LEEA New Rigging Manual
LEEA New Rigging Manual
LEEA New Rigging Manual
ENGINEER
.S T U D E N T M A N U A L .
Prepared by : Mohsen Abozaid
TABLE OF CONTENTS
1. Introduction 3
2. Duties and Responsibilities (Summarized) 4
3. Safety Awareness
3.1. General 5
3.2. Safety System 5
3.3. Personal Protective Equipment 5
3.4. Lifting Hazards 6
3.5. Electrocution Hazard 8
3.6. Overload and Maintenance Hazards 8
4. Hand Signals
4.1. Hand or Radio Signal Policy 9
4.2. Use of Standard Hand Signals 9
5. Types of Hitches 13
6. Wire Rope Slings 14
7. Chain Slings 23
8. Synthetic Flat Webbing 24
9. Synthetic Round Slings 33
10. Shackles 37
11. Plate Clamps 41
12. Hooks 45
13. Eyebolts 48
14. Turnbuckles 51
15. Lifting Beam 52
16. Beam Clamp 54
17. Lifting Appliance
17.1. Hand-Operated Chain Block 57
17.2. Chain Lever Hoist 61
17.3. Wire Rope Grip/Pull Lifting Machine 64
17.4. Familiarization of Crane Operation:
17.4.1. Basic Crane Configuration 66
17.4.2. Basic Crane Function 66
17.5. Familiarization of Crane Types:
17.5.1. Rough Terrain 67
17.5.2. Tower crane 67
17.5.3. Crawler Crane 68
17.5.4. Offshore Crane 68
TABLE OF CONTENTS
18. Load
18.1. Standard Signs Identification 69
18.2. Container/Cargo Boxes 70
18.3. Fuel/Chemical Tanks 70
18.4. Gas Cylinder Rack 71
18.5. Man Baskets 71
18.6. Common Loads
18.6.1. Concrete and Muck Skips 72
18.6.2. Scaffold Tubes 72
18.6.3. Palletized Loads 72
18.6.4. Beams 72
18.6.5. Stillages 73
18.6.6. Rubbish Skips 73
18.6.7. Pipes 73
18.6.8. Mesh 74
18.6.9. Pre Fabricated Rebar Assemblies 74
18.6.10. ISO Containers and Portable Offices 74
18.7. Centre of Gravity 75
19. Table/Chart
19.1. Shackle Angular Loading Capacity 76
19.2. Conversion Table 77
19.3. Formula Volume of Common Shapes 78
19.4. Approximate Density of Common Materials 79
20. Calculation
20.1. Example of Calculating of Sling Loading No. 1 80
20.2. Example of Calculating of Sling Loading No. 2 81
20.3. Sling Angles 82
21. Glossary 83
22. Lifting Plan Preparation
23 Lifting Law.
1. INTRODUCTION
Knowledge of the equipment and materials with which we work is one of the most
important factors in accident prevention. Each piece of equipment and material has
been designed and developed to serve a specific purpose and knowledge of what it
can and cannot do, not only improves efficiency but also eliminates hazards.
Owing to the many variations in rigging practices and the different ways in which rigging is
used, recommendations must, of necessity, be framed in general terms. The
recommendations can only be advisory in nature and are intended to complement
relevant regulations and manufacturers’ requirements which must be observed.
The rigger must apply his or her intelligence, common sense, and experience in
anticipating what will happen when the load is moved. This thought process must
take place before the work is started. In order to ensure the design of a safe and
efficient system, the rigger must answer such question as:
Shackle
Eyebolt
Load
2. RIGGERS
DUTIES AND RESPONSIBILITIES
(SUMMARIZED)
01 Observe all Safety Ensure you have the correct PPE to carry out your job on site.
Pre-cautions Observe All Safety Warning Signs and any Emergency
Stop Signals from anyone
Ensure that you aware of Fire fighting Equipment and
First Aid Procedures (Emergency Contact number for
Qatar is 999)
02 Check the load to Find the weight and Centre of Gravity (COG)
be lifted Ensure that the hook is directly above the centre of gravity of
the load prior to lifting, NO SIDE LOADING
Identify the type of load, and locate the maximum radius.
03 Check the working Identify the hazards (Power Lines, People, other Equipments
area and ground conditions.
04 Inspect Rigging Ensure that you carry out a Pre Use Check on Equipment to be
Gears and Lifting used.
Ensure that the equipment used has a valid Test
Equipment
Certificate and correct colour code.
05 Attaching and Always refer to the correct rigging information chart
Detaching Lifting Identify the type of Hitch to be used (Choker, Vertical or
Basket)
Equipment
Connect the load ensuring that the sling angle is appropriate
to the capacity of the slings used.
06 Communication Ensure that You and Crane Operator understand the
between the Crane correct standard signal being used.
If you can not see the crane operator when carrying out lifts.
Operator and
Ensure that other means of communication are in place
Rigger (Radio’s and the Correct procedure for use)
07 Secure and After using any lifting equipment, Ensure that it is Cleaned
Maintain Lifting and Returned in a Serviceable condition and Stored correctly.
Equipment
08 Reporting Always ensure that you report anything that could be
considered a Danger, Either with equipment on your pre-use
check or by anything you have seen on your working site.
Any defects found on any lifting equipment after use are to be
reported and not to be used until certification. To ensure the
equipment is safe to be used by a competent person.
3.SAFETY AWARENESS
3.1. GENERAL:
Safe lifting and rigging often needs to be carried out
at a height where danger from falling is greater than
normal.
3.2. SAFETY SYSTEMS:
Ensure all hands are free of lifting tackle and stand clear before
the load strain is taken.
Stay back when slings are pulled out from under loads.
(see Fig. 12)
Fig. 12
Ensure that NO load is to be lifted where the weight is not
stated or unknown. (see Fig. 13)
Observe & note other activities within the crane’s operating
area to avoid the development of any unforeseen hazards.
Fig. 13
Check that the area around the load to be lifted is clear and
that the load is not attached to the floor, transportation
cradle or adjacent equipment.
(see Fig. 14)
Fig. 17
4. HAND SIGNALS
4.1. HAND OR RADIO SIGNAL POLICY:
4.1.1. Ensure that both the Rigger and Crane Operator are familiar with the
Method of Signaling to be used.
4.1.2. Always use clear and distinct signals (either by Hand or by Radio) to
control lifting operations.
4.1.3. If radios are chosen, then the following method of use must be followed.
All instructions must be repeated continuously, for example “LOWER, LOWER,
LOWER….” until the movement is complete. If the instructions stop getting
through to the crane operator, he should immediately bring the load to a HALT.
This will guard against failure of the radio system.
4.1.4. In poor light conditions ALL hand signal shall be exaggerated
4.1.5. Clearly indicate to the Crane Operator where the load has to be moved /
placed and, where possible, he should follow each load to its destination
4.1.6. When lifting a load. Stop the load just clear of the ground to check
security and balance of the load, and check the proper function of the crane’s
hoist brakes.
4.1.7. Stop the lifting operation if anything out of the ordinary occurs and check
that it is safe to continue the operation.
4.1.8. When working at night, a reflective orange glove is useful for making
hand signals more visible.
4.2. ALWAYS USE THE STANDARD HAND SIGNALS:
Fig. 1 HOIST. With forearm vertical, Fig. 2 LOWER. With arm extended
forefinger pointing up, move hand in downward, forefinger pointing down,
small horizontal circle move hand in small horizontal circle
4. HAND SIGNALS
4.2. ALWAYS USE THE STANDARD HAND SIGNALS:
Fig. 3 USE MAIN HOIST. Tap fist on Fig. 4 USE WHIPLINE (Auxiliary
head; then use regular signals Hoist). Tap elbow with one hand ;
then use regular signals
Fig. 5 RAISE BOOM. Arm extended, Fig. 6 LOWER BOOM. Arm extended,
fingers closed, thumb pointing upward. fingers closed, thumb pointing downward.
Fig. 7 MOVE SLOWLY. Use one hand to give Fig. 8 RAISE THE BOOM AND LOWER
any motion signal and place other hand THE LOAD. With arm extended, thumb
motionless in front of hand giving the motion pointing up, flex fingers in and out as
signal. (Hoist slowly shown as example) long as load movement is desired
4. HAND SIGNALS
4.2. ALWAYS USE THE STANDARD HAND SIGNALS: (cont.)
Fig. 9 LOWER THE BOOM AND RAISE THE Fig. 10 SWING. Arm extended, pointing
LOAD. With arm extended, thumb the direction of swing of boom.
pointing down, flex fingers in and out as
long as load movement is desired
Fig. 11 STOP. Arm extended, palm down, Fig.12 EMERGENCY STOP. Both arms
move arm back and forth horizontally. extended, palms down, move arms back
and forth horizontally.
Fig. 13 TRAVEL. Arm extended forward, Fig. 14 DOG EVERYTHING. Clasp hands in
hand open and slightly raised, make front of Body
pushing motion in direction of travel
4. HAND SIGNALS
4.2. ALWAYS USE THE STANDARD HAND SIGNALS: (cont.)
Fig. 17 TRAVEL (Both Tracks). Use both Fig. 18 TRAVEL (One Tracks). Lock on side
fists in front of body, making a circular indicated by raised fist. Travel opposite
motion about each other, indicating track in direction indicated by circular
direction of travel, forward or backward. motion of other fist, rotated vertically in
(For land crane only) front of body. (For land crane only)
Fig. 19 EXTEND BOOM (Telescoping Boom) Fig. 20 RETRACT BOOM (Telescoping Boom)
One Hand Signal. One fist in front of chest, One Hand Signal. One fist in front of chest,
with thumb tapping chest. thumb pointing outward and heel of fist
tapping chest.
5. TYPES OF HITCHES
APPLICATION/RIGGING METHOD:
BASKET HITCHES
Metal Mesh
Slings
CHOKER HITCHES
BRIDLE HITCHES
6. WIRE ROPE SLING
6.1. TYPE:
6.2. IDENTIFICATION:
CORE
IDENTIFICATION
MARKING WIRE
Fig. 6
HOOKS
SAFETY CATCHES
Fig. 5
6. WIRE ROPE SLING
6.3. TERMINATION IDENTIFICATION:
6.3.1. Formation of Eyes:
6.3.1.1. Ferrule-secured eye slings – The minimum length of plain rope between
the inside ends of ferrules terminating a sling leg shall be 20 times the nominal rope
diameter.
6.3.1.2. Spliced eye slings – The minimum length of plain rope between the tails of
splices shall be at least 15 times the nominal diameter.
6.3.1.3. Hard eyes – Hard eyes shall be fitted with thimbles.
6.3.1.4. Soft eyes – The peripheral length of a soft eye shall be at least four rope lay
lengths.
ID No.
Aluminum
SWL Sleeve
Fig. 7 Fig. 8 Fig. 9 Fig. 10
Fig. 14
Link Fig. 15
6. WIRE ROPE SLING
6.4. WIRE ROPE TYPES:
7x7
INDEPENDENT
WIRE ROPE CORE
1
(IWRC)
FILLER WIRES
Fig. 16 Fig. 17
6 x 19 (IWRC)
Fig. 18 Fig. 19
6 x 7 (FC)
Composed with:
Improved Plow Steel (IPS)
6.5. INSPECTION:
Bird cages
Fig. 24
Multi-Strand rope
“Bird cages”
Fig. 25
Fig. 26
6. WIRE ROPE SLING
6.5. INSPECTION: (cont.)
TERMINATIONS
1. Eyes
Distortion
Excessive wear, damage to thimble
2. Securing
Any broken wires near to the ferrules/splice
Broken/damaged ferrules or pulling out
Crushing, abrasion of splice, pulling out
3. Links (master & intermediate )
More than 5% stretch of original length of links
More than 8% wear in links
Bent or twisted links
Fig. 27
Fig. 28
6. WIRE ROPE SLING
6.6 APPLICATION/RIGGING METHOD:
Fig. 32
β d
Fig. 35
6. WIRE ROPE SLING
6.6. APPLICATION/RIGGING METHOD: (cont.)
Fig. 36
2. Single-Leg Sling
Single Choke Hitch – This forms a noose in the
rope and tightens as the load is lifted.
Fig. 37
3. Single-Leg Sling
Double Choke Hitch
Fig. 38
4. Endless-Leg Sling
Double Choke Hitch
Fig. 39
5. Two-Leg Sling
Double Basket Hitch
RIGHT
WRONG
Legs will slide
together.
Fig. 40
6. WIRE ROPE SLING
6.6. APPLICATION/RIGGING METHOD: (cont.)
Fig. 42
Fig. 43
8. Double Basket Hitch – Consists of two single
basket hitches passed under the load. The legs of
the hitches must be kept for enough apart to provide
balance without opening excessive sling angles. 60º or more
Fig. 44
Fig. 47
6. WIRE ROPE SLING
6.6. APPLICATION/RIGGING METHOD: (cont.)
No Wrap Roping
Fig. 51
7. CHAIN SLING
7.1. TYPE:
7.2. IDENTIFICATION:
IDENTIFICATION MARKING
MASTER LINK
INTERMEDIATE
ADJUSTING LINKS
CLUTCHES
CHAIN
SAFETY
JOINING LINK
CATCHES
HOOKS
Fig. 10
Fig. 9
7. CHAIN SLING
7.3. INSPECTION:
Mechanical Joined:
Check and Recommend for Replacement if found
any one of the following:
More than 5% stretch of original length (terminal, joining,
intermediate links, chain and hooks)
More than 8% diameter wear of terminal, joining,
intermediate links, chain and hooks
Existence of nicks, cracks and gouges in terminal, joining,
intermediate links and chain Fig. 11
Bent, elongated or twisted links, rings
Lack of free articulation between links
Distortion of terminal fittings
Cracks and faults in welded areas
Excessive corrosion
Heat discoloration
Broken, twisted chain
Improper shortening devices Fig. 12
Repairs by welding
Rusty chain
Welded Chain:
Check For:
More than 8% wear of terminal fittings, joining links Fig. 13
Fig. 14
7. CHAIN SLING
7.4. APPLICATION/RIGGING METHOD:
SINGLE-LEG SLINGS
1. Straight Lift – Safe Working Load
• The SWL will be 100% SWL of a single-leg.
• A suitable method of lifting an a effectively
balanced load from a single lifting point.
(see Fig. 15)
Fig. 18
7. CHAIN SLING
7.4. APPLICATION/RIGGING METHOD: (cont.)
DOUBLE-LEG SLINGS
1. BRIDLE HITCH (see Fig. 23)
• For two-legged slings, the angle between the legs of the
sling will determine its safe working load (SWL).
• A two-legged sling will be marked with its SWL at 90º (45º
with vertical), which will apply for all angles from 0º - 90º
(0º - 45º with vertical).
• It may also be marked with its SWL at 120º which will
apply for angles between 90º - 120º (45º - 60º with
Fig. 23
vertical).
• Note that the SWL for a two-legged sling assumes that
both legs are equally loaded, and that each leg is straight.
Fig. 26
For three-legged slings, the maximum angle between the legs of the
sling and the vertical will determine its safe working load (SWL).
A three-legged sling will be marked with its SWL at 45º, which will
apply for all angles from 0º to 45º.
Note that the SWL for a three-legged sling assumes that all legs are
equally loaded, and that each leg is at the same angle.
Fig. 29
8. SYNTHETIC
FLAT WEBBING SLING
8.1. TYPE & IDENTIFICATION:
Webbing cut
Heat damage including hard
shiny areas due to friction
Fig. 18
Worn stitches
Excessive abrasion
Knots
Cut – a clean break in the webbing structure of fibers. Fig. 20
This usually results when a sling contacts a sharp object
or unprotected edge of a load. (see fig. 19)
Tensile Break – a frayed close to the point of failure or
damage. (see fig. 20)
Fig. 21
Cut and Tensile Damage – a cut by a sharp object along
one edge of the sling body. (see fig. 21)
8. SYNTHETIC
FLAT WEBBING SLING
8.2. INSPECTION: (cont.)
DROPPED BY ACID
Fig. 23
IMMERSED IN ACID
Fig. 24
ALWAYS:
Store and handle slings correctly.
Inspect slings and accessories before use and before placing into
storage.
Always follow safe slinging practices.
Connect the sling over 120° angle of choke
Never:
Attempt to shorten, knot or slings.
Expose slings to direct heat or frames.
Use slings at temperature above 80°C or below 0°C without
consulting the supplier.
Expose slings to chemicals without consulting the supplier.
Shock load slings
Use slings which are cut or which have loose or damaged stitching.
9. SYNTHETIC ROUND
SLING
9.1. TYPE:
9.2. IDENTIFICATION:
Protective Sleeve
Fig. 33
9.3. INSPECTION:
Initial Inspection – before any polyester round sling is placed into service
it shall be inspected by a designated person to ensure that the correct
polyester round sling is being used, as well as to determine that the polyester
round sling meets the requirements of the manufacturer’s specification.
Frequent Visual Inspection – This inspection shall be made by the person
handling the polyester round sling each time the round sling is used.
Periodic Inspection – This inspection shall be conducted by a designated
person.
Frequency of inspection should be based on:
1. Frequency of use.
2. Severity of service conditions.
3. Experience gained on service life of polyester round slings used in
similar applications.
4. periodic inspections should be conducted at least monthly.
9. SYNTHETIC ROUND
SLING
9.3. INSPECTION: (cont.)
Fig. 34 Fig. 35
Fig. 36
Fig. 37
Fig. 38
9. SYNTHETIC ROUND
SLING
9.4. APPLICATION/RIGGING METHOD:
ALWAYS:
Inspect carefully the round slings and accessories before use
and before placing into storage.
Follow safe slinging practices, as given overleaf.
Position the bight for choke lift over 120° angle of choke.
Apply correct mode factor for the slinging arrangement.
Use protection (to avoid cutting, friction etc) and fittings which
allow the sling to form smooth radii.
NEVER:
Attempt to shorten, knot or tie round slings.
Expose round slings to direct heat or flames.
Use round slings at temperatures above 80°C or below 0°C
without consulting the supplier.
Expose round slings to chemicals without consulting the
Manufacturer.
Shock load round slings.
Use round slings with cut or damaged outer covers.
9. SYNTHETIC ROUND
SLING
9.4. APPLICATION/RIGGING METHOD: (cont.)
BUNCHING
Fig. 39
PINCHING
Fig. 40
10. SHACKLES
10.1. TYPE:
10.2. IDENTIFICATION:
Quality Mark
Quality Mark Capacity Safe
Capacity Safe Diameter Of Working Load
Working Load body (SWL) Diameter Of
(SWL) body
Identification Identification
Number Number
Fig. 7 Fig. 8
DEE SHACKLE BOW SHACKLE
10. SHACKLES
10.3. INSPECTION:
Fig. 9
Shackle pin bearing on running line can work
loose. If the load shifts, the sling will unscrew
the shackle pin. (see Fig. 14 & 15)
Fig. 14
Fig. 15
Incorrect
of a shackle pin. (see Fig.16)
Bolt
Fig. 16
10. SHACKLES
Good Practice
Washers can be used to take up the space Packing Hook
between the shackle and hook. (see Fig. 17)
Bad Practice
Never Allow shackle to be Pulled at an Angle, the
legs will open up. (see Fig. 18)
Fig. 17
ALWAYS:
Store and handle shackles correctly.
Inspect shackles before use and before placing into
storage.
Select the correct pattern of shackle and pin for the
application.
Allow for the full resultant imposed load.
Tighten the screw pin by hand only.
Ensure the load acts through the center line of the
shackle using spacers if necessary to meet this
Fig. 18
requirement.
NEVER:
Use shackles with bent pins or deformed bodies.
Force, hammer or wedge shackles into position.
Eccentrically load shackles.
Replace the pin with a bolt.
Fit pins in contact with moving parts which may
loosen or unscrew them.
Shock load shackles.
Use shackle across direction it will reduced 50% SWL
11. PLATE CLAMPS
11.1. TYPE:
11.2. IDENTIFICATION:
CLAMPING
GRIPPING THREADS
LOCKING
LEVER
Fig. 5
Locking Screw Clamp
SPRING IN Fig. 4
LOCKING Vertical Lifting Locking
BENT PIN
LEVER
Fig. 6
Horizontal Lifting Non-Locking
11. PLATE CLAMPS
11.3. INSPECTION:
Fig. 7
Vertical and Universal Plate Clamp Inspection Points
Fig. 8
Horizontal Plate Clamp Inspection Points
11. PLATE CLAMPS
Fig. 9
Fig. 10
Horizontal
Type
Fig. 11 Fig. 12
12. HOOKS
12.1. TYPE:
12.2. IDENTIFICATION:
HOOK EYE
THROAT OPENING
NECK
SAFETY LATCH
SADDLE OR SEAT
Fig. 4
12. HOOKS
12.3. INSPECTION:
Fig. 5
Fig. 6 Fig. 7 Fig. 8 Fig. 9
Fig. 13
When placing two slings on the hook, the sling angle
measured from the horizontal shall be equal to or greater
than 45°. For sling angles less than 45°, a master link, pear
link, bolt-type shackle, or screw pin shackle should be used to
attach the slings to the hook.
Note:
1. Forged swivels and swivel hooks with bronze bushings are to be
used for positioning prior to lifting a load. DO NOT rotate under
load.
2. DO NOT overcrowd the hook.
3. DO NOT swivel the hook while it is supporting a load.
Side Load.
Fig. 16
Back Load.
Fig. 17
Tip Load.
Fig. 18
13. EYEBOLTS
13.1. TYPE & IDENTIFICATION:
13.2. INSPECTION:
Buckling
NOTE:
If used a dynamo eyebolt in pairs a lifting beam
must be used to ensure a vertical lift.
Fig. 10
Wrong
13. EYEBOLTS
ALWAYS:
Store and handle eyebolts correctly.
Inspect eyebolts before use and before placing into storage.
Select the correct pattern eyebolt for the application.
Ensure that the eyebolt and tapped hole threads are compatible and strong
enough for the load.
Correctly align the plane of the eye using shims where necessary.
Ensure that the collar is fully seated when hand tight.
NEVER:
Use Tommy bars, grips or wrenches to tighten eyebolts.
Use dynamo eyebolts for angular loading.
Use a single eyebolt to lift a load that is free to rotate.
Reeve slings through the eyes, links or shackles fitted to pairs of eyebolts.
Force hooks or other fittings into the eye; they must fit freely.
Shock load eyebolts.
14. TURNBUCKLES
14.2. INSPECTION:
Check and Recommend for Replacement if Found
any one of the following:
Cracks and bends.
Damage and bent rods
Check thread damage and thread engaged to full length of threaded body.
Deformation
Severe Corrosion
14.3. APPLICATION/METHOD:
Only rigging screws and turnbuckles that are marked with the appropriate
safe working load after proof loading shall be used for lifting applications.
Securing Turnbuckles – twisting of the turnbuckle might occur, use a lock wire
to prevent rotation of the turnbuckle. (see fig. 6)
The use of locknuts or mousing is an effective method of preventing
turnbuckles from rotating.
Fig. 6
Correct
Fig. 7
Incorrect
(No Lock Wire)
15. LIFTING BEAM
15.4. APPLICATION/METHOD:
The weight of the beam, together with its
attachments, must be added to the weight of
the load when calculating that total load that will
be imposed on the crane hook.
ALWAYS:
Store and handle lifting beam correctly.
Refer to the safe use instructions for slings and attachments used with the
beam.
Include the self weight of the beam and attachments when calculating the
load imposed on the crane hook.
Ensure the load will remain stable when lifted.
Ensure that no one lifting point becomes overloaded by the slinging or
handling methods.
Use tag lines to control long loads.
NEVER:
Use lifting beams to handle Loads other than those for which they are
designed.
Fit lifting beams to a hook other than those for which they are designed.
Use damaged or distorted lifting beams and attachments.
Unevenly load lifting beams.
Allow lifting beams to foul any part of the crane or any other obstructions
in the area.
16. BEAM CLAMP
16.1. TYPE:
Fig. 1 Fig. 2
Fig. 3 Fig. 4
FIXED BEAM CLAMP ADJUSTABLE BEAM CLAMP
16.2. IDENTIFICATION:
FRAME
FRAME
CLAMPING SCREW
Fig. 5 Fig. 6
FIXED BEAM CLAMP ADJUSTABLE BEAM CLAMP
16. BEAM CLAMP
16.3. INSPECTION:
Check identification/location and SWL is clearly marked. Then
compare these markings against the current certificate.
Check all moving parts against seizure, e.g. pivots, pins and load bar.
Where swivel jaws are fitted, ensure that they are free to rotate.
Check operation of unit and alignment of frame.
Check bar handle is not dangerous to the operator’s hand.
Examine stress points for cracks, distortion, nicks, gouging and
corrosion.
Examine load bearing parts for signs of wear. Maximum permissible
wear must not exceed 8% of bearing cross-section.
Check the suspension points, shackle, pivot/pins, bolts & nuts,
threads, load bar, jaws/grips and surfaces.
Check the beam size.
16.4. APPLICATION:
ALWAYS:
Store and handle beam clamps correctly.
Inspect beam clamps and accessories before use and before placing into
storage.
Ensure the supporting structure is adequate for the full load that will be
imposed and suitable for the application.
Check the clamp is of the correct profile and size, or correctly adjusted, for
the beam width and that it seats correctly on the beam flange.
Ensure the beam clamp is strong enough for the full load that will be
imposed.
Check that the clamp is directly over the center of gravity of the load.
16. BEAM CLAMP
NEVER:
Use beam clamps which are unidentified or uncertified for lifting
applications.
Replace bolts, shackles etc without consulting the supplier.
Throw or drop beam clamps
Use beam clamps on damaged or distorted beams.
Force or wedge hooks of lifting appliances into the attachment eye or
lifting (e.g. Shackle)
Obliquely load beam clamps without the authority of the supplier.
17.1.1. TYPES:
Fig. 1 Fig. 2
HEAVY DUTY STANDARD DUTY
17.1.2. IDENTIFICATION:
MAIN FRAME
LOAD CHAIN
HAND CHAIN
Fig. 3
17. LIFTING APPLIANCE
17.1. HAND-OPERATED CHAIN BLOCK (cont.)
17.1.3. INSPECTION:
Keep the chain block clean and regularly lubricate the load
chain and both hook shanks.
SPROCKET
Carry out a visual inspection every time the chain block is DAMAGED
used and listen for any unusual sounds during operation.
Depending upon the frequency of use and local conditions
the load chain will eventually show signs of wear, at which
point it should be replaced.
Overloading or incorrect hooking may distort the hook and
increase the hook opening. If this occurs replace the hook Fig. 4
immediately.
The components shall be free from deformation, cracks,
flaws or other defects and there shall be no loosening of
connections. SAFETY LATCH
DAMAGED
When the hand chain is released at any point during
raising and lowering, the brake shall hold the weight
of the load
The block shall be free from deformation, cracks, flaws or
other defects, there shall be no loosening of connections
and the block shall operate satisfactorily.
On removal of the restraining pin, the brake shall Fig. 5
immediately engage and prevent the load from
descending.
SAFETY LATCH
MISSING
WARNING!
The chain block should be disassembled, cleaned,
inspected, reassembled and tested by an Authorized
Service Agent annually, or more frequently if used outside,
exposed to the weather.
The load chain and the hooks are manufactured from NO NAME
special alloy steels and precisely heat treated. DO NOT PLATE DETAILS
Hand Chain Blocks – are available in range capacity and with various types
of suspension. Select the block to be used and plan the lift taking the
following into account:
Type of suspension – hook, trolley etc.
Capacity, class of use and range of lift.
Chain blocks are designed for vertical lifting only.
ALWAYS:
Store and handle chain blocks correctly.
Inspect chain blocks and accessories before use and before placing into
storage.
For top hook suspension, use hooks that are fitted with safety catches, or
mouse the hook, ensuring the support fits freely into the seat of the hook.
For trolley suspension ensure the trolley is correctly set for the beam
width.
Check that the bottom hook will reach its lowest point without running the
chain fully out.
Adopt safe slinging practices and follow the instructions for the safe use of
the equipment used.
NEVER:
Expose chain blocks to chemicals, particularly acids, without consulting the
manufacturer.
Replace the load chain with a longer one without consulting the
manufacturer.
Use undue effort to force the block to operate.
Throw, drop or drag a chain block.
Allow oil or grease to come into contact with the brake.
Expose a chain block directly to the elements, water spray, steam etc
without consulting the manufacturer.
17. LIFTING APPLIANCE
17.1. HAND-OPERATED CHAIN BLOCK (cont.)
KEEP
The chain block clean for the best and safest performance.
Work area clean and tidy and free from unrelated materials.
RAISE AND LOWER in a smooth, controlled manner and DO NOT shock load the chain block
by allowing the attached load to fall freely, even for very short distances.
CHECK the brake operation by stopping when the load has been raised a short distance
(100mm) and ensuring that it is held with no downward creep.
DO NOT
Operate the chain block if damaged.
Allow untrained persons to operate the chain block.
Exceed the rated capacity (safe working load) of the chain block.
Raise or lower the load with jerky or abrupt movements of the hand chain.
Attempt to lift a load if the load chain is kinked or knotted.
Try to raise a load with two, or more, chain blocks - use a single block of adequate capacity.
Use the chain block to drag the load across the floor. Always position the load directly
below the block.
Wrap the load chain around the load - always us separate, suitable, slings/chains/ropes of
the correct capacity.
Allow anyone to stand or pass beneath the raised load.
Use the chain block for purposes other than that for which it is intended.
DANGER! Use the chain block for lifting only, NOT for supporting the lifted load.
17. LIFTING APPLIANCE
17.1.6. INSPECTION:
Hand Chain
Check For:
Cracks, distortion, wear or corrosion.
Cracks, distortion, wear of hand chain wheel.
Incorrect seating in hand chain wheel.
Rusty chain.
Load chain:
Check For:
Cracks, distortion, wear of blocks, wear, slackness of sheave wheel
Incorrect seating in sprocket wheel.
Damage to slack end or load end anchor
Rusty chain
Twisted chain in multiple fall
17.2. CHAIN LEVER HOIST
17.2.1. IDENTIFICATION:
Hook
Safety catch
Safety catch
Hook
Fig. 7
MAIN FRAME
Check For:
Cracks, distortion or worn in body, gear covers or chain guides.
Loose nuts, bolts, rivets, or pins. Thread damage or wear. Missing locking
devices.
Corrosion, wear or damage to pawl, ratchet or spring.
Cracks or uneven wear of pinions, gear wheels or bearings.
Wear, damage to brakes, chain stripper.
Improper electrical condition, if applicable.
REPAIR:
Check For:
Repair not in accordance with manufacturers recommendations.
Replaced parts incorrectly assembled.
Replaced parts not manufacturer certified.
OPERATIONAL TEST:
Check For:
Undue effort, excessive noise or jumping of chains during
hoisting/lowering.
Malfunction of pawl, operating spring and ratchet.
Incorrect action of chain guides.
Brake operation. Must be kept free of oil, grease etc.
17. LIFTING APPLIANCE
17.2.3. APPLICATION/METHOD:
ALWAYS:
Store and handle lever hoist correctly.
Inspect lever hoists and accessories before use and before placing
into storage.
Ensure any support fits freely into the seat of the hook and does not
exert a side thrust on the point.
Check the operation of the brake.
Check that the bottom hook will reach its lowest point without
running the chain against the stop.
Adopt safe slinging practices and follow the instructions for the safe
use of the equipment used.
NEVER:
Expose lever hoists to chemicals, particularly acids, without
consulting the manufacturer.
Replace the load chain with a longer one without consulting the
manufacturer.
Extend the lever or use undue effort to force the lever hoists to
operate.
Throw, drop or drag a lever hoist.
Allow oil or grease to come into contact with the brake.
Expose a lever hoist directly to the elements, water spray, steam etc
without consulting the manufacturer.
17. LIFTING APPLIANCE
17.3. WIRE ROPE GRIP/PULL LIFTING MACHINE
17.3.1. TYPE:
17.3.2. IDENTIFICATION:
Rope clamp
disengagement Identification
lever Marking
Safety catch
Overload protection
Hook (Shear pin)
Fig. 11
17.3.3. APPLICATION/METHOD:
Rigging Arrangement
Diverters
Pulley Blocks
Anchorage and suspension points
Imposed loads
Storing and Handling
Never return damaged grip/ pull machines, ropes etc. to storage.
Grip/Pull machines should be dry, clean and protected from corrosion.
Rope should be carefully coiled onto a suitable drum or frame for storage,
taking care to avoid any twists
Store machines and ropes on a suitable rack, not on the floor where they may
be damaged.
17. LIFTING APPLIANCE
17.3. WIRE ROPE GRIP/PULL LIFTING MACHINE
17.3.3. APPLICATION/METHOD: (cont.)
ALWAYS:
NEVER:
AXIS OF
ROTATION
BOOM ANGLE
HORIZONTAL
OPERATING
RADIUS
Fig. 12
Onshore Crane (Rough Terrain)
BALANCE POINT OR
FULCRUM
WEIGHT OF:
BOOM BLOCK
ANGLE IN DEGREES SHACKLES AND SLINGS
LOAD
RADIUS IN FEET
OF ROTATION
Fig. 13
Offshore Crane (Pedestal)
BOOMING
LIFTING
SWINGING
Fig. 14
17. LIFTING APPLIANCE
Rigging is
correct.
Fig. 17
17.5.2. Tower Crane
17. LIFTING APPLIANCE
Rigging is
correct.
Fig. 18
17.5.3. Crawler Crane
BOOM POINT
EXTENSION (JIB)
LOAD BLOCK
BOOM HEAD
SECTION
PENDANT CABLES
WHIP LINE
TURNTABLE CAB
COUNTER
PEDESTAL
WEIGHT
Fig. 19
17.5.4. Offshore Crane
18. LOAD
Fig. 6
Fig. 4 Fig. 5
18.3. FUEL /
CHEMICAL TANKS
18. LOAD
18.4.1. INSPECTION:
Securing
all Gas Cylinder racks should have a primary and
secondary method of securing the cylinders for
transit. (see Fig. 12)
Advisable
To have an increased factor of safety.
18.5.2. PERSONNEL:
In suspended baskets a distribution as symmetrical as
possible of the load should be achieved.
Persons in suspended baskets should fasten their safety
harness onto the anchorages provided.
The basket rated capacity should not be exceeded.
Tools and material carried by personnel should be
secured, in particular against displacement, tipping, and
falling out.
Occupants shall not stand on or work from the handrail or
side protection of the suspended basket or anything in it.
The basket shall be positioned on a firm surface during
access and egress.
Any power cables or hoses provided to the basket should
be connected in such a way that they will not interfere
with the safe operation of the basket.
Power cables or hoses shall not be used as guide ropes.
When electric welding from the basket, special care shall
be taken to earth the basket in order to protect the crane
and/or its ropes from becoming conductors of electricity. Fig. 13
All movements should proceed gently with low speeds.
18. LOAD
Fig. 14
Fig. 15
Fig. 16
18.6.4. Beams
Use double wrapped slings when sling legs can slide
together. SWL factor for slings used thus is 0.8 of SWL.
(see Fig. 17)
Fig. 17
18. LOAD
18.6.5. Stillages
Wrap slings round corner posts. Do not attempt to lift double
stacked stillages. Beware of overloading scaffold boards if
landing loaded stillages on a scaffold. SWL factor for chain
slings used thus is 0.8 of SWL. (see Fig. 18)
18.6.8. Mesh
Pass each hook of a four-legged chain through the
mesh and return to form a choke hitch. Lifting
points to be positioned evenly to prevent undue
bending on the mesh bundle. Tighten bite as
necessary. (see Fig. 22)
Fig. 24
PORTABLE OFFICE
18. LOAD
Fig.26 & 27 - This load is not stable. The hook is not over
the load’s centre of gravity. Lifting a load with the centre of
gravity offset will cause the load to shift until a balance is
Fig. 26
restored. The load will shift until the centre of gravity is
under the hook. this will make landing the load very
difficult, and could cause major problems in crainage.
Fig. 27
Fig. 28
19. TABLE/CHART
Fig. 1
19. TABLE/CHART
L
H
L B r
Fig. 3 Fig. 4
L t
B
d
Fig. 5 Fig. 6
r r1
Where:
r1 (outer radius) r2
r2 (inner radius)
Fig. 7 Fig. 8
19. TABLE/CHART
Acetylene 1170 73
Oil 810 50
Paper 1130 70
Water 1025 64
10,000 kg 10,000 kg
Steps:
1. Determine the Horizontal sling
angles. (45°)
Sling 2
60º
10,000 kg
H
8m 2m
COG
STEPS:
• Assume the position of hook directly over the center of gravity of load
• Consider an optimal angle of 60°to the horizontal of load
• Since the angle is 60°, the height of the hook is now fixed as is the sling length.
Because the angle is 60°
• Sling 1 length at 60° = Base/cosine 60º= 8m/0.5 = 16m
• Knowing the L/H = 1.2 for 60° sling angle, the height of the hook is
L/H = 1.2
H = 16/1.2
H = 13.3 m
• Additionally, knowing that L/H = 1.2 for 60° sling angle, the load on sling 1
Force acting on sling 1 is 2000kg, Refer page no: 83, fig 2
• Sling 1’s SWL (minimum) calculation:
Sling 1 = 1.2 x Force A or 1.2 x 2,000 kg = 2,400 kg.
• Sling 2’s length can now be calculated to an exact number
• Length of sling 2 = √ (13.3)2 + (2)2 = 13.44 m
• Sling 2’s SWL (minimum) calculation:
• Force acting on sling 2 is 8000kg, Refer page no: 83, fig 2
L/H = 13.44/13.3 = 1.01
Sling 2 = 1.01 x 8,000 kg = 8,084 kg
• Using wire rope slings, 6 x 19 class rope
• With a ferrule secured wire rope slings , Use velosi Rigging chart no:12.1.1
20. CALCULATION
20.3. SLING ANGLES:
21. GLOSSARY
4 Shackles (Dee & Bow Suitable for use with the BS 3551 other
type shackle) eyes and bodies of US-FED. SPEC-
hooks, eyebolts, egg RR-C-271D
links, wire rope thimbles,
and for the head fittings
of blocks, etc.
DEE BOW
SHACKLE SHACKLE
21. GLOSSARY
Equalizer Beam
FIXED CLAMP
ADJUSTABLE
CLAMP
Lifting Plan
The chart in the middle offers a handy guide for assessing the effective angle of the sling to the relative weight. It
is always better to limit the angle of the sling. Further, such changes in sling angle must be accounted for in
lifts that are close to the sling weight limit and/or for critical lifts (greater than 90% of the crane limit).
Rigging Sketch
Identify the following on your sketch:
a. Lift point identification
b. Method(s) of attachment
c. Load angle factors (e.g., vertical and horizontal vectors of sling loads)
d. Sling angles
e. Accessories used
f. Other factors affecting the equipment capacity
g. Rated capacity of equipment in the configuration(s) in which it will be used. (For mobile cranes, many
factors affect rated capacity, including boom length, boom angle, and work area.)
A load-path sketch shows the load path and height at key points in the job. For lifts with mobile cranes,
include the crane position(s) relative to the load and relative to surrounding obstructions. Where appropriate,
include floor or soil-loading diagrams. Indicate lifting and travel speed limitations if applicable.
Lifting Equipment and the Law
• The employer of a person who uses lifting equipment at work. All responsibilities ascribed to an employer apply to any person who has
control over or supervises the use of lifting equipment.
• The self-employed who uses lifting equipment.
• The equipment user.
• The equipment examiner.
• The designer, supplier and manufacturer of lifting equipment.
Under LOLER Reg.4 Ensure that lifting equipment used in his workplace is of adequate strength and stability for each load.
Under LOLER Reg.5 Make special provisions for lifting equipment that carries people.
Under LOLER Reg.6 Ensure that lifting equipment is installed in such a way as to minimise the risk of a person being struck by
a load, and is otherwise safe.
Under LOLER Reg.7 Ensure that lifting equipment is marked with its Safe Working Load.
Under LOLER Reg.8 Ensure that every lifting operation involving lifting equipment is
(a) properly planned by a competent person;
(b) appropriately supervised; and
(c) carried out in a safe manner.
Under LOLER Reg.9 Have in his possession before the first use of any equipment -
(a) a Report of Thorough Examination of Lifting Equipment; or
(b) an EC Declaration of Conformity if the equipment has not been used before.
Under LOLER Reg.9 (a) Examine “below the hook” items every 6 months.
(b) Examine “above the hook” items every 12 months.
(c) Examine more frequently if circumstances require.
(d) Routine inspect between examinations, where safety requires.
Under LOLER Reg.10 Ensure that equipment is not used until a notified defect is rectified.
Under LOLER Reg.11 Keep the following documents -
(a) EC Declaration of Conformity as long as he keeps the equipment
(b) Report of Thorough Examination for “below the hook” items when examined before first use, for
2 years.
(c) Report of Thorough Examination for “above the hook” items when examined before first use,
as long as he keeps the equipment.
(d) Report of Thorough Examination for all periodic examinations, for 2 years.
3/13
Under HSWA s.7 Take care of himself and others whom his acts or omissions at work might affect.
Under LOLER Reg.10 (a) Immediately notify the employer of any defect he finds.
(b) Give to the employer a written “Report of Thorough Examination of Lifting Equipment”.
(c) Notify the Health & Safety Executive of any imminent risk of serious personal injury.
Under HSWA s.6 (a) Ensure that the equipment he designs and makes is safe.
(b) Ensure it is installed safely.
(c) Carry out necessary tests and examinations to ensure safety.
(d) Provide adequate “Safe Use” information.
.
7/13
• “accessory for lifting” means work equipment for attaching loads to machinery for lifting. It can be assumed that an “accessory for lifting”
is what used to be described as “lifting tackle” and includes slings, shackles, eyebolts, lifting beams and all “below the hook” items of lifting
equipment.
• “examination scheme” means a suitable scheme drawn up by a competent person for such thorough examinations of lifting equipment at
such intervals as may be appropriate for the purpose described in LOLER.
• “lifting equipment” means work equipment for lifting or lowering loads and includes its attachments used for anchoring, fixing or
supporting it. This definition of lifting equipment goes beyond the pre-LOLER definition in that supporting stools, guys and other such
supports are included.
• “lifting operation” means an operation concerned with the lifting or lowering of a load.
• “thorough examination”
(a) means a thorough examination by a competent person;
(b) where it is appropriate to carry out testing for the purpose described in [LOLER], includes such
testing by a competent person as is appropriate for the purpose.
(2) LOLER shall apply to an employer in respect of lifting equipment......provided for use or used by an employee of his at work.
(1) Every employer shall ensure that lifting equipment for lifting persons -
(a) is such as to prevent a person using it being crushed, trapped or struck or falling from the carrier;
(b) is such as to prevent as far as is reasonably practicable a person using it, while carrying out
activities from the carrier, being crushed, trapped or struck or falling from the carrier;
(c) has suitable devices to prevent the risk of a carrier falling;
(d) is such that a person trapped in any carrier is not thereby exposed to danger and can be freed.
(2) Every employer shall ensure that if the risk described in paragraph (1) (c) [above] cannot be prevented for reasons inherent in the site and
height differences -
(a) the carrier has an enhanced safety coefficient suspension rope or chain; and
(b) the rope or chain is inspected by a competent person every working day.
(1) Every employer shall ensure that lifting equipment is positioned or installed in such a way as to reduce to as low as is reasonably
practicable the risk -
(a) of the lifting equipment or load striking a person; or
(b) from a load -
(i) drifting;
(ii) falling freely; or
(iii) being released unintentionally; and is otherwise safe.
“and is otherwise safe” is a significant catch-all. Lifting installations must be safe!
(2) Every employer shall ensure that there are suitable devices to prevent a person from falling down a shaft or hoistway.
(1) Every employer shall ensure that every lifting operation involving lifting equipment is
(d) properly planned by a competent person;
(e) appropriately supervised; and
(f) carried out in a safe manner.
This is a new concept to lifting equipment legislation. It is the “operation” not just the equipment that must be safe.
(1) Every employer shall ensure that before lifting equipment is put into service for the first time by him it is thoroughly examined for any
defect unless either -
(a) the lifting equipment has not been used before; and
(b) the employer has an EC declaration of conformity made not more than 12 months before the
equipment is put into service.
(2) Every employer shall ensure that, where the safety of lifting equipment depends on the installation conditions, it is thoroughly examined
(a) after installation and before being put into service for the first time; and
(b) after assembly and before being put into service at a new site or a new location, to ensure that it
has been installed correctly and is safe to operate.
(3) Every employer shall ensure that lifting equipment which is exposed to conditions causing deterioration which is liable to result in
dangerous situations is
(a) thoroughly examined -
(i) in the case of lifting equipment for lifting persons or an accessory for lifting, at least every
6 months;
(ii) in the case of other lifting equipment, at least every 12 months; or
(iii) in either case, in accordance with an examination scheme; and
(iv) each time that exceptional circumstances which are liable to jeopardise the safety of the
lifting equipment have occurred; and
(b) if appropriate for the purpose, is inspected by a competent person at suitable intervals between
thorough examinations, to ensure that health and safety conditions are maintained and that any
deterioration can be detected and remedied in good time.
(1) A person making a thorough examination for an employer under regulation 9 [of LOLER] shall-
(a) notify the employer forthwith of any defect in the lifting equipment which in his opinion is or
could become a danger to persons;
(b) as soon as is practicable make a report of the thorough examination in writing signed by him or
on his behalf......and containing the information specified in Schedule 1 to -
(i) the employer; and
(ii) any person from whom the lifting equipment has been hired or leased;
(c) where there is in his opinion a defect in the lifting equipment involving an existing or imminent
risk of serious personal injury send a copy of the report as soon as is practicable to the relevant
enforcing authority.
(2) A person making an inspection for an employer under regulation 9 [of LOLER] shall -
(a) notify the employer forthwith of any defect in the lifting equipment which in his opinion is or
10/13
(3) Every employer who has been notified [of a defect] shall ensure that lifting equipment is not used -
(a) before the defect is rectified; or
(b) after a time specified [in the defect report] and before the defect is rectified.
(1) an EC declaration of conformity [shall be kept by an employer] so long as he operates the lifting equipment.
(2) The employer shall ensure that the information contained in -
(a) every report of thorough examination is kept available for inspection -
(i) ...for a “prior to first use thorough examination of equipment” (i.e. under Regulation 9 (1))
lifting equipment other than an accessory for lifting (i.e. for “above the hook” equipment)
until he ceases to use the lifting equipment;
(ii) ...for a “prior to first use thorough examination of equipment” (i.e. under Regulation 9 (1)) an
accessory for lifting, (i.e. for “below the hook” equipment) for two years after the report is made.
(iii) ...for a “prior to first use thorough examination of installation” (i.e. under Regulation 9 (2))
until he ceases to use the lifting equipment it was installed or assembled.
(iv) ...for a “periodic examination of equipment” (i.e. under Regulation 9 (3)) until the next report
is made......or the expiration of two years whichever is later.
(b) every [inspection record] is kept available until the next such record is made.
Sections 22,23 and 25 to 27 of the Factories Act 1961 (d) are repealed.
1 The name and address of the employer for whom the thorough examination was made.
2 The address of the premises at which the thorough examination was made.
3 Particulars sufficient to identify the lifting equipment including where known its date of manufacture.
4 The date of the last thorough examination.
5 The safe working load of the lifting equipment or (where its safe working load depends on the configuration of the lifting equipment) its
safe working load for the last configuration in which it was thoroughly examined.
6 In relation to the first thorough examination of lifting equipment after installation or after assembly at a new site or in a new location -
(a) that it is such a thorough examination;
(b) (if such be the case) that it has been installed correctly and would be safe to operate.
7 In relation to a thorough examination of lifting equipment other than a thorough examination to which paragraph 6 relates -
(a) whether it is a thorough examination -
(i) within an interval of 6 months under regulation 9(3)(a)(i);
(ii) within an interval of 12 months under regulation 9(3)(a)(ii);
(iii) in accordance with an examination scheme under regulation 9(3)(a)(iii); or
(iv) after the occurrence of exceptional circumstances under regulation 9(3)(a)(iv);
(v) (if such be the case) that the lifting equipment would be safe to operate.
8 In relation to every thorough examination of lifting equipment -
(a) identification of any part found to have a defect which is or could become a danger to persons,
and a description of the defect;
(b) particulars or any repair, renewal or alteration required to remedy a defect found to be a danger to
persons;
11/13
(2) Every employer shall ensure that his employees are provided with adequate health and safety training -
(b) on their being exposed to new or increased risks because of -
(iii) the introduction of new work equipment or a change respecting work equipment already in
use within the employer’s undertaking.
(1) ...”work equipment” means machinery, appliance, apparatus, tool or installation for use at work...
(1) Every employer shall ensure that work equipment is maintained in an efficient state, in efficient working order and in good repair.
12/13
(1) Every employer shall ensure that all persons who use work equipment have received adequate training for purposes of health and safety,
including training in the methods which may be adopted when using the work equipment, any risks which such use may entail and
precautions to be taken.
(2) Every employer shall ensure that any of his employees who supervises or manages the use of work equipment has received adequate
training for purposes of health and safety, including training in the methods which may be adopted when using the work equipment, any
risks which such use may entail and precautions to be taken.
The manufacturer (or original importer into the EC) of a lifting machine (the definition of machine includes all useable equipment,
e.g. shackles, chain slings) must
(a) Satisfy the relevant health and safety requirements detailed in the SMR (see below).
(b) Carry out an appropriate test and assessment procedures.
(c) Issue an EC Declaration of Conformity.
(d) Fix a CE mark.
(e) Ensure the machinery is in fact safe.
Essential Health and Safety Requirements to Offset the Particular Hazards Due to a Lifting Operation (Schedule 4)
The SMR places requirements on the designer and manufacturer of machinery. These requirements cover -
(a) Stability.
(b) Guide rails and rail tracks.
(c) Mechanical strength.
(d) Pulleys, drums, chains or ropes.
(e) Separate lifting accessories.
(f) Control of movements.
(g) Handling of loads.
(h) Control devices.
(i) Loading control.
(j) Risks to exposed persons.
(k) Fitness for purpose.
(l) Marking.
(m) Instruction handbook.
The requirements are detailed, but it is the responsibility of the Rossendale Group to ensure that they are complied with when it
manufactures and supplies or installs lifting equipment.
When the Rossendale Group supplies equipment manufactured by others, it is the responsibility of the manufacturer (or supplier) to ensure
compliance with the essential health and safety requirements.
Under SMR a ’machine’ is much more broadly defined than our traditional understanding. If it is a piece of lifting equipment capable of
being used on it’s own, it is a ‘machine’ under SMR. This would include a shackle or a sling.
The Health and Safety at Work Act 1974
Referred to below as “HSWA”.
Wording lifted direct from HSWA in Italics
(1) It shall be the duty of every employer to ensure, so far as is reasonably practicable, the health, safety and welfare at work of all his
employees.
(2) ...the matters to which that duty extends in particular -
(a) the provision and maintenance of plant and
systems of work that are, so far as is reasonably
practicable, safe and without risks to health;
(b) arrangements for ensuring, so far as is reasonably
practicable, safety and absence of risks to health in
connection with the use, handling, storage and
transport of articles and substances;
(c) the provision of such information, instruction, training
and supervision as is necessary to ensure, so far as is
reasonably practicable, the health and safety at work of
his employees.
(d) so far as is reasonably practicable as regards any place
of work under the employer’s control, the maintenance
of it in a condition that is safe and without risks to
health...
(e) The provision and maintenance of a work
environment for his employees that is, so far as is
reasonably practicable, safe...
(1) It shall be the duty of any person who designs, manufactures, imports or supplies [lifting equipment] -
(a) to ensure, so far as is reasonably practicable, that the [equipment] is designed and
constructed as
to be safe and to be without risks to health when properly used;
(2) “When properly used” is a significant caveat.
(b) to carry out........such testing and examination as may be necessary [to ensure that
it is safe];
(c) to make available adequate information about the use
for which [the equipment] is designed........and about
any conditions necessary to ensure that, when put to
that use, it will be safe and without risks to health.
(3) It shall be the duty of any person who erects or installs any article for use at work, so far as is
reasonably practicable, that nothing about the way in which it is erected or installed makes it
unsafe.......when properly used.
American National Standards Institute ASME B56.1, Safety Standard for Powered
and Industrial Trucks – Low Lift and High Lift
American Society of Mechanical Trucks.
Engineers
ASME B56.5, Guided Industrial Vehicles.
ANSI A10.28, Work Platforms Suspended From
Cranes or Derricks. ASME B56.6, Rough Terrain Fork Lift Trucks.
ANSI A10.18, Floor and Wall Openings, ASME B56.7, Industrial Crane Trucks.
Railings and Toe Boards. Special Notice 6-88.
ASME B30.2, Overhead and Gantry Cranes ASME B56.11.4, Forks and Fork Carriers for
(Top-Running Bridge, Single or Multiple Girder, Powered Industrial Fork Lift Trucks, Hook Type.
Top-Running Trolley Hoist).
ASME PALD, Portable Automotive Lifting
ASME B30.5, Mobile and Locomotive Cranes. Devices.
ASME B30.16, Overhead Hoists (Underhung). ASME HST-2M, Performance Standard for
Hand Chain Manually Operated Chain Hoists.
ASME B30.17, Overhead and Gantry Cranes
(Top Running Bridge, Single Girder, Underhung ANSI/ASME HST-3M, Performance Standard
Hoist). for Manually Lever Operated Chain Hoists.
-1
ANSI/ASME HST-4M, Performance Standard
for Electric Wire Rope Hoists. Department of Labor
ANSI/ASME HST-5M, Performance Standard 29 CFR 1910, Occupational Safety and Health
for Air Chain Hoists. Standards for General Industry.
ANSI/ASME HST-6M, Performance Standard 29 CFR 1926, Occupational Safety and Health
for Air Wire Rope Hoists. Regulations for Construction.
Recommended Practice No. ASNT-TC-1A. SAE J874, Center of Gravity Test Code.
Department of Energy