope/Chain/Rigid Leg (Circle)
Master Links
5. Special Purpose Items (i.e., Overhead Protection, Flotation, Platform Controls)
List: (1)
(2)
(3)
6. General Comments:
This chapter describes provisions for hoisting and rigging operations in hostile work environments.
5.1 GENERAL
5.1.1 This chapter contains the special provisions for hoisting and rigging operations and equipment in
hostile environments where standard operating, maintenance, inspection, or test procedures
cannot be followed because of radiation or radioactive contamination, toxic/hazardous chemicals
or gases, or temperature extremes.
5.1.2 Hoisting and rigging activities can usually be accomplished where the environment will allow
normal operations with access for hands-on equipment contact. In those situations, operations,
maintenance, inspections, and tests shall be done in accordance with regular provisions of this
handbook.
5.1.3 Hoisting and rigging equipment or operations shall be reviewed by a designated person to determine
compliance with the requirements of this handbook. If it is determined to be impossible or
unreasonable for the requirements of this handbook to be met because of hostile environmental
conditions, a hostile environment plan shall be prepared to document alternative compliance
methods and procedures.
A hostile environment plan shall be prepared by a designated person and shall cover operations,
equipment, inspection, testing, and maintenance. See Exhibit 5.1, Hostile Environment Plan, at the
end of this chapter.
At a minimum, the plan shall be reviewed and approved by responsible management at the
facility where the crane, hoist, or other equipment is located and by responsible management of
an overview organization such as safety or quality assurance. While the site-specific
organizational structure will determine other required reviews and approvals, approval by the
following is recommended:
The plan shall address only those actions or features that require deviation from the requirements
of this handbook due to a hostile environment. At a minimum, it shall contain the following
information:
5.2.2.5 Specific maintenance, inspections, and tests to be performed whenever access is possible.
5.2.2.6 Replacement or retirement criteria for equipment that is designed to operate with little or no
maintenance.
Detailed operation, inspection, testing, and maintenance procedures that state specific
requirements and acceptance criteria shall be prepared, based on the hostile environment plan.
The Asset Owner shall ensure that the approved hostile environment plan is distributed as
follows:
5.2.4.3 Equipment history file. Hostile environment plans in the equipment history file shall be readily
available to appointed personnel.
Equipment the use of which is required by a hostile environment plan shall be posted with the
following information: Special Maintenance and Operating Instructions Required see Hostile
Environment Plan.
5.2.6.1 Handling fixtures and rigging accessories shall be qualified in accordance with Chapters 11, 12,
and 14 of this handbook prior to being exposed to the hostile environment.
5.2.6.2 Nylon (rope or webbing) slings should not be used in a radiation area unless necessary. When it is
necessary to use a nylon or polyester sling in a radiation area, the Asset Owner shall ensure that
radiation exposure does not exceed 100,000 rad during the life of the sling.
Capacity: (Auxiliary):
Power method:
Manufacturer:
1.a H&R handbook requirement that will not be met Section number:
Copy the applicable section:
1.b Difference between handbook requirement and what is to be allowed by this plan:
Include information regarding replacement or retirement criteria for this equipment. Include information
regarding any special design, maintenance, or test considerations that apply to this equipment.
APPROVALS SIGNATURE/DATE
*Facility Manager:
*Manager, Oversight Organization:
Others:
This chapter describes personnel qualification and training. Only qualified personnel shall operate
the equipment covered in this standard.
6.1 GENERAL
6.1.1 This chapter delineates the requirements for the qualification and training of operators, riggers,
inspectors, maintenance personnel, trainers, On the Job Performance Evaluators (OJPE), Person-
In-Charge (PIC), Designated Leader, and First-line Supervisors.
6.1.2 Personnel who are designated to operate hoisting and rigging equipment or perform work covered
by this standard shall be qualified and trained to the level of proficiency consistent with assigned
tasks.
6.2 QUALIFICATION
6.2.1 General
6.2.1.1 Only qualified personnel or trainees, under the direct supervision of qualified personnel, who meet
the following requirements shall be allowed to rig, operate, inspect, or perform maintenance on
cranes, hoists, or powered forklift trucks:
6.2.1.3 Understand spoken and written English or a language generally in use at the work location.
6.2.2.2 Class and type divisions for OJEs shall be consistent with OSHA and industry standards.
6.2.3.1 The employer will make OJT available for hoisting and rigging equipment operators. If an
operator will use attachments, the OJT will include use and installation of approved attachments
(Example: crane jibs and boom extensions.).
6.2.3.2 Personnel must satisfy prerequisites and physical requirements for the type of equipment to be
operated before being allowed to participate in an OJT program (see paragraph 6.2.3 - 6.2.9).
The OJT program shall be based on the equipment manufacturers operating instructions, typical
tasks, operating environment, and facility or the base operating contractors specific procedures.
The OJT program shall provide training and practice under the direct supervision of a qualified
operator or qualified OJT instructor in the work environment. Complexity of equipment and
tasks, along with the operators experience shall determine the need for OJT.
6.2.3.3 Trainee qualification requirements shall include, but are not limited to the following:
6.2.3.3.1 Satisfactory completion of an on-the-job training program. Previous training may be accepted to
meet training requirements. Previous training may include any of the following:
Certificates of training.
Journeyman card or documents issued by a trade union.
A degree or accreditation from a college or trade school.
6.2.3.4 The employer may allow previously qualified or experienced personnel to bypass the OJT and
undergo an On the Job Evaluation (OJE). The supervisor shall evaluate and validate training.
When previous training and experience are accepted, personnel shall be considered qualified
when they have accomplished the following:
6.2.3.4.1 For mobile or cab operated overhead cranes, they have at least one year of experience on the
same type crane, or 3 years of combined experience on similar or like cranes, or have successfully
completed a mentoring program and have passed an operators test.
6.2.3.4.2 Satisfactory completion of a written examination covering safety, operational characteristics and
limitations, and controls of the type crane for which they are being qualified.
6.2.3.4.3 Demonstrate their ability to read, write, comprehend, and exhibit arithmetic skills and
load/capacity chart usage, in the language of the crane manufacturers operations and
maintenance instruction materials.
6.2.3.4.4 Satisfactory completion of a written and verbal test on load/capacity chart usage covering
various crane configurations.
6.2.3.4.5 Satisfactory completion of a practical operating skill evaluation test (OJE), demonstrating
proficiency, and basic knowledge in handling the specific type crane for which the operator is
being evaluated, including:
6.2.4.1 Operators and operator trainees shall meet the following physical qualifications.
6.2.4.1.1 Have vision of at least 20/30 Snellen in one (1) eye, and 20/50 in the other, with or without
corrective lenses.
6.2.4.1.2 Be able to distinguish colors, regardless of position, if color differentiation is required for
operation.
6.2.4.1.3 Have adequate hearing, with or without a hearing aid, for specific operation.
6.2.4.1.4 Have the physical strength, coordination, and sufficient reaction speed to meet the demands of
equipment operation.
6.2.4.1.5 Show no evidence of physical defects or emotional instability that could be a hazard to
themselves or others, or which, in the opinion of the examiner, could interfere with safe
performance; such evidence may be sufficient cause for disqualification. In these cases, medical
judgments and tests may be required.
6.2.4.1.6 Show no evidence of being subject to seizures or to loss of physical control; such evidence shall
be sufficient reason for disqualification. Medical examinations may be required to determine
these conditions.
6.2.4.1.7 Have normal depth perception, field of vision, manual dexterity, coordination, and no tendencies
to dizziness or similar potentially hazardous characteristics.
6.2.4.1.8 Have no detectable or known disease or physical restriction that would render them incapable of
safely operating equipment or carrying out rigging duties. Where any deficiency of an upper or
lower extremity exists, the acceptability of a candidate shall be the decision of the supervisor,
after consulting with the designated physician.
6.2.4.2 Operators shall be required by the employer to pass a practical operating skill evaluation (OJE).
Qualification shall be limited to the type of equipment for which the operator is being evaluated.
The actual or simulated operation shall enable trainees to demonstrate basic knowledge and skills
at a level that ensures the safety of personnel and equipment.
6.2.5.1 Operators and operator trainees shall meet the following physical qualifications:
6.2.5.1.1 Have vision of at least 20/30 Snellen in one (1) eye and 20/50 in the other, with or without
corrective lenses.
6.2.5.1.2 Be able to distinguish colors, regardless of position, if color differentiation is required for
operation.
6.2.5.1.2 Have adequate hearing, with or without a hearing aid, for a specific operation.
6.2.5.1.4 Have physical strength, coordination, and sufficient reaction speed to meet the demands of
equipment operation.
6.2.5.1.4 Show no evidence of physical defects or of emotional instability that could be a hazard to
themselves or others, or which, in the opinion of the examiner, could interfere with their safe
performance; such evidence may be sufficient cause for disqualification. In these cases, medical
judgments and tests may be required.
6.2.5.1.5 Show no evidence of being subject to seizures or to loss of physical control; such evidence shall
be sufficient reason for disqualification. Medical examinations may be required to determine
these conditions.
6.2.5.1.6 Have normal depth perception, field of vision, manual dexterity, coordination, and no tendencies
to dizziness or similar potentially hazardous characteristics.
6.2.5.1.7 Have no detectable or known disease or physical restriction that would render them incapable of
safely operating equipment or carrying out rigging duties. Where any deficiency of an upper or
lower extremity exists, the acceptability of a candidate shall be the decision of the supervisor,
after consulting with the designated physician.
6.2.5.1.8 Operator physical examinations shall be required every three years or more frequently if
supervision deems it necessary.
6.2.5.2 Operators shall be required to pass a written examination covering characteristic and performance
questions appropriated to the crane type for which qualifications is sought as well as operational
characteristics, controls, and emergency control skills such as response to:
6.2.5.2.1 Fire.
6.2.5.3 Operators shall pass a combination written and verbal test on load/chart usage that covers a
selection of the configurations (the crane may be equipped to handle) for the type crane for which
qualification is being sought.
6.2.5.4 The operator shall complete a practical operating skill evaluation test (OJE), demonstrating
proficiency and basic knowledge in handling the specific type crane for which the operator is
being evaluated, including:
6.2.5.4.3 Shutdown.
6.2.5.5 Qualification shall be limited to the type of equipment for which the operator is being evaluated.
6.2.6.2 Operators of cranes shall be required to pass both the classroom training and operating skill
evaluation (OJE). Operators of hoist are only required pass the classroom training, no OJE is
required. Qualification shall be limited to the type of equipment for which the operator is being
evaluated.
6.2.6.3 The actual or simulated operation shall enable operators to demonstrate basic knowledge and
skills at a level that ensures the safety of personnel and equipment.
6.2.7.1 The use of remote-controlled equipment involves such a wide variety of service requirements and
conditions that each installation should be carefully analyzed and operation reviewed to
determine whether paragraphs 6.2.3 or 6.2.6 should apply.
6.2.7.2 Operators shall be required by the employer to pass a written examination covering operational
characteristics, controls, and emergency control skills.
6.2.7.3 Operators shall be required by their employer to pass a practical operating skill evaluation (OJE).
Qualification shall be limited to the type of equipment for which the operator is being evaluated.
6.2.7.4 The actual or simulated operation shall enable operators to demonstrate basic knowledge and
skills at a level that ensures the safety of personnel and equipment.
6.2.8.2 Operators shall be required to pass a practical operating skill evaluation (OJE). Qualification shall
be limited to the type of forklift for which the operator is being evaluated.
6.2.8.3 The actual or simulated operation shall enable operators to demonstrate basic knowledge and
skills at a level that ensures the safety of personnel and equipment.
6.2.9 Riggers
6.2.9.1 The employer shall ensure that personnel assigned to perform rigging tasks meet the definition of
a qualified person for the specific tasks assigned.
6.2.9.2 The employer shall document the methods used to establish rigging qualifications
6.2.9.3 There shall be a means to verify rigging qualifications for each employee assigned to perform
rigging tasks.
6.2.10.1 The PIC shall have the necessary knowledge and experience of the specific type of equipment
and completion of the operation. The PIC shall understand the rules and procedures implemented
at the site to ensure that the following are completed:
6.2.11.1 The Designated Leader must meets the criteria for both a competent person and a qualified
person, or be a qualified person supervised by a competent person during the lifting operation
(ref. 1926.1432(b)(1)). The Designated Leader shall have sufficient knowledge and experience to
accomplish the following responsibilities (ref. ANSI/ASME B30.5, 5-3.1.3 and B30.23, 23-
3.1.1):
6.2.11.1.1 Ensure that personnel involved understand how the lift is to be made.
6.2.11.1.2 Ensure that the weight of the load is determined and that proper equipment and accessories are
selected.
6.2.11.1.3 Survey the lift site for hazardous or unsafe conditions.
6.2.11.1.4 Ensure that equipment is properly set up and positioned.
6.2.11.1.5 Ensure that a Qualified Signal Person is assigned, if required, and is identified to the operator.
6.2.11.1.6 Direct the lifting operation to ensure that the job is done safely and efficiently.
6.2.11.1.7 Stop the job when any potentially unsafe condition is recognized.
6.2.11.1.8 Direct operations if an accident or injury occurs.
6.2.11.1.9 Allow crane operation near electric power lines only when:
The requirements of Chapter 2 and paragraph 9.6 have been satisfied.
A qualified dedicated spotter is assigned, if required, and is identified to the operator.
6.2.11.1.10 Ensure precautions are implemented when hazards associated with critical lifts or other
special lifting operations are present.
6.2.11.1.11 Ensure that the applicable requirements of Chapter 4 are met when lifting personnel.
6.2.11.1.12 Ensure that a cranes load rigging is performed by a qualified rigger(s).
6.2.11.1.13 Ensure that the load is properly rigged and balanced before it is lifted more than a few inches.
6.2.12 Inspectors
6.2.12.1 Qualified inspectors shall have the necessary knowledge and experience to inspect hoisting and
rigging equipment.
6.2.12.2 Employees who operate cranes to perform crane inspections shall be trained and qualified to
operate the crane on which the inspection is being performed. See general and crane specific
qualification requirements in paragraph 6.2, Qualification.
6.2.11.3 Crane operation by crane inspectors shall be limited to those crane functions necessary to
perform the inspection on the crane.
6.2.13 Instructors
Instructors responsible for developing or presenting hoisting and rigging training programs shall
meet the qualification standards specified by a qualified third-party training source or a qualified
person following the employers train-the-trainer process.
On the Job Performance Evaluators (OJPE) are responsible for conducting On The Job
Evaluations (OJE) of hoisting and rigging equipment operators. These persons may serve as an
instructor if they meet the qualification standards specified in paragraph 6.2.13.
The first-line supervisor of hoisting and rigging operations should be knowledgeable of the
specific types of hoisting and rigging operations under their supervision and their operational
hazards. The supervisor shall be familiar with applicable rules and procedures implemented at
the site to ensure that hoisting and rigging work under their control is done efficiently and safely,
with safety as top priority. Supervisors should ensure that employees fully understand the
importance of safety and that they recognize their own authority and responsibility to stop work
when safety is questionable.
6.2.16.1 Employees who operate cranes to perform crane maintenance shall be trained and qualified to
operate the cranes on which maintenance is being performed.
6.2.16.2 Crane operation by maintenance personnel shall be limited to those crane functions necessary to
perform maintenance on the crane or to verify the performance of the crane after maintenance has
been performed.
6.2.16.3 Employees who perform maintenance activities on equipment covered by this standard should
have an understanding of the following criteria:
6.2.16.3.4 Manufacturers recommendations as to points and frequency of lubrication and levels and types
of lubricant to be used.
6.2.17.1 Employees assigned to the duties of Signal Person for crane operations shall be trained and
qualified to perform the duties prior to giving any signals.
6.2.17.2.2 Demonstrate competence in the application of the type of signals used through a practical
evaluation.
6.2.18.1 The asset owner of hoisting and rigging operations shall be knowledgeable of the specific types
of hoisting and rigging operations under their supervision and the associated hazards.
6.2.18.1.1 The Asset Owner shall be familiar with applicable rules and procedures implemented at the site
to ensure that hoisting and rigging work under their control is done safely.
6.2.18.1.2 Asset Owners shall be qualified for the following responsibilities:
Ensuring that the crane and equipment meets the inspection and maintenance requirements of this
handbook prior to initial site usage.
Determining if additional regulations are applicable to crane operations.
Ensuring that a qualified person is assigned as the Designated Leader.
Ensuring that crane operations are coordinated with other jobsite activities that will be affected by or
will affect lift operations.
Ensuring that the area for the crane is adequately prepared. The preparation includes, but is not limited
to, the following:
o Access roads for the crane and associated equipment
o Sufficient room to assemble and disassemble the crane
o An operating area that is suitable for the crane with respect to levelness, surface conditions,
support capability, proximity to power lines, excavations, slopes, underground utilities, subsurface
construction, and obstructions to crane operation
o Traffic control as necessary to restrict unauthorized access to the cranes working area
Ensuring that work involving the assembly and disassembly of a crane is supervised by a qualified
person.
Ensuring that crane operators meet the requirements of para. 5-3.1.2.
Ensuring that conditions that may adversely affect crane operations are addressed. Such conditions
include, but are not limited to, the following:
o Poor soil conditions
o Wind velocity or gusting winds
o Heavy rain
o Fog
o Extreme cold
o Artificial lighting
Permitting critical lifts only when equipment and procedures required by Chapters 2 and 4, the crane
manufacturer, or a qualified person are employed. multiple crane lifts
Ensure lifting of personnel meets the requirements of Chapter 4.
Allowing crane operation near electric power lines only when the requirements of paragraph 9.6 have
been met.
Ensuring that work performed by the rigging crew is supervised by an appropriately qualified person.
Ensuring that crane maintenance is performed by qualified crane maintenance personnel.
6.3 TRAINING
6.3.1 General
6.3.1.1 Organizations that employ personnel who operate, rig, inspect, or perform maintenance on
equipment covered in this standard shall provide training programs, including a means of
evaluation, to ensure that the personnel are competent to perform the operations. This training
shall also include applicable site-specific hoisting and rigging procedures, which address
abnormal or emergency operations as well as possible equipment failure.
6.3.1.2 Training shall utilize the methods best suited for the students and the subject material. This may
include, but is not limited to, computer-aided training, classroom training, simulated field
training, on-the-job training (OJT), and training by equipment manufacturer or commercial
training companies.
6.3.1.3 Score standards shall be set for each examination. The minimum passing score will depend on the
subject, testing technique, and test difficulty. Management shall determine the course of action
for persons receiving negative evaluations.
6.3.2.1 Only qualified and authorized operators or operator trainees under the direct supervision of a
qualified operator shall be permitted to operate cab-operated and floor-operated cranes.
6.3.2.2.1 Applicant training on equipment for which qualification is sought, under the direction of a
qualified operator or instructor who is designated by management to instruct in the operation of
hoisting equipment.
6.3.2.2.2 Instructors review of the applicants knowledge includes results of written and oral evaluation,
and witnessing a demonstration of the operators skills.
6.3.2.3.7 Inspections/tests.
6.3.2.3.10 Rigging.
6.3.2.3.19 Two-blocking.
6.3.3.1 Only qualified and authorized operators or operator trainees under the direct supervision of a
qualified operator shall be permitted to operate mobile cranes.
6.3.3.2 In addition to the listed basic factors from paragraph 6.3.2.3, the following factors need to be
taken into consideration by mobile crane operators:
6.3.3.2.1 Stability.
6.3.3.2.4 Refueling.
6.3.3.2.7 Outriggers.
6.3.4.1 Only authorized operators or operator trainees under the direct supervision of an authorized
operator shall be permitted to operate truck mounted cranes capacity 1 ton or less.
6.3.4.2 There is no formal training program for these type cranes. All training is provided under direct
supervision of an authorized operator and through manufacturers operation manuals.
6.3.4.3 Operators should be able to demonstrate knowledge of the equipment operating characteristics,
capabilities, limitations, effects of variables, safety features, and operating procedures.
6.3.5.1 Only qualified and authorized operators shall be permitted to operate powered forklift trucks.
Operator trainees may operate powered forklift trucks under the direct supervision of a qualified
operator or trainer and only where such operation does not endanger the trainee or other
employees.
6.3.5.2.1 A combination of formal instruction (e.g., lecture, discussion, interactive computer learning,
videotape, written material).
6.3.5.2.2 Practical training (demonstrations performed by the trainer and practical exercises performed by
the trainee).
6.3.5.2.3 Evaluation of the operators performance in the workplace including results of written and oral
evaluation, and witnessing a demonstration of the operators skills.
6.3.5.3 The following checklist contains basic factors with which a forklift truck operator should be
familiar. This checklist must be tailored to suit actual conditions.
6.3.5.3.1 Operating instruction, warnings, and precautions for the type of forklift truck the operator will
be authorized to operate.
6.3.5.3.10 Forklift truck inspections and maintenance that the operator will be required to perform.
6.3.5.3.13 Any other operating instructions, warning, or precautions listed in the operators manual for the
type of forklift truck that the employee is being trained to operate.
6.3.5.3.21 Modifications.
6.3.5.4 The following checklist contains basic factors with which a forklift operator should be familiar as
they relate to workplace topics.
6.3.5.4.5 Narrow aisles and other restricted places where the forklift will be operated.
6.3.5.4.7 Ramps and other sloped surfaces that could affect the forklifts stability.
6.3.5.4.8 Closed environments and other areas where insufficient ventilation or poor vehicle maintenance
could cause a buildup of engine exhaust (gasoline or diesel).
6.3.5.4.9 Other unique or potentially hazardous environmental conditions in the workplace that could
affect safe operation.
6.3.5.5 Refresher training in relevant topics shall be provided to the operator when:
6.3.5.5.1 The operator has been observed to operate the forklift truck in an unsafe manner.
6.3.5.5.3 The operator has received an evaluation that reveals that the operator is not operating the forklift
truck safely.
6.3.5.5.5 A condition in the workplace changes in a manner that could affect the safe operation of the
forklift truck.
6.3.6 Riggers
6.3.6.1 Training programs for riggers should address two levels of required performance:
6.3.6.1.1 Persons who perform rigging functions as an incidental part of their normal work assignment
6.3.6.2 Only qualified and authorized persons or trainees in OJT status and under the direct supervision of
a qualified person shall be permitted to perform rigging functions.
6.3.6.3 Training of personnel performing rigging tasks shall include the applicable portions of Chapters
11 thru 14 of this handbook and safe rigging practices. Classroom training shall be presented by a
Hoisting and Rigging Instructor. OJT trainers shall be assigned by the trainees supervisor or
management according to the employers policies.
6.3.7.1 Employees who perform required, documented inspections of equipment covered by this standard
shall receive inspector training.
6.3.7.2 Inspector training shall include basic inspection techniques and acceptance/rejection criteria as
specified in this standard and other applicable sources.
6.3.7.3 The following equipment categories for general inspection are examples that should be
considered:
6.3.7.4 Employees who perform crane inspections do not have to be a fully qualified crane operator to
operate the crane for inspection purposes; however, they must be trained on the operation of the
crane. These crane inspectors will be given a crane inspector sticker to show proof of training.
6.3.8.1 Instructors designated by management to be responsible for developing or presenting hoisting and
rigging training programs shall develop technical competence by becoming familiar with the
6.3.8.2 Instructors should attend recognized training courses, workshops, or seminars in order to remain
current on industry practices and changes in applicable codes and standards.
6.3.9.1 OJPE Evaluators shall be designated by management and shall be fully qualified to operate the
piece of hoisting and rigging equipment for which they are performing the OJE on.
6.3.9.2 OJPE Evaluators shall evaluate each operator and certify in writing that the operator has
demonstrated to them that they have the necessary knowledge and skills to operate the equipment
safely before deeming the operator qualified.
Employees who operate cranes to perform crane maintenance shall be trained and qualified to
operate the cranes on which maintenance is being performed.
6.3.11.1.3 Non-standard hand signals. When they are is allowed and provisions for using them.
6.3.11.1.6 Equipment operation and limitations including the crane dynamics involved in swinging and
stopping loads and boom deflection from hoisting loads.
6.3.11.2 Signal person shall demonstrate knowledge and understanding through an oral or written test.
And be designated as qualified per paragraph 6.2.17 above.
6.4 REQUALIFICATION
6.4.1 Mobile Crane Operators shall re-qualify at least every 5 years in accordance with OSHA 29 CFR
1926 Subpart CC.
6.4.2 Overhead Crane operator shall re-qualify in accordance with employers requirements or every 5
years.
6.4.3 Forklift Operators shall re-qualify at least every 3 years in accordance with OSHA 29 CFR 1910.
178.
6.5 RECORDS
A record of training and skill evaluations shall be kept on file and shall be readily available.
This chapter specifies operation, inspection, maintenance, and testing requirements for the use of
overhead and gantry cranes and implements the requirements of ASME B30.2, B30.11, and
B30.17. Only equipment built to the appropriate design standards shall be used at AEDC.
7.1 GENERAL
This chapter applies to overhead and gantry cranes, including semi-gantry, cantilever gantry, wall
cranes, storage bridge cranes, and others having the same fundamental characteristics. Overhead
and gantry cranes include top-running single- or multiple-girder bridge with top-running trolley
hoists (Figure 7-1), top-running single-girder bridge with underhung trolley hoists (Figure 7-2),
and monorails/underhung cranes (Figure 7-3). Hoist units and trolleys are most commonly
electric powered, but can be air powered or hand chain operated. These cranes may be cab
operated, pulpit operated, floor operated, or remotely operated. Such cranes are grouped together
because all have trolleys and similar travel characteristics and are governed by OSHA 29 CFR
Figure 7-1. Top-running single- or multiple-girder bridge with top-running trolley hoist
Anyone accessing the structure of an overhead cab or pulpit operated crane, this includes
operators, inspectors, electricians, etc., shall wear a full body harness and carry a lanyard or self-
retracting lifeline. This is done for several reasons: If an emergency arises and self-rescue
becomes necessary, the employee will have the necessary equipment on; if rescue becomes
necessary because of incapacitation of the employee the fire departments rescue team will not
have to spend precious time trying to fit the employee with a harness; and should it become
necessary to walk on the gantry or bridge or work from an area not protected by guardrails, fall
protection equipment will be available.
7.1.2.1 Operators of overhead cranes shall be trained and qualified as required in Chapter 6.
7.1.2.2.3 Maintenance, inspection, and test personnel, when it is necessary in the performance of their
duties.
7.1.2.3 No one other than personnel specified above shall enter a crane cab or pulpit, with the exception
of persons such as oilers and supervisors, whose duties require them to do so, and then only with
the knowledge of the crane operator.
The rated capacity shall be marked on each side of the cranes bridge. If the crane has more than
one hoisting unit, each hoist shall have its rated capacity marked on it or on its load block.
Markings on the bridge, trolley, and load block shall be legible from the ground or floor. Load
blocks should be painted to contrast with the bridge and trolley to facilitate quick visual
identification.
7.1.4 Modification
Cranes may be modified or rerated if the modifications or supporting structures are analyzed
thoroughly by a qualified engineer or by a manufacturer of cranes. Modifications and reratings
must be approved by the base operating contractors safety office. A rerated crane, or one whose
load-supporting components have been modified, shall be tested in accordance with paragraph
7.3.2 Rated Load Tests . The new rated capacity shall be displayed in accordance with paragraph
7.1.3.
7.1.5 Egress
On cab-operated cranes, there shall be a means of egress to permit departure under emergency
conditions.
7.1.6 Brakes
7.1.6.1 Each independent hoisting unit shall be equipped with at least one holding brake applied directly
to the motor shaft or some part of the gear train.
7.1.6.2 Each independent hoisting unit greater than 1 ton (except worm-geared hoists, the angle of whose
worm prevents the load from accelerating as it is being lowered) shall be equipped with a
controlled-braking means in addition to the holding brake to control speed of lowering.
7.1.6.3 Holding brakes on hoists shall be applied automatically when power is removed.
7.1.6.4 A hand-operated hoist shall be so designed that when the actuating force is removed, it will
automatically stop and hold a test load up to 125% of the rated load
7.1.6.5 Brakes shall be provided with a means for adjustment to compensate for wear. The wearing
surface of all brake drums or discs shall be smooth.
7.1.6.6 Any combination of service, emergency, and parking functions may be provided by a single
friction brake if it can be applied without having power available.
7.1.6.7 If holding brakes are provided on the bridge or trolleys, they shall not prohibit the use of a drift
point in the control circuit.
7.1.6.8 Foot brake pedals shall be cleaned and properly maintained so that the operators foot will not
easily slip off the pedal.
7.1.7.1 The power supply to the runway conductors shall be controlled by a switch or circuit breaker
located on a fixed structure. The switch shall be easily accessible and visible from the floor and
capable of being locked in the OPEN position.
7.1.7.2 On cab-operated cranes, an enclosed switch or circuit breaker (with provisions for locking in the
OPEN position) shall be provided in the leads from the runway conductors. A means of opening
this device shall be located within reach of the operator when the operator is in the operating
position. When the operator opens this switch or circuit breaker, the holding brakes shall set.
7.1.7.3 On floor, remote, or pulpit-operated cranes, an enclosed disconnect device shall be provided in the
leads from the runway conductors. This device shall be mounted on the bridge or footwalk near
the runway collectors. There shall be provisions for locking the device in the OPEN position
unless the crane is the only load on a lockable switch or circuit breaker that is accessible from the
floor. One of the following types of floor, remote, and pulpit-operated disconnects shall be
provided.
7.1.7.3.1 A nonconductive rope attached to the main disconnect device on a floor-operated crane. If this
is selected, the rope shall be suspended adjacent to the operating ropes if manual controllers are
used or near the pendant push-button station if magnetic controls are used.
7.1.7.3.2 An under-voltage trip for a main circuit breaker, operated by an emergency stop button in the
pendant push-button station or the pulpit.
7.1.7.3.3 A main-line contactor operated by a switch or push button on the pendant push-button station,
the remote-control station, or the pulpit.
7.1.8.1 The hoisting motion of all cranes shall have an overtravel-limit switch/ device in the hoisting
direction to stop the hoisting motion.
7.1.8.2 Lower-travel limit switches/devices should be provided for all power-driven hoists where the load
block enters pits or hatchways in the floor.
7.1.9.1 No crane shall be loaded beyond its rated load except for test purposes as provided in paragraph
7.3.2 below.
7.1.9.2 Provisions for special overrated load lifts (also called planned engineered lifts) are outlined in
ASME B30 standards. However, no such lift shall be made without the authorization of the
AEDC Crane System Engineer. This authorization will only be granted after the AEDC
Structural Engineer has reviewed the design of the crane-supporting structure, has inspected the
structure as required by ASME B 30 standards and has approved its use for the intended lift.
7.1.10.1 Wiring and equipment shall comply with the National Electrical Code, NFPA 70, Article 610,
Cranes and Hoists.
7.1.10.2 Lever-operated controllers shall be provided with a notch or latch that in the off position
prevents the handle from being inadvertently moved to the on position. An off detent or
spring return arrangement is acceptable.
7.1.10.3 For floor operated cranes, the control or controls, if rope operated, shall automatically return to
the off position when released by the operator.
7.1.10.4 Cranes not equipped with spring-return controllers, spring-return master switches, or momentary-
contact pushbuttons shall be provided with a device that will disconnect all motors from the line
in the event of a power failure. This disconnect device shall not permit any motor to be restarted
until the control or master switch handle is brought to the off position, or a reset switch or
power-on button is operated.
7.1.105. As far as practicable, the movement of each control handle shall be in the same general direction
as the resultant movements of the load.
7.1.10.6 Remotely operated cranes shall function so that if the control signal for any motion becomes
ineffective, that motion shall stop. In addition, signals received from any source other than the
operating station (transmitter) shall not result in operation of any motion.
7.1.10.7 The control circuit voltage shall not exceed 600 volts alternating current (AC) or direct current
(DC). The voltage at pendant push buttons shall not exceed 150 volts AC and 300 volts DC.
7.1.10.8.1 A pendant push-button station shall be supported so that the electrical conductors are protected
from strain.
7.1.10.8.2 Makeshift field-fabricated pendants shall not be used. Pendant control boxes shall be
constructed to prevent electrical shock.
7.1.10.8.3 Push buttons (except on/off buttons) shall spring-return to the off position when the operator
releases pressure. Buttons shall be clearly marked to identify their function. To minimize
operator fatigue, return-spring force shall be the minimum necessary for positive return.
7.1.10.8.4 To the extent possible, each crane control shall be marked to indicate the direction of resultant
motion.
7.1.10.9 Unless the crane is the only load on a lockable switch or circuit breaker accessible from the floor,
a lockable switch, or enclosed type circuit breaker in the leads from the runway conductors shall
be mounted on the bridge or footwalk near the runway collectors. In either the floor or
bridge/footwalk mount, a means to open the switch with a magnetic contactor controlled from the
operator's station shall be provided. This provides for emergency shutdown of all power to the
crane.
7.1.10.10 Open-type runway conductors mounted on the crane runway beams or overhead shall be
positioned or fitted with guards so that persons cannot inadvertently come into contact with them.
Securely fastened guards shall be provided to prevent contact between bridge conductors and
hoist ropes if hoist ropes could come into contact with conductors.
7.1.10.11 A crane using a lifting magnet shall have a magnet circuit switch (enclosed type) with provision
for locking in the open position. Means for discharging the inductive load of the magnet shall be
provided.
7.1.10.12 If a service receptacle is provided in the cab or on the bridge, it shall be a grounded three-prong
permanent receptacle not exceeding 300 volts.
7.1.11.1 Except for floor-operated cranes, a gong, bell, horn, flashing light, or other effective warning
device shall be provided for each crane with a power traveling mechanism. A warning device is
recommended for floor-operated cranes with a power traveling mechanism.
7.1.11.2 A warning light visible from the operating floor, crane bridge, and runways should be provided.
The warning light, if provided, shall be activated at all times when the runway conductors are
energized.
7.1.11.3 For outdoor, overhead, and gantry crane operations with a top-running trolley, a wind-indicating
device shall be provided. The device shall give a visible and audible alarm to the crane operator
at a predetermined wind velocity.
7.1.12.1 The crane maintenance file is a compilation of various documents and records relating to
operation, maintenance, inspection, testing, evaluating, and repair of the equipment.
7.1.12.2 The master file shall be located in the AEDC crane library. A secondary file may be centrally
located or proportioned into satellite holding areas.
7.1.12.3 The maintenance history of the crane shall be retained throughout its service life. Maintenance
records shall be retained in the crane history file, or an electronic record keeping system may be
used. If a computer system is used, and maintenance records are not retained in the crane history
file, the crane history file shall state where the electronic maintenance records are available.
7.1.12.4 The most recent copy of dated records that document maintenance of critical items such as
hoisting machinery, sheaves, hooks, chains, ropes, and other lifting devices shall be retained in a
maintenance file.
7.1.12.5 The intent of the crane maintenance files are to provide the user with evidence of a safe and
reliable maintenance program. Inspection records should be retained in a format and location that
provides for ease in accessibility. Maintenance file information should provide a source for
comparing present conditions with past conditions to determine whether existing conditions show
a trending pattern of wear, deterioration, or other comparable factors that may compromise safe,
continued use of the equipment
7.1.12.6 Crane maintenance files shall contain the following documentation, as applicable:
7.2 INSPECTIONS
7.2.1 General
There shall be no apparent damage, excessive wear, or deformation of any load-bearing part of
the equipment. Brakes shall work satisfactorily and load brakes shall be designed to hold any
load up to at least 125% of the rated capacity of the equipment without slipping or overheating.
All safety devices, load indicators, controls, and other operating parts of the equipment shall be
checked during each inspection and shall be in good working order. Parts found to be defective
during inspection or nondestructive examination shall be replaced or repaired.
7.2.2.1 Normal service operating at less than 85% of rated load and not more than 10 lift cycles/hr
except for isolated instances.
7.2.2.2 Heavy service operating at 85 to 100% of rated load or in excess of 10 lift cycles/hr as a regular
specified procedure.
7.2.2.3 Severe service operating at normal or heavy service under abnormal operating conditions (i.e.,
extreme temperatures, corrosive atmospheres).
Prior to their initial use, all new, reinstalled, modified, or repaired cranes shall be inspected by a
qualified inspector to ensure compliance with applicable provisions of this chapter. Inspections
of repaired and modified cranes may be limited to the provisions affected by the alteration, repair,
or modification as determined by a qualified person. Dated and signed inspection reports shall be
kept on file and shall be readily available.
7.2.4.1 Operators or other designated personnel shall visually inspect at a minimum the following items
each day or prior to first use if the hoist has not been in regular service (records are not required):
7.2.4.1.1 All functional operating mechanisms for maladjustment interfering with proper operation.
7.2.4.1.2 Deterioration or leakage in lines, tanks, valves, drain pumps, and other parts of air or hydraulic
systems.
7.2.4.1.3 Hooks for cracks, deformation, latch engagement (if provided), and damage from chemicals (see
Chapter 13).
7.2.4.1.4 Hoist rope for significant wear, kinking, crushing, bird caging, corrosion, or broken strands or
wires.
7.2.4.1.5 Hoist chains, including end connections, for excessive wear, twist, distorted links interfering
with proper function, or stretch beyond manufacturers recommendations.
7.2.4.2 Operators or other designated personnel shall examine deficiencies and determine whether the
equipment should be removed from service or if a more detailed inspection is required.
7.2.5.1 On a monthly basis, the operator or other designated person shall thoroughly inspect the following
items for damage, wear, or other deficiencies that might reduce capacity or adversely affect the
safety of the crane:
7.2.5.1.1 This shall be accomplished by lowering the hook block to its lowest position and examining for
any condition that could result in an appreciable loss of strength.
7.2.5.1.2 Hoist rope, including end connections, for significant wear, kinking, crushing, bird caging,
corrosion, broken strands or wires.
7.2.5.1.3 Hoist chains, including end connections, for excessive wear, twist, distorted links interfering
with proper function, or stretch beyond manufacturers recommendations.
7.2.5.1.4 Hooks for cracks, deformation, damage from chemicals, and evidence of heat damage. The hook
attachment and securing means should also be checked. (See Chapter 13).
7.2.5.1.5 Signed and dated inspections records shall be kept on file in accordance with 7.1.12.6.
7.2.5.2 Before the crane is returned to service, deficiencies that could reduce its capacity or adversely
affect its safety shall be corrected.
7.2.6.1 Designated personnel shall visually inspect the crane at the following intervals (records are
required):
7.2.6.2 In addition to the requirements of Section 7.2.4 these inspections shall include the following:
7.2.6.2.2 Rope or chain reeving for compliance with hoist manufacturers recommendations.
7.2.6.2.3 Operating mechanisms for proper operations, proper adjustment, unusual sounds, or excessive
wear.
7.2.6.2.5 Rope for proper spooling onto the drums and sheaves.
7.2.6.3 Operators or other designated personnel shall examine deficiencies and determine whether the
equipment should be removed from service or if a more detailed inspection is required.
7.2.6.4 Dated and signed inspection records shall be kept on file in accordance with paragraph 7.1.12.6.
7.2.7.1 General
7.2.7.1.1 A qualified inspector shall perform a complete inspection at the following intervals:
7.2.7.1.2 The qualified inspector shall examine deficiencies and determine whether they constitute a
safety hazard and whether the crane should be removed from service until it is repaired.
7.2.7.1.3 Dated and signed inspection records shall be kept on file in accordance with 7.1.12.6.
7.2.7.2 Cranes - In addition to the requirements of Section 7.2.6, periodic inspections shall include the
following:
7.2.7.2.2 Bolts, rivets, nuts, and pins for being loose or absent.
7.2.7.2.5 Parts such as pins, bearings, shafts, gears, rollers, locking and clamping devices, bumpers, and
stops for wear, cracks, or distortion.
7.2.7.2.6 Brake system parts, linings, pawls, and latches for excessive wear.
7.2.7.2.7 Load, wind, and other indicators over their full range for any significant inaccuracies.
7.2.7.2.8 Gasoline, diesel, electric, or other power plants for improper performance or noncompliance
with other applicable standards.
7.2.7.2.9 Chain-drive sprockets for excessive wear and chains for excessive stretch.
7.2.7.2.10 Electrical apparatus for signs of pitting or any deterioration of controllers, master switches,
contacts, limit switches, and push-button stations (not limited to these items).
7.2.7.2.11 Hooks with damage from chemicals, deformation, cracks; having more than 5% in excess of
normal throat opening, not to exceed inch; or any visibly apparent bend or twist from the plane
of the unbent hook (see Chapter 13).
7.2.7.2.12 Hook retaining nuts or collars and pins, welds, or riveting used to secure the retaining members
for soundness.
7.2.7.2.13 Nondestructive examination of hooks, welds, bearings, or other suspect load-bearing parts
when required by the inspector.
7.2.7.2.14 Testing of motion limit devices, which interrupt power or cause a warning to be activated, for
proper performance (each motion shall be inched or operated at low speed into the limit device
with not load on the crane).
7.2.7.2.15 All function, instruction, caution, and warning labels or plates for legibility.
7.2.7.2.16 Deterioration of controllers, master switches, contacts, limit switches, and push-button stations,
but not limited to these items
7.2.7.3.1 A qualified inspector shall inspect all ropes at least annually. This inspection shall include
examination of the entire length of the rope, without detaching it from the hoist drum. More
frequent intervals shall be determined by a qualified person, based on such factors as expected
rope life as determined by experience on the particular installation or similar installations,
severity of environment, percentage of capacity lifts, frequency rates of operation, and exposure
to shock loads. The qualified inspector shall carefully note any deterioration such as described
below resulting in appreciable loss of original strength and determine whether further use of the
rope constitutes an acceptable risk.
7.2.7.3.1.4 Sections of rope that are normally hidden during inspection or maintenance procedures, such
as parts passing over sheaves (these are points most subject to deterioration).
7.2.7.3.2 All rope on cranes that have been idle for 1 month or more, but less than 1 year, shall be
inspected before the crane is returned to service. This inspection conducted in accordance with
7.2.6.
7.2.7.3.3 No precise rules can be given for determining the exact time to replace rope because many
variables are involved. Safety in this respect depends largely on the use of good judgment by an
appointed person in evaluating remaining strength in a used rope, after allowance for
deterioration disclosed by inspection. Safety of rope operation depends on this remaining
strength.
7.2.7.3.4 Conditions such as the following shall be sufficient reason for questioning rope safety and
considering replacement:
7.2.7.3.4.1 In running ropes, 12 randomly distributed broken wires in one rope lay, or 4 broken wires in
one strand in one rope lay.
7.2.7.3.4.3 Kinking, crushing, bird caging, or any other damage resulting in distortion of the rope
structure.
7.2.7.3.5 Replacement rope and connections shall have a strength at least as great as the original rope and
connections furnished by the crane manufacturer. Any deviation from the original size, grade, or
construction shall be specified by a rope manufacturer, the crane manufacturer, or a qualified
person.
7.2.7.4.1 Operate the crane under load in raising and lowering directions, and observe the operation of the
chain and sprockets. The chain should feed smoothly into and away from the sprockets.
7.2.7.4.2 If the chain binds, jumps, or is noisy, first see that it is clean and properly lubricated. If the
trouble persists, inspect the chain and mating parts for wear, distortion, or other damage.
7.2.7.4.3 The chain should be cleaned before inspection. Examine visually for gouges, nicks, weld spatter,
corrosion, and distorted links. Slacken the chain and move adjacent links to one sire to inspect for
wear at contact points. If wear is observed or stretching is suspected, the chain should be
measured according to the hoist manufacturers instructions. If instructions are not available,
proceed as follows:
7.2.7.4.3.1 Select an unworn, unstretched length of the chain (e.g., at the slack end).
7.2.7.4.3.2 Suspend the chain vertically under tension and, using a caliper-type gauge, measure the
outside length of any convenient number of links approximately 12 in. (305 mm) to 14 in. (356
mm) overall.
7.2.7.4.3.3 Measure the same number of links in the used sections and calculate the percentage of increase
in length.
7.2.7.4.4 Conditions such as the following shall be sufficient reason for questioning safety and for
considering replacement:
7.2.7.4.4.1 If the used chain exceeds a crane manufacturers recommended length or, in the absence of
such a recommendation, the used chain is 1.5% longer than the unused chain for powered hoists
or is 2.5% longer than the unused chain for hand-operated chain, replace the chain.
7.2.7.4.4.2 The existence of gouges, nicks, corrosion, weld spatter, or distorted links.
7.2.7.4.5 Repairing the load chain by welding or any other means shall not be attempted by anyone other
than the chain manufacturer.
7.2.7.4.6 Replacement chain shall be the same size, grade, and construction as the original chain furnished
by the crane manufacturer unless otherwise recommended by the manufacturer due to working
conditions.
7.2.7.4.7 Load-chain links that pass over the load sprocket on edge (alternate to those that lie flat in the
pockets) should be installed with the welds away from the center of the sprocket. This precaution
is not required on idler sprockets, which change the direction but not the tension in the chain.
7.2.7.4.8 The chain shall be installed without any twist between the hoist and an anchored end on either
the loaded side or the slack side.
7.2.7.4.9 When a chain is replaced, disassemble and inspect the mating parts (sprockets, guides, and
stripper) for wear, and replace if necessary.
7.2.7.5.1 Test the crane under load in raising and lowering directions, observing the operation of the chain
and sprockets. If the chain binds, jumps, or is noisy; clean and properly lubricate it. If the trouble
persists, inspect the chain and mating parts for wear distortion, or damage.
7.2.7.5.2 If wear is observed or stretching is suspected, the chain shall be measured according to the crane
manufacturers instructions. If instructions are not available, proceed as follows:
7.2.7.5.2.1 Suspend the hoist in normal position and apply a light load of approximately 50 lb (23 kg).
7.2.7.5.2.2 Select a 12 in. (305 mm) section of chain that normally travels over the load sprocket.
7.2.7.5.2.3 Determine elongation by measuring with a caliper from the edge of one chain pin to the
corresponding edge of another pin. If elongation exceeds in. (6.3 mm) in 12 in. (305 mm)
compared to new or unstretched chain values, the chain shall be replaced.
7.2.7.5.2.4 Inspect for twist. Replace if the twist in any 5-ft (1.52 m) section exceeds 15.
7.2.7.5.2.5 Check for straightness in a plane perpendicular to the plane of the rollers. Replace if the chain
has a bow exceeding in. (6.3 mm) in any 5-ft (1.52 M) section.
7.2.7.5.2.6 Additional inspection shall be made by removing the chain from the crane and cleaning it
thoroughly. Deficiencies such as those listed below shall be carefully examined and a
determination shall be made as to whether they constitute a safety hazard:
7.2.7.5.2.6.2 Rollers that do not run freely with light finger pressure.
7.2.7.5.3 Roller chain shall be replaced if any of the conditions exist as stated in Sections 7.2.7.5.2.6.1
through 7.2.7.5.2.6.6.
7.2.7.5.4 Deficiencies as stated in Section 7.2.7.5.2.6.6 above are reason for questioning chain safety and
considering its replacement.
7.2.7.5.6 Replacement chain shall be the same size, grade, and construction as the original chain furnished
by the crane manufacturer unless otherwise recommended by the manufacturer due to working
conditions.
7.2.7.5.7 Roller chain, discarded or new, shall not be used for slings.
7.2.8.1 A crane that has been shut down, due to lack of need, shall be locked and tagged out of service.
The asset owner of the crane shall be responsible to initiate the work request to have the crane
inspected.
7.2.8.2 Cranes that have been idle for 1 month or more but less than 6 months, shall be inspected before
being placed in the service according to the requirements listed above in Section 7.2.6.
7.2.8.3 Cranes that have been idle for 6 months or longer shall be inspected before being placed in service
according to the requirements listed above in Section 7.2.7.
7.2.8.4 The determination supporting these alternate inspection frequencies and procedures shall be made
by a qualified person for each affected crane. Documentation supporting this determination shall
be kept readily available.
7.3 TESTING
7.3.1.1 Prior to initial use, all new, reinstalled, repaired, or modified cranes shall be tested by a designated
person to ensure compliance with this chapter, including the following functions:
7.3.1.2 The trip setting of hoist-limit devices shall be determined by tests with an empty hook traveling at
increasing speeds up to the maximum speed. The actuating mechanism of the upper-limit device
shall be located so that it will trip the device under all conditions and in sufficient time to prevent
contact of the hook or load block with any part of the trolley or crane.
7.3.2.1 Scheduled load-tests are not routinely required. Overhead and gantry cranes may be load-tested up
to 100% of rated capacity when or if specified in a critical lift procedure. For cranes that
frequently make critical lifts, responsible management may implement a periodic load-test
program. Such periodic load- tests shall not exceed the rated capacity. Responsible management
shall set the load-test frequency. (A 5-year frequency is recommended.)
7.3.2.2 At the discretion of the AEDC Crane System Engineer, a crane that has been out of service may
be load-tested before returning to service. Consider the following when determining whether a
load-test shall be required: (1) Will the crane make critical lifts? (2) What is the general condition
and age of the crane? (3) What is the previous load-test and maintenance history of the crane?
This load test shall be done only after a return-to-service inspection is completed and should not
exceed the rated capacity.
7.3.2.3 Prior to initial use, all new or reinstalled cranes and cranes in which the load sustaining parts have
been altered, modified, repaired, or replaced, or whose rated capacities have been affected shall
be tested by or under the direction of a qualified inspector. Test may be limited to the functions
affected by the alteration, repair, or modification, as determined by the qualified person.
7.3.2.4 The replacement of load chain and rope is specifically excluded from load-test requirements;
however, an operational test of the hoist shall be made before returning the crane to service.
7.3.2.5 When rope clips or wedge socket end connections are used on a load line, the hoist should be
cycled several times with a load approximately 15% of the rated capacity. Next, if rope clips are
used, check and retighten nuts to the recommended torque. If a wedge socket is used, verify that
the rope is properly seated.
7.3.2.6 A written report confirming the rated load testing of the crane shall be furnished by the inspector.
7.3.2.7 Test loads shall not be less than 100% or more than 125% of the rated capacity, unless otherwise
recommended by the manufacturer or a qualified person.
7.3.2.8.1 Hoist the test load a sufficient distance to ensure that the load is supported by the crane and held
by the hoist brakes. Personnel shall be kept clear of the test load while it is suspended.
7.3.2.8.2 Transport the test load by means of the trolley for the full length of the bridge or as practical
when obstructions are present.
7.3.2.8.3 Transport the test load by means of the bridge for the full length of the runway, in one direction
with the trolley as close to the extreme right-hand end of the crane as practical, and in the other
direction with the trolley as close to the extreme left-hand end of the crane as practical.
7.3.2.9 The replacement of load chain and rope is specifically excluded from this requirement; however,
an operational test of the crane shall be made in accordance with 7.3.1.1.1 prior to putting the
crane back in service.
7.3.2.10 Operational testing of altered, repaired, or modified cranes whose load sustaining parts or rated
capacities have not been affected may be limited to the functions affected by the alteration, repair
or modification as determined by a qualified person.
7.3.2.11 The transporting of test loads as required by 7.3.2.1 above, shall be done insofar as interfering
equipment/structures permit and in accordance with recommendations from the manufacturer or a
responsible engineering organization. However, test loads should not be carried over critical
systems or components.
7.3.2.12 Test weights shall be accurate to within 5%, +0% of stipulated values.
7.3.2.13 Load tests shall be performed only after inspection and maintenance of the crane are confirmed
as current and any outstanding discrepancies have been addressed.
7.3.2.14 If a load test is conducted, it shall be performed as follows or as modified by a qualified person.
Use Exhibit 7.1, to document this test. This will become the load test report.
7.3.2.14.1 Move the trolley to bridges midspan, position the bridge at a location convenient for rigging
the load test.
7.3.2.14.2 Rig and raise the test load approximately one foot above the floor (ground) to ensure the load is
supported by the crane and held by the hoist brakes.
7.3.2.14.2.2 Verify that the hoist operates properly and holds the load without slippage of more than 0.5
inch.
7.3.2.14.2.3 Verify that there is no rotation of the cable drum during the test.
7.3.2.14.2.5 Lower the test load at full speed and stop abruptly. Verify the brake application is positive
and effective.
7.3.2.14.3 Raise the test load for ample clearance and transport the test load by means of the trolley for
the full length of the bridge; verify smooth starting, running and stopping.
7.3.2.14.4 With the trolley as close as practical to one end of the crane, transport the test load by means of
the bridge for the full length of the runway in one direction and in the other direction with the
trolley as close as practical to the other end of the crane; verify smooth starting, running and
stopping.
7.3.2.14.5 Return the bridge to the starting position, lower the load to approximately one foot above the
floor (ground); stop and hold the load for three minutes with the brakes.
7.3.2.14.5.1 Verify that the hoist operates properly and holds the load without slippage of more than 0.5
inch.
7.3.2.14.5.2 Verify that there is no rotation of the cable drum during the test.
7.3.2.14.6 Lower the load, disconnect the rigging, tag, and stow the crane.
7.3.2.14.7 Verify that no visible load bearing part (eg. Gearing, shafting, bearing, rope or chain end
connections, brake component) has been adversely affected by the test.
7.3.2.15 After the test is completed, the load-test report shall be signed and dated by the Person-In-Charge
of conducting the load test. The Person-In-Charge shall ensure that the test is forwarded to the
AEDC Crane System Engineer so that it can be placed in the crane maintenance file. Test reports
shall be retained in the crane maintenance file.
7.4 MAINTENANCE
7.4.1.1 A preventive maintenance program shall be established and based on the recommendation of the
crane manufacturer. If equipment maintenance procedures deviate from published manufacturer's
recommendations, the alternate procedures shall be approved in advance by the manufacturer or
another qualified person and be kept readily available. Dated maintenance records should be kept
where readily available to appointed personnel.
7.4.1.2 Replacement parts shall be at least equal to the original manufacturers specifications.
7.4.1.3 All moving parts of the crane for which lubrication is specified shall be regularly lubricated.
Check lubricating systems for delivery of lubricant. Follow manufacturers recommendations as
to points and frequency of lubrication, maintenance of lubricant levels, and types of lubricant to
be used.
7.4.1.4 Maintenance personnel shall take the following precautions before performing maintenance on a
crane:
7.4.1.4.1 Move the crane to a location where it will cause the least interference with other cranes and
operations.
7.4.1.4.4 Perform a lockout/tagout procedure. Facility-specific lock and tag procedures shall be strictly
followed. While maintenance is under way, warning or out of order signs shall be placed on
the crane.
7.4.1.4.5 If personnel have access to the floor beneath the crane use warning signs and barriers on the
floor where overhead maintenance work creates a hazard.
7.4.1.4.6 If the runway remains energized, place stops or signalers full-time at a visual vantage point to
observe the approach of active cranes and prohibit contact by the active cranes with the idle
crane, with persons performing maintenance, or with the maintenance equipment.
7.4.1.4.7 Install a guard or barrier between adjacent runways for the length of the established work area to
prevent contact between persons performing maintenance and any crane on the adjacent runway.
7.4.1.4.8 After maintenance work is completed and before restoring the crane to normal operation, the
following activities shall be completed:
Personnel using wire rope shall ensure proper care by doing the following:
7.4.2.2 Unreel or uncoil rope as recommended by the rope manufacturer and with care to avoid kinking or
inducing a twist.
7.4.2.3 Before cutting rope, use some method to prevent unlaying the strands. Heat affected zones of
flame cut wire rope shall not be allowed to bear load.
7.4.2.4 During installation, avoid dragging the rope in dirt or around objects that will scrape, nick, crush,
or induce sharp bends in it.
7.4.2.5 Maintain rope in a well-lubricated condition to reduce internal friction and prevent corrosion.
Ensure that lubricant applied, as part of a maintenance program, is compatible with the original
lubricant and is a type that does not hinder visual inspection. Those sections of rope located over
sheaves or otherwise hidden during inspection and maintenance procedures require special
attention when the rope is being lubricated.
7.4.3.2 Toeboards and handrails shall meet the requirements of ANSI A1264.1.
7.4.3.3 Ladders shall be permanently and securely fastened in place and shall be constructed in
compliance with ANSI 14.3. Hands shall be free from encumbrances while using ladders.
7.4.3.4 Rails shall be level, straight, joined, and spaced to the crane span compatible with the design of
the crane. When curves or grades are required, special design is necessary. Tolerances shall be in
accordance with the crane specification. In lieu of crane specification tolerances, Crane
Manufacturers Association of America (CMAA) Specification 70, Table 1.4.2-1, or CMAA
Specification 74, Table 1.4.1-1, may be used as a guideline.
7.4.4.1 The trolley shall be provided with stops at the limits of travel. A stop engaging the tread of the
wheel shall be of a height at least equal to the radius of the wheel.
7.4.4.2 The bridge shall be provided with bumpers or other automatic means providing equivalent effect
unless the crane has a fast deceleration rate caused by the use of sleeve bearings. The crane is not
operated near the ends of bridge travel; or the crane is restricted to a limited distance and there is
no hazard of striking any object in this limited distance.
7.4.4.3 Trolley bumpers or other automatic means of equivalent effect shall be provided, unless the trolley
is not operated near the ends of trolley travel, or is restricted to a limited distance of the bridge
girder and there is no hazard of striking any object in this limited distance, or is used in similar
operating conditions.
7.4.4.4 When more than one bridge or trolley is mounted on the same runway, bumpers shall be provided
between adjacent bridge ends or trolleys.
7.4.4.5 Bridge trucks shall have rail sweeps that extend below the rail top and are adjacent to and
outboard of the leading wheels with respect to any direction of travel.
7.4.4.6 Exposed moving parts, such as gears, set screws, projecting keys, chains, chain sprockets, and
reciprocating components, that constitute a hazard under normal operating conditions, shall be
fitted with guards.
7.4.4.6.1 The following shall apply to all personnel involved in overhead and gantry crane operation.
7.4.4.6.2 At the initial stage of the planning process, an appointed person shall classify each lift into one
of the AEDC specified lift categories (ordinary, critical or non-standard).
7.5 OPERATION
7.5.1.1 Do not engage in any practice that will divert your attention while operating the crane.
7.5.1.2 Do not operate cranes without complying with the requirements of Chapter 6. Your immediate
supervisor shall participate in this determination.
7.5.1.3 Do not allow other personnel in the cab or on any part of the crane unless their presence is
imperative to the operation of the machine. Additional qualified operators may be in the cab only
if required by procedure and will conduct themselves in a professional manner so as not to
distract the on-duty operator.
7.5.1.5 Operators shall be held directly responsible for the safe operation of their equipment. Whenever
there is any question as to the safety of the activity, an operator has the authority to stop and
refuse to handle loads until the matter has been resolved by supervisory personnel.
7.5.1.6 If a warning device is furnished, it shall be activated each time before traveling and intermittently
when approaching work persons. If warning device is not available, the operator or PIC shall
instruct all personnel not directly related to the lift to clear the area. The purpose of this
instruction is simply to ensure that personnel are not exposed to unnecessary risk in accordance
with Air Force Operational Risk Management (ORM) policy.
7.5.1.7 If you find the cranes main or emergency switch open when starting on duty, do not close it until
it has been determined that no one is on or close to the crane. If there is a warning sign on the
switch, do not remove it unless you placed it there. Do not close the switch until the warning sign
has been removed by the person who placed it there.
7.5.1.8 Before closing the main switch, ensure that all controllers are in the OFF position.
7.5.1.9 If a power failure occurs during operation, immediately switch all controllers to the OFF position.
7.5.1.10 Before leaving a crane unattended, the operator shall place controllers in the off position and
ensure that the main line disconnect device of the crane is open.
7.5.1.11 Become familiar with your equipment and its proper care. If adjustments or repairs are necessary,
or any defects are known, report them promptly to your supervisor. Also, notify the next operator
of the defects at shift change.
7.5.1.12 Contacts with runway stops or other cranes shall be made with extreme caution. If you are
ordered to engage with or push other cranes, do this with particular care for the safety of persons
on or below the. cranes, and only after making certain that any persons on the other cranes are
aware of what action is to be taken.
7.5.1.14 When the wind-indicating alarm is given, anchor the bridge on outside cranes.
7.5.1.15 Before any maintenance work on the crane, maintenance personnel shall ensure the main switch
is locked and tagged in the de-energized (OPEN) position. LOTO procedures contained in
AEDC Safety, Health, and Environmental Standard B4 High Voltage Electrical Work shall
be strictly followed.
NOTE: It is recognized that selected maintenance work must be performed with the power on; however,
such maintenance work shall be performed by maintenance personnel, not by the operator.
7.5.1.16 Operate all controls before beginning a new shift. If any controls do not operate properly, adjust
or repair them before operations begin.
7.5.1.17 Do not hoist two or more separately rigged loads in one lift, even though the combined load is
within the cranes rated capacity.
7.5.1.18 Ensure that a 10BC or larger fire extinguisher is installed in the cab of cab-operated cranes. The
extinguisher shall be maintained in a serviceable condition.
7.5.1.19 Do not lift, lower, or travel the crane while anyone is on the load or hook.
7.5.2 Stowage
If tools, lubricants, or maintenance materials are stowed on the crane, a metal box securely
fastened to the crane or walkway shall be used.
7.5.3.1 At the beginning of each work shift, or the first time the crane is used during a shift, test the
upper-limit switch/device of each hoist under no load. Exercise extreme care to avoid two-
blocking; inch the block into the limit switch or run it in at slow speed. If the switch/device
does not operate properly, immediately notify the supervisor.
7.5.3.2 If a lift is in progress during a shift change, this testing requirement is considered to have been
satisfied for the completion of that lift. However, test the limit switch again before the next lift.
7.5.3.3 Do not use the final hoist-limit switch/device that controls the upper limit of travel of the load
block as an operating control.
The standard hand signals for AEDC use shall be as specified in the latest edition of the ASME
B30 standards for the particular type of crane or hoist being used (Figure 7-4).
Figure 7-4 Standard hand signals for controlling overhead crane operation
7.5.5.1 Any person acting as the signal person during crane operations shall be clearly identified to the
crane operator before the lift is begun.
7.5.5.2 In those cases where the crane operator cannot see the signal person, a second qualified signal
person shall be stationed where he or she can be seen by the operator and can effectively relayed
signals to the operator.
7.5.5.3 Where voice (direct or two-way radio) communication is used, the signal person shall
communicate directly with the operator, not through a third person. When using two-way radio,
it is important to have channels devoted exclusively to crane communications. Signals shall be
discernible and audible.
7.5.5.4 The operator shall obey signals only from the designated signal person. Obey a STOP signal no
matter who gives it.
7.5.6.1 The weight of the load shall be determined prior to making the lift.
7.5.6.2 The crane and rigging equipment shall not be loaded beyond its rated capacity, except for
authorized testing described in paragraph 7.3.
7.5.7.1 Ensure that the hoist rope is free from kinks or twists. Do not wrap the hoist rope around the load.
7.5.7.2 Ensure the load is attached to the load-block hook by means of slings or other approved devices.
7.5.7.3 Take care to make certain that the sling clears all obstacles.
7.5.8.1 The person appointed to direct the lift shall see that the load is well secured and properly balanced
in the sling or lifting device before it is lifted more than a few inches.
7.5.8.2.3 The hook shall be positioned above the center of gravity of the load in such a manner as to
minimize swinging when the load is lifted.
7.5.8.2.4 If there is a slack-rope condition, it should be determined that the rope is properly seated on the
drum and in the sheaves.
7.5.8.2.5 All personnel including the qualified rigger shall be clear of the load.
7.5.8.3.1 The load is lifted slowly until it clears the ground or other support to minimize swinging.
7.5.8.3.3 The load does not contact any obstructions. A dry run shall be conducted in areas where
clearance is limited.
7.5.8.4 Cranes shall not be used for side pulls except when specifically authorized by an appointed person
who has determined that the stability of the crane is not endangered and that load-bearing parts of
the crane will not be overstressed.
7.5.8.6 Each time a load approaching the rated capacity is handled, test the hoist brakes by raising the
load a few inches and applying the brakes. Any slippage or downward motion is unacceptable.
7.5.8.7 Do not lower the hook below the point where less than two full wraps of rope remain on the
hoisting drum.
7.5.8.8 When the load or hook approaches personnel, sound the warning signal.
7.5.8.9 Tag lines should be used as required to guide, snub, or otherwise control the load.
7.5.8.10 Do not leave a suspended load unattended unless specific precautions have been instituted and
are in place.
7.5.8.11 Work on suspended loads is prohibited under normal conditions. If the supervisor believes it is
necessary to work on a suspended load, guidelines for safe operation shall be established through
consultation with the appropriate safety organization. Suspended loads that must be worked on
shall be secured against unwanted movement.
7.5.9.1 The requirements of paragraph 7.5.1 through 7.5.8 also apply to ordinary lifts.
7.5.9.2 An appointed person shall classify each lift into one of the AEDC categories (ordinary, critical, or
non-standard) before the lift is planned.
7.5.9.3 Hoisting and rigging operations for ordinary lifts require a Designated Leader who shall be present
at the lift site during the entire lifting operation. If the lift is being made by only one person, that
person assumes all responsibilities of the Designated Leader.
7.5.9.4 Leadership designation may be by written instructions, specific verbal instructions for the
particular job, or clearly defined responsibilities within the assigned craftsmens organizational
structure.
7.5.9.5.1 Ensure that personnel involved understand how the lift is to be made.
7.5.9.5.2 Ensure that the weight of the load is determined, that proper equipment and accessories are
selected, and that rated capacity is not exceeded.
7.5.9.5.5 Ensure that a Qualified Signal Person is assigned, if required, and is identified to the operator.
7.5.9.5.6 Direct the lifting operation to ensure that the job is done safely and efficiently.
7.5.9.5.7 Stop the job when any potentially unsafe condition is recognized.
7.5.9.6 The operator, or a designated person, shall ensure that the crane is still within the inspection
interval.
7.5.9.7 The operator, or a designated person, shall visually examine the crane in accordance with
paragraph 7.2.4.
Exhibit 7.1 Bridge, Wall, Gantry Crane Load Test Sample Form
Page 1 of 3
NOTE: Test loads shall not be more than 125% of the rated load, unless recommended by the manufacturer.
DEFECTIVE/OK/NA
________ e. Gears
________ g. Blocks.
Visually inspect rope in accordance with Chapter 11, Wire Rope and Slings.
________ b. Wear
________ c. Kinks
________ a. Wear
________ b. Deformation
________ c. Deterioration.
INITIAL
________ 10. Qualified inspector shall perform nondestructive tests on hook by visual
examination, liquid penetrant examination, or magnetic-particle examination. Acceptance: No cracks,
linear indications, laps, or seams.
Hooks with more than 5% normal (new hook) throat opening, not to exceed inch shall be replaced.
Hooks with any visibly apparent bend or twist from the normal (new hook) plane of the hook shall be
replaced. Hooks having more than 10% wear in the throat section or 5% elongation of the shank shall be
replaced. Lubricate hook bearing and latch pin as applicable.
Establish two marks, A and B with center punch. For ease in measuring, set distances on an even number
of inches.
Page 2 of 3
Check for:
Operated By _____________________________________________
Page 3 of 3
This chapter provides safety standards for inspecting, testing, and operating hoists not permanently
mounted on overhead cranes and implements the requirements of ASME B30.11, B30.16, and
B30.21.
8.1 GENERAL
Hoists described in this chapter include hand-powered, air-powered, and electric-powered hoists
that are not permanently mounted on overhead cranes. This chapter applies to the following types
of equipment (Figures 8-1 through 8-6): Overhead hoists (underhung); Jib cranes/hoists (floor and
wall mounted); Monorail systems. Manual-lever-operated hoists (wire rope, chain, and web-strap
types).
Wire-rope ratchet and pawl lever-operated hoists should not be used for lifting service (Figures 8-
7 and 8-8).
Systems used for transporting personnel and specially insulated hoists used for handling
electrically energized power lines require special considerations and are not included in this
chapter.
Hoist operators shall be trained and qualified according to requirements found in Chapter 6.
8.1.4 Marking
8.1.4.1 The rated capacity shall be permanently marked on the hoist or load block.
8.1.4.2 Electric-powered hoists shall be marked with:
8.1.4.2.1 Name of manufacturer.
8.1.4.2.2 Manufacturers model or serial number.
8.1.4.2.3 Voltage of AC or DC power supply and phase/frequency of AC power supply.
8.1.4.2.4 Circuit ampacity.
8.1.4.3 Air-powered hoists shall be marked with:
8.1.4.3.1 Name of manufacturer.
8.1.4.3.2 Manufacturers model or serial number.
8.1.4.3.3 Rated air pressure.
8.1.4.4 Hand-chain-operated hoists shall be marked with:
For electric or air-powered hoists, load-suspending parts of powered hoists shall be designed so
that the static stress calculated for the rated load will not exceed 20% of the average ultimate
material strength. This requirement is commonly reflected by quoting a minimum design factor
of 5:1. For hand-chain-operated and manual-lever-operated hoists, load-suspending parts shall be
designed so that the static stress calculated for the rated load will not exceed 25% of the average
ultimate strength. This requirement is commonly reflected by quoting a minimum design factor
of 4:1.
8.1.8.4.3 The friction brake mechanism shall have provision for adjustment where necessary to
compensate for wear.
8.1.9.1 Wire rope shall be of a construction specified by the hoist manufacturer or by a qualified person.
8.1.9.2 If a load is supported by more than one part of wire rope, the tension on the parts shall be
equalized.
8.1.9.3 Socketing shall be done in the manner specified by the manufacturer of the assembly or the rope.
8.1.9.4 Eye splices shall be made in a manner recommended by a qualified person. Rope thimbles shall
be used in the eye.
8.1.9.5 Swaged or compressed fittings shall be applied as recommended by the rope, hoist, or fitting
manufacturer or a qualified person.
8.1.9.6 Use rope having an independent wire-rope, wire-strand core, or other temperature-damage-
resistant core if the rope will be exposed to ambient temperatures greater than 180o F (82o C).
8.1.9.7 The rope ends should be attached to the hoist in a manner to prevent disengagement throughout
rated hook travel. No less than two wraps of rope shall remain on the anchorage of the hoist load
sprocket (drum) when the hook is in its fully extended position, unless a lower-limit device is
provided, in which case one wrap shall remain on each anchorage of the drum hoist.
8.1.11.2 If a load is supported by more than one part of web strap, the tension on the parts shall be
equalized.
8.1.11.3 End terminations shall be done in the manner specified by the manufacturer of the assembly or
the web strap.
8.1.11.4 Eyes shall be made in a manner recommended by the hoist manufacturer or a qualified person.
8.1.11.5 Nylon and polyester web straps shall not be exposed to an ambient temperature greater than 200
F (93 C).
8.1.11.6 The web strap shall be attached to the hoist in a manner to prevent disengagement throughout
rated hook travel; no less than two wraps of web strap shall remain on the hoist load sprocket
(drum) when the hook is extended to its full rated lift length.
8.1.12 Overtravel Protection
8.1.12.1 Upper-Limit Switches/Devices
For electric- or air-powered hoists, the hoist shall be designed and constructed so that the load
hook, either loaded or empty, shall not exceed the upper limit of travel. In lieu of a limit switch, a
mechanism such as a slip clutch may be used.
8.1.12.2 Lower-Limit Switches/Devices
8.1.12.2.1 For electric-or air-powered hoists, the hoist shall not be installed where, during normal
operating conditions, the hook can be lowered beyond rated hook travel unless the hoist is
equipped with a lower-limit device. Lower-limit devices should be provided for hoists where the
load block enters pits or hatchways in the floor.
8.1.12.2.2 For hand-chain-operated and manual-lever-operated hoists, before the load chain can be
completely run out of the hoist, it shall be restrained in its fully extended position. The restraint
shall be such that the unloaded hoist can withstand a lowering hand chain or operating lever force
equivalent to twice the pull required to lift the rated load, or with the rated load on the hoist, a
hand chain or operating lever force equivalent to the pull required to lift the rated load.
On cab- and remote-operated carriers, an audible or visual warning means shall be provided,
unless it is impossible for personnel to work on the floor below the hoist.
8.1.14 Support
Support structures, including trolleys and monorails, shall have a rated capacity at least equal to
that of the hoist.
8.1.15 Location
The hoist shall be installed only in locations that will permit the operator to remain clear of the
load at all times. Clearances shall be provided and maintained at the curves of a monorail system
to allow for the swing of the load when negotiating the curve. The amount of clearance shall be
determined by giving due consideration to the size, weight, and speed of the carrier and the radius
of the track curve.
The rated capacity shall not be exceeded except for properly authorized tests (paragraph 8.3.1).
8.1.17.1 Stops on Jib Cranes and Monorails: Stops shall be provided at the ends of carrier travel. Stops
or forks shall be provided at open ends of monorail track, track openers, and track switches.
Stops shall be an integral part of a movable monorail track to prevent a carrier from running off
either end of the movable track when the movable track is not in alignment with the stationary
tracks.
8.1.17.2 Lugs on Jib Cranes and Monorail Carriers: Lugs or other means shall be provided to limit the
drop of the carrier frame to 1 inch in case of wheel or axle failure, and shall be on both flanges of
the track.
Sheaves carrying ropes, which can be momentarily unloaded, shall be provided with close-fitting
guards, or other devices, to guide the rope back into the groove when the load is reapplied.
Sheaves in the load block shall be equipped with close-fitting guards that will minimize the
possibility of ropes becoming fouled when the load block is lying down with the ropes loose.
Latch-equipped hooks shall be used for hoisting and rigging (H&R) operations unless the
application makes use of the latch impractical or unsafe. The absence of a hook throat latch is not
allowed (see paragraph 13.1.3).
Wiring and equipment shall comply with NFPA 70, National Electrical Code, Article 610,
Cranes and Hoists. When electric hoists are used in locations other than general indoor
applications, control enclosures should be selected per NEMA ICS-6, Enclosures for Industrial
Control and Systems.
8.1.20.1 Pendant Controls
8.1.20.1.1 Pushbutton Station: A pendant pushbutton station shall be supported so that the electrical
conductors are protected from strain.
8.1.20.1.2 Pendant Construction: Makeshift field-fabricated pendants shall not be used. The voltage at
pendant push-buttons shall not exceed 150 volts for AC and 300 volts for DC. Pendant control
boxes shall be constructed to prevent electrical shock.
8.1.20.1.3 Spring Return and Marked Pushbuttons: Pushbuttons (except on/off buttons) shall spring
return to the off position when pressure is released by the operator. Buttons shall be clearly
marked to identify their function.
8.4.20.1.4 Resultant Motion: To the extent possible, each control shall be marked to indicate the
direction of resultant motion.
8.1.20.2 Electrical Supply, Hoist and Monorail Systems
The electrical supply for hoists and monorail systems shall be controlled by a lockable switch or
circuit breaker located on a fixed structure accessible from the floor. For temporarily installed
hoists, a standard electrical connection (plug) that can be readily disconnected by the operator
meets this requirement.
8.1.20.3 Monorail Conductors
Monorail conductors shall be guarded or located to minimize inadvertent contact with the
conductor.
8.1.21 Modifications
8.1.21.1 Monorail Systems: A monorail system may be modified or rerated, provided such modifications
and the supporting structure are analyzed by a qualified person or the manufacturer of the
equipment. A rerated system or one whose load-supporting components have been modified shall
be subjected to a load test (see paragraph 8.3.2). The new rated load shall be displayed in
accordance with paragraph 8.3.
8.1.20.2 Manual- or Power-Operated Hoists: Modifications to upgrade, rerate, or modernize hoist
equipment shall be authorized only by the original equipment manufacturer or a qualified person.
The new rated load shall be displayed in accordance with paragraph 8.1.2. See paragraph 8.3.2,
regarding load test requirements.
8.1.21.3 Documentation for Modifications: Documentation supporting rerating and modifications shall
be retrievable and readily available to authorized personnel.
8.1.22 Inspection Records
Inspection records shall be kept for the life of the equipment. Following is a summary of
inspection record requirements.
8.1.22.1 Initial Inspection: A record of the initial inspection shall be made.
8.1.22.3 Periodic Inspection: The most recent records, dated and signed by a qualified inspector, shall be
retained in the maintenance file.
8.2 INSPECTIONS
8.2.1.1 Normal service: Operation with randomly distributed loads within the rated load limit, or uniform
loads less than 65% of rated load for not more than 15% of the time for manual-lever-operated
hoists or for not more than 25% of the time for electric- or air-powered hoists.
8.2.1.2 Heavy service: Operation within the rated capacity that exceeds normal service.
8.2.1.3 Severe service: Operating at normal or heavy service under abnormal operating conditions, (i.e.,
extreme temperatures, corrosive atmospheres).
Prior to their initial use, all new, repaired, or modified hoists shall be inspected by a qualified
inspector to ensure compliance with the applicable provisions of ASME B30.11, B30.16, and
B30.21. Dated and signed inspection records shall be kept on file and shall be readily available.
8.2.3.1 Operators or other designated personnel shall visually inspect items such as the following at the
start of each shift or prior to first use if the hoist has not been in regular service (records are not
required):
8.2.3.1.1 Controls and operating mechanisms for proper operation.
8.2.4.1 Operators or other designated personnel shall visually inspect the hoist at the following intervals
(records are not required):
8.2.4.1.1 Normal service monthly.
8.2.4.1.2 Heavy service weekly to monthly.
8.2.4.1.3 Severe service daily to weekly.
8.2.4.2 In addition to the requirements listed above in Daily Inspection, these inspections shall include the
following:
8.2.4.2.1 Hoist braking system for proper operation.
8.2.4.2.2 Hoist rope or chain reeving for compliance with hoist manufacturers recommendations.
8.2.4.2.3 Lever for bends, cracks, and the like.
8.2.4.2.4 Observations during operation.
8.2.4.3 Examine deficiencies and determine whether a more detailed inspection is required. If
deficiencies are found, contact the AEDC Crane System Engineer.
8.2.5.1 General
8.2.5.1.1 A qualified inspector shall perform a complete inspection at the following intervals:
Normal service yearly.
Heavy service semiannually.
Severe service - quarterly
8.2.5.1.2 The qualified inspector shall examine deficiencies and determine whether they constitute a
safety hazard and whether disassembly is required.
8.2.5.1.3 Dated and signed inspection records shall be kept on file and shall be readily available.
8.2.5.2 Hoists
8.2.5.3.2 No precise rules can be given for determining the exact time to replace wire rope because many
factors are involved. Safety depends largely on the use of good judgment by an appointed person
in evaluating remaining strength in a used rope, after allowance for deterioration disclosed by
inspection. Safety of rope operation depends on this remaining strength.
8.2.5.3.3 Conditions such as the following shall be reason for questioning rope safety and considering
replacement:
In hoist ropes, 12 randomly distributed broken wires in one rope lay, or 4 broken wires in
one strand in one rope lay.
Wear of one-third of the original diameter of outside individual wires.
Kinking, crushing, bird caging, or any other damage resulting in distortion of the rope
structure.
Evidence of heat damage from any cause.
Reductions from nominal diameter greater than 5%.
8.2.5.3.4 The qualified inspector shall give special attention to end fastenings and shall examine ropes
frequently at socketed fittings; on the development of two broken wires adjacent to this point,
resocket or replace the rope. Resocketing shall not be attempted if the resulting rope length will
be insufficient for proper operation. Those portions of the rope subjected to reverse bends and
operation over small-diameter drums or sheaves shall be closely examined.
8.2.5.3.5 Replacement rope and connections shall have a strength rating at least as great as the original
rope and connections furnished by the hoist manufacturer. Any deviation from the original size,
grade, or construction shall be specified by a rope manufacturer, the hoist manufacturer, or a
qualified person.
8.2.5.3.6 Never use discarded rope for slings.
8.2.5.4 Welded-Link Chain
A qualified inspector shall do the following during periodic inspections:
8.2.5.4.1 Operate the hoist under load in raising and lowering directions, and observe the operation of the
chain and sprockets. The chain should feed smoothly into and away from the sprockets.
8.2.5.4.2 Make sure that, if the chain binds, jumps, or is noisy, first clean and properly lubricate it. If the
trouble persists, inspect the chain and mating parts for wear, distortion, or other damage.
8.2.5.4.3 The chain should be cleaned before inspection. Examine visually for cracks, gouges, nicks,
weld spatter, corrosion, and distorted links. Slacken the chain and move adjacent links to one
side to inspect for wear at the contact points. If you observe wear or suspect stretching, measure
the chain according to the hoist manufacturers instructions. If instructions are not available,
proceed as follows:
Select an unworn, unstretched length of the chain (e.g., at the slack end).
Suspend the chain vertically under tension and, using a tool, measure the outside length of any
convenient number of links approximately 12 in. (305 mm) to 14 in. (356 mm) overall.
Measure the same number of links in the used sections and calculate the percentage of increase in
length.
If the used chain exceeds a hoist manufacturers recommended length, or in the absence of such a
recommendation, if the used chain is 1.5% longer than the unused chain for powered hoists or is
2.5% longer than the unused chain for hand-operated hoists, replace the chain.
Examine the chain for gouges, nicks, corrosion, weld spatter, or distorted links. Any of these
conditions shall be sufficient reason for questioning safety and considering replacement. Safety
in this respect depends largely on the use of good judgment by an appointed person in evaluating
the degree of damage.
8.2.5.4.4 No one except the chain manufacturer shall repair the load chain by welding or any other means.
8.2.5.4.5 Ensure that replacement chain is the same size, grade, and construction as the original chain
furnished by the hoist manufacturer, unless otherwise recommended by the hoist manufacturer
due to working conditions.
8.2.5.4.6 Load-chain links that pass over the hoist-load sprocket on edge (alternate to those that lie flat in
the pockets) should be installed with the welds away from the center of the sprocket. This
precaution is not required on idler sprockets, which change the direction but not the tension in the
chain.
8.2.5.4.7 Ensure that replacement chain is installed without any twist between the hoist and an anchored
end on either the loaded side or the slack side.
8.2.5.4.8 When a chain is replaced, disassemble and inspect the mating parts (sprockets, guides, stripper)
for wear, and replace if necessary.
8.2.5.4.9 Never use discarded load chain for slings.
8.2.5.5 Roller Chain
A qualified inspector shall do the following during periodic inspections:
8.2.5.5.1 Test the hoist under load in raising and lowering directions, observing the operation of the chain
and sprockets. If the chain binds, jumps, or is noisy; clean and properly lubricate it. If the
trouble persists, inspect the chain and mating parts for wear, distortion, or damage.
8.2.5.5.2 If you observe wear or suspect stretching, measure the chain according to the hoist
manufacturers instructions. If instructions are not available, proceed as follows:
Suspend the hoist in normal position and apply a light load of approximately 100 lb (46
kg).
Select a 12-in. (305 mm) section of chain that normally travels over the load sprocket.
Determine elongation by measuring with a tool, from the edge of one chain pin to the
corresponding edge of another pin. If elongation exceeds in. (6.3 mm) in 12 in. (305
mm) compared to new or unstretched chain values, replace the chain.
Inspect for twists. Replace if the twist in any 5-ft (1.52 m) section exceeds 15.
Check for straightness in a plane perpendicular to the plane of the rollers. Replace if the
chain has a bow exceeding in. (6.3 mm) in any 5-ft (1.52 m) section.
8.2.5.5.3 Make additional inspections by removing the chain from the hoist and cleaning it thoroughly.
Carefully examine deficiencies such as those listed below and determine whether they constitute
a safety hazard. Any deficiencies are reason for questioning chain safety and considering its
replacement.
Pins turned from original position.
Rollers that do not run freely with light finger pressure.
Joints that cannot be flexed by easy hand pressure.
Side plates that are spread open.
8.2.6.1 A hoist that is not in regular service (idle for a period of 1 month or more, but less than 1 year)
shall be inspected before being placed in service according to the requirements listed above in
paragraph 8.2.4, Frequent Inspection.
8.2.6.2 A hoist that is not in regular service (idle for a period of 1 year or more) shall be inspected before
being placed in service according to the requirements listed above in paragraph 8.2.5, Periodic
Inspection.
8.2.6.3 The determination supporting these alternate inspection frequencies and procedures shall be made
by a qualified person for each affected hoist. Documentation supporting this determination shall
be kept readily available.
8.3 TESTING
8.3.1.1 General
8.3.1.1.1 All new hoists shall be tested by the hoist manufacturer. All modified or repaired hoists or
hoists that have not been used within the preceding 12 months shall be tested before being placed
in service. All tests shall be done by a qualified inspector or under the direction of that inspector
as detailed in the following paragraphs.
8.3.1.1.2 Scheduled periodic load tests are not routinely required. If a load test is conducted, the test load
shall not be less than 100% of the rated load of the hoist or more than 125% of the rated load of
the hoist unless otherwise recommended by the hoist manufacturer or a qualified person. For
hoists that frequently make critical lifts, especially if lifts are at or near rated capacity, a
scheduled load-test program may be implemented. Such periodic load-tests shall not exceed the
rated capacity. If a scheduled load-test program is implemented, a 5-year frequency is
recommended.
8.3.1.1.3 No hoist shall be loaded beyond its rated load except for test purposes or for special overrated
lifts as provided in 8.3.1.4.
8.3.1.1.4 Planned engineered lifts are outlined in the ASME B30 standards. No such lift shall be made
without the authorization of the AEDC Crane System Engineer. This authorization will only be
granted after the AEDC Structural Engineer has reviewed the design of the crane-supporting
structure, has inspected the structure as required by ASME B 30 standards and has approved its
use for the intended lift.
8.3.1.2 Electric- or Air-Powered Hoists
8.3.1.2.1 Check lifting and lowering (testing through complete rated lift length is not required).
8.3.1.2.2 Check operation of brakes.
8.3.1.2.3 Determine the trip setting of limit devices by tests under no-load conditions. Conduct tests first
by hand, if practical, and then under slowest speed obtainable. Test with increasing speeds up to
maximum speed.
8.3.1.3 Hand-Chain-Operated Hoists
8.3.1.3.1 Check all functions of the hoist, including lifting and lowering, with the hoist suspended in an
unloaded state.
8.3.1.3.2 After testing unloaded, apply a load of at least 50 lb (23 kg) multiplied by the number of load-
supporting parts of chain to the hoist to check proper load control.
8.3.1.4 Manual-Lever-Operated Hoists
8.3.1.4.1 Check all functions of the hoist with the hoist suspended in an unloaded state.
8.3.1.4.2 After testing unloaded, apply a load of at least 100 lb (46 kg) multiplied by the number of load-
supporting parts of load line to the hoist to check proper load control.
shall be accomplished at another location or job site by a qualified inspector or under the
direction of that inspector. If a load test is conducted, the test load shall not be less than 100% of
the rated load of the hoist or more than 125% of the rated load of the hoist unless otherwise
recommended by the hoist manufacturer or a qualified person.
8.3.2.1.2 A qualified inspector shall test hoists in which load suspension parts have been modified,
replaced, or repaired as specified in paragraph 8.3.1.2, steps a. and b., by or under the direction of
a qualified inspector, and a record of the test should be made. A designated or authorized person
shall determine if repairs made to a hoist are extensive, and require a rated load test, or routine
maintenance and require only an operational test. The applied test load shall not be less than
100% of the rated capacity of the hoist, or more than 125% of the rated capacity of the hoist
unless otherwise recommended by the manufacturer or a qualified person. The replacement of
load chain and rope is specifically excluded from this hoist test; however, a functional test of the
hoist under a normal operating load should be made in accordance with 8.3.1, Operational
Tests, prior to putting the hoist back in service.
8.3.2.2 Hand-Chain-Operated or Manual-Lever-Operated Hoists
8.3.2.2.1 The manufacturer shall dynamically test new hoists with a test load of at least 125% of the rated
capacity. If the manufacturer cannot test the hoist, the user shall be notified and the test shall be
accomplished at another location or job site by a qualified inspector or under the direction of that
inspector.
8.3.2.2.2 Hoists in which load suspension parts have been modified, replaced, or repaired shall be tested
statically or dynamically by or under the direction of a qualified inspector and a record of the test
should be kept. A designated or authorized person shall determine if repairs made to a hoist are
extensive and require a rated load test or are routing maintenance and require only an operational
test. The applied test load shall not be less than 100% of the rated capacity of the hoist or more
than 125% of the rated capacity of the hoist, unless otherwise recommended by the manufacturer
or a qualified person. The replacement of load chain is specifically excluded from this hoist load
test; however, a functional test of the hoist should be made in accordance with paragraph 8.3.1.2,
or 8.3.1.3, Hand-Chain-Operated Hoists, and Manually Lever-Operated Hoists, respectively,
prior to putting the hoist back in service.
8.3.2.2.3 A sample load test and inspection form is included as Exhibit 8.1, which appears at the end of
this chapter. This form is intended to be a sample only, and is not intended to be mandatory.
Load tests shall be conducted in accordance with a written step-by-step procedure. A hold point
shall be included in the load-test procedure to verify that inspection and maintenance is up to
date. Load tests should be made where no critical items are installed, stored, or being worked on.
The following guidelines are for information. Actual conditions may require changes to meet
different situations and equipment configurations. Use Exhibit 8.5, Hoist, Jib Cranes and
Monorail Systems Load Test Checklist, to document this test. This will become the load test
report.
8.3.3.1 Verify that hoist inspection and maintenance is up to date.
8.3.3.2 State the type of load test. Example: Special Test Before Critical Lift, Test Before Returning
to Service, or a Rated Load Test.
8.3.3.3 State test loads used.
8.3.3.4 Lift the test load a few inches and hold for 5 minutes; from this position, lift an additional
distance, not less than 3 feet above the floor (ground), and hold for 5 minutes. Then slowly lower
the load; stop about 1 foot above the floor (ground), and hold for 5 minutes. At intermediate
levels during hoisting and lowering, verify that the hoist operates properly and holds the load
without slippage of more than 0.5 inch.
8.3.3.5 For electric- or air-powered hoists, at least once in a raising and once in a lowering condition, at a
height of no more than 1 foot, disconnect the electric or air power source. The load shall stop
immediately with less than 0.5-inch movement. There should be no slippage of the load or
overheating of the brakes after 5 minutes of power off. The holding brakes should control the
load throughout the test, and the load should not drop more than 0.5 inch when the lifting motion
is again initiated.
8.3.3.6 For monorail and jib cranes, transport the test load with the carrier (trolley) over the trolley's entire
range. For jib cranes, rotate the jib boom over the full range of motion while the carrier is at the
outside end of the boom. Load transporting should be done with the test load approximately 1
foot or less above the floor (ground) or obstructions.
8.3.3.7 The test load should not rotate on the load block. Use taglines as appropriate. If the hook has
power rotation, rotate the load through the full range of motion.
8.3.3.8 The hoist and carrier (trolley) shall function smoothly, without sticking or binding.
8.3.3.9 Following the load test, verify that no visible load-bearing part (e.g., gearing, shafting, bearing,
rope or chain end-connection, brake components) has been adversely affected by the test.
8.3.3.10 Place the load test report in the maintenance file.
8.4 MAINTENANCE
8.4.1.1 A preventive maintenance program shall be established and be based on the hoist manufacturers
recommendations. If equipment maintenance procedures deviate from published manufacturer's
recommendations, the alternate procedures shall be approved in advance by the manufacturer or
another qualified person and be kept readily available. Dated maintenance records shall be
retained in the maintenance file and readily available to appointed personnel.
8.4.1.2 Replacement parts shall be at least equal to the original manufacturers specifications
CAUTION: Adhere to established fall-protection requirements (guardrail system, safety net system, or
personal fall-arrest system) when positioned on a walking or working surface with an unprotected
side or edge that is 6 ft (2 m) or more above a lower level. Consult with your supervisor or
occupational safety representative for specific details. The following precautions shall be taken
as applicable.
8.4.2.1 The hoist, monorail crane, or carrier (trolley) to be repaired shall be moved to a location where it
will cause minimum interference with other equipment. Equipment that cannot be readily moved
from its operating location can be maintained at the operating location, providing precautions are
taken to ensure the safety of maintenance personnel and other personnel.
8.4.2.2 All controllers shall be placed in the off condition.
8.4.2.3 If the equipment is electrically powered, the main or emergency switch on the line feeding the
hoist or monorail system shall be locked in the de-energized position, except as required to
perform the maintenance. Lock and tag procedures shall be strictly followed.
8.4.2.4 If air-powered, the supply shall be disconnected or the valve on the air line feeding the hoist or
monorail system shall be closed, except as required to perform the maintenance. Lock and tag
procedures shall be strictly followed.
8.4.2.5 Effective markings and barriers shall be used where work creates a hazardous area on the floor
beneath the equipment. Warning or out of order signs should be placed on the hoist. If
personnel can access the equipment and signs are not visible from the floor beneath, warning
signs should be visible from the floor.
8.4.2.6 Only properly trained personnel shall work on energized equipment. Extra caution is required
when working on energized equipment.
8.4.2.7 For monorail systems:
8.4.2.7.1 Where other carriers are operating on the same monorail track, temporary stops should be
provided to prevent interference with the idle equipment.
8.4.2.7.2 Where temporary stops are not possible or practical, a signal person shall be placed at a vantage
point for observing the approach of an active unit and warning its operator when it reaches a safe
distance from the idle unit.
8.4.2.8 After adjustments and repairs have been made, the equipment shall not be restored to service until
all guards have been reinstalled, safety devices reactivated, and maintenance equipment removed.
8.4.3.1 Any hazardous conditions disclosed by inspection or during operation shall be corrected before
normal hoist operation is resumed. Adjustments and repairs shall be done only by designated
personnel.
8.4.3.2 Adjustments shall be maintained to ensure correct functioning of components. The following are
examples of functional operating mechanisms:
8.4.3.2.1 Limit devices
8.4.3.2.2 Control systems
8.4.3.2.3 Brakes.
8.4.3.3 Repairs or replacements shall be made as needed. The following are examples:
8.4.3.3.1 Hooks showing indications described in Chapter 13.
8.4.3.3.2 All critical parts that are cracked, broken, bent, or excessively worn.
8.4.3.3.3 Pitted or burned electrical contacts should be corrected only by replacement and in sets.
Controller parts should be lubricated as recommended by the manufacturer.
8.4.3.3.4 Function labels on pendant control stations shall be kept legible.
8.3.4.4.5 If repairs of load-sustaining members are made by welding, materials shall be identified and
appropriate welding procedures shall be assigned by a qualified welding engineer, and welds shall
be made by a qualified welding operator.
A preoperational check shall be performed to verify the proper function of activities such as
motion controls and interlocks. Special attention shall be given to those areas likely to have been
affected by maintenance or repair.
8.5 OPERATION
The following shall apply to all personnel involved in hoist operations. At the initial stage of the
planning process, an appointed person shall classify each lift into one of the AEDC-specified
categories (ordinary, critical or non-standard).
Know the weight of the load and do not load the hoist beyond the rated capacity, except as
provided for in paragraph 8.3, Testing.
8.5.3.1 The supporting structure or anchoring means shall have a load rating at least equal to that of the
hoist.
8.5.3.2 Use hoists only in areas that will allow you to be clear of the load.
8.5.3.3 Do not wrap the hoist rope or chain around the load.
8.5.3.4 Attach the load to the hook using slings or other approved devices.
8.5.3.5 Do not use chain or wire rope as a ground for welding.
8.5.3.6 Do not touch a welding electrode to the chain, wire rope, or any other part of the hoist or monorail
system.
8.5.3.7 Operate hand-chain-operated hoists with hand power only and with no more than one operator per
hand chain.
8.5.3.8 Do not use a lever extension (cheater) on manual-lever-operated hoists.
8.5.3.9 Properly seat the slings or other approved devices in the saddle of the hook before carrying out
hoisting operations.
8.5.5.1 At the beginning of a shift, test the upper-limit switch of each hoist under no load conditions. If
the hoist has a lower-limit switch, test it with no load before lowering any load that could bring
the lower-limit switch into operation. Exercise extreme care; inch the block into the limit switch
or run in at slow speed. If the limit switch does not operate properly, notify the designated person
immediately.
8.5.5.2 If a lift is in progress during a shift change, this testing requirement is considered to have been
satisfied for the completion of that lift. However, test the limit switch again before the next lift.
8.5.5.3 Never use the hoist-limit switch that controls the upper limit of travel of the load block as an
operating control.
8.5.6.1 Hoisting and rigging operations for ordinary lifts require an Designated Leader. The Designated
Leader shall be present at the lift site during the entire lifting operation. If the lift is being made
by only one person, that person assumes all responsibilities of the Designated Leader.
8.5.6.2 Leadership designation may be by written instructions, specific verbal instructions for the
particular job, or clearly defined responsibilities within the assigned craftsmens organizational
structure.
8.5.6.3 The Designated Leaders responsibility shall include the following:
8.5.6.3.1 Ensure that personnel involved understand how the lift is to be made.
8.5.6.3.2 Ensure that the weight of the load is determined, that proper equipment and accessories are
selected, and that rated capacity is not exceeded.
8.5.6.3.3 Survey the lift site for hazardous/unsafe conditions.
8.5.6.3.4 Ensure that equipment is properly set up and positioned.
8.5.6.3.5 Ensure that a Qualified Signal Person is assigned, if required, and is identified to the operator.
8.5.6.3.6 Direct the lifting operation to ensure that the job is done safely and efficiently.
8.5.6.3.7 Stop the job when any potentially unsafe condition is recognized.
8.5.6.3.8 Direct operations if an accident or injury occurs.
8.5.6.4 The operator or other designated person shall visually examine the hoist in accordance with the
requirements for a daily inspection described in paragraph 8.2, Inspections.
8.5.6.5 A qualified person shall examine any deficiencies and determine whether they constitute a hazard.
Correct these deficiencies before operating the hoist.
8.5.6.6 Load lines shall be checked after strain is put on them, before the load is lifted clear of the ground.
If not plumb, the slings or equipment shall be repositioned so that the lines are plum before
continuing.
Notes:
1. Load test prior to initial use, at 125 percent of rated capacity, all new hoists or hoists in which load-
sustaining parts have been modified, repaired, or replaced. Test weights shall be accurate to within 5%,
+0% of stipulated values. Load test at 100% of rated capacity hoists with overload devices. Test the
function of the overload device.
2. Qualified inspector shall verify all steps as listed below.
3. Craftsmen will initial all tests, work, and inspections completed below.
1. Perform the annual periodic inspection. Check unit for proper operation.
HAND-CHAIN-OPERATED HOISTS ONLY. Check brake mechanism for work
glazed, or contaminated disks, worn pawls, cams, or ratchets. Check for broken,
2. corroded, or stretched pawl springs. Repair as needed.
3. ELECTRIC- AND AIR-POWERED HOISTS. Check:
All functional operating mechanisms for misadjustment interfering with proper
3a. operation
3b. Limit switches or devices for proper operation
External evidence of damage or excessive wear of load sprockets, idler sprockets, and
3c. drums or sheaves
3d. External evidence of wear on motor or load brake
Electrical apparatus for signs of pitting or any deterioration of visible controller
3e. contacts
3f. All anchorage or hoist suspensions.
4. Set hoist up for load test and inspection.
Perform load test using the required test weights (See Note 1, Exhibit 8.5) and
appropriate slings. Measure a length of the load chain under tension; measure a length
5. of 15 links. If wire rope is used, measure the diameter.
Qualified inspector shall perform nondestructive tests on hook by visual examination, liquid penetrant
examination, or magnetic particle examination.
Acceptance: No cracks, linear indications, laps, or seams.
Hooks with more than 5% normal (new hook) throat opening, not to exceed inch, shall be replaced.
Hooks with any visibly apparent bend or twist from the normal (new hook) plane of the hook shall be
replaced. Hooks having more than 10% wear in the bowl section or 5% elongation of the shank shall
be replaced. Lubricate hook bearing and latch pin as applicable.
Establish two marks, A and B with a center punch. For ease in measuring, set distances on an even
number of inches.
BEFORE LOAD TEST AFTER LOAD TEST
Length AB Inches Length AB Inches
Check for:
1. Wear and deformation
2. Cracks
3. Signs of opening between Point A and Point B.
STATUS CODE: - O.K., A Adjusted, R Repaired, NR Needs Repair, N/A Not Applicable
CODE COMMENT CODE COMMENT
Housing Cable
Kinked or
Warning Label
Distorted
Corrosion
- Worn or
distorted Trolley
- Load Beam
Chains
Condition
Cracked
- Brake Pad
Distorted
Condition
- Lubrication Corroded
Worn Chain
- Sheaves
Guide
STATUS CODE: - O.K., A Adjusted, R Repaired, NR Needs Repair, N/A Not Applicable
CODE COMMENT CODE COMMENT
Hook Sheaves
Loose Retaining
Excess Wear
Hardware
Cracked or
Cracks
Scored
Bent
Inspection Tag
Latch
Update
semiannual
quarterlyc
monthlya
weeklya
Record
Record
Record
yearlyb
Visual
Visual
Visual
Item
dailya
lyc
Frequent inspections (see Para 8.2.4)
All functional operating mechanisms for
X X X
maladjustment and unusual sounds
Limit devices for operation X X X
Air lines, valves, and other parts for leakage X X X
Hooks in accordance with Chapter 13 X X X
Hook latch operation, if used X X X
Hoist rope in accordance with Para 8.2.4 X X X
Load chain in accordance with Para 8.2.5.4 X X X
Rope or load chain reeving for compliance with hoist
X X X
manufacturer's recommendations
Periodic inspections (see Para 8.2.5)
Requirements of frequent inspection X X X
Hoist rope in accordance with Para 8.2.5.3 X X X
Evidence of loose bolts, nuts, or rivets X X X
Evidence of worn, corroded, cracked, or distorted parts
such as load blocks, suspension housing, chain
attachments, clevises, yokes, suspension bolts, shafts, X X X
gears, bearings, pins, rollers, and locking and clamping
devices
Evidence of damage to hook retaining nuts or collars
and pins, and welds or rivets used to secure the X X X
retaining members
Evidence of damage or excessive wear of load
X X X
sprockets, idler sprockets, and drums or sheaves
Evidence of excessive wear on motor or load brake X X X
Electrical apparatus for signs of pitting or any
X X X
deterioration of visible controller contacts
Evidence of damage to supporting structure or trolley X X X
Warning label required by Para 8.1.3.1 X X X
End connections of load chain X X X
a
By operator or other designated personnel with records not required.
b
Visual inspection by a qualified inspector making records of conditions to provide the basis for a continuing evaluation.
c
As in b unless conditions indicate that disassembly should be done to permit detailed inspection.
Exhibit 8.4. Minimum Inspection Requirements For Hand Operated Or Lever-Operated Hoists--
Chain Type.
weekly to
quarterlyc
semiannu
monthlya
monthlya
weeklya
daily to
Record
Record
Record
yearlyb
Visual
Visual
Visual
Item
allyc
Frequent inspections (see Para 8.2.4)
All functional mechanisms for maladjustment
X X X
interfering with proper operation
Hoist support for damage X X X
Hooks and latches for deformation, chemical
X X X
damage, cracks, and wear (See Chapter 13)
Hook latch operation, if used X X X
Load chain in accordance with Para 8.2.5.4 X X X
Load chain reeving for compliance with the
recommendations of the hoist manufacturer or X X X
a qualified person
Lever for problems such as bends or cracks X X X
Periodic inspections (see Para 8.2.5)
Requirements of frequent inspection X X X
Evidence of loose bolts, nuts, or rivets X X X
Evidence of worn, corroded, cracked, or
distorted parts such as load blocks, suspension
housing, levers, chain attachments, clevises,
X X X
yokes, suspension bolts, shafts, gears,
bearings, pins, rollers, and locking and
clamping devices
Evidence of damage to hook retaining nuts or
collars, and pins and welds or rivets used to X X X
secure the retaining members
Evidence of damage or excessive wear of load
X X X
sprockets or idler sprockets
Evidence of worn, glazed, or oil- contaminated
friction disks; worn pawls, cams, or ratchet;
X X X
corroded, stretched, or broken pawl springs in
brake mechanism
Evidence of damage to the supporting structure
X X X
or trolley, if used
Warning label required by Para 8.1.3.2 X X X
End connections of load chain, including over-
X X X
travel restraints
a
By operator or other designated personnel with records not required.
b
Visual inspection by a qualified inspector making records of conditions to provide the basis for a continuing evaluation.
c
As in b, unless conditions indicate that disassembly should be done to permit detailed inspection.
Exhibit 8.5 Hoist, Jib Cranes And Monorail Systems Load Test Checklist
Date: Crane ID #
Supervisor: Badge # Signature:
Latest Crane Inspection Date:
Purpose of Load Test:
1. Special Test Before Critical Lift.
NOTE: Test loads shall not be less than 100 percent of the rated load of the equipment or more than 125
percent of the rated load of the equipment, unless otherwise recommended by the manufacturer.
This chapter specifies operation, inspection, maintenance, and testing requirements for the use of
mobile cranes and implements the requirements of ASME B30.5, PCSA-4 (Mobile Power Crane
and Excavator Standards and Hydraulic Crane Standards), SAE J376-85 (Load-Indicating Devices
in Lifting Crane Service), SAE J765 (Crane Load Stability Test), SAE J874 (Center of Gravity
Test Code) and SAE J987(Crane Structure, Method of test). Only equipment built to appropriate
design standards shall be used at AEDC.
9.1 GENERAL
This chapter applies to commercial truck-mounted cranes; crawler cranes; locomotive cranes;
wheel-mounted cranes, multiple control stations; wheel-mounted cranes, single control station; and
any variation that retains the same fundamental characteristics. These cranes have a superstructure
capable of rotating 360 mounted on a carrier and have boom raising and lowering capabilities.
Operators of mobile cranes shall be trained and qualified in accordance with the requirements of
Chapter 6, Personnel Qualification and Training.
9.1.2.1 Since the load rating for mobile cranes may be based on stability and hydraulic or structural
competence, load ratings established by manufacturers shall not be exceeded in operational
application.
9.1.2.2 No crane shall be loaded beyond its rated capacity, except for load test purposes as described in
Section 9.3, Testing.
9.1.2.3 When loads are to be handled that are limited by hydraulic or structural competence rather than by
stability, the appointed person shall ensure that the weight of a load approaching rated capacity
has been determined within -10%, +0% before it is lifted.
9.1.3.1 A durable rating chart with legible letters and figures shall be provided with each crane and
attached in a location accessible to the operator while at the controls. Table 9-1 (next page)
provides a sample load rating chart. The data and information to be provided on these charts shall
include, but not be limited to, the following:
9.1.3.1.1 A full and complete range of manufacturers crane load ratings at all stated operating radii,
boom angles, work areas, and all stated boom lengths and configurations, jib lengths and angles
(or offset), as well as alternate ratings for use and nonuse of optional equipment on the crane,
such as outriggers and extra counterweights, that affect ratings.
9.1.3.1.2 A work area chart for which capacities are listed in the load rating chart [Figure 9-1 (which
follows Table 9-1)].
9.1.3.1.3 Where ratings are limited by structural, hydraulic, or factors other than stability, the limitations
shall be shown and emphasized on the rating charts.
9.1.3.1.4 In areas where no load is to be handled, the work area figure and load rating chart shall state that
information.
9.1.3.1.5 Recommended reeving for the hoist lines shall be shown.
9.1.3.2 In addition to the data required on the load rating chart, the following information shall be shown
either on the rating chart or in the operating manual:
9.2.3.2.1 Recommended parts of the hoist reeving, and size and type of rope for various crane loads.
9.2.3.2.2 Recommended boom hoist reeving diagram, where applicable; size, type, and length of rope.
9.2.3.2.3 Tire pressure, where applicable.
9.2.3.2.4 Cautionary or warning notes relative to limitations on equipment and operating procedures,
including indication of the least stable direction.
9.2.3.2.5 Position of the gantry and requirements for intermediate boom suspension, where applicable.
9.2.3.2.6 Instructions for boom erection and conditions under which the boom, or boom and jib
combinations, may be raised or lowered.
9.2.3.2.7 Whether the hoist-holding mechanism is automatically controlled or manually controlled,
whether free-fall is available, and whether any combination of those exists.
9.2.3.2.8 The maximum telescopic travel length of each boom telescopic section.
9.2.3.2.9 Whether sections are telescoped with power or manually.
9.2.3.2.10 The sequence and procedure for extending and retracting the telescopic boom section.
9.2.3.2.11 Maximum loads permitted during actual boom-extending operation and any limiting conditions
or cautions.
9.2.3.2.12 Hydraulic relief valve settings specified by the manufacturer.
When power-operated brakes that have no continuous mechanical linkage between the actuating
and braking means are used, an automatic means shall be provided to set the brake to prevent the
load from falling in event of loss of brake-actuating power.
A power-controlled lowering system shall be provided and shall be capable of handling rated
loads and speeds as specified by the manufacturer of the crane.
9.1.6 Booms
9.1.6.1 Booms, boom sections, and jibs shall be clearly identified and shall be used only for the purpose
recommended by the manufacturer.
9.1.6.2 Lattice booms shall meet the performance requirements of SAE J987, Crane Structure, Method
of Test (Chapter 17, References).
This table is an example of the type of load rating chart that should be included in each crane.
Manitowoc Model 3900 Lift Crane Extra-Heavy Boom
Working 50 60 70 80 90 100 120 140
Radius lbs.
12 120,000 120,000
14 111,200 110,800 109,000
16 104,200 103,600 102,700 100,000 95,000
18 97,800 97,400 97,000 96,600 92,500 90,000
20 93,200 92,400 91,600 90,600 89,600 86,000 83,000
22 87,800 86,800 85,800 84,800 83,800 82,800 80,000
24 83,400 81,200 80,300 79,400 78,700 77,800 75,200 66,500
26 75,900 75,500 74,700 73,900 73,200 72,600 70,500 63,100
28 68,100 67,700 67,300 66,900 66,400 65,800 64,000 59,800
30 61,700 61,300 60,900 60,500 60,000 59,400 58,500 56,400
32 56,500 56,100 55,700 55,300 54,800 54,200 53,300 52,300
34 52,000 51,600 51,200 50,800 50,300 49,700 48,800 47,800
36 48,100 47,700 47,300 46,900 46,400 45,800 44,900 43,900
38 44,700 44,300 43,900 43,500 43,000 42,400 41,500 40,500
40 41,700 41,300 40,900 40,500 40,000 39,400 38,500 37,500
42 39,100 38,700 38,300 37,900 37,400 36,800 35,900 34,900
44 36,800 36,400 36,000 35,600 35,100 34,500 33,600 32,600
46 34,700 34,300 33,900 33,500 33,000 32,400 31,500 30,500
48 32,900 32,500 32,100 31,700 31,200 30,600 29,700 28,700
50 30,800 30,400 30,000 29,500 28,900 28,000 27,000
52 29,300 28,900 28,500 28,000 27,400 26,500 25,500
54 27,900 27,500 27,100 26,600 26,000 25,100 24,100
56 26,500 26,100 25,700 25,200 24,600 23,700 22,700
58 25,300 24,900 24,500 24,000 23,400 22,500 21,500
60 23,800 23,400 22,900 22,300 21,400 20,400
65 21,300 20,900 20,400 19,800 18,900 17,900
70 18,900 18,400 17,800 16,900 15,900
75 31,200 17,100 16,600 16,000 15,100 14,100
80 15,200 14,600 13,700 12,700
85 24,200 13,900 13,300 12,400 11,400
90 19,300 12,100 11,200 10,200
95 15,700 11,100 10,200 9,200
100 12,700 9,300 8,300
110 10,200 6,800 5,600
120 4,500 3,840
9.1.7 Counterweight
9.1.7.1 Cranes shall not be operated without the ballast or counterweight being in place as specified by the
crane manufacturer. Under specific conditions, such as during crane assembly, unusual boom
configurations, etc., the crane manufacturers recommendations for ballast or counterweight shall
be adhered to.
9.1.7.2 Ballast or counterweight as specified by the manufacturer shall not be exceeded.
9.1.8 Rerating
9.1.8.1 Cranes may be modified or rerated providing such modifications are analyzed thoroughly by a
qualified engineer or manufacturer of cranes. Such action must be approved by the base
operating contractors safety office.
9.1.8.2 When rerated, crawler, truck, and wheel-mounted cranes shall be tested in accordance with SAE
J765, Crane Load Stability Test Code.
9.1.8.3 A rerating test report shall be readily available.
9.1.8.4 No cranes shall be rerated in excess of the manufacturers original load ratings.
9.1.9.1 The crane maintenance file is a compilation of various documents and records relating to
operation, maintenance, inspection, testing, evaluating and repair of the equipment. The intent of
the crane maintenance files are to provide the user with evidence of a safe and reliable
maintenance program. Inspection records should be retained in a format and location that
provides for ease in accessibility. Maintenance file information should provide a source for
comparing present conditions with past conditions to determine whether existing conditions show
a trending pattern of wear, deterioration, or other comparable factors that may compromise safe,
continued use of the equipment.
9.1.9.1.1 The master file shall be located in the AEDC crane library. A secondary file may be centrally
located or proportioned into satellite holding areas.
9.1.9.2 The maintenance history of the crane shall be retained throughout its service life. Maintenance
records shall be retained in the crane master file, or an electronic record keeping system may be
used. If a computer system is used, and maintenance records are not retained in the crane history
file, the crane history file shall state where the electronic maintenance records are available.
9.1.9.3 The crane maintenance file shall contain, as a minimum, the required current dated periodic
inspection records and other documentation to provide the user with evidence of a safe and
reliable maintenance program. Maintenance file information should provide a source for
comparing present conditions with past conditions to determine whether existing conditions show
a trending pattern of wear, deterioration, or other comparable factors that may compromise safe,
continued use of the equipment.
9.1.9.4 Crane maintenance files shall contain the following documentation, as applicable:
9.1.9.4.1 All documented inspection records.
9.1.9.4.2 Load test reports.
9.1.9.4.3 Documentation of altered, replaced, or repaired load-sustaining parts.
9.1.9.4.4 Records of special inspections on safety related items such as brakes, crane hooks, ropes,
hydraulic and pneumatic cylinders, and hydraulic and pneumatic relief pressure valves.
9.1.9.4.5 Copies of waivers, exemptions, hostile environment plans, or similar documentation applicable
to the crane (to include manufactures safety bulletins, safety alerts, and product recall
information).
9.1.9.4.6 Documentation for replacement ropes (see Chapter 11, Wire Rope and Slings)
9.1.9.4.7 Wire rope manufactures certification for replacement ropes.
9.1.9.4.8 Records of inspection on load indicating devices, anti-two block, two-block warning, and two-
block damage prevention systems.
NOTE: Although complete maintenance information for old cranes may not be available, the AEDC
Crane System Engineer should acquire as much of the pertinent information as possible.
9.1.10.1 Structural, mechanical, and electrical components of the crane design shall meet accepted crane
design standards, such as PCSA-4, Mobile Power Crane and Excavator Standards and Hydraulic
Crane Standards.
9.1.10.2 The safety features and operation shall conform, at a minimum, to the provisions of ASME
B30.5, Mobile and Locomotive Cranes.
Personnel are not permitted to ride the bare hook, hook ball or a suspended load. (For personnel lifting,
see Chapter 4)
Cribbing / blocks / mats / dunnage / pads shall be used under outrigger floats at all times and shall
meet the following conditions:
9.1.12.1 Have sufficient strength to prevent crushing, bending, or shear failure.
9.1.12.2 Be of adequate size and thickness to completely support the float, transmit the load to the
supporting surface, and prevent shifting, toppling, or excessive settlement under load.
9.1.12.3 Use blocking only under the bearing surface of the outrigger float.
Wind speed and other weather conditions shall be considered. Do not attempt lifts if weather
conditions are adverse to safe load-handling operations. Contact the AEDC Operations Center
for current local weather conditions.
9.1.13.1 Refer to manufacturers written operating instructions for any wind speed limitations. However,
without directorate approval, all operations will be ceased when winds are in excess of 30 mph.
9.1.13.2 Cease operations when electrical storms are within 10 miles.
AEDC has adopted the policy that neither the load nor the boom shall be lowered below the point
where less wraps of rope remain on the respective drums than manufacturers instructions and in
no case will the wraps be less than three full wraps. This requirement is applicable to mobile
cranes only.
9.1.16 Sheaves
9.1.16.1 Sheave grooves shall be smooth and free from surface defects that could cause rope damage.
The cross-sectional radius at the bottom of the groove shall form a close-fitting saddle for the size
of rope used.
9.1.16.2 Sheaves carrying ropes, which can be momentarily unloaded, shall be provided with close-fitting
guards or other devices to guide the rope back into the groove when the load is reapplied. The
sheaves in the lower load block shall be equipped with close-fitting guards that will prevent ropes
from becoming fouled when the block is lying on the ground with loose ropes.
Load hooks, ball assemblies, and load blocks shall be of sufficient weight to overhaul the line
from the highest hook position. Hook and ball assemblies and load blocks shall be labeled with
their rated capacity and weight.
Latch-equipped hooks shall be used for hoisting and rigging (H&R) operations unless the
application makes use of the latch impractical or unsafe. The absence of a hook throat latch is not
allowed (see paragraph 13.1.3).
9.1.20.1 Telescopic boom cranes manufactured after February 28, 1992, shall be equipped with an anti-
two-block device or a two-block damage prevention feature for all points of two-blocking.
Telescopic boom cranes manufactured before February 28, 1992, should be equipped with a two-
block warning feature(s), a two-block damage prevention feature, or an anti-two-block device for
all points of two-blocking (i.e., jibs, boom extensions, etc.).
9.1.20.2 Lattice boom cranes manufactured after February 28, 1992, shall be equipped with an anti-two-
block warning feature, which functions for all points of two-blocking. Lattice boom cranes
manufactured before February 28, 1992, should be equipped with a two-block warning feature
which functions for all points of two-blocking.
9.1.20.3 Cranes used to lift suspended personnel platforms shall have an anti-two-block device or a two-
block damage prevention feature. A two-block warning feature and/or assigning a person to
watch for, and guard against, two-blocking provides insufficient safety for personnel lifting and is
not allowed.
9.1.20.4 All cranes with a maximum load capacity of 3 tons or more shall have a load indicator (Mfg after
1993), rated load capacity indicator, or rated capacity (load) limiter (Mfg after 2005).
9.1.20.5 An audible horn or signal device shall be provided. The control for the device shall be within
reach of the operator.
9.1.20.6 Means shall be provided for the operator to visually determine the levelness of the crane.
9.1.20.7 If a seat belt is provided with a wheel-mounted, single-control station crane, it shall be used
during transit and travel.
9.2 INSPECTIONS
9.2.1 General
Equipment shall operate with a smooth, regular motion without any hesitation, abnormal
vibration, binding, gross shimmy, or irregularity. There shall be no apparent damage, excessive
wear, or deformation of any load-bearing part of the equipment. All safety devices, load
indicators, boom angle and radius indicators, controls, and other operating parts of the equipment
shall be checked during each inspection and shall be in good working order.
Prior to initial use, all new or modified cranes shall be inspected as required in paragraph 9.2.6,
Periodic Inspection, by a qualified inspector to ensure compliance with the applicable
provisions of this chapter. Dated and signed inspection reports shall be kept on file and shall be
readily available.
9.2.3.1 Operators or other designated personnel shall visually inspect items such as the following
each day or prior to use if the crane has not been in regular service (records are not required).
Any deficiencies shall be carefully examined and a determination made as to whether they
constitute a hazard.
9.2.3.1.1 All control mechanisms for maladjustment, excessive wear, and contamination by lubricants or
other foreign matter that could interfere with proper operation: daily, when used.
9.2.3.1.2 Hooks and latches for deformation, chemical damage, cracks, and wear: daily when used.
9.2.3.1.3 Hydraulic systems for proper oil level: daily when used.
9.2.3.1.4 Hydraulic hoses, particularly those that flex in normal operation of crane functions, should be
visually inspected once every working day, when used.
9.2.3.1.5 Operational aids for malfunction: daily, when used.
9.2.3.1.6 Anti-two-block, two-block warning, and two-block damage prevention systems for proper
operation: daily, when used.
9.2.3.1.7 Boom sections for damaged, deformed, or missing structural members or parts: daily when used.
9.2.3.1.8 Rope reeving for noncompliance with crane manufacturers recommendations: daily when used.
9.2.3.1.9 Hoist ropes for kinking, bird caging, and corrosion: daily when used
9.2.3.1.10 Electrical apparatus for malfunctioning, signs of excessive deterioration, and accumulation of
dirt or moisture.
9.2.3.1.11 Tires for recommended inflation pressure.
9.2.5.1 A crane that has been idle for a period of 1 month or more, but less than 6 months, shall be given
an inspection by a qualified person conforming to the requirements of paragraphs 9.2.3 and 9.2.6
before being placed in service.
9.2.5.2 A crane that has been idle for a period of over 6 months shall be given a complete inspection by a
qualified person conforming to the requirements of paragraphs 9.2.3, 9.2.4, and 9.2.6 before
being placed in service.
9.2.5.3 Standby cranes shall be inspected by a qualified person at least semiannually in accordance with
the requirements of paragraphs 9.2.3 and 9.2.6. Cranes that are exposed to adverse environmental
conditions should be inspected more frequently.
9.2.5.4 The determination supporting these alternate inspection frequencies and procedures shall be made
by the AEDC Crane System Engineer for each affected crane. Documentation supporting this
determination shall be kept readily available.
9.2.6.1 A qualified inspector shall inspect wire ropes at least annually. More frequent intervals shall be
determined by a qualified person and shall be based on such factors as expected rope life as
determined by severity of environment, percentage of capacity lifts, frequency rates of operation,
and exposure to shock loads. The qualified inspector shall carefully note any deterioration, such
as described below, that results in appreciable loss of original strength and determine whether
further use of the rope constitutes an acceptable risk. This inspection shall include examination
of the entire rope length without detaching it from the drum.
9.2.6.1.1 Reduction from nominal diameter of more than 5%.
9.2.6.1.2 The number and distribution or concentration of broken outside wires.
9.2.6.1.3 Worn outside wires.
9.2.6.1.4 Corroded or broken wires at end connections.
9.2.6.1.5 Corroded, cracked, bent, worn, or improperly applied end connections.
9.2.6.1.6 Kinking, crushing, cutting, or unstranding.
9.2.6.2 The qualified inspector shall take care when inspecting running rope where rapid deterioration
could occur, such as in the following:
9.2.6.2.1 Sections in contact with saddles, equalizer sheaves, or other sheaves where rope travel is limited.
9.2.6.2.2 Sections of the rope at or near terminal ends where corroded or broken wires may protrude.
9.2.6.3 The qualified inspector shall take care when inspecting certain ropes such as the following:
9.2.6.3.1 Rotation-resistant ropes, because of their higher susceptibility to damage. The internal
deterioration of rotation-resistant ropes may not be readily observable.
9.2.6.3.2 Boom hoist ropes, because of the difficulties of inspection and the important nature of these
ropes.
9.2.6.4 No precise rules can be given for determining the exact time to replace wire rope because many
factors are involved. Safety in this respect depends largely on the use of good judgment by an
appointed person in evaluating remaining strength in a used rope, after allowance for
deterioration disclosed by inspection. Safety of rope operation depends on this remaining
strength.
9.2.6.5 Conditions such as the following shall be sufficient reason for questioning wire-rope safety and
for considering replacement:
9.2.6.5.1 In running ropes, six (6) randomly distributed broken wires in one rope lay, or three (3) broken
wires in one strand in one rope lay.
9.2.6.5.2 In standing ropes, more than two broken wires in one lay in sections beyond end connections or
more than one broken wire at an end connection.
9.2.6.5.3 In rotation resistant ropes, two randomly distributed broken wires in six rope diameters or four
randomly distributed broken wires in thirty rope diameters.
9.2.6.5.4 One outer wire broken at the point of contact with the core of the rope that has worked its way
out of the rope structure and protrudes or loops out from the rope structure; additional inspection
of this part of the rope is required.
9.2.6.5.5 Wear of one-third the original diameter of outside individual wires.
9.2.6.5.6 Kinking, crushing, bird caging, or any other damage resulting in distortion of the rope structure.
9.2.6.5.7 Evidence of heat damage from any cause.
9.2.6.5.8 Reduction from nominal diameter greater than 5%.
9.2.6.6 All rope that has been idle for a month or more due to shutdown or storage of a crane on which it
is installed shall be inspected before it is placed in service. This inspection shall be for all types
of deterioration and shall be performed by an appointed person whose approval shall be required
before further use of the rope. A written and dated report of the rope condition shall be filed.
9.2.6.7 In order to establish data as a basis for judging the proper time for replacement, a continuing
inspection record shall be maintained.
9.2.6.8 Replacement rope shall be the same size, grade, and construction as recommended by the crane
manufacturer, unless otherwise recommended by a rope or crane manufacturer due to actual
working-condition requirements.
9.2.6.9 Never use discarded wire rope for slings.
Load hooks/load blocks that have been changed out shall be inspected by a qualified inspector
before returning the crane to service. Inspection records shall be retained per 9.1.9.
9.3 TESTING
9.3.2.1 Prior to initial use, all cranes in which load-sustaining parts have been modified, replaced, or
repaired shall be load-tested by a qualified inspector or under the direction of that inspector. A
designated or authorized person shall determine if repairs made to a crane are extensive and
require a rated load test, or if repairs are routine maintenance and require only operational testing.
The replacement of rope is excluded from this requirement. However, a functional test of the
crane under a normal operating load should be made prior to putting it back in service.
9.3.2.2 Test weights shall not exceed 110% of the rated capacity and shall be accurate to within 5%,
+0% of stipulated values.
NOTE: Load tests shall not be conducted in locations where the lift meets the definition of a critical lift
(see Chapter 1, Terminology and Definitions).
9.3.2.3 A written report shall be furnished by the inspector showing test procedures and confirming the
adequacy of repairs or alterations. Test reports shall be kept on file and shall be readily available
to appointed personnel.
9.3.2.4 After a load test is completed, the load-test report shall be signed and dated by the Person-In-
Charge of conducting the load test. The Person-In-Charge shall ensure that the test is forwarded
to the AEDC Crane System Engineer so that it can be placed in the crane maintenance file. Use
Exhibit 9.5 AEDC Mobile Crane Load Test Checklist to document this test. This will become
the load test report.
9.4 MAINTENANCE
9.4.1 Preventive Maintenance
9.4.1.1 A preventive maintenance program, based on the recommendations of the crane manufacturer,
shall be established. If equipment maintenance procedures deviate from published manufacturer's
recommendations, the alternate procedures shall be approved in advance by the manufacturer or
another qualified person and be kept readily available. Dated maintenance records shall be kept
where readily available to appointed personnel.
9.4.1.2 Replacement parts shall be at least equal to the original manufacturers specifications.
9.4.1.3 All moving parts of the crane for which lubrication is specified shall be regularly lubricated.
Lubricating systems should be checked for proper delivery of lubricant. Operators and
maintenance personnel shall follow the manufacturers recommendations as to the points and
frequency of lubrication, maintenance of lubricant levels, and types of lubricant to be used.
9.4.2 Maintenance Procedures
9.4.2.1 Before starting adjustments or repairs on a crane, maintenance personnel shall take the following
precautions as applicable:
9.4.2.1.1 Place the crane where it will cause the least interference with other equipment or operations in
the area.
9.4.2.1.2 Lower the lower load block to the ground or otherwise secure it against dropping.
9.4.2.1.3 Lower the boom to the ground, if possible, or otherwise secure it against dropping.
9.4.2.1.4 Place all controls in the OFF position and secure all operating features from inadvertent motion
by brakes, pawls, or other means.
9.4.2.1.5 Ensure starting means are rendered inoperative.
9.4.2.1.6 Stop the power plant or disconnect it at the power takeoff.
9.4.2.1.7 Relieve hydraulic oil pressure from all hydraulic circuits before loosening or removing hydraulic
components.
9.4.2.2 Warning or out-of-order signs shall be placed on the crane controls. Signs or flags shall be
removed only by authorized personnel.
9.4.2.3 After adjustments and repairs have been made, the crane shall not be returned to service until all
guards have been reinstalled, trapped air has been removed from the hydraulic system, safety
devices are reactivated, and maintenance equipment is removed.
9.4.3 Wire Rope Maintenance
Personnel using wire rope shall ensure proper care by doing the following:
9.4.3.1 Store rope to prevent damage or deterioration.
9.4.3.2 Unreel or uncoil rope as recommended by the rope manufacturer and with care to avoid kinking or
inducing a twist.
9.4.3.3 Before cutting a rope, use some method to prevent unlaying the strands. Heat-affected zones of
flame cut wire rope shall not be allowed to bear load.
9.4.3.4 During installation, avoid dragging the rope in the dirt or around objects, which will scrape, nick,
crush, or induce sharp bends in it.
9.4.3.5 Maintain rope in a well-lubricated condition to reduce internal friction and to prevent corrosion.
Ensure that lubricant applied as part of a maintenance program is compatible with the original
lubricant. Consult the rope manufacturer when in doubt. Lubricant applied shall be of the type
that does not hinder visual inspection. Those sections of rope that operate over sheaves or are
otherwise hidden during inspection and maintenance procedures require special attention when
the rope is lubricated.
9.4.3.6 When an operating rope shows greater wear at its ends than on the remainder, its life can be
extended (in cases where a reduced rope length is adequate) by cutting off the worn end, thus
shifting the wear to different areas of the rope.
9.4.3.7 Wire rope clips shall be drop-forged steel of the single- or double-saddle type. Wire rope clips
used in conjunction with wedge sockets shall be attached to the unloaded dead end of the rope
only (see example below). Eye splices shall be made in a manner recommended by the rope or
crane manufacturer, and rope thimbles should be used in the eye.
Notes: 1. It is important that wedge socket assemblies consist of a wedge and a socket, matched pair of the correct size,
and from the same manufacturer (Figure 9.2.).
2. Crosby Group, Inc., now manufactures a patented wedge socket assembly that clips the rope to the wedge.
This product may be found on new cranes and is suitable as a replacement part on existing cranes.
3. Tighten wire rope clips evenly to the recommended torque.
4. Rope clip nuts should be checked monthly and tightened as necessary to compensate for any decrease in rope
diameter during usage.
5. Swaged, compressed, or wedge-socket fittings shall be applied as recommended by the rope, crane, or fitting
manufacturer.
9.5 OPERATION
The following shall apply to all personnel involved in mobile crane operations: At the initial stage
of the planning process, an appointed person shall classify each lift into one of the AEDC-specified
lift categories (ordinary, critical or non-standard).
9.5.1.1 General
9.5.1.1.1 Do not engage in any practice that will divert your attention while operating the crane.
9.5.1.1.2 Do not operate the crane if you do not meet the requirements contained in Chapter 6, or if you
are experiencing a condition resulting in reduced physical or mental capabilities.
9.5.1.1.3 Keep the operating area free of water, snow, ice, oil, and debris that could cause your hands or
feet to slip from the controls.
9.5.1.1.4 Keep the operating cab windshields clean and free of anything that obstructs vision. Replace
broken windows.
9.5.1.1.5 Ensure proper functioning of tires, horn, lights, battery, controller, lift system (including load-
engaging means, chains, hoist rope, and limit switches), brakes, and steering mechanisms. If at
any time a lifting device is found to be in need of repair, is defective, or is in any way unsafe,
report it immediately and take the unit out of service until it has been restored to safe-operating
condition or a determination has been made by the person in charge and a qualified engineer that
the deficiency will not adversely affect the safe operation of the unit.
9.5.1.1.6 When two or more cranes are used to lift one load, one designated person shall be responsible
for the operation. That person shall analyze the operation and instruct all personnel involved in
the proper positioning, rigging of the load, and the movements to be made. That person shall also
determine the necessity to reduce crane ratings, position of load, boom location, ground support,
and speed of movement.
9.5.1.1.7 Determine that no one is working on the crane or is close to it before starting the engine or
beginning to operate the crane.
9.5.1.1.8 Barricade accessible areas within the swing radius of the rear of the rotating superstructure of
the crane to prevent anyone from being struck or crushed by the crane.
9.5.1.1.9 Do not hoist two or more separately rigged loads in one lift, even though the combined load is
within the cranes rated capacity.
9.5.1.1.10 When fueling the crane, stop the engine(s) and ensure that smoking or open flames are not
permitted within 25 ft of the fueling area.
9.5.1.1.11 Ensure that a 10BC or larger fire extinguisher is installed at all operator stations. Fire
extinguishers shall be maintained in a serviceable condition.
9.5.1.1.12 Do not store gasoline, acids, caustics, or cleaning solvents that emit toxic fumes in operating
cabs. Store fuel in safety cans in safe locations.
9.5.1.1.13 Ensure that alternate egress routes are not locked on mobile units with operating enclosures.
9.5.1.1.14 Position the crane on a solid and level footing. It may be necessary in certain situations to use
heavy timber mats to build a good working foundation.
9.5.1.1.15 When swinging the crane, watch out for centrifugal force. Swing the crane slowly to avoid an
outward swing of the load. Attach a tag-line to the load if necessary to control the swing.
9.5.1.1.16 Watch for boom kickback. Never operate with the boom at a higher angle than shown on the
capacity charts.
9.5.1.1.17 Use extreme caution when operating the crane near workers in elevated areas.
9.5.1.1.18 Use power lowering when lowering loads. When lowering heavy loads, keep the hoist brake as
reserve. Use a safety pawl on the boom-hoist drum when not lowering.
9.5.1.1.19 Avoid two-blocking, caused when the hook block makes contact with boom-point sheaves. A
continuing pull on the hoist lines can break the rope or pull the boom back over the cab on some
types of booms. On hydraulically telescoping booms, be sure to play out the hoist line when
extending and spool in the hoist line when retracting.
9.5.1.1.20 Lock carrier air brakes ON when operating, and check the pressure of the air brakes frequently.
9.5.1.1.21 Watch out for the carrier-cab on truck-mounted units when swinging the boom. Keep boom
high enough to swing clear of cab.
9.5.1.1.22 In the absence of crane manufacturers instructions regarding maximum wind speeds for
operation, no operations shall be undertaken at wind speeds in excess of 30 mph without
directorate approval.
9.5.1.1.23 When a crane is to be operated at a fixed radius, the boom-hoist pawl or other positive locking
device shall be engaged.
9.5.1.1.24 On truck-mounted cranes, no loads shall be lifted over the front area, except as approved by the
crane manufacturer.
9.5.1.1.25 Crane cabs, necessary clothing and personal belongings shall not interfere with access or
operations.
9.5.1.1.26 Tools, oil cans, waste, extra fuses, and other necessary articles shall be stored in the tool box,
and shall not be permitted to lie loose in or about the cab.
9.5.1.2 Traveling the Machine
When traveling the machine:
9.5.1.2.1 Secure the boom and hook block.
9.5.1.2.2 Check bridges before crossing; make sure they will support the weight of the machine.
9.5.1.2.3 Check river depths before fording.
9.5.1.2.4 Check clearances under overpasses, overhead lines, or any overhead obstruction; when side
clearances are tight, install a barrier or post a lookout, and make certain there is sufficient
clearance for tail swing.
9.5.1.2.5 When traveling with a load, snub the load to prevent swaying if possible; never travel with near-
capacity loads.
9.5.1.2.6 Never travel a rubber-tired unit with a load over the side.
9.5.1.2.7 On soft surfaces, always move with the load behind; it helps to raise the leading end of the
crawlers, and makes traveling safer. (for crawler cranes)
9.5.1.2.8 Always set swing brakes when the unit is idle or holding loads for a period of time, especially
on slopes; if swinging during travel is necessary, engage swing-jaw clutch before releasing
brakes.
9.5.1.2.9 Never back up until it is determined that everyone is clear of the machine.
9.5.1.2.10 Position the boom in the direction of travel for long moves.
9.5.1.2.11 Block treads when moving uphill; be sure they are blocked to prevent downhill movement
before shifting steering clutches.
9.5.1.2.12 Lock the turntable before traveling on a highway. Use a house lock or swing brake, and lower
boom into the rack to prevent swing.
9.5.1.2.13 When loading machine on the trailer, always use a ramp.
9.5.1.3 Making Adjustments or Repairs
9.5.1.3.1 When making adjustments or repairs:
Stop the machine.
Lower the boom or secure it against dropping.
Neutralize all controls.
Remove ignition key to make the machine inoperative.
Display proper warning signs on controls of machine.
Keep hands, feet, and clothing away from gears, ropes, drums, and sheaves.
Never put hands on wire rope when climbing to the top of the cab.
Use a bar or stick to guide wire rope onto drums.
Keep hands well away from the fan drive while engine is running.
Safeguard the crane oiler; do not resume operation until a positive ALL CLEAR signal
has been given.
Replace all guards and shields before resuming operation.
9.5.1.3.2 Place blocking or other adequate supports under the boom before beginning boom disassembly
operations. Never stand under or on the boom during this work.
9.5.1.3.3 Before disconnecting oil lines, if machine has hydraulic controls, be sure to place boom on the
ground or in the boom rest; then move the pedals and control levers to equalize pressures within
the cylinders. Always release any air supercharge on the hydraulic reservoir and shut off the
engine (or declutch pumps) before disconnecting oil lines.
9.5.1.3.4 Do not reach into hydraulic-boom holes unless the sections are securely anchored together.
9.5.1.4 Ensuring Stability
9.5.1.4.1 Know the rated capacity of the crane and the weight of the load. A safe lift depends on many
factors including boom length, boom angle, and load radius. Follow these requirements to avoid
buckling the boom or tipping:
Know the radius of the load; the radius is measured from center of rotation, not from the
boom foot pin.
Always operate within the rated capacity of the machine.
The gross capacity includes weight of hook, block, and any material-handling devices,
(i.e., slings, concrete bucket, magnet lifter, etc.); subtract the weight of all these to find
the true weight (net capacity) the crane can handle safely.
Ratings are based on operating the machine on firm, level ground; outriggers should be
properly extended and lowered before operation.
Avoid fast swings, hoists, or sudden braking; these can cause overloads.
Do not handle large, heavy loads in strong winds; the wind can catch the load and create
an unstable condition.
9.5.1.4.2 Test stability before lifting heavy loads. Check outrigger footing. Lift load slightly off the
ground and stop. Check the machine for movement and check to be sure the brakes hold with the
load elevated.
9.5.1.4.3 Never use machine stability to determine capacity.
9.5.1.4.4 If there are any indications of tipping, the machine is already overloaded for that working radius.
9.5.1.4.5 Do not back crane away from the load while carrying a maximum load; this may cause the crane
to tip.
9.5.1.4.6 Always use outriggers when making lifts (with pick-and-carry units), and never lift a load
forward of the front outriggers, unless allowed on manufacturers load chart.
9.5.1.4.7 Lower outrigger jacks until the tires clear the ground, and level the unit to reach the machines
full capacity. Recheck and, if necessary, reset outriggers between heavy lifts.
9.5.1.4.8 Outrigger beams shall be extended in accordance with manufacturers instructions.
9.5.1.5 Observing Boom-Length Precautions
9.5.1.5.1 Always use the shortest boom possible.
9.5.1.5.2 Make only vertical lifts; never pull the load sideways.
9.5.1.5.3 Keep speed slow in lifting and lowering loads.
9.5.1.5.4 Swing carefully and slowly, and avoid boom or jib whipping; check counterbalance clearance.
9.5.1.5.5 Do not let the load strike the boom or outriggers.
9.5.1.5.6 Allow maximum clearance between the hook block and boom-point sheaves.
9.5.1.5.7 Keep near-capacity loads as close to the ground as possible.
9.5.1.5.8 Avoid hitting anything with the boom; an engineering analysis shall be made before putting the
crane back in service if this occurs.
9.5.2 Operating Near Power Lines and Transmission Towers (see section 9.6)
Check all limit switches, if supplied, without a load on the hook at the beginning of each work
shift or the first time the crane is used that shift. Inch each motion into its limit switch to ensure
that two-blocking does not occur during the test. If a lift is in progress during a shift change, this
testing requirement is considered to have been satisfied for the completion of that lift. However,
test the limit switch again before the next lift.
9.5.4 Standard Hand Signals
The standard hand signals for AEDC use shall be as specified in the latest edition of the ASME
B30 standards for the particular type of crane or hoist being used (see Figure 9-7a/b below).
Figure 9-7a. Standard hand signals for controlling mobile crane operations.
Figure 9-7b. Standard hand signals for controlling mobile crane operations.
9.5.5.1 All personnel acting as signalers during crane operations shall be clearly identified to the crane
operator before the lift is begun.
9.5.5.2 In those cases where the crane operator cannot see the signaler, a second qualified signal person
shall be stationed where he or she can see both the signaler and the crane operator, and can relay
the signals to the operator.
9.5.5.3 Where voice (direct or two-way radio) communication is used, the signaler shall communicate
directly with the operator, not through a third person.
9.5.5.4 The operator shall obey signals only from the designated signal person. Obey a STOP signal no
matter who gives it.
The crane shall not be loaded beyond its rated capacity, except of authorized testing described in
paragraph 9.3.
9.5.7.1 Ensure hoist rope is free from kinks or twists. Do not wrap the hoist rope around the load.
9.5.7.2 Ensure load is attached to the load-block hook by means of slings or other approved devices.
9.5.7.3 Ensure load is well secured and properly balanced in the sling or lifting device before it is lifted
more than a few inches.
9.5.7.4 Make certain sling clears all obstacles.
9.5.8.1The appointed person directing the lift shall make certain that the load is well secured and properly
balanced in the sling or lifting device before it is lifted more than a few inches.
9.5.8.2 Before starting to hoist, note the following conditions:
9.5.8.2.1 Hoist rope shall not be kinked.
9.5.8.2.2 Multiple-part lines shall not be twisted around each other.
9.5.8.2.3 The hook shall be positioned above the center of gravity of the load in such a manner as to
minimize swinging when the load is lifted.
9.5.8.2.4 Following any slack-rope condition, it should be determined that the rope is properly seated on
the drum and in the sheaves.
9.5.8.2.5 All personnel including the qualified rigger shall be clear of the load.
9.5.8.3 During hoisting, take care to ensure that:
9.5.8.3.1 There is no sudden acceleration or deceleration of the moving load.
9.5.8.3.2 Load does not contact any obstructions. A dry run shall be conducted in areas where
clearance is limited.
9.5.8.4 Cranes shall not be used for side pulls, except when specifically authorized by a designated person
who has determined that the stability of the crane is not endangered and that various parts of the
crane will not be over stressed.
9.5.9.1 The requirements of preceding paragraphs under 9.5 also shall apply to ordinary lifts.
9.5.9.2 The PIC shall classify each lift into one of the AEDC categories (ordinary, critical or non-
standard) before the lift is planned.
9.5.9.3 The Asset Owner shall appoint a Designated Leader who shall be present at the lift site during the
entire lifting operation. If the lift is being made by only one person, that person assumes all
responsibilities of the Designated Leader.
9.5.9.4 Leadership designation may be by written instructions, specific verbal instructions for the
particular job, or clearly defined responsibilities within the assigned craftsmens organizational
structure.
9.5.9.5 The Designated Leaders responsibility shall include the following:
9.5.9.5.1 Ensure that personnel involved understand how the lift is to be made.
9.5.9.5.2 Ensure that the weight of the load is determined, that proper equipment and accessories are
selected, and that rated capacity is not exceeded.
9.5.9.5.3 Survey the lift site for hazardous/unsafe conditions.
9.5.9.5.4 Ensure that equipment is properly set up and positioned.
9.5.9.5.5 Ensure that a Qualified Signal Person is assigned, if required, and is identified to the operator.
9.5.9.5.6 Direct the lifting operation to ensure that the lift is completed safely and efficiently.
9.5.9.5.7 Stop the job when any potentially unsafe condition is recognized.
9.5.9.5.8 Direct operations if an accident or injury occurs.
9.5.9.6 The Designated Leader shall inspect all cranes in use to ensure they are still within the inspection
interval.
9.5.9.7 The Designated Leader shall inspect all lifting devices to ensure that the rated capacity of these
items of equipment will not be exceeded.
9.5.9.8 The operator shall inspect for damage and defects in accordance with paragraph 9.2.3, including
observations during operation. A qualified person shall examine deficiencies and determine
whether they constitute a hazard.
9.5.9.9 Check hoist-limit switches, if provided, according to paragraph 9.5.3, Hoist-Limit Switch.
9.5.9.10 Ensure that basic operating instructions of power-operated equipment, together with charts,
tables, or diagrams showing the rated capacity, boom angle, swing, and stability data are posted
in convenient view of the operator.
9.5.9.11 Assure load lines are plumb by applying strain to them, but not enough to lift the load from the
ground. If load lines are not plumb, reposition the slings or equipment before continuing.
In addition to the requirements of this chapter, see Chapter 2, Critical Lifts, for critical-lift
requirements.
Note: This section completely replaces previously AEDC requirements with the mandatory OSHA
requirements of 29 CFR 1926 subpart CC.
Where voltage information is required (e.g. Table 9-2), requested voltage information must come
from the utility owner/operator of the power lines.
The employer must assume that all power lines are energized unless the utility owner/operator
confirms that the power line has been and continues to be de-energized and visibly grounded at
the worksite
9.6.3 Posting Of Electrocution Warnings.
There must be at least one electrocution hazard warning conspicuously posted in the cab so that it
is in view of the operator and at least two on the outside of the equipment.
No part of the equipment, load line, or load (including rigging and lifting accessories) is allowed
below a power line unless the employer has confirmed that the utility owner/operator has de-
energized and (at the worksite) visibly grounded the power line, except where one of the
following exceptions applies:
9.6.4.1 The work is covered by 29 CFR 1926, Subpart V, Power Transmission and Distribution.
9.6.4.2 For equipment with non-extensible booms: The uppermost part of the equipment, with the boom
at true vertical, would be more than 20 feet below the plane of the power line or more than the
Table 9-2 minimum clearance distance below the plane of the power line.
9.6.4.3 For equipment with articulating or extensible booms: The uppermost part of the equipment, with
the boom in the fully extended position, at true vertical, would be more than 20 feet below the
plane of the power line or more than the Table 9-2 of this section minimum clearance distance
below the plane of the power line.
9.6.4.4 The employer demonstrates that compliance with this prohibition is infeasible and the work meets
the requirements of paragraph 9.6.8, Power Line Safety (all voltages) equipment operation
closer than Table 9-2 zone.
9.6.5 Power line safety (up to 350 kV) during assembly and disassembly (Ref: 1926.1407)
Before assembling or disassembling equipment, determine if any part of the equipment, load line,
or load (including rigging and lifting accessories) could get, in the direction or area of
assembly/disassembly, closer than 20 feet to a power line during the assembly/disassembly
process. If so, the requirements in Option (1), Option (2), or Option (3) under paragraph 9.5.2.6.2
must be followed.
Assembly/disassembly below power lines prohibited. No part of a crane/derrick, load line, or
load (including rigging and lifting accessories), whether partially or fully assembled, is allowed
below a power line unless the employer has confirmed that the utility owner/operator has de-
energized and (at the worksite) visibly grounded the power line.
Assembly/disassembly inside Table 9-2 clearance is prohibited. No part of a crane/derrick, load
line, or load (including rigging and lifting accessories), whether partially or fully assembled, is
allowed closer than the minimum approach distance under Table 9-2 to a power line unless the
PIC has confirmed that the utility owner/operator has de-energized and (at the worksite) visibly
grounded the power line.
9.6.6 Power line safety (up to 350 kV) during equipment operation (ref: 1926.1408)
9.6.6.1 Training. The employer must train each operator and crew member assigned to work with the
equipment per Chapter 6
9.6.6.2 Hazard Assessment. Before beginning equipment operations, the employer must conduct a
hazard assessment to include:
9.6.6.2.1 Identify the work zone by either:
Demarcating boundaries (such as with flags, or a device such as a range limit device or
range control warning device) and prohibiting the operator from operating the equipment
past those boundaries
Defining the work zone as the area 360 degrees around the equipment, up to the
equipment's maximum working radius
9.6.6.2.2 Determine if any part of the equipment, load line or load (including rigging and lifting
accessories), if operated up to the equipment's maximum working radius in the work zone, could
get closer than 20 feet to a power line. If so, the employer must meet the requirements in Option
(1), Option (2), or Option (3), as follows:
Option (1) De-energize and ground. Confirm from the utility owner/operator that the
power line has been de-energized and visibly grounded at the worksite.
Option (2) - Maintain 20 foot clearance. Ensure that no part of the equipment, load line,
or load (including rigging and lifting accessories), gets closer than 20 feet to the power
line by implementing the encroachment precautions specified in paragraph 9.6.6.3.
Option (3) Maintain Table 9-2 clearance.
o Determine the line's voltage and the minimum approach distance permitted under
Table 9-2.
o Determine if any part of the equipment, load line or load (including rigging and
lifting accessories), while operating up to the equipment's maximum working radius
in the work zone, could get closer than the minimum approach distance of the power
line permitted under Table 9-2. If so, then the encroachment precautions in paragraph
9.6.6.3 are required to ensure that no part of the equipment, load line, or load
(including rigging and lifting accessories), gets closer to the line than the minimum
approach distance.
9.6.6.3 Preventing encroachment/electrocution. Where encroachment precautions are required, all of
the following requirements must be met:
9.6.6.3.1 Conduct a planning meeting with the operator and the other workers who will be in the area of
the equipment or load to review the location of the power line(s), and the steps that will be
implemented to prevent encroachment/electrocution.
9.6.6.3.2 If tag lines are used, they must be non-conductive.
9.6.6.3.3 Erect and maintain an elevated warning line, barricade, or line of signs, in view of the operator,
equipped with flags or similar high-visibility markings, at 20 feet from the power line (if using
Option (2) of this section) or at the minimum approach distance under Table 9-2 (if using Option
(3) of this section).
NOTE: If the operator is unable to see the elevated warning line, a dedicated spotter must be used as
described below in paragraph 9.6.6.3.4 in addition to implementing another one of the other
measures described in that paragraph.
9.6.6.3.4 Implement at least one of the following measures:
A proximity alarm set to give the operator sufficient warning to prevent encroachment.
A dedicated spotter who is in continuous contact with the operator. Where this measure is
selected, the dedicated spotter must:
o Be equipped with a visual aid to assist in identifying the minimum clearance
distance. Examples of a visual aid include, but are not limited to: A clearly visible
line painted on the ground; a clearly visible line of stanchions; a set of clearly visible
line-of-sight landmarks (such as a fence post behind the dedicated spotter and a
building corner ahead of the dedicated spotter).
o Be positioned to effectively gauge the clearance distance.
o Where necessary, use equipment that enables the dedicated spotter to communicate
directly with the operator.
o Give timely information to the operator so that the required clearance distance can be
maintained.
A device that automatically warns the operator when to stop movement, such as a range
control warning device. Such a device must be set to give the operator sufficient warning
to prevent encroachment.
A device that automatically limits range of movement, set to prevent encroachment.
An insulating link/device installed at a point between the end of the load line (or below)
and the load.
9.6.6.3.5 The requirements of paragraph 9.6.6.3 above do not apply to work covered by OSHA 1926
Subpart V Power Distribution and Transmission.
barricade from being at least 10 feet away, the barricade must be as far from the equipment as
feasible.
9.6.8.4.9 Limit worker contact. Workers other than the operator must be prohibited from touching the
load line above the insulating link/device and crane. Operators remotely operating the equipment
from the ground must use either wireless controls that isolate the operator from the equipment or
insulating mats that insulate the operator from the ground.
9.6.8.4.10 Only personnel essential to the operation are permitted to be in the area of the crane and load.
9.6.8.4.11 The equipment must be properly grounded.
9.6.8.4.12 Insulating line hose or cover-up must be installed by the utility owner/operator except where
such devices are unavailable for the line voltages involved.
9.6.8.5 Written procedures developed to comply with paragraph 9.6.8.4 must be documented and
immediately available on-site.
9.6.8.6 The equipment user and utility owner/operator (or registered professional engineer) must meet
with the equipment operator and the other workers who will be in the area of the equipment or
load to review the procedures that will be implemented to prevent breaching the minimum
approach distance established in paragraph 9.6.8.3 and prevent electrocution.
9.6.8.7 The procedures developed to comply with paragraph 9.6.8.4 must be implemented.
9.6.8.8 The utility owner/operator (or registered professional engineer) and all employers of employees
involved in the work must identify one person who will direct the implementation of the
procedures. The person identified in accordance with this paragraph must direct the
implementation of the procedures and must have the authority to stop work at any time to ensure
safety.
9.6.8.9 If a problem occurs implementing the procedures being used to comply with paragraph (d) of
this section, or indicating that those procedures are inadequate to prevent electrocution, the
employer must safely stop operations and either develop new procedures to comply with
paragraph (d) of this section or have the utility owner/operator deenergize and visibly ground or
relocate the power line before resuming work.
9.6.8.10 Devices originally designed by the manufacturer for use as a safety device, operational aid, or a
means to prevent power line contact or electrocution, when used to comply with this section,
must comply with the manufacturer's procedures for use and conditions of use.
9.6.8.11 The employer must train each operator and crew member assigned to work with the equipment in
accordance with Chapter 6,
9.6.9 Power line safety--while traveling under or near power lines with no load. (Ref: 1926.1411)
This section establishes procedures and criteria that must be met for equipment traveling under or near a
power line with no load. Equipment traveling with a load is governed by paragraphs 9.5.2.6
through 9.5.2.9 as appropriate.
9.6.9.1 The employer must ensure that:
9.6.9.1.1The boom/mast and boom/mast support system are lowered sufficiently to meet the requirements
of this paragraph.
9.6.9.1.2 The clearances specified in Table T of this section are maintained.
9.6.9.1.3 The effects of speed and terrain on equipment movement (including movement of the
boom/mast) are considered so that those effects do not cause the minimum clearance distances
specified in Table T of this section to be breached.
9.6.9.1.4 Dedicated spotter. If any part of the equipment while traveling will get closer than 20 feet to the
power line, the employer must ensure that a dedicated spotter who is in continuous contact with
the driver/operator is used. The dedicated spotter must:
Be positioned to effectively gauge the clearance distance.
Where necessary, use equipment that enables the dedicated spotter to communicate
directly with the operator.
Give timely information to the operator so that the required clearance distance can be
maintained.
9.6.9.1.5 Additional precautions for traveling in poor visibility. When traveling at night, or in conditions
of poor visibility, the employer must also ensure that:
The power lines are illuminated or another means of identifying the location of the lines
is used.
A safe path of travel is identified and used.
TABLE 9-3MINIMUM CLEARANCE DISTANCES WHILE TRAVELING WITH NO LOAD
Voltage While travelingminimum clearance distance
(nominal, kV, alternating current) (feet)
up to 0.75 4
over .75 to 50 6
over 50 to 345 10
over 345 to 750 16
Over 750 to 1,000 20
Over 1,000 (as established by the utility owner/operator or registered
professional engineer who is a qualified person with
respect to electrical power transmission and
distribution).
NOTE: Exhibit 9.1 thru 9.4 are intended to be a sample forms only. The equipment manufacturers
inspection/testing criteria supersede any other criteria. In cases where the equipment manufacturer does
not include inspection/testing criteria, other forms developed to facilitate required inspection/testing are
acceptable.
Exhibit 9.3 Mobile Crane Frequent Inspection Report (Sample Forms, 2 pages)
Exhibit 9.4 Mobile Crane Periodic Inspection Report (Sample Forms, 3 Pages)
This chapter implements the requirements of ANSI/ITSDF B56.1 (Safety Standard for powered
Industrial Trucks Low Lift and High lift Trucks) and B56.6 (Rough Terrain Fork Lift Trucks),
and ANSI/UL 558 (Internal-Combustion-Engine-Powered Industrial Trucks) and 583 (Electric-
Battery-Powered Industrial Trucks).
10.1 GENERAL
This chapter specifies operation, inspection, testing, and maintenance requirements for industrial
trucks controlled by a riding or walking operator and powered by electric motors or internal-
combustion engines. (See Exhibit 10.1 at the end of this chapter for examples of powered
industrial trucks.) Guidelines may also be taken from this chapter regarding pallet trucks and
other small miscellaneous non-powered lift trucks (see Exhibit 10.2 at the end of this chapter),
but training, operating, maintenance, inspection, and testing requirements for non-powered
equipment shall be based on the manufacturers instructions and recommendations.
10.1.1.1 Summary
Only trained and authorized persons shall be permitted to operate a powered industrial truck.
Operators of powered industrial trucks shall be qualified as to visual, auditory, physical, and
mental ability to operate the equipment safely according to paragraph 10.1.1.2 and all other
applicable parts of this chapter.
10.1.1.2 Operator Training
10.1.1.2.1 Personnel who have not been trained to operate powered industrial trucks may operate a truck
for the purposes of training only, and only under the direct supervision of the trainer (OJT, see
paragraph 6.2.2). This training should be conducted in an area away from other trucks, obstacles,
and pedestrians. Management may allow previously qualified or experienced personnel to bypass
OJT and undergo OJE.
10.1.1.2.2 The operator training program should include the users policies for the site where the trainee
will operate the truck, the operating conditions for that location, and the specific truck the trainee
will operate. The training program shall be presented to all new operators regardless of previous
experience.
10.1.1.2.3 The training program shall inform the trainee of the following:
The primary responsibility of the operator is to use the powered industrial truck safely
following the instructions given in the training program.
Unsafe or improper operation of a powered industrial truck can result in
o Death or serious injury to the operator or others
o Damage to the powered industrial truck or other property
10.1.1.2.4 The training program shall emphasize safe and proper operation to avoid injury to the operator
and others and prevent property damage, and shall cover the following areas:
Fundamentals of the powered industrial truck(s) the trainee will operate, including
o Proper pre-shift inspection and approved method for removing from service a truck
that is in need of repair
o Load handling techniques: lifting, lowering, picking up, placing, tilting
o Traveling, with and without loads; turning corners
o Parking and shutdown procedures
o Other special operating conditions for the specific application
Operating safety rules and practices, including:
o Provisions of this handbook in paragraph 10.5.1 to 10.5.4 address operating safety
rules and practices
o Provisions of this Standard in paragraph 10.3.3 address care of the truck
o Other rules, regulations, or practices specified by the employer at the location where
the powered industrial truck will be used
Operational training practice, including:
o If feasible, practice in the operation of powered industrial trucks shall be conducted
in an area separate from other workplace activities and personnel
o Training practice shall be conducted under the supervision of the trainer
o Training practice shall include actual operation or simulated performance of all
operating tasks such as load handling, maneuvering, traveling, stopping, starting, and
other activities under the conditions that will be encountered in the use of the truck
10.1.1.3 Testing, Retraining, and Enforcement
10.1.1.3.1 On-the-job-evaluations, OJEs, shall be conducted by the designated On-The-Job Performance
Evaluator (OJPE) (see paragraph 6.2.14). OJPEs shall evaluate each operator and certify in
writing that the operator has demonstrated to them that they have the necessary knowledge,
meeting the requirements of the ANSI/ITSDF B56.1, and skills to operate the equipment safely
before deeming the operator qualified. This document shall become part of the operators training
record. Contractors, facilities, and/or organizations may choose to implement facility-specific
OJT and/or OJE requirements.
10.1.1.3.2 Operators shall be retrained when new equipment is introduced, existing equipment is
modified, operating conditions are changed, or an operators performance is unsatisfactory.
10.1.1.3.3 Operators qualification is for a period not to exceed 3 years, unless the qualification is revoked
sooner by the employees manager.
Rated capacity is the maximum weight the truck can transport and stack at a specified load center and for
a specified load elevation. Trucks shall not be used or tested above their rated capacities.
Every truck shall have appended to it a durable, corrosion-resistant nameplate(s), legibly inscribed with
the following information:
10.1.3.1 Truck model and truck serial number.
10.1.3.2 Weight of truck.
10.1.4 Attachments
Attachments almost always affect rated capacity of the truck. When a forklift truck is equipped
with an attachment, the rated capacity of the truck/attachment combination shall be established by
the truck manufacturer. Capacity, operation, and maintenance instruction plates, tags, or decals
shall be changed accordingly.
10.1.4.1 The rated capacity of an attachment/truck combination shall not be exceeded.
10.1.4.2 On every removable attachment (excluding fork extensions see paragraph 10.1.4.3), a corrosion-
resistant nameplate with the following information is required:
10.1.4.2.1 Model number
10.1.4.2.2 Serial number on hydraulically actuated attachments
10.1.4.2.3 Maximum hydraulic pressure (on hydraulically actuated attachments)
10.1.4.2.4 Weight
10.1.4.2.5 Capacity
10.1.4.2.6 The following instructions (or equivalent); Capacity of truck and attachment combination may
be less than capacity shown on attachment. Consult truck nameplate.
10.1.4.3 Fork extensions:
10.1.4.3.1 Should not be longer than 150% of the supporting forks length.
10.1.4.3.2 Each fork extension shall be capable of supporting a uniformly distributed, or equivalent load
of three times its rated capacity when mounted on a fork of the specified size. No permanent
deformation shall be produced by the application of this test load after having removed the effects
of any local manufacturing irregularities by up to three preliminary applications of the test load.
10.1.4.3.3 For purpose of rating, the rated load center of the fork extension should be at 50% of the fork
extension load supporting length.
10.1.4.3.4 Each fork extension shall be clearly stamped with its individual load rating and supporting fork
size in an area readily visible and not subject to wear. For example, 4400 lbs (2000 kg) x 24 in
(600 kg) 3 in (80 mm) x 7 in (180 mm) x 32 in (800 mm) means a 4400 lb (2000 kg) load at a
24 in (600 mm) load center with a recommended supporting fork size of 3 in (80 mm) x 7 in (180
mm) and not less than 32 in (800 mm) long.
10.1.4.3.5 Fork extensions shall be designed to avoid unintentional disengagement from the forks. Lateral
clearance shall not exceed .5 in (12 mm) between fork and extension.
NOTE: The above information concerning fork extensions should be provided by the attachment
manufacturer.
10.1.5 Modifications
steering knobs may be used. When used, steering knobs shall be of a type that can be engaged by
the operators hand from the top, and shall be within the periphery of the steering hand wheel.
10.1.5.2.12 Batteries used in electric trucks shall comply with the minimum/maximum battery weight
range shown on the truck nameplate.
10.1.6.1 Every truck shall be equipped with an operator-controlled horn, whistle, gong, or other sound-
producing device(s).
10.1.6.2 The using organization shall determine if operating conditions require the truck to be equipped
with additional sound-producing or visual devices (such as lights or blinkers), and shall be
responsible for providing and maintaining such devices. Backup or motion alarms that sound
continuously may be warranted in special cases, but generally are less effective than operator-
controlled devices.
An overhead guard is intended to offer protection to the operator from falling objects, but it
cannot protect against every possible impact. Therefore, it should not be considered a substitute
for good judgment and care in load handling.
10.1.7.1 High lift rider trucks, including order picker trucks, shall be equipped with an overhead guard
manufactured in accordance with ASME B56.1, unless the following conditions are met:
10.1.7.1.1 Vertical movement of the lifting mechanism is restricted to 72 in. (1800 mm) or less from the
ground.
10.1.7.2 The truck will be operated only in an area where:
10.1.7.2.1 The bottom of the top tiered load is not higher than 72 in. (1800 mm) and the top is not more
than 120 in. (3000 mm) from the ground where tiered.
10.1.7.2.2 Only stable (preferably interlocked, unitized or containerized) loads are handled.
10.1.7.2.3 There is protection against falling objects from adjacent high stack areas.
10.1.7.3 Rough terrain forklift trucks shall be fitted with an overhead guard manufactured in accordance
with ASME B56.6.
Powered forklift trucks for operation in fire hazard areas shall be of the type recommended in
ANSI/NFPA 505 (Powered Industrial Trucks, Type Designation and Areas of Use).
10.1.9.1 The operation of forklift trucks may affect the concentrations of carbon monoxide and oxygen in
the work location. Concentrations of these materials in the work location must meet Z-1 Limits
for Air Contaminants, Occupational Safety and Health Standards for General Industry.
10.1.9.2 Where general lighting is less than 2 lumens per square foot, auxiliary directional lighting shall
be provided on the truck.
TYPE DESCRIPTION
DS Diesel-powered units that are provided with all the requirements for the type D units and that
have additional safeguards to the exhaust, fuel, and electrical systems
DY diesel-powered units that have all the safeguards of the type DS units except that they do not
have any electrical equipment, including ignition; they are equipped with temperature-
limitation features
ES Electrically powered units that are provided with all the requirements for the type E units and
that have additional safeguards to the electrical system to prevent emission of hazardous
sparks and to limit surface temperatures
EE Electrically powered units that are provided with all the requirements for the type E and ES
units, and that also have electric motors and all other electrical equipment completely
enclosed
EX Electrically powered units that differ from type E, ES, or EE units in that the electrical fittings
and equipment are designed, constructed, and assembled so that the units may be used in
atmospheres containing specifically named flammable vapors, dusts, and, under certain
conditions, fibers; type EX units are specifically tested and classified for use in Class I, Group
D, or for Class II, Group G locations as defined in NFPA 70, National Electrical Code.
GS Gasoline-powered units that, in addition to all the requirements for the type G units, are
provided with additional safeguards to the exhaust, fuel, and electrical systems
LPS Liquefied-petroleum-gas-powered units that, in addition to the requirements for the type LP
units, are provided with additional safeguards to the exhaust, fuel, and electrical systems
The atmosphere or location where the powered forklift is to be used shall be classified. Location
classifications are described below:
Class I Locations in which flammable gases or vapors are present or may be present in the air
in quantities sufficient to produce explosive or ignitable mixtures.
Class II Locations that are hazardous because of the presence of combustible dust.
Class III Locations where easily ignitable fibers or filings are present but are not likely to be
suspended in quantities sufficient to produce ignitable mixtures.
Unclassified Locations not possessing atmospheres defined as Class I, II, or III locations.
10.3 INSPECTIONS
10.3.1.1 Instructions for pre-operational inspections shall be readily available to the operator. It is
recommended that the instructions be attached to the equipment. Standard instructions will be
suitable for most forklift trucks; however, operating conditions may require additional
instructions. A sample Pre-operational inspection checklist is included as Exhibit 10.3, which
appears at the end of this chapter.
10.3.1.2 Before operating the truck, check its condition, giving special attention to the following:
Condition of the tires
Prior to initial use, all new, or newly arrived rental equipment, or modified forklifts shall be
inspected by a qualified inspector to ensure compliance with the provisions of this chapter. For
new equipment, an initial inspection shall verify that requirements of the purchase order (or rental
agreement) have been met and that the equipment is suitable for its intended use. This inspection
shall be documented and should be retained in the forklift trucks history file. A sample load test
and inspection form is provided as Exhibit 10.4, which appears at the end of this chapter. This
form is intended to be a sample only and is not intended to be mandatory.
Inspection and maintenance of powered forklift trucks shall be performed in conformance with the
following practices:
10.3.3.1 The inspection and maintenance program shall follow the manufacturers recommended
procedures. If equipment maintenance or inspection procedures deviate from published
manufacturer's recommendations, the alternate procedures shall be approved in advance by the
manufacturer or another qualified person and be kept readily available.
10.3.3.2 Only trained and authorized personnel shall be permitted to inspect, maintain, repair, and adjust
forklift trucks.
10.3.3.3 No repairs shall be made while the truck is in a hazardous (explosive/classified) area.
10.3.3.4 Inspect brakes, steering mechanisms, control mechanisms, warning devices, lights, governors,
lift-overload devices, guards, and safety devices regularly and maintain them in a safe-operating
condition.
10.3.3.5 Carefully inspect all parts of lift and tilt mechanisms and frame members and maintain them in a
safe-operating condition.
10.3.3.6 Check for suspect/counterfeit parts (see Terminology and Definitions, Chapter 1).
10.3.3.7 For special trucks or devices designed and approved for operation in hazardous areas, ensure that
the original, approved safe-operating features are preserved by maintenance.
10.3.3.8 Check fuel systems for leaks and for the proper condition of the parts. Give special
consideration in the case f a fuel system leak. Take action to prevent use of the truck until the
leak has been corrected.
10.3.3.9 Inspect and maintain all hydraulic systems. Check tilt cylinders, valves, and other similar parts
to ensure that drift or leakage has not developed to the extent that it would create a hazard.
10.3.3.10 Maintain capacity, operation safety, and maintenance-instruction plates, tags, or decals in
legible condition.
10.3.3.11 Inspect and maintain batteries, motors, controllers, limit switches, protective devices, electrical
conductors, and connections. Pay special attention to the condition of electrical insulation.
10.3.3.12 Those repairs to the fuel and ignition systems of industrial trucks which involve fire hazards
shall be conducted only in locations designated for such repairs.
10.3.3.13Trucks in need of repairs to the electrical system shall have the battery disconnected prior to
such repairs.
10.3.3.14 Water mufflers shall be filled daily or as frequently as is necessary to prevent depletion of the
supply of water below 75% of the filled capacity. Vehicles with mufflers having screens or other
parts that may become clogged shall not be operated while such screens or parts are clogged.
Any vehicle that emits hazardous sparks or flames from the exhaust system shall immediately be
removed from service, and not returned to service until the cause for the emission of such sparks
and flames has been eliminated.
10.3.3.15 When temperature of any part of any truck is found to be in excess of its normal operating
temperature, the vehicle shall be removed from service and not returned to service until the cause
for such overheating has been eliminated.
10.3.3.16 Industrial trucks originally approved for the use of gasoline for fuel may be converted to
liquefied petroleum gas fuel provided the complete conversion results in a truck which embodies
the features specified for LP or LPS designated trucks. Conversion equipment and the
recommended method of installation shall be approved by the manufacturer.
10.3.3.17 All parts that require replacement shall be replaced only with parts that are equivalent, in
regards to safety, to those used in the original design.
10.3.3.18 Attachments shall be included in a scheduled maintenance/inspection program. Inspection steps
shall be tailored for the attachment. Load-bearing components shall be examined for deformation
and load-bearing welds shall be visually examined for cracks. Mechanical or hydraulic
components shall be inspected and maintained in accordance with the manufacturers
instructions.
10.3.3.19 Attachments shall be inspected not less than annually and the inspection should be documented.
10.3.3.20 Hooks that are included as part of attachments shall be inspected as specified for hooks on
cranes/hoists (see Chapter 13.0, Load Hooks).
10.3.4 Forks
10.3.5.1 Facilities shall be provided for flushing and neutralizing spilled electrolyte, for fire protection,
for protecting charging apparatus from damage by trucks, and for adequate ventilation for
dispersal of fumes from gassing batteries.
10.3.5.2 A conveyor, overhead hoist, or equivalent material handling equipment shall be provided for
handling batteries.
10.3.5.3 Reinstalled batteries shall be properly positioned and secured in the truck.
10.3.5.4 A carboy tilter or siphon shall be provided for handling electrolyte.
10.3.5.5 When introducing electrolyte into batteries, acid shall be poured into water; water shall not be
poured into acid.
10.3.5.6 Trucks shall be properly positioned and brake applied before attempting to change or charge
batteries.
10.3.5.7 Care shall be taken to assure that vent caps are functioning. The battery (or compartment)
cover(s) shall be open to dissipate heat.
10.3.5.8 Smoking shall be prohibited in the charging area.
10.3.5.9 Precautions shall be taken to prevent open flames, sparks or electric arcs in battery charging
areas.
10.3.5.10 Tools and other metallic objects shall be kept away from the top of uncovered batteries
10.3.6.1 A history file should be maintained for each forklift truck. The history file should contain
information necessary to operate, maintain, test, and evaluate the forklift truck. A typical history
file would contain the following types of documentation, as applicable:
10.3.6.1.1 Manufacturers operation and maintenance manuals.
10.3.6.1.2 Waivers applicable to the forklift truck.
10.3.6.1.3 Documentation for replacement forks.
10.3.6.1.4 Documentation from the manufacturer authorizing modifications to the forklift truck.
10.3.6.1.5 Inspection procedures and inspections records.
10.3.6.1.6 Records of repair, modification, and overhaul.
10.3.6.1.7 Fork inspection records, including record of fork repair.
10.3.6.1.8 Authorization from truck manufacturer to use specifically identified attachments.
NOTE: For forklift trucks on rental, ensure that a suitable maintenance and inspection program is
established for the duration of the rental period. For rental equipment onsite for 6 months or less,
a history file is not recommended.
10.4 TESTING
10.4.1.4 Forklift trucks shall be load tested by or under the direction of a qualified person and in
accordance with the manufacturers recommendations.
10.4.1.5 Test weights shall be accurate within 5%, +0% of stipulated values.
10.4.1.6 After a load test is performed, a written report shall be furnished by the qualified person that
shows test procedures, and confirms the adequacy of repairs or alterations. Test reports shall be
retained in the trucks history file.
A fork that has undergone repair, other than repair or replacement of positioning locks or
marking, shall be subject to a load test as described in ASME B56.1, paragraph 7.26, Forks,
Item 3, which lists loading and method of test for forks; except for the test load, which shall
correspond to 250% of the rated capacity marked on the fork.
Load capacity of an attachment shall be verified by the manufacturer or by a load test at 100%
capacity that is performed onsite. Load tests are not routinely required since a catalog cut, users
manual, decals on attachment, or other manufacturers data serves as capacity verification.
10.5 OPERATIONS
The following requirements shall be observed by the operator when operating forklift trucks:
10.5.1.1 General
10.5.1.1.1 Safe operation is the responsibility of the operator. Report all accidents and near misses
promptly.
10.5.1.1.2 The operator shall develop safe working habits and also be aware of hazardous conditions in
order to protect himself, other personnel, the truck, and other material.
10.5.1.1.3 The operator shall be familiar with the operation and function of all controls and instruments
before operating the truck.
10.5.1.1.4 Before operating any truck, the operator shall be familiar with unusual operating conditions
which may require additional safety precautions or special operating instructions.
10.5.1.1.5 Be certain the truck has successfully passed a pre-use inspection.
10.5.1.1.6 Do not start or operate the truck, any of its functions or attachments, from any place other than
from the designated operators position.
10.5.1.1.7 Keep hands and feet inside the operators designated area or compartment. Do not put any part
of the body outside the operator compartment of the truck.
10.5.1.1.8 Never put any part of the body within the reach mechanism of the truck or other attachments.
10.5.1.1.9 Avoid reaching through the mast for any purpose.
10.5.1.1.10 To safeguard pedestrians, understand the trucks limitations and observe the following
precautions:
Do not drive a truck up to anyone standing in front of an object.
Ensure that personnel stand clear of the rear swing area before conducting turning
maneuvers.
Exercise particular care at cross aisles, doorways, and other locations where pedestrians
may step into the path of travel of the truck.
Do not allow anyone to stand or pass under the elevated portion of any truck, whether
empty or loaded.
10.5.1.1.11 Do not permit passengers to ride on powered industrial trucks unless a safe place to ride has
been provided by the manufacturer.
10.5.1.1.12 Ensure that fire aisles, access to stairways, and fire equipment is kept clear.
10.5.1.1.13 A powered industrial truck is considered unattended when the operator is more than 25 ft. (7.6
m) from the truck, which remains in his view, or whenever the operator leaves the truck and it is
not in his view.
10.5.1.1.14 Before leaving the operators position, the operator shall perform the following:
Bring truck to a complete stop.
Place directional controls in neutral.
Apply the parking brake.
Fully lower load-engaging means, unless supporting an elevated platform.
10.5.1.1.15 In addition, when leaving the truck unattended the operator shall perform the following:
Stop the engine or turn off the controls.
If the truck must be left on an incline, block the wheels.
Fully lower the load-engaging means.
10.5.1.1.16 Maintain a safe distance from the edge of ramps, platforms, and other similar working
surfaces. Do not move railroad cars with a powered industrial truck.
10.5.1.1.17 Do not use a truck for operating or closing railroad car doors except as follows:
Unless the truck utilizes a device specifically designed for opening and closing railroad
car doors and the operator is trained in its use.
The design of the door-opening device shall require the truck to travel parallel to the
railroad car, with the force applied in a direction parallel with the door travel.
Care should be exercised when engaging the railroad car door with the door opening
device, in order to prevent damage to the doors and/or fork truck by heavy impact forces.
The entire door opening operation shall be in full view of the operator.
The fork truck shall always be positioned to safeguard the dock attendant while removing
the door lock pin.
Whenever a railroad car door requires an abnormal force to open, the truck operator shall
report the condition to his supervisor.
10.5.1.1.18 Wheel stops, hand brakes, or other recognized positive protection shall be provided to prevent
railroad cars from moving during loading or unloading operations.
10.5.1.1.19 Consider both the truck and load weight when operating in railcars and semitrailers.
10.5.1.1.20 Inspect floors on trucks, boxcars, unfamiliar ramps, or platforms before start of operation.
10.5.1.1.21 Other workers should not be inside the truck when the forklift truck is performing loading or
unloading operations. Load arrangements and spacing issues should be determined before the
forklift enters the truck.
10.5.1.1.22 Fixed jacks or supports may be needed to prevent upending or corner dipping when powered
industrial trucks are driven on and off semitrailers that are not coupled to the tractor.
10.5.1.1.23 The brakes of highway trucks shall be set and wheel chocks placed under the rear wheels to
prevent the trucks from rolling while they are boarded.
10.5.1.1.24 Care shall be taken to not contact overhead installations such as lights, wiring, pipes, sprinkler
systems, etc. If in doubt, measure.
10.5.1.1.25 Motorized hand trucks shall not be ridden unless they are of the hand/rider design.
10.5.1.2 Traveling
10.5.1.2.1 Observe all traffic regulations and under all travel conditions, operate the truck at a speed that
will permit it to be brought to a stop in a safe manner. Unless facility-specific procedures state
otherwise, the guideline is: within plant buildings 5 mph; on plant roads 15 mph. Drive
slowly around curves.
10.5.1.2.2 Yield the right of way to pedestrians and emergency vehicles. Whenever possible, establish
eye contact with approaching pedestrians or vehicle drivers before continuing.
10.5.1.2.3 Do not pass another truck traveling in the same direction at intersections, blind spots, or at
other locations where vision is obstructed.
10.5.1.2.4 Slow down and sound horn at cross aisles and other locations where vision is obstructed.
10.5.1.2.5 Railroad tracks shall be crossed diagonally whenever possible.
10.5.1.2.6 Never travel with forks raised to unnecessary heights. Approximately 4 to 6 inches (10 to 15
cm) above floor level is adequate.
10.5.1.2.7 Do not park closer than 6 ft (1800 mm) to the nearest rail or a railroad track.
10.5.1.2.8 Face in the direction of travel, except if the load being carried obstructs forward view. In such
cases, travel with the load trailing.
10.5.1.2.9 When ascending or descending grades, ramps, and inclines:
In excess of 5% grade, drive loaded rider trucks with the load upgrade.
Use low gear or slowest speed control.
Operate unloaded trucks with the load-engaging means downgrade.
The load and load-engaging means shall be tilted back, if applicable and raised only as
far as necessary to clear the road surface.
Avoid turning if possible, and normally travel straight up and down.
10.5.1.2.10 While turning, be cautious of rear end swing and keep clear of the edge of loading docks.
10.5.1.2.11 Make starts, stops, turns, or direction reversals in a smooth manner s as not to shift load
and/or overturn the truck.
10.5.1.2.12 Do no indulge in stunt driving or horseplay.
10.5.1.2.13 Slow down for wet and slippery floors.
10.5.1.2.14 Before driving over a dock board or bridge plate, be sure that it is properly secured.
10.5.1.2.15 Drive carefully and slowly across the duckboard or bridge plate, and never exceed its rated
capacity.
10.5.1.2.16 Do not drive trucks onto any elevator unless specifically authorized to do so. In cases
operation are authorized:
Do not exceed the capacity of the elevator.
Approach elevators slowly, and then enter squarely after the elevator car is properly
leveled.
Once on the elevator, neutralize the controls, shut off the power, and set brakes.
It is advisable that all other personnel leave the elevator before truck is allowed to enter
or leave.
10.5.1.2.17 Unless a towing hitch is supplied by the manufacturer, do not use forklift trucks as tow trucks.
When a towing hitch is provided, use tow bars rather than wire rope for towing.
10.5.1.2.18 At the end of the operators shift, return the forklift truck to its assigned parking place, set
brakes, fully lower load-engaging means, place controls in neutral position, turn ignition off, and
secure the key.
10.5.1.2.19 Seat belt use, while operating a lift truck, is mandatory.
Only the operator-up high lift trucks have been designed to lift personnel. If a work platform is
used on forklift trucks designed and intended for handling materials, take the following
precautions:
10.5.2.1 Use a lift platform manufactured for the purpose of lifting personnel with a forklift truck. The
platform shall include:
10.5.2.1.1 A 4 in. (10 cm) minimum height toe plate provided on the work platform.
10.5.2.1.2 The floor of the platform located not more than 8 in. (20 cm) above the upper face of the
supporting truck fork blade.
10.5.2.1.3 A restraining means such as a guard rail or a means for securing personnel such as a body belt
or lanyard, whenever the platform can be elevated to a height greater than 48 inches (1200 mm).
NOTE: A guard rail shall have a height above the platform floor of 42 inches (1067 mm) nominal,
around its upper periphery and include a midrail.
10.5.2.1.4 An access opening in the guard rail may be hinged or removable, or chains may be used if
proper positioning is easily accomplished and secured condition is discernible.
10.5.2.1.5 Guard rails and access openings shall be capable of withstanding a concentrated force of 200 lb
(91 kg) in any direction.
10.5.2.1.6 Means to securely attach the platform to the lifting carriage or forks in such a manner that it
cannot slide or bounce off the forks.
10.5.2.1.7 Means to correctly locate the platform centered laterally on the truck.
10.5.2.1.8 Floor dimensions that neither exceed two times the load center distance listed on the truck
nameplate, measured parallel to the longitudinal center plane of the truck, nor have a width
greater than the overall width of the truck (measured across the load bearing tires) plus 10 in. (25
cm) on either side.
10.5.2.1.9 The following information should be prominently indicated on the platform:
Maximum load including personnel and equipment;
Weight of empty platform;
Minimum capacity of the truck on which the platform can be used.
10.5.2.2 The combined weight of the platform, load, and personnel shall not exceed one-half of the
capacity as indicated on the nameplate of the truck on which the platform is used.
10.5.2.3 Whenever a truck (except for high-lift order-picker trucks) is equipped with vertical hoisting
controls elevateable with the lifting carriage or forks, take the following additional precautions to
protect personnel:
10.5.2.3.1 Means shall be provided whereby personnel on the platform can shut off power to the truck.
10.5.2.3.2 Means shall be provided to render inoperative all operating controls on the elevating platform,
when the controls on the elevating platform have been selected for use; only one location of
controls shall be capable of being operated at one time.
10.5.2.3.3 Emergency-lowering means available at ground level should be provided; such means shall be
protected against misuse.
10.5.2.4 Take the following precautions whenever personnel are elevated with a forklift truck:
10.5.2.4.1 Ensure the truck has a firm and level footing.
10.5.2.4.2 Place all travel controls in neutral and set parking brake.
10.5.2.4.3 Before elevating personnel, mark area with cones or other devices to warn of work by elevated
personnel.
10.5.2.4.4 Lift and lower personnel smoothly, with caution, and only at their request.
10.5.2.4.5 Avoid overhead obstructions and electric wires.
10.5.2.4.6 Keep hands and feet clear of controls other than those in use.
10.5.2.4.7 Move truck and/or platform slowly, only for minor adjustments in horizontal positioning when
personnel are on the platform, and only at their request.
10.5.2.4.8 Ensure the mast is vertical do not operate on a side slope.
10.5.2.4.9 The platform is horizontal and never tilted forward or rearward when elevated.
10.5.2.4.10 Personnel are to remain on the platform floor. The use of railings, planks, ladders, etc., on the
platform for the purpose of achieving additional reach or height is prohibited.
10.5.2.4.11 Ensure approved fall protection equipment is used by personnel working from basket or
platform.
10.5.2.4.12 Ensure personnel and equipment on the platform do not exceed the available space.
10.5.2.4.13 Lower platform to floor level for personnel to enter and exit. Do not climb on any part of the
truck in attempting to enter or exit.
10.5.2.4.14 The operator shall remain in the control position of the forklift truck at all times.
10.5.2.4.15 Be certain that the lifting mechanism is operating smoothly throughout its entire lift height,
both empty and loaded, and that lift limiting devices and latches, if provided, are functional.
10.5.2.4.16 Means shall be provided to protect personnel from moving parts of the forklift truck that
present a hazard when the personnel platform is in the normal working position.
10.5.2.4.17 Overhead protection, as necessary for operating conditions, shall be provided.
10.5.2.4.18 Do not transport personnel from one location to another while they are on the work platform.
10.5.2.4.19 When not in the operating position, engage the parking brake and block the wheels.
10.5.2.4.20 Be certain that required restraining means such as railings, chains, cable, full body harness
with lanyards, or deceleration devices, etc., are in place and properly used.
10.5.3.1 Refueling
10.5.3.1.1 Refueling of forklifts shall be conducted in areas with good ventilation and away from any
ignition sources such as sparks, open flames, electrical arcs, etc.
10.5.3.1.2 Fire protection devices, such as fire extinguishers, shall be readily available in any refueling or
recharging areas.
10.5.3.1.3 Smoking is not permitted at any refueling or recharging area.
10.5.3.1.4 Refueling of gas and diesel engine forklifts shall be conducted outdoors due to the possibility
of spills and vapor accumulation.
10.5.3.1.5 Refueling shall not be conducted with the engine running. Properly dismount prior to
refueling.
10.5.3.1.6 Connect the bonding wire if required; otherwise, ensure the pump nozzle makes contact the
tank while filling. This will prevent static electricity that could cause a fire or explosion.
10.5.3.1.7 Avoid spillage. Spillage of oil or fuel shall be carefully washed away or completely
evaporated and the fuel tank cap replaced before restarting engine.
10.5.3.1.8 Trained personnel shall conduct refueling of liquefied petroleum gas (LPG) forklifts. Always
consult and follow the manufacturers instructions for LPG cylinder change out. As a minimum:
Close the main LPG cylinder valve.
Restart the forklift and allow it to run out of fuel; this will purge all LPG and pressure
from the lines.
After the engine stops, turn the ignition off, close the LPG valve and disconnect the
cylinder from the forklift.
Remove and replace the cylinder.
Reconnect the cylinder, open the LPG valve, and check for leaks.
10.5.3.2 Changing or Recharging Batteries
10.5.3.2.1 Trained personnel shall conduct battery charging and battery replacement. Always consult and
follow the manufacturers instructions for battery replacement or recharging.
10.5.3.2.2 Battery charging operations shall be conducted in adequately ventilated areas that are
designated for that purpose.
10.5.3.2.3 Smoking is prohibited in battery charging areas. No Smoking signs shall be posted in plain
view of incoming personnel.
10.5.3.2.4 Emergency eye/face and skin flushing and drenching facilities shall be provided.
10.5.3.2.5 Forklifts shall be properly positioned and dismounted before charging or replacing batteries.
10.5.3.2.6 Ensure vent caps are functioning properly. The battery compartment shall be open to dissipate
heat.
10.5.3.2.7 Facilities shall be provided for flushing and neutralizing spilled electrolyte.
10.5.3.2.8 A carboy tilter or siphon shall be provided for handling electrolyte.
10.5.3.2.9 When charging batteries, acid shall always be poured into water. Never pour water into acid.
10.5.3.2.10 An adequate lifting device, such as an overhead hoist or conveyor shall be available for
changing batteries.
10.5.3.2.11 Tools and other metallic objects shall be kept away from the top of uncovered batteries.
10.5.3.2.12 Precautions shall be taken to prevent open flames, sparks, or electric arcs in battery charging
areas.
10.5.4.1 Standard hand signals for use at AEDC shall be as specified in the latest edition of the ANSI
standards for the particular forklift being used (see Figure 10-5).
10.5.4.2 The operator shall recognize signals only from the designated signal person. However Obey a
STOP signal no matter who gives it.
10.5.4.3 For operations not covered by standard hand signals, special signals shall be agreed on in
advance by both the operator and the signal person, and should not conflict with the standard
signals.
INSPECTION: Forklifts shall be inspected when assigned to service and at least every 12 months
thereafter.
Prior to initial use, all new, modified, or extensively repaired forklifts shall be inspected.
Craftsmen shall initial all tests, work, and inspections completed below.
Qualified inspector shall verify inspections have been complete prior to load test.
CRAFTSMAN
INITIAL
____________ 1. Ensure capacity, operation, and maintenance-instruction plates, tags, or decals are
legible.
____________ 2. Check all hydraulic systems including tilt cylinders, valves, and other similar parts
to ensure drift has not developed.
____________ 3. Check fuel system for leaks and condition of parts. Special consideration shall be
given in the case of a leak in the fuel system. Immediate action shall be taken to take
the forklift out of service until the leak is corrected.
____________ 4. Check all parts of lift and tilt mechanisms and frame members to ensure safe
operating conditions, such as, but not limited to, hoist chain for damage and excessive
wear.
____________ 5. Check for proper tire inflation (where applicable). Check that tires are secured
properly and are level with each other.
____________ 6. Check batteries, motors, controllers, limit switches, protective devices, electrical
conductors and connections, with special attention paid to the condition of electrical
insulation.
____________ 7. Check brakes, steering mechanisms, warning devices, lights, governors, lift
overload devices, guards, and safety devices.
Qualified inspector shall use the criteria for Items 8, 9, and 10 to perform visual examination; or as
required by the manufacturer, liquid penetrant examination, or magnetic particle examination.
Acceptance: No cracks, linear indications, laps, or seams.
____________ 8. Check for forks being secured properly and level with each other.
____________ 9. Performs nondestructive test (NDT) on the right angle joint of the fork once every
12 months.
____________ 10. Performs NDT on the load or stress-bearing welds that attach the tines to the
forklift once every 12 months.
LOAD TEST
2. Forklifts in which load-sustaining parts have been altered, replaced, or repaired shall
be load tested prior to initial use.
Weight ________________________
2. Perform load test using the required weight (see Note 3).
3. Static Test: Forklift trucks shall demonstrate ability to withstand the appropriate test load for a period
of at least 10 min without permanent deformation or apparent damage. Load slippage for this equipment
shall not be greater than a maximum of 3 in. vertically and 1 in. horizontally at the cylinder.
This chapter provides requirements for the fabrication and use of wire rope and slings used in
hoisting and rigging.
11.1 GENERAL
11.1.1 The information in this section provides guidance for safely handling lifted loads. Diagrams are
used to illustrate hoisting and rigging principles and good and bad rigging practices. This is not a
rigging textbook; the information should be applied only by qualified riggers.
11.1.2 Wire rope and slings that have
been irreversibly damaged or
removed from service shall be
made useless for hoisting and
rigging operations before
being discarded.
11.1.3 Load tables are representative
only and are not exact for all
materials or all manufacturers.
11.4.4 Determine the weight of the
load:
11.1.4.1 From markings on the load.
11.1.4.2 By weighing, if the load is
still on a truck or railroad car.
11.1.4.3 From drawings or other
documentation.
11.1.4.4 By calculation, using the load
dimensions and the weights of
common materials in Table
11-1.
11.1.5 Determine the center of gravity
of the load as accurately as
possible:
11.1.5.1 From drawings or other
documentation.
11.5.1.2 From markings on the load. Table 11-1. Weights of common materials
11.5.1.3 By calculation.
11.1.6 Determine the best method to attach the load and select the appropriate lifting devices (e.g., wire-
rope, steel-chain, metal-mesh, or synthetic-web slings).
11.1.7 Bending a wire rope over a fixed object such as a pin or a shackle has an effect on the capacity of
the rope: The outside wires and strands of a bend have to stretch farther and therefore take a
greater percentage of the load.
11.1.8 There is a convenient method for estimating the efficiency of the rope as it passes over the bend.
This method uses the ratio (R) of the diameter (D) of the object (sheave, pin, corner) about which
the wire rope is being bent to the diameter (d) of the rope. The efficiency of the bend can then be
estimated using the formula shown in Figure 11-1. Note that the efficiency decreases quickly as
the ratio of the diameters decreases.
11.1.9 Aside from efficiency, there are other reasons to avoid sharp bends in wire rope, including physical
damage to the rope, reduction of service life, and damage to the object about which the rope is
bent.
11.1.10 When the ratio of the diameter of the bend to the nominal rope diameter (D/d ratio) is small, the
strength efficiency factor is lower than when the D/d ratio is relatively large. Load tables do not
take into account such factors as abnormal temperatures, excessive corrosion, and vibration.
11.1.11 Determine the appropriate ratings of the device to be used, allowing for:
11.1.11.1 The number of sling legs Note that a sling leg completely doubled back on itself constitutes
two sling legs.
11.1.11.2 The angle between the horizontal surface of the load and the sling leg The smaller the angle,
the smaller the lifting capacity of the equipment.
11.1.11.3 Wear The reduction in strength of the equipment due to normal wear.
11.2.1.1 In a right-lay rope, the strands twist to the right around the core like a conventional screw thread;
in a left-lay rope, the strands twist to the left.
11.2.1.2 A rope has a lang lay when the strands and the individual wires have the same lay direction.
When the strands and the wires have an opposite lay direction, the rope has a regular lay.
11.2.1.3 A standard wire rope, unless otherwise stated, is understood to be right regular lay. With few
exceptions, all wire rope is made right lay. Left-lay rope is a special-purpose rope.
11.2.1.4 Figure 11-2 shows ropes with right and left lays combined with regular and lang lays.
11.2.1.5 Lay length is the lengthwise distance measured along a wire rope in which a strand makes one
complete revolution about the ropes axis.
Wire rope consists of multistrand metal wires wrapped around a suitable core material. Wire-rope cores
are carefully designed and must be precisely manufactured to close tolerances to ensure a perfect
fit in the rope. The most common types of cores include the following:
11.2.2.1 Fiber Core (FC) or Sisal Core Sisalanna is the most common fiber that is used
in the manufacture of wire-rope cores. In smaller ropes, cotton and jute are
sometimes used for the core. (See illustration at right.)
11.2.2.2 Independent Wire-Rope Core (IWRC) The primary function of the core is to
provide adequate support for the strands. As the name implies, an IWRC is a
separate small-diameter wire rope that is used as the core for a larger wire rope.
When severe crushing or flattening of the rope is encountered, an IWRC is
usually specified. (See illustration at right.)
11.2.2.3 Strand Core This type of core has a single strand used as the core. This type is
generally confined to the smaller ropes as a substitute for IWRC. The strand core
may or may not have the same cross section as the surrounding strands. (See
illustration at right.)
11.2.3.1 - 6 x 9 Classification
Most applications can use a rope from this classification; it is the most versatile of all ropes made.
There are four varieties of 6 x 19 wire ropes with FCs and IWRCs as shown below:
Table 11-2 provides breaking strengths for 6 x 19 and 6 x 37 wire ropes with FC and IWRC
cores.
Table 11-2 Nominal strengths and weights for standard 6 x 19 and 6 x 37 classification ropes
11.3 SLINGS
11.3.1 General
11.3.1.1 Overview
11.3.1.1.1 Slings shall have a minimum design factor appropriate to the type of material as specified in
the appropriate section. Features that affect the rated capacity of the sling and that shall be
considered in calculating the design factor are:
Nominal breaking strength of material from which it is constructed.
Splicing or end-attachment.
Number of parts in the sling.
Type of hitch (e.g., straight pull, choker hitch, or basket hitch).
Angle of loading and load center of gravity.
Diameter of curvature around which the sling is bent.
11.3.1.1.2 The center of gravity of an object is a point around which the entire weight may be
concentrated. To make a level lift, the crane hook or point of suspension must be directly above
this point. While slight variations are usually permissible, if the crane hook is too far to one side
of the center of gravity, dangerous tilting will result and should be corrected at once. For this
reason, when the center of gravity is closer to one point of the sling attachment than to the other,
the slings must be of unequal length. Sling stresses and sling angles will also be unequal (see
Figure 11-3).
11.3.1.1.3 Rigging shall be configured such that slings do not reeve or slip through the hook. To attach
the load, locate the center of gravity, position the crane hook directly above the center of gravity,
and then rig the load so that it will lift level and true.
11.3.1.1.4 If a wire rope, nylon or chain sling is known to have been shock loaded; the component is to be
removed from service and destroyed (rendered useless).
Step 1: Using the Load angle factor (LAF) from Fig. 11-4 we find the LAF for 45 = 1.414
Step 2: Multiply the vertical load on one sling by the LAF. 500 lbs. X 1.414 = 707 lbs. on each leg
Explanation: Each of the two legs would lift 500 lb if a vertical lift were made. However, there is a
45 sling angle involved. Therefore, the 500-lb load would be multiplied by the load-angle factor in
the chart, giving a total of 707 lb (500 lb x 1.414) tension in each sling leg. Each sling leg, therefore,
must have a rated capacity of at least 707 lb.
When legs are not of equal length, use smallest H/L ratio.
NOTE: Load may be supported on only two legs while third leg
balances it. Therefore, the required SWL is determined by the
following:
When legs are not of equal length, use smallest H/L ratio.
NOTE: Load may be supported on only two legs while other two legs
balance it. Therefore, the required SWL is determined by the
following:
Proper care and usage are essential for maximum service and safety. Wire-rope slings shall be
protected from sharp bends and cutting edges by means of corner saddles, burlap padding, or
wood blocking. Overloading shall be avoided, as shall sudden dynamic loading that can build up
a momentary overload sufficient to break the sling.
11.3.1.6 Sling Storage
Personnel using slings shall ensure that they are stored properly as follows:
11.3.1.6.1 Slings should be stored in racks (preferably vertical) and in designated locations when not in
use. Do not store slings in a location (such as a job box) where they will be subjected to
mechanical damage, corrosive action, moisture, extreme heat, or kinking. Slings may require
segregated storage as determined on a case-by-case basis.
11.3.1.6.2 Before storage and periodically during storage, wipe slings clean to remove as much dirt and
abrasive grit as possible and relubricate wire rope and chain slings to extend their useful life.
Chains should not be lubricated when in use.
11.3.1.6.3 Do not store metal-mesh slings in areas where the temperature exceeds 550 F (288 C) or
200 F (93 C) if elastomer covered.
11.3.1.6.4 Do not store synthetic-web slings where the temperature exceeds 200 F (93 C).
11.3.2 Wire Rope Slings
11.3.2.1 General
11.3.2.1.1 In general, wire-rope slings are made up of 6 x 19 or 6 x 37 classification wire rope. Rotation-
resistant wire rope shall not be used for wire-rope slings. Different kinds of slings have been
developed for specific purposes. These are divided into different groups or types as follows:
Endless-loop slings (grommet construction) and single-part slings with single-rope legs,
double-rope legs, or multiple-part rope legs.
Two-leg bridle slings with single-rope legs, equalizing double-rope legs, or multiple-part
tope legs.
Three-leg bridle slings.
Four-leg bridle slings.
Special slings and combinations.
11.3.2.1.2 The total load that can be safely lifted with slings depends on the rating of the slings and the
manner in which they are attached to the load. Consult (load) Tables 11-3 through 11-11 and
Figure 11-7.
11.3.2.1.3 Braided slings are made by braiding ordinary wire ropes together, thus making them more
flexible than wire-rope slings. The size of a braided sling is determined by the diameter of one
wire rope and the number of ropes in the cross section of the slings.
11.3.2.1.4 The design factor for wire-rope slings shall be a minimum of 5:1 based upon breaking strength.
11.3.2.1.5 When a wire rope sling is used in a choker hitch, the normal angle formed in the rope body as it
passes through the choking eye is 120 or greater [do not confuse the choke angle with the angle
of inclination of the load (see Figure 11-7)]. Rated load in load capacity Tables 11-4 through 11-
9 are for angles of 120 or greater. For smaller angles, reduce the rated load to the % given in
Figure 11-7.
Table11-3. Rated Load for Single- and Two-Leg Slings 619 or 636 Classification.
Extra Improved Plow Steel (EIPS) Grade Fiber Core (FC) Wire Rope. Based on Design Factor = 5 and Rated Loads Expressed in Tons (2,000 lb)
Single-Leg Two-Leg Bridle Choker
Hitch
Type
Horizontal Angle Horizontal Angle
Vertical
Vertical Choker Vertical 60 45 30 60
Basket
Rope
Diameter, HT MS S HT&MS HT MS S HT MS S HT MS HT MS HT MS HT&MS HT&MS
in.
0.54 0.56 0.60 0.42 1.1 1.1 1.1 1.1 1.1 1.1 0.94 0.97 0.77 0.79 0.54 0.56 0.73 0.42
5
/16 0.83 0.87 0.94 0.66 1.7 1.7 1.7 1.7 1.7 1.7 1.4 1.5 1.2 1.2 0.83 0.87 1.1 0.66
3
/8 1.2 1.2 1.3 0.94 2.4 2.5 2.5 2.4 2.5 2.5 2.0 2.2 1.7 1.8 1.2 1.2 1.6 0.94
7
/16 1.6 1.7 1.8 1.3 3.2 3.4 3.4 3.2 3.4 3.4 2.7 2.9 2.2 2.4 1.6 1.7 2.2 1.3
2.0 2.2 2.4 1.6 4.0 4.4 4.4 4.0 4.4 4.4 3.5 3.8 2.9 3.1 2.0 2.2 2.9 1.6
9
/16 2.5 2.7 3.0 2.1 5.0 5.5 5.5 5.0 5.5 5.5 4.4 4.8 3.6 3.9 2.5 2.7 3.6 2.1
5
/8 3.1 3.4 3.7 2.6 6.2 6.8 6.8 6.2 6.8 6.8 5.3 5.9 4.4 4.8 3.1 3.4 4.5 2.6
4.3 4.8 5.2 3.7 8.6 9.7 9.7 8.6 9.7 9.7 7.4 8.4 6.1 6.8 4.3 4.8 6.3 3.7
7
/8 5.7 6.6 7.1 5.0 11 13 13 11 13 13 9.8 11 8.0 9.3 5.7 6.6 8.6 5.0
1 7.4 8.3 9.2 6.4 15 17 17 15 17 17 13 14 10 12 7.4 8.3 11 6.4
1 1/8 9.3 10 12 8.1 19 21 21 19 21 21 16 18 13 15 9.3 10 14 8.1
1 1/4 11 13 14 9.9 23 26 26 23 26 26 20 22 16 18 11 13 17 9.9
GENERAL NOTES:
HT = hand-tucked splice. MS = mechanical splice. S = swaged or poured socket. Rated loads based on minimum D/d ratio of 25/1.
(e) Rated load based on pin diameter no larger than natural eye width or less than the nominal sling diameter.
(f) For choker hitch, the angle of choke is 120 deg or greater.
Table 11-4 Rated Load for Three- and Four-Leg Slings 6x19 or 636 Classification
Extra Improved Plow Steel (EIPS) Grade Fiber Core (FC) Wire Rope Based on Design Factor = 5 and Rated Loads Expressed in Tons (2,000 lb)
Three-Leg Four-Leg
Hitch Type
GENERAL NOTES:
HT = hand-tucked splice.
MS = mechanical splice.
Rated loads based on minimum D/d ratio of 25/1.
Rated load based on pin diameter no larger than natural eye width or less than the nominal sling diameter.
Table 11-5 - Rated Load for Single-and Two-Leg Slings 619 or 636 Classification.
Extra Improved Plow Steel (EIPS) Grade Independent Wire Rope Core (IWRC) Wire Rope. Based on Design Factor = 5 and Rated Loads
Expressed in Tons (2,000 lb)
Single-Leg Two-Leg Bridle or Basket Choker
Hitch Type
Table 11-6 Rated Load for Three- and Four-Leg Slings 619 or 636 Classification
Extra Improved Plow Steel (EIPS) Grade Independent Wire Rope Core (IWRC) Wire Rope. Based on Design Factor = 5 and Rated Loads
Expressed in Tons (2,000 lb)
Three-Leg Four-Leg
GENERAL NOTES: HT = hand-ticked splice; MS = mechanical splice. Rated loads based on minimum D/d ratio of 25/1. Rated load based on pin diameter no
larger than natural eye width or less than the nominal sling diameter.
Table 11-7 Rated Load for Single- and Two-Leg Slings 619 or 636 Classification. Extra Extra Improved Plow Steel (EEIPS) Grade
Independent Wire Rope Core (IWRC) Wire Rope. Based on Design Factor = 5 and Rated Loads Expressed in Tons (2,000 lb)
Hitch
Type
Vertical
Vertical Choker Vertical 60 45 30 60 30
Basket
Rope
Dia-
HT MS S HT MS HT MS S HT MS HT MS HT MS HT MS HT MS HT MS
meter,
in.
0.60 0.71 0.74 0.46 0.52 1.2 1.4 1.4 1.2 1.4 1.0 1.2 0.84 1.0 0.60 0.71 0.80 0.90 0.46 0.52
5
/16 0.92 1.1 1.2 0.72 0.81 1.8 2.2 2.1 1.8 2.2 1.6 1.9 1.3 1.6 0.92 1.1 1.2 1.4 0.72 0.81
3
/8 1.3 1.6 1.7 1.0 1.2 2.6 3.2 3.1 2.6 3.2 2.3 2.7 1.8 2.2 1.3 1.6 1.8 2.0 1.0 1.2
7
/16 1.7 2.1 2.2 1.4 1.6 3.5 4.3 4.1 3.5 4.3 3.0 3.7 2.5 3.0 1.7 2.1 2.4 2.7 1.4 1.6
2.2 2.8 2.9 1.8 2.0 4.5 5.5 5.4 4.5 5.5 3.9 4.8 3.1 3.9 2.2 2.8 3.1 3.5 1.8 2.0
9
/16 2.8 3.5 3.7 2.3 2.6 5.6 7.0 6.8 5.6 7.0 4.8 6.1 3.9 5.0 2.8 3.5 4.0 4.5 2.3 2.6
5
/8 3.4 4.3 4.5 2.8 3.2 6.8 8.6 8.4 6.8 8.6 5.9 7.5 4.8 6.1 3.4 4.3 4.9 5.5 2.8 3.2
4.7 6.2 6.5 4.0 4.5 9.4 12 12 9.4 12 8.2 11 6.7 8.7 4.7 6.2 7.0 7.9 4.0 4.5
7
/8 6.2 8.3 8.8 5.5 6.1 12 17 16 12 17 11 14 8.8 12 6.2 8.3 9.4 11 5.5 6.1
1 8.1 11 11 7.1 8.0 16 22 21 16 22 14 19 11 15 8.1 11 12 14 7.1 8.0
1
1 /8 10 ... 14 8.9 ... 20 ... 26 26 ... 18 ... 14 ... 10 ... 15 ... 8.9 ...
1 13 ... 18 11 ... 25 ... 33 25 ... 22 ... 18 ... 13 ... 19 ... 11 ...
3
1 /8 15 ... 21 13 ... 30 ... 39 30 ... 26 ... 21 ... 15 ... 23 ... 13 ...
1 18 ... 25 16 ... 36 ... 46 36 ... 31 ... 25 ... 18 ... 27 ... 16 ...
5
1 /8 21 ... 29 18 ... 41 ... 54 41 ... 36 ... 29 ... 21 ... 31 ... 18 ...
1 24 ... 34 21 ... 48 ... 63 48 ... 42 ... 34 ... 24 ... 36 ... 21 ...
7
1 /8 27 ... 38 24 ... 55 ... 71 55 ... 47 ... 39 ... 27 ... 41 ... 24 ...
2 31 ... 43 27 ... 62 ... 80 62 ... 54 ... 44 ... 31 ... 47 ... 27 ...
GENERAL NOTES: HT = hand-tucked splice; MS = mechanical splice; S = swaged or poured socket.
Rated loads based on minimum D/d ratio of 25/1.
(e) Rated load based on pin diameter no larger than natural eye width or less than the nominal sling diameter.
(f) For choker hitch, the angle of choke is 120 deg or greater.
Table 11-8 Rated Load for Three- and Four-Leg Slings 619 or 636 Classification. Extra Extra Improved Plow Steel (EEIPS) Grade
Independent Wire Rope Core (IWRC) Wire Rope. Based on Design Factor = 5 and Rated Loads Expressed in Tons (2,000 lb)
Three-Leg Four-Leg
Table 11-9 Rated Load for Cable-Laid Wire Rope Single- and Two-Leg Slings. Mechanical Splice Only. Based on Design Factor = 5 and
Rated Loads Expressed in Tons (2,000 lb)
Table 11-10 Rated Load for Six-Part Braided Single- and Two-leg Slings 6x19 or 6x36. Classification Extra Improved Plow Steel (EIPS)
Independent Wire Rope Core (IWRC) Wire Rope. Based on Design Factor = 5 and Rated Loads Expressed in Tons (2,000 lb)
Table 11-11 Rated Load for Eight-Part Braided Single- and Two-leg Slings 6x19 or 6x36. Classification Extra Improved Plow Steel (EIPS)
Independent Wire Rope Core (IWRC) Wire Rope. Based on Design Factor = 5 and Rated Loads Expressed in Tons (2,000 lb)
11.3.2.2. Inspections
11.3.2.2.1 Wire-rope sling users shall visually inspect all slings each day they are used or prior to use if
the sling has not been in regular service (records are not required). In addition, a periodic
inspection (with records) shall be made at least annually by a qualified inspector. More frequent
intervals should be established if necessary as determined by a qualified person based on:
Frequency of sling use.
Severity of service conditions.
Nature of lifts being made.
Experience gained on the service life of slings used in similar circumstances.
11.3.2.2.2 Users shall carefully note any deterioration that could result in an appreciable loss of original
strength and determine whether further use of the sling would constitute a safety hazard.
11.3.2.2.3 A sample annual inspection form is included as Exhibit 11.1 at the end of this section. This
form is intended to be a sample only and is not intended to be mandatory.
11.3.2.2.4 Annual and initial inspections shall be documented by entering inspection data into a computer
generated data base and color coding the sling.
11.3.2.2.5 Slings shall be immediately removed from service if any of the following conditions are
present:
Ten randomly distributed broken wires in one rope lay or five broken wires in one strand in one
rope lay.
Wear or scraping of one-third the original diameter of the outside individual wire.
Kinking, crushing, birdcaging, or any other damage resulting in distortion of the rope structure.
Evidence of heat damage.
End attachments that are cracked, deformed, or worn.
Corrosion of the rope or end attachments.
Missing or illegible sling identification.
Note: Use only slings with permanently affixed identification markings that show the maximum load
capacity for each sling.
11.3.2.2.6 Hooks shall be inspected according to Chapter 12, Rigging Accessories.
11.3.2.3 Proof-Testing
11.3.2.3.1 All swaged socket and poured socket sling assemblies shall be proof-tested to the wire rope or
fitting manufacturers recommendations but in no case greater than 50% of the component wire
ropes or structural strands nominal strength. All other sling assemblies shall be proof-tested
when specified by the purchaser.
11.3.2.3.2 As a minimum, the proof load shall be equal to the rated capacity but shall not exceed:
125% of the vertical rated capacity for single-let, hand-tucked slings.
200% of the vertical rated capacity for mechanical-splice single-leg slings and endless slings.
11.3.2.3.3 The proof-load for multiple-leg bridle slings assemblies shall be applied to the individual leg
and shall be in accordance with paragraph 11.3.2.3.4 and 11.3.2.3.5 as applicable.
11.3.2.3.4 Master links to which multiple-leg slings are connected shall be proof-loaded to 200% times
the force applied by the combined legs.
11.3.2.3.5 Welded end attachments shall not be used unless proof-tested at 2 times rated capacity prior to
initial use.
11.3.2.3.6 Test loads described above shall be accurate to within 5%, +0% of stipulated values. A
written letter of certification by the manufacturer or a pull test witnessed and certified in writing
by a qualified person is acceptable.
11.3.2.4 Operation
The following shall apply to all personnel who use wire-rope slings:
11.3.2.4.1 Start and stop slowly; sudden starts and stops dramatically increase the stresses in hoist ropes
and slings. Lift slowly until the load is suspended to minimize swinging.
11.3.2.4.2 Loads shall be set on blocks. Do not pull a sling from under a load that is resting on the sling.
11.3.2.4.3 Ensure that wire-rope slings are protected against weather, chemicals, solvents, and high
temperatures.
11.3.2.4.4 Permanently remove from service fiber-core rope slings that have been exposed to
temperatures in excess of 180 F (82 C).
11.3.2.4.5 When wire rope slings of any grade are to be used at temperatures above 400 F (204 C) or
below -60 F (-51 C), the sling manufacturer should be consulted.
11.3.2.4.6 Extremely low temperatures (less than 0 F) may cause brittle fractures. Under these
conditions, sudden loading should be avoided and the rope should be carefully observed while the
load is being applied.
11.3.2.4.7 Do not use knotted slings.
11.3.2.4.8 Do not use single-leg wire-rope slings unless proper precautions are taken to prevent suspended
loads from rotating.
11.3.2.4.9 Rigging shall be configured such that slings do not reeve or slip through the hook.
11.3.2.4.10 Do not make a complete turn of wire rope around the crane hook.
.11 Use protector pads or blocking at sharp corners.
11.3.2.4.12 Keep hands and fingers out of the area between the sling and the load.
11.3.2.4.13 Ensure that the weight of the load is within the rated capacity of the sling.
11.3.2.4.14 Do not use damaged slings.
11.3.2.4.15 Ensure that all personnel stand clear of the suspended load.
11.3.2.4.16 Avoid shock loading.
11.3.2.4.17 In a basket hitch, ensure that the load is balanced to prevent slippage.
11.3.2.4.18 Avoid handling hot material with wire-rope slings. See paragraph 11.3.2.4.5.
11.3.2.4.19 Store slings on racks away from moisture and acids when not in use.
11.3.2.4.20 Ensure that damaged wire-rope slings are removed from service and returned to the competent
person, for destruction (rendered useless) and removal from inspection data base.
11.3.2.4.21 Before use and before storage, check wire-rope slings for:
11.3.2.4.23 As a minimum, wire-rope slings shall be marked with the following information:
Name of trademark of manufacturer
Rated capacity for the type of hitch(s)
Diameter or size
Number of legs if more than one
Evidence of periodic inspection date
NOTE: Marking requirements specified in paragraphs 11.3.2.4.24.1, 11.3.2.4.24.2, and 11.3.2.4.24.3 are
ASME B30.9 requirements effective January 2001. In addition, use only slings with permanently
affixed identification markings that show the maximum load capacity for each sling. Sling
identification should be maintained by the user so as to be legible during the life of the sling.
(Stenciling or stamping on the swages of a sling is not recommended.)
11.3.2.4.24 Slings made of rope with 6 x 19 and 6 x 36 construction and cable-laid slings shall have a
minimum clear length of rope 10 times the rope diameter between splices, sleeves, or end fittings.
11.3.2.4.25 Braided slings shall have a minimum clear length of rope 40 times the component (individual)
rope diameter between the loops or end fittings.
11.3.2.4.26 Grommets and endless slings shall have a minimum circumferential length of 96 times the
body diameter of the grommet or endless sling.
11.3.2.5 Cautions and Prohibitions
The sling's intended use shall determine by the type of rope and termination. The following cautions and
restrictions apply to this determination:
11.3.2.5.1 Rotation-resistant wire rope shall not be used for slings.
11.3.2.5.2 Wire rope wedge sockets shall not be used to fabricate wire rope slings.
11.3.2.5.3 Wire rope slings larger than inch, with eyes formed by folding back the rope (not a Flemish
eye loop) and secured with one or more metal sleeves pressed (not forging) over the wire rope
junction are prohibited for lifting service.
11.3.2.5.4 Wire rope clamps (clips) shall not be used to fabricate wire rope slings larger than 1/4 inch.
(See Figures 11-9 through 11-11.)
Note that the base of the clip bears against The U of the clips shall not bear against
the live end of the wire rope, while the the live end of the wire rope because of the
U of the bolt presses against the dead possibility of the rope being kinked or
end. crushed.
Figure 11-9. Wire-rope clips correct. Figure 11-10. Wire-rope clips wrong.
11.3.2.6 Onsite Sling Fabrication - Slings for lifting service may be fabricated onsite by knowledgeable
craftsmen using one of the following methods:
11.3.2.6.1 Hand tucked--The terminal efficiency is reduced (see Figure 12). This sling type is usually
more expensive than most commercially made slings.
11.3.2.6.2 Flemish eye with swaged socket--This is the best selection for general purposes and shall be
used except when use is impractical.
11.3.2.6.3 Slings shall be made only from new wire rope. When swaged fittings are used, they shall be
used as recommended by the fitting manufacturer and the swaging machine manufacturer.
Thimbles should be used unless their use makes the sling impractical.
11.3.2.6.4 Identification of fabricated slings shall be as described in paragraph 11.3.2.4.23.
11.3.2.7 Critical Lifts
See Chapter 2 for critical lift requirements.
11.3.2.7.1 All provisions of paragraph 11.3.2.4 also shall apply to critical lifts.
11.3.2.7.2 Wire-rope slings used for critical lift service should have an initial proof test, performed and
documented by OEM. If proof test cannot be verified, the wire rope sling shall be load tested
before used to make a critical lift. As a minimum the load test shall be equal to the expected load
seen by the sling, but shall not exceed the slings' rated capacity.
Test weights shall be accurate to within 5%, +0% of stipulated values.
11.3.2.7.3 Wire-rope sling eyes with thimbles shall be made with a thimble having a ratio of thimble
diameter (D) to rope diameter (d) of 3 or more (D/d greater than or equal 3).
11.3.2.7.4 Do not use wedge sockets or wire-rope clips on slings used for critical lifts.
11.3.2.7.5 Ensure that working loads of wire-rope slings do not exceed their rated capacities.
11.3.2.7.6 Do not splice slings together.
NOTE: It is strongly recommended by the AEDC Crane Committee that chain slings not be used at
AEDC; however, it is understood at some time chain slings may be necessary under certain
conditions. If chain slings are to be used, then the following procedures shall be complied with.
11.3.3.1 General
11.3.3.1.1 Chain for alloy steel chain slings shall conform to the requirements of ASTM A906/A 906M,
Standard Specification for Grade 80 and Grade 100 Alloy Steel Chain Slings for Overhead
Lifting. If chain other than this is used, it shall be used in accordance with the recommendations
of the chain manufacturer.
11.3.3.1.2 Alloy Steel-chain slings differ from wire-rope slings in that components using wire are
replaced by link chain. Other sling components are similar. Chain slings are more rugged and
flexible, but less shock resistant than wire-rope or braided slings. This size is measured by the
link stock.
11.3.3.1.3 Two basic types with many variations are used: basket type and hook type. An example of
each is shown in Figure 11-13.
11.3.3.1.4 Alloy-steel-chain slings shall not be heated above 1,000 F (537 C) after being received from
the manufacturer.
11.3.3.1.5 When exposed to service temperatures in excess of 600 F (315 C), reduce working load
limits in accordance with the chain manufacturers recommendations. (See Table 11-12)
11.3.3.1.6 Extremely low temperatures (less than 0 F) may cause brittle fractures. Under these
conditions, sudden loading should be avoided and the load should be lifted a very short distance
while the chains are carefully inspected.
11.3.3.1.7 The design factor for steel-chain slings shall be a minimum of 4:1 based upon breaking
strength.
11.3.3.1.8 Chains should be stored in racks or in designated locations when not in use. Chains should
never be stored in damp or dirty places, nor in places exposed to the weather. For long-term
storage, they should receive a coating of oil. The ends of all empty chains should be hooked onto
the hoist hook or bull ring.
11.3.3.1.9 Chains should not be lubricated when in use because this might make them dangerous to
handle. Chains should be cleaned periodically to remove abrasive grit and to facilitate inspection.
11.3.3.1.10 The total load that can be lifted safely with steel-chain slings depends on the manner by which
the slings are attached to the load. If all legs of a steel-chain sling are hooked back into the
master link, the safe-load capacity of the whole sling may be increased by 100% if the capacity of
the master link is not exceeded.
11.3.3.1.11 The safe-load level of any chain sling is a function of three basic factors: size and number of
legs, condition of chain and other components, and sling angle between legs and horizontal.
Tables 11-13 thru 11-16 show safe loads in pounds per leg which can be carried by various chain-
sling arrangements. Note the effect of very low hook height and wide leg spreads.
11.3.3.1.12 Attachments: Hooks, rings, oblong links, pear shaped links, welded or mechanical coupling
links and other attachments shall have a rated capacity at least equal to that of the alloy steel
chain with which they are used or the sling shall not be used in excess of the rated capacity of the
weakest component.
11.3.3.3.3 After annual inspection each chain sling will be color coded, using a colored nylon wire tie
attached to the sling, to show when next inspection is due as follows, with colors continuing in
sequence thereafter:
The color GREEN will be used for FY 2014
The color RED will be used for FY 2015
The color WHITE will be used for FY 2016
The color BLUE will be used for FY 2017
The color GREEN will be used for FY 2018
Colors will continue in sequence thereafter.
11.3.3.4 Proof Testing
11.3.3.4.1 Single-leg and endless alloy-steel chain slings shall be certified as having been proof-tested to
200% of the rated capacity prior to initial use.
11.3.3.4.2 The proof load for multiple-leg bridle slings shall be applied to the individual legs and shall be
200% of the vertical rated capacity of a single-leg sling.
11.3.3.4.3 Master links to which multiple-leg slings are connected shall be proof-loaded to 200%
multiplied by the force applied by the combined legs.
11.3.3.4.4 Test loads shall be accurate to within 5%, +0% of stipulated values. Either certification by
the manufacturer or a pull test certified by a qualified person is acceptable.
11.3.3.5 Operation
The following shall apply to all personnel who use steel-chain slings:
11.3.3.5.1 Do not set a load on a sling or pull a sling from under a load. Place wooden blocks or other
supports under the load to provide sufficient clearance for the chain.
11.3.3.5.2 Shorten chain slings by hooking back into the chain, into the master link, or with grab hooks.
Do not shorten by knotting, twisting, bolting, or inserting the tip of the hook into a link.
11.3.3.5.3 Do not hammer a chain to force it into position.
11.3.3.5.4 Protect chain slings from sharp corners that might bend the links. Use a suitable pad to prevent
gouging or bending of the chain links, as well as possible scarring of the load.
11.3.3.5.5 When making choker hitches with chain slings, always face the hook opening out and away
from the pull of the sling so that the hooks will not slip out when slack is taken out of the sling.
11.3.3.5.6 Check steel-chain slings for:
Nicks, cracks, gouges, and wear.
Bending, stretching, or shearing of links.
Bends or distortions in hooks.
Rust and corrosion.
Uneven lengths when sling legs are hanging free.
Evidence of heat damage.
11.3.3.5.7 Do not weld or perform local repairs on chain slings. All defective chain slings should be
returned, through a formal procedure, to the manufacturer for examination, repair, and
recertification.
11.3.3.5.8 Avoid sudden loading of chain slings.
11.3.3.5.9 Maintain latches on hooks in good condition.
11.3.3.5.10 If a chain sling does not look safe, do not use it. Do not assume that a chain sling is safe
because it looks new; look for stretched links. If in doubt, check with the AEDC Crane System
Engineer.
11.3.3.5.11 Do not carry loads on the point or tip of a hook.
11.3.3.5.12 Avoid unbalanced loads.
11.3.3.5.13 Do not use homemade links, makeshift fasteners formed from bolts, rods, and the like, or
other nonstandard attachments.
11.3.3.5.14 Do not use makeshift or field-fabricated hooks on steel-chain slings.
11.3.3.5.15 Hook the ends of all empty chain onto the hoist hook or bull ring.
11.3.3.5.16 Ensure the steel-chain slings used in AEDC-controlled areas are marked, at a minimum, with
the following:
Chain size.
Manufacturers grade (Only ASTM A 906 is allowed for lifting purposes (ASTM A906/A 906M,
Standard Specification for Grade 80 and Grade 100 Alloy Steel Chain Slings for Overhead
Lifting.)).
Rated load and angle on which the rating is based.
Reach.
Number of legs.
Sling manufacturer.
11.3.3.5.17 This information may be stenciled or stamped on a metal tag or tags affixed to the sling.
11.3.3.5.18 Where slings have more than one leg, ensure that the tag is affixed to the master link.
11.3.3.5.19 Ensure that the working load does not exceed the rated capacity of the sling.
11.3.3.6 Critical Lifts
See Chapter 2, Critical Lifts, for critical lift requirements.
11.3.3.6.1 Single-leg and endless alloy-steel chain slings used for critical-lift service should have an
initial proof test, performed and documented by OEM. If proof test cannot be verified, the alloy-
steel chain sling shall be load tested before used to make a critical lift. As a minimum the load
test shall be equal to the expected load seen by the sling, but shall not exceed the slings' rated
capacity.
11.3.4.1 General
11.3.4.1.1 Metal-mesh slings (Figure 11-14) shall be classified with the designations shown in Table 11-
18, based on types of duty and material classification.
11.3.4.1.2 The carbon steel used in metal-mesh slings shall be processed to produce the required
mechanical properties.
11.3.4.1.3 The material used for stainless-steel metal-mesh slings shall conform, at least, to the American
Iron and Steel Institute standards for Type-302 or Type-304 stainless steel. Other materials may
be used. When metal-mesh slings are produced from such materials, however, the sling
manufacturer should be consulted for specific data.
11.3.4.2 Inspections
11.3.4.2.1 Users of metal-mesh sling shall visually inspect all metal-mesh slings before each use.
Annual inspections shall be made by a qualified inspector, and inspections shall be documented
by entering inspection data into a computer generated data base and color coding, using a color
nylon wire tie attached to the sling.
11.3.4.2.2 Metal-mesh slings shall be removed from service if any of the following defects are present:
11.3.4.2.3 A broken weld or brazed joint along the sling edge.
A broken wire in any part of the mesh.
11.3.5.1 General
11.3.5.1.1 Synthetic web shall posses the following qualities:
Be of sufficient strength to meet the sling manufacturers requirements.
Have uniform thickness and width.
Have edges which prevent raveling.
11.3.5.1.2 The thread used in the manufacture of a synthetic-web sling shall be of the same type of
material as the web.
11.3.5.1.3 Fitting shall be:
Of sufficient strength to sustain twice the rated capacity without permanent deformation.
Of a minimum breaking strength equal to that of the sling.
Free of all sharp edges that would in any way damage the mesh.
11.3.4.4.4 The stitching in all load-bearing splices shall be of sufficient strength to maintain the sling
design factor.
11.3.4.4.5 Synthetic-web slings may be coated with elastomers or other suitable material that will provide
characteristics such as abrasion resistance, sealing of pores, and increased coefficient of friction.
11.3.4.4.6 The design factor for synthetic-web slings shall be a minimum of 5:1 based upon breaking
strength.
11.3.4.4.7 Rated capacities are affected by the type of hitch used and by the angle from the vertical when
used as multilegged slings or in basket hitches. The sling manufacturer shall supply data on these
effects.
11.3.4.4.8 Synthetic-web slings are available in a number of configurations as described below:
11.3.4.4.9 In place of the sewn eyes, synthetic-web slings are also available with metal end fittings (see
Figure 11-15). The most common are triangle and choker hardware. Combination hardware
consists of a triangle for one end of the sling and a triangle/rectangle choker attachment for the
other end. With this arrangement, both choker and basket hitches, as well as straight hitches, may
be rigged. They help reduce wear in the sling eyes and thus lengthen sling life.
11.3.5.1.10 Despite their inherent toughness, synthetic-web slings can be cut by repeated use around
sharp-cornered objects. They eventually show signs of abrasion when they are repeatedly used to
hoist rough-surfaced products. There are, however, protective devices offered by most sling
manufacturers that minimize these effects (see Figure 11-16). Other protective devices include:
Buffer strips of leather, nylon, or other materials that are sewn on the body of a sling protect
against wear. Leather pads are the most resistant to wear and cutting, but are subject to
weathering and gradual deterioration. They are not recommended in lengths over 6 ft due to the
different stretching characteristics of the leather and webbing. On the other hand, nylon-web
wear pads are more resistant to weathering, oils, grease, and most alkalis; and they stretch in the
same ratio as the sling body.
Edge guards consist of strips of webbing or leather sewn around each edge of the sling. This is
necessary for certain applications where the sling edges are subject to damage.
Sleeve- or sliding-tube-type wear pads are available for slings used to handle material having
sharp edges. They can be positioned on the sling where required, do not move when the sling
stretches, adjust to the load, and cover both sides of the sling.
Reinforcing strips that double or triple the eyes thickness and greatly increase its life and safety
can be sewn into the sling eyes.
Coatings can be applied to provide added resistance to abrasion and chemical damage. These
treatments also increase the coefficient of friction, affording a better grip when loads with
slippery surfaces are to be handled. These coatings can be brightly colored for safety or load-
rating purposes.
Cotton-faced nylon webbing can be used for hoisting rough-surfaced material.
11.3.5.1.11 The synthetic-web sling capacities listed in Tables 11-20 and 11-24 are approximate only and
are based on nylon webbing having breaking strengths between 6,000 and 9,000 lb/in. of webbing
width. The capacities are also based on a 5:1 design factor and assume that the end fittings are of
adequate strength.
11.3.5.1.12 Although safe working loads for bridle hitches in the choker or double-basket configuration
are provided, they should be used only with extreme caution because, as the sling angle
decreases, one edge of the web will take all the load, producing a risk of tearing (see Figure 11-
17).
11.3.5.1.13 Synthetic-web slings, other than those described in this section [i.e., polyester round and
kevlar fiber (yarn) slings], shall be used in accordance with the sling manufacturers
recommendation.
11.3.5.1.14 Conventional three-strand natural or synthetic fiber rope slings are NOT recommended for
lifting service, and should be used only if conventional sling types are not suitable for a unique
application. The requirements of ASME B 30.9 (Slings), paragraph 9-4, and 29 CFR
1910.184(h) shall be followed.
CAUTION: Tiedown and/or ratchet strap shall not be used as synthetic-web slings. Only synthetic-web
slings constructed from webbing approved for sling construction by the manufacturer or other
qualified person shall be used at AEDC.
11.3.5.2 Inspections
11.3.5.2.1 Users of synthetic-web sling shall visually inspect all slings before each use.
11.3.5.2.2 Annual inspection shall be made by a qualified inspector, and shall be documented by entering
inspection data into a computer generated data base and color coding, by attaching a colored
nylon wire tie to the sling. After annual inspection each synthetic sling will be color coded to
show when next inspection is due as follows:
The color GREEN will be used for FY 2014
The color RED will be used for FY 2015
The color WHITE will be used for FY 2016
The color BLUE will be used for FY 2017
The color GREEN will be used for FY 2018
Colors will continue in sequence thereafter.
11.3.5.2.3 Slings shall be removed from service if any of the following defects are visible:
Acid or caustic burns.
Melting or charring of any part of the surface.
Snags, punctures, tears, or cuts.
11.3.5.4.14 Do not use aluminum fittings where acid or caustic fumes, vapors, sprays, mists or liquids are
present.
11.3.5.4.15 Ensure that each sling is permanently marked to show:
Name or trademark of manufacturer.
Manufacturers code or stock number.
Rated capacity for types of hitches used.
Type of synthetic-web material.
Number of legs, if more than one.
NOTE: Slings may be marked with serial number or other identifying number that can be used to
determine capacity in situations where it becomes impossible to mark the sling as described
above due to security classification of the load or other valid reason approved by the person in
charge.
11.3.5.4.13 Ensure that synthetic-web slings are marked with the inspection due date.
11.3.5.4.17 Synthetic slings (e.g., Kevlar, K-Spec, nylon, polyester) may be used in radiation areas only
when a qualified person ensures that the absorbed dose does not exceed 100,000 rad during the
life of the sling.
11.3.5.5 Critical Lifts
See Chapter 2 for critical lift requirements.
11.3.5.5.1 Synthetic web slings used for critical lift service should have an initial proof test, performed
and documented by OEM. If proof test cannot be verified, the synthetic web sling shall be load
tested before used to make a critical lift. As a minimum the load test shall be equal to the
expected load seen by the sling, but shall not exceed the slings' rated capacity.
11.3.6 Synthetic Roundslings
11.3.6.1 General
11.3.6.1.1 Synthetic roundslings shall possess the following qualities:
Core yarn shall be of a synthetic fiber wound together on a plurality of turns for even distribution
of the load.
In chemically active environments the cover shall be the same type yarn as the load-bearing core.
The thread used in the manufacture of a synthetic roundsling shall be of the same type of material
as the core.
Finishes and coatings shall be compatible with material of the core, cover, and thread and not
impair the performance of the roundsling.
11.3.6.1.2 Fittings shall be:
Of sufficient strength to sustain twice the rated capacity without permanent deformation.
Of a minimum breaking strength equal to that of the roundsling.
Free of all sharp edges that would in any way damage the roundsling.
Compatible with the mechanical and environmental requirements imposed on the roundsling.
11.3.6.1.3 The roundsling manufacturer should be consulted before using roundslings in chemically active
environments.
11.3.6.1.4 Nylon and polyester slings shall not be used on contact with objects or at temperatures in
excess of 194 F (90 C), or below -40 F (-40 C). Polypropylene slings shall not be used in
contact with objects or at temperatures in excess of 150 F (66 C), or below -40 F (-40 C).
The sling manufacturer should be consulted for the temperature range of slings made from other
synthetic yarns.
11.3.6.1.5 The design factor for synthetic roundslings shall be a minimum of 5:1 based on breaking
strength.
11.3.6.1.6 Rated capacities are affected by the type of hitch used and by the angle from the vertical when
used as multi-legged slings or in basket hitches. The sling manufacturer shall supply data on
these effects.
11.3.6.1.7 Despite their inherent toughness, synthetic roundslings can be cut by repeated use around
sharp-cornered objects. They eventually show signs of abrasion when they are repeatedly used to
hoist rough-surfaced products. There are, however, protective devices offered by most sling
manufacturers that minimize these effects.
11.3.6.1.8 Synthetic roundslings are available in a number of configurations (see Figure 11-18).
Roundlsing capacities are listed in Table 11-25; these capacities are approximate only. The
capacities are also based on a 5:1 design factor, and assume that the end fittings are of adequate
strength.
11.3.6.2 Inspections
11.3.6.2.1 Users of synthetic roundslings shall visually inspect all slings before each use.
11.3.6.2.3 Annual inspection shall be made by a qualified inspector, and shall be documented by entering
inspection data into a computer generated data base and color coding, using a colored nylon wire
tie attached to the sling. After annual inspection each roundsling will be color coded to show
when next inspection is due as follows with colors continuing in sequence thereafter:
The color GREEN will be used for FY 2014.
The color RED will be used for FY 2015.
The color WHITE will be used for FY 2016.
The color BLUE will be used for FY 2017.
The color GREEN will be used for FY 2018.
Colors will continue in sequence thereafter.
11.3.6.2.3 When it is necessary to use a polyester or nylon roundsling in a radiation area, the supervisor or
manager in charge of the operation shall ensure that radiation exposure does not exceed 100,000
rad during the life of the sling.
11.3.6.2.4 Slings shall be removed from service if any of the following defects are visible:
Acid or caustic burns.
11.3.6.4.15 For multiple leg roundslings used with non-symmetrical loads, an analysis should be
performed by a qualified person to prevent overloading of any leg.
11.3.6.4.16 Ensure that each sling is permanently marked to show:
Name or trademark of manufacturer.
Manufacturers code or stock number.
1Rated capacity for types of hitches used.
Type of core material and cover material if different from core material.
Number of legs, if more than one.
NOTE: Slings may be marked with a serial number or other identifying number that can be used to
determine capacity in situations where it becomes impossible to mark the sling as described
above due to security classification of the loads to be lifted or for other valid reasons approved by
the person in charge.
11.3.6.4.17 Ensure that roundslings are marked with the inspection due date.
11.3.6.5 Critical Lifts
See Chapter 2 for critical lift requirements.
11.3.6.5.1 Roundslings used for critical lift service should have an initial proof test, performed and
documented by OEM. If proof test cannot be verified, the wire rope sling shall be load tested
before used to make a critical lift. As a minimum the load test shall be equal to the expected load
seen by the sling, but shall not exceed the slings' rated capacity.
NOTE: Exhibits 11.1 through 11.5 are intended to be sample forms only. The equipment manufacturers
inspection/testing criteria supersede any other criteria. In cases where the equipment
manufacturer does not include inspection/testing criteria, other forms developed to facilitate
required inspection/testing are acceptable.
(SAMPLE FORM)
DIAMETER
Rope Breaking
Crane/Sling Location Application
Description Strength
DATE
Lay Length
Measured Diameter
Rope Damage
Excess Wear
Corrosion
Lubrication
Pass/Fail
Signature
Exhibit 11.4 Rigging Tackle Periodic Inspection Chain (Sample form page 1 of 2)
Exhibit 11.5 Rigging Tackle Periodic Inspection (Synthetic Web And Round Slings)
12.1.2 Inspections
12.1.2.1 The operator or other designated person shall visually inspect rigging accessories at the
beginning of each work shift or prior to use for the following (records not required):
12.1.2.1.1 Wear.
12.1.2.1.2 Corrosion.
12.1.2.1.3 Cracks.
12.1.2.1.4 Nicks and gouges.
12.1.2.1.5 Distortion such as bending or twisting.
12.1.2.1.6 Evidence of heat damage from any cause.
12.1.2.2 A designated person shall determine whether conditions found during the inspection constitute a
hazard and whether a more detailed inspection is required.
12.1.2.3 Rigging accessories having any of the following conditions shall be removed from service:
12.1.2.3.1 Cracks.
12.1.2.3.2 Bent, twisted, distorted, stretched, elongated, cracked, or broken load-bearing components
12.1.2.3.3 Any sign of incipient failure in shear for shackle pins.
12.1.2.3.4 Wear exceeding 10% of original dimensions.
12.1.2.3.5 Excessive corrosion.
12.1.2.3.6 Shackles not marked according to paragraph 12.3, Shackles.
12.1.2.3.7 Heat damage.
12.1.2.4 A designated person shall perform nondestructive examinations according to applicable ASTM
standards.
12.1.2.5 A sample load test and inspection form is included as Exhibit 12.1 at the end of this chapter.
This form is a sample only and is not intended to be mandatory.
12.1.3 Testing
12.1.3.1 Mulitleg assemblies shall be proof-tested based on any two legs sharing the entire load. Attach
legs not undergoing test in a manner to ensure that load stability is not lost during the test.
12.1.3.2 Dynamometers and load cells shall be calibrated at least once a year and when specified in the
critical lift procedure before being used to make a critical lift. This also applies if they have not
been used in the previous 6 months. All calibrated devices shall have a tag affixed indicating date
of calibration, by whom they were calibrated, and the date that the next calibration is due.
Chokers
Hook Slings
Eyebolts
Eye Splices
12.2.1 Design
12.2.1.1 Hook design shall meet generally accepted hook design standards and be compatible with the
requirements of ASME B30.10, Chapter 10-2 (see Chapter 13 for equipment load hook
requirements.)
12.2.1.2 Latch-equipped hooks shall be used unless the application makes the use of the latch impractical
or unnecessary.
12.2.2 Marking
The manufacturers identification shall be forged, cast, or die-stamped on a low-stress and nonwearing
area of the hook.
12.2.3 Construction
12.2.3.1 The hook material shall have sufficient ductility to permanently deform before failure at the
temperature at which the hook will be used.
12.2.3.2 Rated capacities for hooks shall equal or exceed the rated capacity of the chain, wire rope, or
other suspension members to which they are attached.
A hook shall not be loaded beyond its rated capacity. See Table 12-2 for hook capacity.
12.2.5 Inspections
12.2.6.1 Performance testing of hooks shall not be required except where necessary to conform to the
requirements for the equipment of which they are part. When tests are specified, documentation
shall be uniquely identified to the hook by serial number or other identifier.
12.2.6.2 If detailed inspections are performed (refer to paragraphs 12.2.5.2.2, 12.2.5.3.4, and 12.2.5.4.2),
the results shall be evaluated by a qualified person to determine the need for subsequent
nondestructive testing (NDT). If NDT is deemed necessary, it shall be performed in accordance
with paragraph 13.4.3.
12.2.7 Maintenance
12.2.7.1 A designated person shall repair cracks, nicks, and gouges by grinding longitudinally, following
the contour of the hook, provided that no dimension is reduced more than 10% of its original
value (or as recommended by the manufacturer).
12.2.7.2 All other repairs shall be performed by the manufacturer.
12.2.8 Operation
12.3 SHACKLES
12.3.1 General
12.3.1.1 Shackles are made of drop-forged steel bent into shape. They are strong, closed attachments that
will not unhook. The shackle shall have sufficient ductility to permanently deform before losing
the ability to support the load at the temperatures at which the manufacturer has specified for use.
The size is specified by the diameter of the body. Side pulls on shackle body are only permitted
if the manufacturer has rated the shackle for that type of lift.
Note: Round pin shackles (restrained by cotter pin only) shall not be used for lifting.
12.3.1.1.1 Body types covered are anchor, chain, and synthetic sling.
12.3.1.1.2 Pin types covered are screw pin and bolt-type.
12.3.1.1.3 Shackles other than those detailed in this chapter shall be used only in accordance with
recommendations of the shackle manufacturer or a qualified person.
12.3.1.2 Shackle pins should fit free without binding. Do not substitute a bolt for the shackle pin. Figure
12-3 shows shackles and provides examples of good and bad practices and inspection points.
12.3.1.3 Each shackle body shall be permanently and legible marked by the manufacturer. Raised or
stamped letters on the side of the bow shall be used to show:
12.3.1.3.1 Manufacturers name or identifiable trademark.
12.3.1.3.2 Shackle size.
12.3.1.3.3 Rated capacity (Safe working load SWL/WLL).
12.3.1.4 Each new shackle pin shall have forged, cast, or die stamped markings by the manufacturer to
show:
12.3.1.4.1 Name or trademark of manufacturer
12.3.1.4.2 Grade, material type, or load rating
12.3.1.5 Shackles and/or pins not properly marked shall be permanently removed from rigging service.
12.3.1.6 When shackles are used at load angles other than 90, the safe-load rating shall be reduced
accordingly. (See figure 12-2. Side Loading)
Side Loading
Not recommended to
load in this condition.
Over 90
Consult manufacturer or
qualified person.
12.3.2 Inspections
12.3.2.3.2 Periodic inspection intervals shall not exceed one year. The frequency of periodic inspections
should be based on:
Frequency of shackle use.
Severity of service conditions.
Nature of lifts being made.
Experience gained on the service life of shackles used in similar circumstances.
Guidelines for the time intervals are:
o Normal service yearly
o Severe service monthly to quarterly
o Special service as recommended by a qualified person
12.3.2.3.3 Written records are not required.
12.3.3.1 Shackles shall be removed from service if damage such as the following is visible and shall only
be returned to service when approved by a qualified person:
12.3.3.1.1 Missing or illegible manufacturers name or trademark and/or rated load identification.
12.3.3.1.2 Indications of heat damage including weld spatter or arc strikes.
12.3.3.1.3 Excessive pitting or corrosion.
12.3.3.1.4 Excessive nicks or gouges.
12.3.3.1.5 A 10% reduction of the original or catalog dimension at any point around the body or pin.
12.3.3.1.6 Incomplete pin engagement.
12.3.3.1.7 Excessive thread damage.
12.3.3.1.8 Evidence of unauthorized welding.
12.3.3.1.9 Bent, twisted, distorted, stretched, elongated, or broken load bearing components
12.3.3.1.10 Other conditions that cause doubt as to the continued use of the shackle.
12.3.5.1.3 Shackles that appear to be damaged shall not be used until inspected and accepted as usable
under paragraph 12.3.2.
NOTE: The angle of loading affects the stress in the shackle. As the horizontal angle decreases, the
stress increases in the shackle.
12.3.5.2 Cautions to Personnel
12.3.5.2.1 All portions of the human body shall be kept from between the shackle, the load, and any other
rigging during the lift.
12.3.5.2.2 Personnel should stand clear of the suspended load.
12.3.5.2.3 Personnel shall not ride the shackle.
12.3.5.3 Storage and Work Environments
12.3.5.3.1 Shackles should be stored in an area where they will not be subjected to damage, corrosive
action, or extreme heat.
12.3.5.3.2 If extreme temperatures or chemically active environments are involved, the guidance provided
in paragraph 12.3.6.1 or 12.3.6.2 shall be followed.
12.3.5.4 Rigging Practices
12.3.5.4.1 The screw pin shall be fully engaged, with the shoulder in contact with the shackle body (see
Fig. 12-2).
12.3.5.4.2 If a shackle is designed for a cotter pin, it shall be used and maintained in good working
condition. Alterations or modifications shall comply with paragraph 12.3.4.
12.3.5.4.3 Contact with sharp edges that could damage the shackle should be avoided.
12.3.5.4.4 Shock loading should be avoided.
12.3.5.4.5 The load applied to the shackle should be centered in the bow of the shackle to prevent side
loading of the shackle.
12.3.5.4.6 Multiple sling legs should not be applied to the shackle pin.
12.3.5.4.7 If the shackle is to be side loaded, the rated load shall be reduced according to the
recommendations of the manufacturer or a qualified person.
12.3.5.4.8 The screw pin shackle shall not be rigged in a manner that would cause the pin to unscrew.
12.3.5.4.9 For long-term installations, bolt type shackles should be used; if screw pin type shackles are
used, the pin shall be secured from rotation or loosening.
12.3.5.4.10 Shackles should not be dragged on an abrasive surface.
12.3.5.4.11 Multiple slings in the body of a shackle shall not exceed 120 included angle.
12.3.5.4.12 When a shackle is used in a choker hitch, the pin shall be connected to the choking eye of the
sling.
12.3.6.1 Temperature - When shackles are to be used at temperatures above 400F (204C) or below -
40F (-40C), the shackle manufacturer or a qualified person should be consulted.
12.3.6.2 Chemically Active Environments - The strength of shackles can be affected by chemically
active environments such as caustic or acid substances or fumes. The shackle manufacturer or a
qualified person should be consulted before shackles are used in chemically active environments.
Rated load shall be in accordance with the recommendation of the shackle manufacturer. The terms
rated capacity and working load limit are commonly used to describe rated load.
12.3.10 Training
Shackle users shall be trained in the selection, inspection, cautions to personnel, effects of
environment, and rigging practices as covered by this Chapter.
12.4.1 General
12.4.1.1 This section applies to adjustable hardware including turnbuckles, eyebolts, eye nuts, and swivel
hoist rings that are used as rigging hardware during normal hoisting and rigging activities.
12.4.1.2 Hardware designed for and permanently installed on existing engineered equipment is considered
part of the engineered equipment, and they may not meet all requirements specified for rigging
hardware. Hardware permanently installed on engineered equipment is acceptable for their
intended use so long as they pass normal visual inspection before use. It is important to know
how the manufacturer or engineered equipment intends permanently installed hardware to be
used. In some cases the intended use is obvious to an experienced craftsman in other cases
engineering review of vendor information may be necessary.
CAUTION: Hardware installed by the manufacturer to lift only parts of the engineered equipment are
not suitable for lifting the completed piece of equipment. When questions arise regarding the use
of manufactured-installed hardware, the asset owner, system manager or AEDC Crane System
Engineer shall be consulted.
12.4.2.1 Types
12.4.2.1.1 Turnbuckles, including open and pipe body types with hook, eye, or jaw end fittings (see Fig.
12.4a and 12.4b).
12.4.2.1.2 Eyebolts including shoulder nut, non-shoulder nut, non-shoulder machinery, and shoulder
machinery types (see Fig. 12.5).
12.4.2.1.3 Swivel hoist rings (see Fig. 12.6).
12.4.2.1.4 Adjustable hardware other than those detailed in this chapter shall be used only in accordance
with recommendations of the manufacturer or a qualified person.
12.4.2.2 Materials
The hardware, excluding bushings and bearings, shall have sufficient ductility to permanently
deform before losing ability to support the load at the temperatures at which the manufacturer has
specified for use.
12.4.2.2.1 Eyebolts used for hoisting shall be fabricated from forged carbon alloy or alloy steel.
12.4.2.2.2 Turnbuckles used for hoisting shall be fabricated from forged alloy steel.
12.4.2.2.3 Swivel Hoist Rings shall be fabricated from forged carbon alloy or alloy steel.
Rated load shall be in accordance with the recommendation of the hardware manufacturer. The
terms rated capacity and working load limit are commonly used to describe rated load.
12.4.6.1 Each turnbuckle, eyebolt, and eye nut shall be marked to show:
12.4.6.1.1 Name or trademark of manufacturer.
12.4.6.1.2 Size or rated load.
12.4.6.1.3 Grade for alloy eyebolts.
12.4.6.2 Each swivel hoist ring shall be marked to show:
12.4.6.2.1 Name or trademark of manufacturer.
12.4.6.2.2 Rated load.
12.4.6.2.3 Torque value.
12.4.6.3 Adjustable hardware identification shall be provided by the manufacturer.
12.4.6.4 Maintenance of Identification
Turnbuckle, eyebolt, eye nut, and swivel hoist ring identification should be maintained by the
user to be legible during the life of the hardware.
12.4.7.1 Temperature
12.4.7.1.1 When adjustable hardware, excluding swivel hoist rings and carbon steel eyebolts, is to be used
at temperatures above 400F (204C) or below -40F (-40C), the hardware manufacturer or a
qualified person should be consulted.
12.4.7.1.2 When swivel hoist rings are to be used at temperatures above 400F (204C) or below -20F (-
29C), the hardware manufacturer or a qualified person should be consulted.
12.4.7.1.3 When carbon steel eyebolts are to be used at temperatures above 275F (135C) or below 30F
(-1C), the hardware manufacturer or a qualified person should be consulted.
12.4.7.2 Chemically Active Environments
The strength of adjustable hardware can be affected by chemically active environments such as
caustic or acid substances or fumes. The adjustable hardware manufacturer or a qualified person
should be consulted before use in chemically active environments.
12.4.8 Training
Adjustable hardware users shall be trained in the selection, inspection, cautions to personnel,
effects of environment, and rigging practices as covered by this Chapter.
12.4.9.1 Initial Inspection - Prior to use, all new, altered, modified, or repaired adjustable hardware shall
be inspected by a designated person to verify compliance with the applicable provisions of this
section. Written records are not required.
12.4.9.2 Frequent Inspection
12.4.9.2.1 A visual inspection shall be performed by the user or other designated person each shift before
the adjustable hardware is used. Semi-permanent and inaccessible locations where frequent
inspections are not feasible shall have periodic inspections performed.
12.4.9.2.2 Conditions such as those listed in paragraph 12.4.9.4 or any other condition that may result in a
hazard shall cause the adjustable hardware to be removed from service. Adjustable hardware shall
not be returned to service until approved by a qualified person.
12.4.9.2.3 Written records are not required.
12.4.9.3 Periodic Inspection
12.4.9.3.1 A complete inspection of the adjustable hardware shall be performed by a designated person.
The adjustable hardware shall be examined for conditions such as those listed in paragraph
12.4.9.4 and a determination made as to whether they constitute a hazard.
12.4.9.3.2 Periodic inspection intervals shall not exceed one year. The frequency of periodic inspections
should be based on:
Frequency of use.
Severity of service conditions.
Nature of lifts being made.
Experience gained on the service life of adjustable hardware used in similar circumstances.
Guidelines for the time intervals are:
o Normal service yearly
o Severe service monthly to quarterly
o Special service as recommended by a qualified person
12.4.9.3.3 Written records are not required.
12.4.9.4 Removal Criteria - Adjustable hardware shall be removed from service if damage such as the
following is present and shall only be returned to service when approved by a qualified person:
12.4.9.4.1 Missing or illegible identification.
12.4.9.4.2 Indications of heat damage including weld spatter or arc strikes.
12.4.9.4.3 Excessive pitting or corrosion.
12.4.9.4.4 Bent, twisted, distorted, stretched, elongated, cracked, or broken load-bearing components.
12.4.9.4.5 Excessive nicks or gouges.
12.4.9.4.6 A 10% reduction of the original or catalog dimension at any point.
12.4.9.4.7 Excessive thread damage or wear.
12.4.9.4.8 Evidence of unauthorized welding or modification
12.4.9.4.9 For swivel hoist rings, lack of the ability to freely rotate or pivot.
12.4.9.4.10 Other conditions, including visible damage, that cause doubt as to continued use.
12.4.9.5 Repairs and Modifications
12.4.9.5.1 Repairs, alterations, or modifications shall be as specified by the adjustable hardware
manufacturer or a qualified person.
12.4.9.5.2 Replacement parts, including nuts, pins, and bolts, shall meet or exceed the original equipment
manufacturers specifications.
Turnbuckles used in applications where there is vibration shall be secured to the frame with locks,
pins, or wires to prevent turning or loosening
For long-term installations, turnbuckles shall be secured to prevent unscrewing.
Turnbuckles should not be dragged on an abrasive surface.
Turnbuckles should be adjusted with a properly sized wrench, used on the wrench flats of the
turnbuckle body.
12.4.10.4.2 Eyebolts
When load is applied to the hoist ring, there should be no interference between the load (work
piece) and the hoisting ring (see Figure 12-6).
Check the condition of the threads in the hole to ensure that the hoist ring will secure and the
bushing can be brought down snug.
Destroy hoist rings that are cracked, bent, have damaged threads, or do not operate freely.
Permanently installed hoist rings shall be inspected before each use to ensure free movement of
bail and swivel. Refer to specific requirements for load (work piece) with permanently installed
hoist rings, before checking or retorquing.
When used in a threaded-hole, the effective thread length shall be 1-1/2 times the diameter of the
bolt for steel (see Fig. 12.6). For other thread engagements or engagement in other materials,
contact the swivel hoist ring manufacturer or a qualified person.
When used in a through-hole application, a nut and washer shall be used. The washer and nut
shall be in accordance with the swivel hoist ring manufacturers recommendations. The nut shall
be fully engaged (see Fig. 12.6).
The bushing flange (see Fig. 12.6) shall fully contact the load surface.
Spacers or washers shall not be used between the bushing flange and the mounting surface of the
load being lifted.
The load applied to the swivel hoist ring shall be centered in the bail to prevent side loading.
Any attached lifting component shall be narrower than the inside width of the bail to avoid
spreading (see Fig. 12.6).
Ensure that the swivel hoist ring WLL meets or exceeds the anticipated angular rigging tension.
Shock loading should be avoided.
12.5.1 General
Links and rings are usually designed and manufactured as a part of the lifting hardware for a
specific purpose, such as the peak link on multiple-leg slings. However, the rings and links may
also be found on the load-attachment end of slings. Figure 12-7 shows typical rings and links.
Table 12-4 a , b and c provide safe loads for weldless rings and links.
Ring and Link and Link and Link and Short link
thimble thimble closed short link and and
socket thimble thimble
Links and rings used for critical-lift service shall have an initial proof load test of 200% of the
rated capacity. Test weights shall be accurate to within -5%, +0% of stipulated values. If proof
testing cannot be verified, the links and/or rings shall be proof tested before being used to make a
critical lift.
12.6.1 Load-indicating devices are not required in routine operations where loads of known and
essentially consistent weight are to be handled. Rather, load-indicating devices are required for
use with loads of uncertain weight that could be within 90-100% of the rated capacity of the
equipment or maximum working load of any part of the tackle. Use load-indicating devices
where the equipment/tackle configuration could result in binding or friction of the load that could
cause a greater stress in the hoist or tackle than would result from the apparent hook load.
12.6.2 The accuracy of load-indicating devices shall depend on the requirements of the load system
planned and shall not restrict the system requirements; an accuracy of 2% of full-scale reading
within 10-70% of instrument range is recommended. The device should be selected so that the
estimated hook load lies between 10 and 70% of the instrument range.
12.6.3 Load-indicating devices shall have a design factor of not less than 3:1
12.7.1 General
12.7.1.1 A precision load positioning device in the load path shall have a design factor of no less than 5:1,
based on ultimate strength of the devices load bearing components.
12.7.1.2 Critical Lifts
See Chapter 2 for critical lift requirements.
12.8.1 General
12.8.1.1 Compression Hardware includes forged wire rope clips and wedge sockets.
12.8.1.2 Types cover by this section include:
12.8.1.2.1 U-bolt and double saddled. (see Fig 12-8)
12.8.1.2.2 Wedge sockets. (see Fig 12-9)
12.8.1.2.3 4 Other compression hardware shall be used only in accordance with recommendations of the
manufacturer or a qualified person.
12.8.1.3 Materials
12.8.1.3.1 Wire rope clip materials shall be of sufficient strength such that failure of the wire rope will
occur before failure of the wire rope clip at the temperatures that the manufacturer has specified
for use. Saddles shall be forged steel.
12.8.1.3.2 Wedge socket materials shall be of sufficient strength such that failure of the wire rope will
occur before failure of the wedge socket at the temperatures, specified for use by the
manufacturer.
12.8.1.4 Design Factor
12.8.1.4.1 The rated load for wire rope assemblies using compression hardware is based on the wire rope
minimum breaking force, 80% minimum connection efficiency, and the design factor of the wire
rope application. The rated load shall not be exceeded.
12.8.1.4.2 Compression hardware is not required to be proof tested unless specified by the purchaser. If a
proof test is specified, the load shall be applied to the wedge socket or the connection made by
the wire rope clips after the assembly is complete.
The proof load shall be at least 40%, but not exceed 50% of the minimum breaking force unless
approved by the compression hardware manufacturer or a qualified person.
After proof testing, wire rope clips on a finished assembly shall be re-tightened to the torque
recommended by the wire rope clip manufacturer or a qualified person.
The compression hardware shall then be inspected in accordance with paragraph 12.8.5
12.8.1.5 Identification
12.8.1.5.1 Wire rope clips shall have the manufacturers name or trademark and the saddle size either
forged or die-stamped into the saddle.
12.8.1.5.2 Wedge sockets shall have the manufacturers name or trademark, the size and model (if
required to match the wedge to the body) either forged, cast or die stamped into the wedge and
socket body.
12.8.1.6 Use
12.8.1.6.1 Compression hardware should not be in contact with the load or any obstruction during the lift.
12.8.1.6.2 Rigging using compression hardware should not be dragged on an abrasive surface or in
contact with sharp edges.
12.8.1.6.3 Wedge sockets should not be side loaded. Impacts can dislodge the wedge from the body and
should be avoided.
12.8.2 Assembly
12.8.3.1 Compression hardware are to be used at temperatures above 400F (204C) or below-40F (-
40C), the compression hardware manufacturer or a qualified person should be consulted.
12.8.3.2 The strength of compression hardware can be affected by chemically active environments such
as caustic or acid substances or fumes. The compression hardware manufacturer or a qualified
person should be consulted before compression hardware is used in chemically active
environments.
12.8.4 Training
Compression hardware users shall be trained in the selection, inspection, cautions to personnel,
effects of environment, and rigging practices as covered by this standard.
12.8.5 Inspections
Compression hardware shall be removed from service if damage such as the following is visible,
and shall only be returned to service when approved by a qualified person:
12.8.6.1 Missing or illegible manufacturers name or trademark and/or rated load identification.
12.8.6.2 Indications of heat damage including welding spatter or arc strikes.
12.8.6.3 Excessive pitting or corrosion.
12.8.6.4 Bent, twisted, distorted, stretched, elongated, cracked, or broken components.
12.8.6.5 Excessive nicks or gouges.
12.8.6.6 A 10% reduction of the original or catalog dimension at any point.
12.8.6.7 Evidence of unauthorized welding or modification
12.8.6.8 Unauthorized replacement components
12.8.6.9 Insufficient number of wire rope clips
12.8.6.10 Improperly tightened wire rope clips
12.8.6.11 Indications of wire rope slippage
12.8.6.12 Indications of wire rope damage
12.8.6.13 Improper assembly of other conditions, including visible damage, that cause doubt as to
continued use.
NOTE: Exhibit 12.1 is intended to be a sample form only. The equipment manufacturers
inspection/testing criteria supersede any other criteria. In cases where the equipment
manufacturer does not include inspection/testing criteria, other forms developed to facilitate
required inspection/testing are acceptable.
Exhibit 12.1 Rigging Accessories Load Test and Inspection (Hooks, Shackles, Rings, Etc.) (SAMPLE
FORM)
13.1.1 Marking
The manufacturers identification shall be forged, cast, or die-stamped on a low-stress and non-
wearing area of the hook.
13.1.2 Attachments
Hoisting hooks shall be fitted with a latch to bridge the throat opening to prevent the accidental
release of slings or attachments. Hooks without latches may be used in special applications
where the latch would interfere with the proper use of the hook, providing that (1) the use of the
hook is restricted to the application for which it is approved, and (2) in questionable cases,
concurrence is obtained from the appropriate safety organization.
13.1.3.1 A latch or mousing, bridges the throat opening of the hook for retaining slings, chains, or similar
parts under slack conditions and is not intended to support the load. Mousing shall not be used to
secure the hook throat in manlift operations.
13.1.3.2 Latch equipped hooks shall be used for all hoisting and rigging (H&R) operations unless the
application makes use of the latch impractical, or unsafe. The absence of a hook throat latch is
not allowed. Unless a specific impractical or unsafe situation can be substantiated, the hook latch
is mandatory.
13.1.3.3 Questions concerning requirements for throat latches shall be resolved by the AEDC Crane
System Engineer.
13.1.3.4 If a handle or latch support whose design requires heat-treating is welded to the hook, welding
shall be done prior to final heat-treating.
Hooks shall not be loaded beyond rated capacity except during load tests of equipment of which
they are a part.
13.1.5.1 Hook design shall meet generally accepted hook design standards and be compatible with the
requirements of ASME B30.10.
13.1.5.2 The hook material shall have sufficient ductility to permanently deform before failure at the
ambient temperatures at which the hook will be used.
13.1.5.3 When a latch is provided, it shall be designed to retain such items as slings under slack
conditions. The latch is not intended to support the load.
13.1.5.4 The bearing surfaces of new hooks shall be the arc of a circle. Gauge points, or hook gauges, for
measuring spread after load testing should be provided.
13.1.5.5 Field-fabricated hooks shall meet the requirements of this section and shall be approved by the
cognizant engineering and safety organizations.
13.2 INSPECTIONS
13.2.2.1 Prior to initial use, all new and repaired hooks shall be inspected by a qualified inspector to
ensure their compliance with the applicable provisions of ASME B30.10, paragraph 10-1.2.
Dated and signed inspection records shall be kept on file and shall be readily available.
13.2.2.2 Inspection procedure and record keeping requirements for hooks in regular service shall be
governed by requirements for the kind of equipment in which they are used. When such
requirements are stated in standards for the specific equipment, they shall take precedence over
the requirements of this section.
13.2.2.3 Operators or other designated personnel shall visually inspect hooks for deficiencies such as the
following each day or prior to use if the hook has not been in regular service (records are not
required):
13.2.2.3.1 Cracks, nicks, and gouges.
13.2.2.3.2 Deformation.
13.2.2.3.3 Damage from chemicals.
13.2.2.3.4 Latch engagement, damage to or malfunction of latch (if provided).
13.2.2.3.5 Evidence of heat damage.
13.2.2.4 A designated person shall examine deficiencies and determine whether they constitute a safety
hazard and whether a more detailed inspection is required.
13.2.3 [Deleted]
13.2.4.1 Operators or other designated personnel shall visually inspect the hook at the following intervals
(records are not required):
13.2.4.1.1 Normal service monthly. Operation at less than 85% of rated capacity except for isolated
instances.
13.2.4.1.2 Heavy service - weekly to monthly. Operation at 85 to 100% of rated capacity as a regular
specified procedure.
13.2.4.1.3 Severe service daily to weekly. Operation at heavy service coupled with abnormal operating
conditions, (i.e., extreme temperatures, corrosive atmospheres, etc.).
13.2.4.2 These inspections shall, in addition to the requirements of 13.2.3, include wear and hook
attachment and securing means.
13.2.4.3 A designated person shall examine deficiencies and determine whether they constitute a safety
hazard and whether a more detailed inspection is required.
13.2.5.1 A qualified inspector shall perform a complete inspection at the following intervals:
13.2.5.1.1 Normal service yearly.
13.2.5.1.2 Heavy service - semiannually.
13.2.5.1.3 Severe service quarterly.
13.2.5.2 A qualified person shall examine deficiencies and determine whether they constitute a safety
hazard.
13.2.5.3 The inspection shall include the requirements of paragraph 13.2.4, Frequent Inspection.
13.2.5.4 Hooks having any of the following conditions shall be removed from service until repaired or
replaced:
13.2.5.4.1 Deformation; any visibly apparent bend or twist from the plane of the unbent hook.
13.2.5.4.2 Any distortion of throat opening causing an increase in throat opening exceeding 5% not to
exceed inch (or as or as recommended by the manufacturer).
13.2.5.4.3 Any wear exceeding 10% (or as recommended by the manufacturer) of the original section
dimension of the hook or its load pin.
13.2.5.4.4 Cracks
13.2.5.4.5 If a latch is provided and it becomes inoperative because of wear or deformation or fails to
fully bridge the throat opening, the hook shall be removed from service until the device has been
repaired or replaced and the throat opening has been assessed as described above.
13.2.5.4.6 Missing or illegible hook manufacturers identification or secondary identification and rate
load identification.
13.2.5.4.7 Excessive pitting or corrosion.
13.2.5.4.8 Inability to lock any self-locking hook
13.2.5.4.9 Evidence of unauthorized alterations such as drilling, machining, grinding, or other
modifications.
13.2.5.5 If hooks are painted, a visual inspection should take the coating into consideration. Surface
variations can disclose evidence of heavy or severe service. The surface condition may call for
stripping the paint in such instances.
13.2.5.6 Dated and signed inspection records shall be kept on file and shall be readily available.
13.2.5.7 A sample load test and inspection form is included at Exhibit 12.1 in Chapter 12, Rigging
Accessories. This form is intended to be a sample only and is not intended to be mandatory.
13.3 LOAD HOOKS
13.3.1 Each new or replacement hook of 150-ton capacity or greater and a prototype of each hook design
of less than 150-ton capacity shall be proof-tested by the manufacturer in accordance with Table
13-1.
13.3.2 When proof tests are used, the hooks shall withstand the proof load application without permanent
deformation when the load is applied for a minimum of 15 seconds. This condition is considered
satisfied if the permanent increase in the throat opening does not exceed 0.5% or 0.01 in. (0.25
mm), whichever is greater.
13.3.3 For a duplex (sister) hook having a pin eye, the proof load for the eye shall be in accordance with
Table 13-1. The proof load shall be shared equally between the two prongs of a sister hook,
unless the hook is designed for unbalanced loading.
13.3.4 Hooks that have been proof-tested shall be inspected by the magnetic-particle method in
accordance with ASTM E-709 (Standard Practice for Magnetic Particle Examination) and shall
show no cracks, inclusions, or other relevant discrepancies; casting shall be evaluated in
accordance with ASTM E-165 (Standard Practice for Liquid Penetrant Inspection Method).
13.3.5 Performance testing of hooks shall not be required except where necessary to conform to the
requirements for the equipment of which they are part. When testing is specified, documentation
shall be uniquely identified to the hook by serial number or other identifier.
13.4.1.1 Hooks in normal service shall receive NDT for site-specific reasons if deemed appropriate by
facility management, the asset owner, a qualified inspector, or another designated person.
13.4.1.2 New crane/hoist hooks that will be assigned to critical lift service should receive an NDT by the
hook manufacturer. New crane/hoist hooks that will be assigned to heavy or severe service should
receive an NDT by the hook manufacturer. The NDT method, acceptance criteria, and
documentation requirements should be determined before the hook is purchased and specified on
the purchase requisition.
13.4.1.3 Existing crane/hoist hooks with a rated load greater than or equal to 10 tons and assigned to
heavy or severe service shall receive an NDT by a qualified inspector at the following intervals:
13.4.1.3.1 Heavy service Annually. Service that involves operating at 85% to 100% of rated load as a
regular specified procedure.
13.4.1.3.2 Severe service Semi-annually (every 6 months). Heavy service coupled with abnormal
operating conditions.
13.4.1.4 If visual examination reveals a surface intersecting discontinuity, twist, increased throat opening,
or any other potential defect, NDT shall be employed to further evaluate the hook, regardless of
the hooks service classification or rated load.
13.4.1.5 If detailed inspections are performed (refer to paragraphs 13.2.3.2., 13.2.4.3, and 13.2.5.2.), the
results shall be evaluated by a qualified person to determine the need for subsequent NDT.
13.4.1.6 If NDT is deemed necessary, it shall be performed in accordance with paragraph 13.4.3.
Dated and signed NDT records, traceable to the hook by a serial number or other identifier, shall
be kept on file as long as the hook remains in service and shall be retained in a master equipment
maintenance file which shall be maintained by the AEDC Crane System Engineer. A secondary
file may be centrally located or proportioned into satellite holding areas.
13.4.3.1 Use magnetic-particle testing or liquid-penetrant testing methods to inspect for surface
intersecting discontinuities.
13.4.3.2 A qualified inspector or designated person shall perform NDTs in accordance with the following
ASTM E-709 and ASTM E-165.
13.4.3.3 For magnetic-particle testing, a coil, yoke, or wet technique should be used to eliminate the
possibility of prod burns or arc strikes.
13.4.3.4 Perform an NDT with the hook in place unless conditions indicate that disassembly for thread or
shank inspection is necessary.
A designated person shall document and resolve the following relevant indications:
13.4.4.1 Arc strikes (welding or electrical).
13.4.4.2 Surface intersecting discontinuities 0.25 in. long or longer.
13.4.5 Discontinuity Removal
13.4.5.1 Two directions of discontinuity, P and T, are shown on Figure 13-1. Discontinuity P
parallels the contour of the hook, is considered nonserious, and does not require removal.
Discontinuity T, on the other hand, is transverse to the contour of the hook and is more serious;
when occurring in zones B, C, or D, discontinuity T may reduce the longevity of the hook.
13.4.5.2 Discontinuities may be removed by grinding longitudinally following the contour of the hook to
produce a smooth, gently undulating surface. In zones B and D, such grinding shall not reduce
the original hook dimension by more than 10%. Such a reduction will not affect the working load
limit rating or the ultimate load rating of the hook. In zone C, grinding shall not reduce the
original dimension by more than 5%.
13.4.5.3 Under normal and proper application, zone A is an unstressed zone. Therefore, it is not required
that discontinuities in that zone be ground out.
13.4.5.4 The hook shall be reexamined by performing an NDT after grinding to verify removal of relevant
discontinuities.
13.5 MAINTENANCE
13.6 OPERATION
Hook users shall do the following:
13.6.1 Determine that the weight of the load to be lifted does not exceed the load rating of the hook.
13.6.2 Avoid shock loading.
13.6.3 Center the load in the base (bowl or saddle) of the hook to prevent point loading of the hook.
13.6.4 Do not use hooks in such a manner as to place a side- or backload on the hook.
13.6.5 When using a device to bridge the throat opening of the hook, ensure that no portion of the load is
carried by the bridging device.
13.6.6 Keep hands and fingers from between the hook and the load.
13.6.7 Load duplex (sister) hooks equally on both sides, unless the hook is specifically designed for single
loading.
13.6.8 Do not load the pinhole in duplex (sister) hooks beyond the rated load of the hook.
NOTE: Exhibit 13.1 is intended to be a sample form only. The equipment manufacturers
inspection/testing criteria supersedes any other criteria. In cases where the equipment
manufacturer does not include inspection/testing criteria, other forms developed to facilitate
required inspection/testing are acceptable.
14.2.3 Modification/Rerating
14.2.3.1 Structural and mechanical lifting devices may be modified or rerated if the changes are analyzed
by a qualified engineer or the manufacturer of the lifting device.
14.2.3.2 Rerated or modified lift fixtures shall be load-tested as described in paragraph 14.2.6.2, Rated
Load Test, below.
14.2.4 Guarding
Exposed moving parts or pinch points, such as gearing, chain drives, and rotating shafts, that may
be a hazard to personnel during lifting operations if feasible, shall be guarded.
14.2.5 Inspections
Figure 14-3. Indentation-type gripping lifting devices Figure 14-4. Typical cask lift fixture
Safe Unsafe
14.2.6 Testing
14.2.6.2.1 All new, altered, modified, or repaired lifting devices shall be tested and inspected before use.
The results of the test and inspection shall be documented in the equipment history file.
14.2.6.2.2 The rated capacity shall not be more than 80% of the maximum load sustained during the test.
Test loads shall not be more than 125% of the rated capacity unless otherwise recommended by
the manufacturer. Test weights shall be accurate to within -5%, +0% of stipulated values.
14.2.6.2.3 The rated load test shall consist of the following:
Hoist the test load a sufficient distance to ensure that it is supported by the lifting device, or apply
the required load if the test is made using a testing machine. Personnel shall remain clear of
suspended loads.
Visually inspect the lifting device for deformation, cracks, or other defects after the load test is
completed.
14.2.7 Maintenance
14.2.8 Training/Qualification
14.2.8.1 Below-the-hook lifting device operators shall be trained and qualified as required in Chapter 6.
At a minimum, instruction should include the following:
14.2.8.1.1 Application of the lifting device to the load and adjustments to the device, if any, that adapt it
to various sizes or kinds of loads.
14.2.8.1.2 Any special operations or precautions.
14.2.8.1.3 Condition of the load itself required for operation of the lifting device such as balance, of
order of stacked loads, surface cleanliness, bending, and load thickness.
14.2.8.1.4 Procedure for storage of lifting device to protect it from damage.
14.2.8.1.5 Instructions for not exceeding the rated capacity of the lifting device or the capacity of the
hoisting equipment by the combined weight of the load, the lifting device, and the rigging.
14.2.8.2 Operators shall demonstrate the ability and competence to operate the lifting device as instructed
before assuming responsibility for using it.
14.2.9 Operation
14.2.9.1 Only the following personnel shall operate structural and mechanical lifting devices:
14.2.9.1.1 Qualified operators or riggers.
14.2.9.1.2 Trainees under the direct supervision of a qualified operator.
14.2.9.1.3 Maintenance and test personnel, when it is necessary in the performance of their duties.
14.2.9.1.4 Inspectors of lifting devices.
14.2.9.2 The following shall apply to all personnel who operate structural and mechanical lifting devices:
14.2.9.2.1 Observe the condition of the lifting device before use and during operation. If you observe a
defect that affects the continued safe use of the lifting device, remove it from service.
14.2.9.2.2 Place any attached load on the floor or ground and, after use, properly store the lifting device
before leaving.
14.2.9.2.3 Before they are used on each shift, test the lifting device controls. If any controls do not
operate properly, adjust or repair them before operations begin.
14.2.9.2.4 Do not load the lifting device in excess of its rated capacity (except for test loads) or handle
any load for which it is not designed.
14.2.9.2.5 Apply the lifting device to the load in accordance with established procedures.
14.2.9.2.6 Before lifting, ensure that lifting-device ropes or chains are not kinked and multiple-part lines
are not interwoven.
14.2.9.2.7 Ensure that the load is correctly distributed for the lifting device being used.
14.2.9.2.8 Do not use the lifting device for side pulls or sliding the load unless specifically authorized by
a qualified person or by an approved procedure.
14.2.9.2.9 Do not use a lifting device that is tagged Danger Do Not Operate or otherwise designated
as nonfunctional.
14.2.9.2.10 Do not remove Danger Do Not Operate tags from lifting devices without the approval of
the person who placed them or an authorized person.
14.2.9.2.11 Store the lifting device in a dry, inside location when not in use
14.2.9.2.12 Ensure that markings or tags are not removed or defaced. Replace missing or defaced
markings or tags.
See Chapter 2, Critical Lifts, for critical lift requirements. Structural and mechanical lifting
devices for critical-lift service shall have an initial proof-load test of not more than 125% of its
rated capacity. If proof-testing cannot be verified, the lifting device shall be proof-tested before
being used to make a critical lift.
Typical power-operated and mechanically operated vacuum lifting and manipulating devices are
shown in Figures 14-6 and 14-7. This section does not cover devices used to handle porous
materials, which requires special design and construction.
Four-pad powered vacuum lifting device Four-pad powered vacuum lifting device
manipulator
14.3.1 Design/Fabrication
Power- and mechanically-operated vacuum lifting devices shall be designed and fabricated
according to the provisions of ASME B30.20, 20-2.2.2.
14.3.2 Marking
14.3.2.1 The rated load of the lifter and each pad shall be legibly marked on its main structure or on a tag
attached to its main structure where it is visible.
14.3.2.2 Individual pads or groups of pads, controlled by shutoff valves, shall be marked with the rated
capacity of each pad or group of pads.
14.3.2.3 At a minimum, a nameplate, name tag, or other permanent marker shall be affixed to each lifter
displaying the following data:
14.3.2.3.1 Manufacturers name.
14.3.2.3.2 Model number or unit identification.
14.3.2.3.3 Weight of lifting-device.
14.3.2.3.4 Electric power (when applicable).
14.3.2.3.5 Pressure and volume of compressed air (when applicable).
14.3.2.3.6 Rated capacity.
14.3.2.4 Manual shutoff valves on individual pads or groups of pads shall be marked to show operating
position.
14.3.2.5 A label or labels shall be affixed to each vacuum lifting device in a readable position that
displays the word WARNING or other legend designed to bring the label to the attention of the
operator. The label shall also contain information cautioning against:
14.3.2.5.1 Exceeding the rated capacity or lifting loads not specified in the manufacturers instruction
manual.
14.3.2.5.2 Operating a damaged or malfunctioning unit or a unit with missing parts.
14.3.2.5.3 Operating when vacuum indicators show insufficient vacuum.
14.3.2.5.4 Operating the unit when vacuum pads are not spaced for equal loading.
14.3.2.5.5 Incorrect positioning of the lifting device on the load.
14.3.2.5.6 Lifting people.
14.3.2.5.7 Moving loads above people.
14.3.2.5.8 Removing/obscuring warning labels.
14.3.2.5.9 Operating the lifting device when the rated capacity, lifting-device weight, or safety markings
are missing (except in cases where the device cannot, for security or other reasons, be marked).
14.3.2.5.10 Making alterations or modifications to the lifting device.
14.3.2.5.11 Lifting loads higher than necessary and leaving suspended loads unattended.
14.3.2.6 A label shall be affixed to each unit that directs the user to consult the manufacturers manual if
the size or shape of the unit prohibits the inclusion of the above markings.
14.3.3 Installation
14.3.3.1 Vacuum lifting devices shall be assembled and installed in accordance with the manufacturers
instructions.
14.3.3.2 The power supply to the vacuum lifting device shall be the same as that shown on the nameplate
and shall be connected to the line side of the crane disconnect or to an independent circuit.
14.3.3.3 The user shall check for correct rotation of all pumps.
14.3.4 Inspections
Prior to their initial use, a qualified inspector shall inspect all new or repaired vacuum lifting
devices to ensure their compliance with paragraph 14.3.4.3, Periodic Inspection.
14.3.4.2 Frequent Inspection
14.3.4.2.1 The operator or other designated person shall inspect each vacuum lifting device at the
beginning of each shift or prior to use, if it has not been in regular service.
14.3.4.2.2 The inspection shall be for the following (records are not required):
Deformation, cracks, and excessive wear of load-bearing parts.
Adequate vacuum generator output
Cuts, tears, excessive wear, and foreign particles at vacuum pad seal rings.
Leakage, cuts, kinks, and collapsed areas of vacuum lines/connections.
Leaks or damage to the vacuum reservoir.
Failure of the entire vacuum system to function properly by attaching a non-porous, clean test
plate to the vacuum pads and then stopping the vacuum source. Vacuum levels in the system
shall not decrease by more than the manufacturers specified rate.
14.3.4.3.Periodic Inspection
14.3.4.3.1 A qualified inspector shall perform a complete inspection at the following intervals:
Normal service yearly. Inspect equipment at site of use.
Heavy service semiannually. Inspect equipment at site of use unless external conditions
indicate that disassembly should be done to permit detailed inspection
Severe service quarterly. Inspect equipment at site of use unless external conditions indicate
that disassembly should be done to permit detailed inspection.
Special or infrequent service as recommended by a qualified person before the first use and as
directed by the qualified person for any subsequent occurrences.
14.3.4.3.2 Lifting device service is defined as follows:
Normal operation with various weights within the rated load limit, or uniform loads less than
65% of rated load.
Heavy operation within the rated load limit that exceeds normal service.
Severe operation under normal or heavy service with abnormal operating conditions
14.3.4.3.3 This inspection shall include those conditions or items specified in 14.3.4.2, Frequent
Inspection, in addition to the following:
External evidence of looseness, wear, deformation, cracking, or corrosion.
External evidence of damage to supporting structure, motors, controls, and other auxiliary
components.
Check for suspect/counterfeit parts (see Chapter 1).
Presence of warning label required in 14.3.2.
14.3.4.3.4 A qualified inspector shall inspect fixtures not in regular use according to periodic inspection
requirements before placing them in service.
14.3.4.3.5 Dated inspection reports shall be prepared for each inspection. Inspection records shall be kept
on file and shall be readily available.
14.3.5 Testing
14.3.6 Maintenance
14.3.6.1 A preventive maintenance program shall be established and be based on recommendations made
by the vacuum lifting device manufacturer or a qualified person.
14.3.6.2 Replacement parts shall be equivalent to the original specifications.
14.3.6.3 The vacuum generator, vacuum pads, sealing rings, mufflers, and filters should be maintained
and cleaned according to the manufacturers specifications.
14.3.7 Training/Qualification
14.3.7.1 Vacuum lifting device operators shall be trained and qualified as specified in Chapter 6,
Personnel Qualification and Training. At a minimum, instruction should include the following
(as applicable):
14.3.7.1.1 Application of the lifting device to the load and adjustments of the device, if any, that adapt it
to various sizes or kinds of loads.
14.3.7.1.2 Any special operations or precautions.
14.3.7.1.3 Condition of the load itself required for operation of the lifting device such as balance, of
order of stacked loads, surface cleanliness, bending, and load thickness.
14.3.7.1.4 Procedure for storage of lifting device to protect it from damage.
14.3.7.1.5 Instructions for not exceeding the rated capacity of the lifting device or the capacity of the
hoisting equipment by the combined weight of the load, the lifting device, and the rigging.
14.3.7.1.6 Charging of the battery (if required).
14.3.7.1.7 The purpose of indicators, meters, or alarms on the vacuum lifting device.
14.3.7.1.8 The proper attachment of adaptors to vacuum lifting devices for handling of special loads.
14.3.7.2 Users shall demonstrate the ability and competence to operate the lifting device as instructed
before assuming responsibility for using it.
14.3.8 Operation
14.3.8.1 Only the following personnel shall operate vacuum lifting devices:
14.3.8.1.1 Qualified operators or riggers.
14.3.8.1.2 Trainees under the direct supervision of a qualified operator.
14.3.8.1.3 Maintenance and test personnel, when it is necessary in the performance of their duties.
14.3.8.1.4 Inspectors of lifting devices.
14.3.8.2 Operating
14.3.8.2.1 Before starting the lift, verify that the vacuum on indicator has reached the required level.
Also, verify that the vacuum lifting device has been correctly applied and a stable vacuum level
exists by lifting the load a few inches and observing conditions
14.3.8.2.2 Observe the condition of the lifting device before use and during operation. If you observe a
defect that affects the continued safe use of the lifting device, remove it from service.
14.3.8.2.3 Place any attached load on the floor or ground and, after use, properly store the lifting device
before leaving.
14.3.8.2.4 Before they are used on a shift, test the lifting device controls. If any do not operate properly,
adjust or repair them before operations begin.
14.3.8.2.5 Do not load the lifting device in excess of its rated capacity (except for test loads) or handle
any load for which it is not designed.
14.3.8.2.6 Apply the lifting device to the load in accordance with established procedures.
14.3.8.2.7 Before lifting, ensure that lifting-device ropes or chains are not kinked and multiple-part lines
are not interwoven.
14.3.8.2.8 Ensure that the load is correctly distributed for the lifting device being used.
14.3.8.2.9 Do not use the lifting device for side pulls or sliding the load unless specifically authorized by
a qualified person or by an approved procedure.
14.3.8.2.10 Warn all personnel near the lifting device and place the load on the floor or ground, if
possible to do so, if electrical power goes off while a load is being lifted.
14.3.8.2.11 Do not leave your position at the controls.
14.3.8.2.12 Do not use a lifting device that is tagged Danger Do Not Operate or otherwise designated
as nonfunctional.
14.3.8.2.13 Do not remove Danger Do not Operate tags from lifting devices without the approval of
the person who placed them or an authorized person
14.3.8.2.14 Store the lifting device in a dry, inside location when not in use.
14.3.8.2.15 Ensure that markings or tags are not removed or defaced. Replace missing or defaced
markings or tags.
See Chapter 2 for critical lift requirements. Vacuum lifting devices for critical-lift service shall
have an initial proof-load test of not more than 125% of its rated capacity. If proof-testing cannot
be verified, the lifting device shall be proof-tested before being used to make a critical lift.
14.4.1 Design/Fabrication
14.4.2 Marking
14.4.2.1 General
14.4.2.1.1 At a minimum, a nameplate, name tag, or other permanent marker shall be affixed to each
lifting magnet, and shall display the following data:
Manufacturers name, or if the magnet has been repaired or modified, the name and address of the
repairer/modifier.
Model or unit identification.
Weight.
Duty cycle, if applicable.
Cold current.
Rated capacity.
14.4.2.1.2 Also, battery-powered and external-powered lifting electromagnets and electrically controlled
permanent-magnet lifting magnets shall be marked with:
The voltage of the battery or primary power supply.
The cold current or watts at 68 F (20 C) and rated voltage.
14.4.2.1.3 A label or labels shall be affixed to each lifting magnet in a readable position that displays the
word CAUTION or other legend designed to bring the label to the attention of the operator.
The label shall also contain information cautioning against:
Operating when the battery capacity is inadequate.
Exceeding magnet duty cycle and disconnecting the magnet with the power on (for externally
powered electromagnets).
Operating if the internal control function indicator, where applicable, does not indicate a
complete cycle (on electrically controlled permanent magnets).
14.4.2.1.3 Operating with the control handle not fully in the Lift position (on manually controlled
permanent magnets)
14.4.2.2 Rated Load (Capacity)
14.4.2.2.1 General-application magnets shall include the rated load (capacity) of the magnet on the lifting
magnet or on a tag attached to it. This capacity rating shall refer to the instruction manual for
information relating to decreases in rating due to the load surface condition, thickness, percentage
of contact with magnet, temperature, metallurgical composition, and deflection.
14.4.2.2.2 Specified-application magnets shall include the application load (capacity) of the magnet on
the lifting magnet or on a tag attached to it. This capacity rating shall refer to the specific loads
for which it applies.
14.4.2.3 Controls
The position of the control switch or handle of a lifting magnet shall be marked with Lift,
Off, and Drop, or equivalent terms indicating the mode of operation of the lifting magnet.
14.4.3 Installation
14.4.4 Inspections
Deformation, wear, and corrosion of all members, fasteners, locks, switches, warning labels, and
lifting parts.
Check for suspect/counterfeit parts (see Terminology and Definitions, Chapter 1).
Operation and condition of electrical components (i.e., meters, indicators, and alarms).
Magnet coil tested for ohmic/ground readings and readings compared to manufacturers
standards.
14.4.4.3.4 A qualified inspector shall inspect a lifting magnet that has been idle for 1 month or more
according to periodic inspection requirements before placing it in service.
14.4.4.3.5 Dated inspection reports shall be prepared for each inspection. Inspection records shall be kept
on file and shall be readily available.
14.4.5 Testing
14.4.6 Maintenance
14.4.6.1 A preventive maintenance program shall be established and be based on recommendations made
by the manufacturer or a qualified person.
14.4.6.2 Replacement parts shall be equivalent to the original specifications.
14.4.6.3 Before adjustment and repairs are started on a lifting magnet or its controls, maintenance
personnel shall take the following precautions:
14.4.6.3.1 Ensure that all sources of magnet power are disconnected and locked out, tagged out, or
flagged.
14.4.6.3.2 Ensure that a magnet removed for repair is tagged as defective.
14.4.6.4 Only qualified personnel shall work on equipment when adjustments and tests are required.
14.4.6.5 After adjustments and repairs have been made, the lifting magnet shall not be returned to service
until it has been inspected according to paragraph 14.4.4.3.
14.4.6.6 Dated records of repairs and replacements should be available.
14.4.6.7 Maintenance personnel shall ensure that any defective condition disclosed by the inspection is
corrected before operation of the lifting magnet is resumed. Repairs shall be done only by
designated persons.
14.4.7 Training/Qualification
14.4.7.1 Magnetic lifting device operators shall be trained and qualified as specified in Chapter 6,
Personnel Qualification and Training. At a minimum, instruction should include the following:
14.4.7.1.1 Application of the lifting device to the load and adjustments of the device, if any, that adapt it
to various sizes or kinds of loads.
14.4.7.1.2 Any special operations or precautions.
14.4.7.1.3 Condition of the load itself required for operation of the lifting device such as balance, degree
of order of stacked loads, surface cleanliness, bending, and load thickness.
14.4.7.1.4 Procedure for storage of lifting device to protect it from damage.
14.4.7.1.5 Instructions for not exceeding the rated capacity of the lifting device or the capacity of the
hoisting equipment by the combined weight of the load, the lifting device, and the rigging.
14.4.7.1.6 Charging of the lifting magnet battery (if required).
14.4.7.1.7 The purpose of indicators, meters, or alarms on the lifting magnet.
14.4.7.1.8 The proper attachment of adaptors to lifting magnets for handling of special loads.
14.4.7.2 Operators shall demonstrate the ability and competence to operate the lifting device as instructed
before assuming responsibility for using it.
14.4.8 Operation
14.4.8.4.4 Before raising the load more than 2 inches (50 mm), ensure that nay adjustable input control is
switched to the FULL POWER or FULL ON position and remains in this position until the
load is removed.
14.4.8.5 Electrically Controlled Permanent Magnets
Before raising the load, check the internal control function indicator, where applicable, to confirm
proper operation of the lifting magnet.
14.4.8.6 Manually Controlled Permanent Magnets
Before raising the load, confirm that the control handle is in the LIFT or ON position and the
control handle latch is operating.
14.5.1 Design/Fabrication
Remote-operated magnetic lifting devices shall be designed and fabricated in accordance with the
provisions of ASME B30.20, 20-4.2.2.
14.5.2 Marking
At a minimum, all new lifting magnets shall be provided with a nameplate, name tag, or other
permanent marker displaying the following information
14.5.2.1 Manufacturers name and address, or if the magnet has been repaired or modified, the name and
address of the repairer/modifier.
14.5.2.2 Manufacturers model or unit identification.
14.5.2.3 Weight.
14.5.3.4 Duty cycle, if applicable.
14.5.3.5 Cold current.
14.5.3 Installation
14.5.3.1 Remote-operated magnets shall be installed according to the manufacturers recommendations.
14.5.3.2 Operators shall ensure that:
14.5.3.2.1 External power input is of the correct voltage and amperage.
14.5.3.2.2 Power conductors and controls are of adequate rating and are insulated or otherwise protected
against accidental interruption or damage.
14.5.4 Inspections
14.5.4.1 Initial Inspection
Prior to their initial use, a qualified inspector shall inspect all new, modified, or repaired lifting
magnets to ensure compliance with paragraph 14.5.4.3, Periodic Inspection.
14.5.4.2 Frequent Inspection
14.5.4.2.1 The operator or other designated personnel shall visually inspect each magnetic lifting device
at the beginning of each shift or prior to use, if it has not been in regular service.
14.5.4.2.2 The inspection shall be for the following (records are not required):
Lifting magnet face for smoothness or presence of foreign materials, if applicable.
Magnet suspension system.
All visible electrical conductors (without disassembly).
14.5.4.3 Periodic Inspection
14.5.4.3.1 A qualified inspector shall perform a complete inspection of the lifting device with the
equipment in place at the following intervals:
Normal service yearly.
Heavy service quarterly.
Severe service quarterly.
Special or infrequent service as authorized by a qualified person before the first use and as
directed by the qualified for any subsequent occurrences.
14.5.5.1 All new, modified, or repaired lifting magnets shall be tested prior to initial use. Tests shall be
performed by a qualified inspector or under the direction of that inspector. Dated reports shall be
kept on file.
14.5.5.2 Testing shall include the following:
14.5.5.2.1 A check for proper operation of all electrical equipment.
14.5.5.2.2 A visual inspection of the lifting magnet for visible defects.
14.5.6 Maintenance
14.5.6.1 A preventive maintenance program shall be established and be based on the recommendations of
the manufacturer or a qualified person.
14.5.6.2 Replacement parts shall be equivalent to original specifications.
14.5.6.3 Before maintenance is started on a lifting magnet or controls, maintenance personnel shall take
the following precautions:
14.5.6.3.1 Ensure that all sources of magnet power are disconnected and locked out, tagged out, or
flagged.
14.5.6.3.2 Ensure that a magnet removed for repair is tagged as defective.
14.5.6.4 Only qualified personnel shall work on equipment when maintenance and test are required.
14.5.6.5 After repairs have been made, the lifting magnet shall not be returned to service until it has been
inspected according to paragraph 14.5.4.3, Periodic Inspection.
14.5.6.6 Dated records of repairs and replacements should be available.
14.5.6.7 Any defective condition disclosed by the inspection shall be corrected before the lifting magnet
is returned to service.
14.5.7 Training/Qualification
14.5.7.1 Operators shall be trained and qualified as specific in Chapter 6, Personnel Qualification and
Training. At a minimum, instruction should include the following:
14.5.7.1.1 Application of the lifting device to the load and adjustments of the device, if any, that adapt it
to various sizes or kinds of loads.
14.5.7.1.2 Any special operations or precautions.
14.5.7.1.3 Condition of the load itself required for operation of the lifting device, such as balance, of
order of stacked loads, surface cleanliness, bending, and load thickness.
14.5.7.1.4 Procedure for storage of the lifting device to protect it from damage.
14.5.7.1.5 Instructions for not exceeding the rated capacity of the lifting device or the capacity of the
hoisting equipment by the combined weight of the load, the lifting device, and the rigging.
14.5.7.1.6 Charging of the lifting magnet battery (if required).
14.5.7.1.7 The purpose of indicators, meters, or alarms on the lifting magnet.
14.5.7.1.8 The proper attachment of adaptors to lifting magnets for handling of special loads.
14.5.7.2 Operators shall demonstrate the ability and competence to operate the lifting device as instructed
before assuming responsibility for using it.
14.5.8 Operation
14.5.8.1 Only the following qualified personnel shall operate lifting devices:
14.5.8.1.1 Designated persons.
14.5.8.1.2 Trainees under the direct supervision of a designated person.
14.5.8.1.3 Maintenance and test personnel, when it is necessary in the performance of their duties.
14.5.8.1.4 Inspectors of lifting devices.
14.5.8.2 The following shall apply to all personnel who operate remote-operated magnets:
14.5.8.2.1 Place any attached load on the floor or ground and, after use, properly store the lifting device
before leaving it.
14.5.8.2.2 Before they are used during a shift, test all controls. If any do not operate properly, adjust or
repair them before operations begin.
14.5.8.2.3 Do not load the lifting device in excess of its rated capacity or handle any load for which it is
not designed.
14.5.8.2.4 Apply the lifting device to the load in accordance with established procedures.
14.5.8.2.5 Before lifting, ensure that lifting-device ropes or chains are not kinked and that multiple-part
lines are not interwoven.
14.5.8.2.6 Ensure that the load is correctly distributed for the lifting device being used.
14.5.8.2.7 Ensure that the temperature of the load does not exceed the maximum allowable limits of the
lifting device.
14.5.8.2.8 Do not use the lifting device for side pulls or sliding the load unless specifically authorized by
a qualified person.
14.5.8.2.9 Do not use a lifting magnet that is tagged Danger Do Not Operate or otherwise designated
as nonfunctional.
14.5.8.2.10 Do not remove Danger Do Not Operate tags without the approval of the person who
placed them or an authorized person.
14.5.8.2.11 Store the lifting device in a designated location when not in use.
NOTE: Exhibit 14.1 is intended to be a sample form only. The equipment manufacturers
inspection/testing criteria supersede any other criteria. In cases where the equipment
manufacturer does not include inspection/testing criteria, other forms developed to facilitate
required inspection/testing are acceptable.
Exhibit 14.1 Lifting Bars And Spreaders Load Test (Sample Form)
This chapter provides safety standards designated to verify, based on personal observations, certified
records, or direct reports, that a specific action has been performed in accordance with specified
requirements. It provides requirements for the operation, inspection, testing, and maintenance for
miscellaneous lifting devices, including self-contained shop cranes (see Figure 16-1) as addressed by
ASME PALD (Portable Automotive Lifting Devices.); truck mounted cranes (See Figure 16-2) with
a capacity of 1 ton or less not covered in ASME B30.5 (Mobile and Locomotive Cranes.); and
portable A frames (sometimes referred to as portable gantries) (see Figure 16-3),
16.1 GENERAL
16.1.1.1 Operators of self-contained shop cranes and portable A frames shall be familiar with,
understand and follow the operating instructions provided by the equipment manufacturer.
16.1.1.2 Operators of truck mounted cranes with capacities of 1 ton or less shall be trained as required in
Chapter 6.
16.1.2.1 Safety markings shall be legible and conform to the ANSI Z535.
16.1.2.2 Markings, or decals, etc. must be provided and affixed by the use of durable materials in a
location visible to the operator in order to provide a clear understanding of any special warning,
capacity information, etc.
16.1.2.3 Shop cranes shall have the rated capacity for each specified boom and leg position marked in a
prominent location on the equipment.
16.1.2.4 Small cranes 1 ton or less shall have a durable rating chart with legible letters and figures
attached in a location accessible to the operator.
16.1.2.5 Each portable A frame shall have its rated capacity legibly marked on the structure on each
side of the primary beam.
16.1.2.6 The manufacturers name, product serial number, and model number must be permanently and
legibly marked on each portable A frame.
16.1.2.7 Operating instructions developed by the original manufacturer or supplier shall be maintained
and readily available to the operator.
16.1.2.8 For small cranes 1 ton or less, operating instructions may be maintained on the vehicle on which
the crane is installed.
16.1.2.9 Safety instructions for shop cranes and portable A frames should include the following:
16.1.2.9.1 Study, understand, and follow all instructions before operating this device.
16.1.2.9.2 Do not exceed rated capacity.
16.1.3 Modifications
16.1.3.1 Miscellaneous lifting devices may be modified or re-rated provided that the modifications of
supporting structures are analyzed thoroughly by a qualified engineer or by the manufacturer of
the lifting device.
16.1.3.2 A re-rated lifting device, or one whose load-supporting components have been modified, shall be
tested per 16.3. The new rated capacity shall be displayed per 16.1.2.
Miscellaneous lifting devices shall not be loaded beyond its rated capacity, except for test
purposes, as described in 16.3.
16.1.5.1 Operating controls shall be readily visible and accessible to the operator and shall not subject the
operator to pinch points, sharp edges, or snagging hazards.
16.1.5.2 The release system for shop cranes shall require intentional positive action by the operator for
release to prevent accidental lowering.
16.1.6.1 Shop cranes shall be equipped with load hooks and/or chain capable of sustaining the proof load
of the crane.
16.1.6.2 Latch-equipped hooks shall be used for all operations unless the application makes using the
latch impractical, unnecessary, or unsafe. The absence of a hook-throat latch is not
indiscriminately allowed.
16.1.7.1 Wire rope, (single line capacity) used on small cranes 1 ton or less shall have a minimum design
factor of 3.5:1, based upon breaking strength.
16.1.7.2 Small cranes 1 ton or less shall be equipped with properly sized wire rope sheaves in lieu of flat
spools.
16.1.8 Assembly
16.1.8.1 Portable A frames shall only be assembled by qualified personnel. Manufacturers instructions
shall be adhered to regarding setup and assembly.
16.1.8.2 Portable A frame components from different manufacturers shall not be intermixed with
components from other A frames regardless of similarities in manufacturers or rated capacities.
16.1.8.3 Only manufacture-approved methods of attaching a hoist to the A frame structure such as
approved beam clamp or trolley shall be used. Trolleys or beam clamp working load limits shall
not exceed the capacity rating of the A frame and must be designed for the type frame flange (see
Figures 16-4 and 16-5). Hoists attached to the A frame must have a rated capacity equal to or less
than all supporting components. [Down rating of hoist to A frame capacity is acceptable with
administrative controls and markings in place)
16.1.8.4 Load-carrying trolleys must suit the shape and weight of the specific load. Trolley wheel design
must be matched properly to the rail shape and size to ensure that trolleys do not slip off the track
and drop the load.
16.1.8.5 If a new or replacement trolley is installed on a monorail, the qualified person installing the
trolley shall ensure by actual operational verification or measurement that the installed trolley
stops on the system are compatible with the new trolley, thereby preventing trolley travel past a
point where it could fall from the rail. On those systems where a series of monorails may be
connected by a bridge or turntable, verification of functional trolley stops on all accessible rails
must be established or administrative controls placed limiting access to a specific work area
during the period the trolley is in service.
Figure 16-1. Self-Contained Shop Crane. Figure 16-2. Truck Mounted Crane
Capacity 1 Ton or Less.
16.2 INSPECTIONS
16.2.1 General
Equipment shall operate with a smooth, regular motion without any hesitation, abnormal
vibration, binding, or irregularity. There shall be no apparent damage, excessive wear, or
deformation of any load-bearing part of the equipment. All safety devices, controls, and other
operating parts of the equipment shall be checked during each inspection and shall be in good
working order.
A qualified inspector shall inspect all miscellaneous lifting devices prior to initial use, after
disassembly and reassembly, and after load testing. The inspection shall be performed in
accordance with manufacturer's requirements. If manufacturer's instructions are not available, an
engineering evaluation of the equipment shall be performed to establish necessary inspection
procedures. Dated and signed inspection reports shall be kept on file and shall be readily
available.
16.2.3.1 Operators or other designated personnel shall visually inspect miscellaneous lifting equipment
each day or prior to use if the equipment has not been in regular service (records are not
required). The inspection shall include, but not be limited to inspecting the following:
16.2.3.1.1 All control mechanisms for maladjustment interfering with proper operation.
16.2.3.1.2 Hook and latch for deformation, cracks, and wear.
16.2.3.1.3 Hydraulic systems for proper operation.
16.2.3.1.4 Wire rope for kinking, crushing, bird caging, and corrosion.
16.2.3.1.5 Chain for bent links, stretched links, cracks, scores, abrasions or heat damage.
16.2.3.1.6 All safety devices for malfunction
16.2.3.1.7 Inspection items identified in manufacturers operating instructions.
16.2.3.1.8 Visually inspect for bent, broken, damaged, corroded, cracked, or missing parts.
16.2.3.1.9 Verify the hoist and all components installed on portable A frames do not exceed the rated
capacity of the unit
16.2.3.1.10 Verify required markings are installed and legible.
16.2.3.1.11 Perform a function test of trolley and hoist installed on portable A frames to ensure proper
operation.
16.2.3.2 Operators or other designated personnel shall examine deficiencies and determine whether they
constitute a safety hazard.
16.3 TESTING
The load lifting and lowering mechanisms shall be tested during an initial test and after load
testing.
16.3.2.1 Prior to initial use, all new portable A frames and small cranes (1 ton or less) and those upon
which load-sustaining parts have been modified, replaced, or repaired shall be load-tested by a
qualified inspector or under the direction of that inspector.
16.3.2.2 A written report shall be furnished by the inspector showing test procedures and confirming the
adequacy of repairs or alterations. Test reports shall be kept on file and shall be readily available
to appointed personnel.
16.3.2.3 Test loads shall not be less than 100% or more than 125% of the rated capacity, unless otherwise
recommended by the manufacturer or a qualified person.
16.3.2.4 Shop cranes built to design specifications are proof-tested by the manufacturer in accordance
with ASME PALD, Part 12. After repair or modification, a qualified engineer shall determine if
testing is required.
16.4 MAINTENANCE
16.5.1 Before operating, operators shall have an understanding of the lifting devices operating safety
instructions.
16.5.2 Operators shall not:
16.5.2.1 Engage in any practice that will divert their attention while operating miscellaneous lifting
devices.
16.5.2.2 Operate the lifting device beyond its rated capacity (except for rated load tests).
16.5.2.3 Operate miscellaneous lifting devices when physically or mentally unfit.
16.5.3 Operators shall:
16.5.3.1 Before moving the load, lower the load to the lowest possible point.
16.5.3.2 Only operate shop cranes on hard, level surfaces capable of sustaining the load.
16.5.3.3 Ensure the load does not drop suddenly or swing during transportation.
16.5.3.4 Whenever there is doubt as to safety, consult with the responsible management before operating
miscellaneous lifting devices.
16.5.3.5 If adjustment or repairs are necessary, or any other defects are known, report the potential
problem promptly to responsible management.
16.5.3.6 Ensure inspections are current and required markings are clearly labeled on the A frame and all
hoisting components.
16.5.3.7 Always push the portable A frames, not the load when movement of the A frame is required.
16.5.3.8 Ensure the load is not attached to the floor or any other component prior to hoisting. Remove all
obstacles that impede lifting.
16.5.3.9 When moving a load, keep it as close to the floor as possible. Make sure that no part of the body
is placed under the load at any time.
16.5.3.10 Not allow the load to swing or roll against support members.
16.5.3.11 Not adjust the height of portable A frames when the unit is under load.
16.5.3.12 Secure trolley and hoist on portable A frames in center of I beam when adjusting height.
16.5.4 If necessary to leave a shop crane or a portable A frame with a suspended load unattended, the
immediate area (about 30 inches) around the shop crane or portable A frame should be posted or
barricaded to restrict entry of unauthorized personnel.
ASME B30.17, Overhead and Gantry Cranes (Top Running Bridge, Single Girder, Underhung Hoist)
ASME B30.20, Below-The-Hook Lifting Devices
ASME B30.21, Manually Lever Operated Hoists
ASME B30.22, Articulating Boom Cranes
ASME B30.23, Personnel Lifting Systems
ASME B30.26, Rigging Hardware, Safety Standard for Cableways, Cranes, Derricks, Hoist, Hooks,
Jacks, and slings
ASME PALD, Portable Automotive Lifting Devices
ASME HST-1M, Performance Standard for Electric Chain Hoists
ASME HST-2M, Performance Standard for Hand Chain Manually Operated Chain Hoists.
ASME NQA-1, Quality Assurance Program Requirements for Nuclear Facilities
American Society for Nondestructive Testing
Recommended Practice No. ASNT-TC-1A
American Welding Society
ANSI/AWS D1.1 Structural Welding Code Steel
Crane Manufacturers Association of America
CMAA No. 70, Specification for Electric Overhead Traveling Cranes
CMAA No. 74, Specification for Top Running and Under Running, Single Girder, Electric Overhead
Traveling Cranes
Department of Energy
DOE 440.1A, Worker Protection Management for Federal and Contractor Employees.
DOE 440.1-6, Suspect Counterfeit Items Guide
DOE 1090 Hoisting and Rigging Standard
Department of Labor
29 CFR 1910, Occupational Safety and Health Standards for General Industry
29 CFR 1926, Occupational Safety and Health Regulations for Construction
Department of Transportation
49 CFR 391.41, physical Qualification for Drivers
National Fire Protection Association
NFPA 505, Powered Industrial Trucks, Type Designation and Areas of Use.
NFPA 70, National Electrical Code
Power Crane and Shovel Association
PCSA-4, Mobile Power Crane and Excavator Standards and Hydraulic Crane Standards
Society of Automotive Engineers
SAE J376-85, Load-Indicating Devices in Lifting Crane Service