Gent Fire Alarm Guide
Gent Fire Alarm Guide
Gent Fire Alarm Guide
Introduction
This guide, due to its size, provides a basic overview to anyone involved in the design or
action of a fire detection system. It will identify the current legislative requirements as well as
clarify the responsibilities placed on the three key roles involved with the provision of a new
system, namely the Designer, Installer and Commissioning Engineer, as well as remind the
End User or Owner/Occupier what part they play in ensuring that the best possible system
is supplied to protect life and property from fire.
It is important that everyone involved is conversant with the current British Standard Codes
of Practice BS 5839-1:2013 for general buildings and should also be conversant with the
British Standard relating to general wiring BS 7671.
The guide, which has been prepared by Gent, one of the UKs largest manufacturers of fire
detection systems, is intended to offer practical advice and is not a substitute for any of the
standards or legislation referred to.
Legal elements
4
by Honeywell
System Design
Any design should be prepared by a competent individual/organisation, who has consulted
all interested parties and created a set of drawings, a specification, a cause & effect or fire
plan, a list of Variations and completed a Design certificate, detailed within BS 5839-1:2013.
If designs are undertaken without this research being carried out, the fire detection system is
unlikely to comply with the legal requirements. This could result in prosecution of the parties
involved, particularly those within the supply chain as well as the Owner/Occupier.
WARNING: Anyone who takes on the responsibility for design will do so at their own risk
and design liability insurance is advisable.
Design Stage 1
Talk to the interested parties to decide on the level of protection or category
and agree Variations
The importance of pre-design planning cannot be overstated. Many parties are likely to
have an interest in what the fire detection system is expected to do. Ultimately it is up to
the Owner/Occupier, who is responsible by law, to make the final decision on the level of
protection provided for a particular building.
In most circumstances the Owner/Occupier will appoint a competent Designer to carry out
this work and take liability for the design as a whole.
The nominated Designer is expected to consult the following organisations:
4 The User or Facilities Manager
4 The Building Control Officer
4 The Health and Safety Executive
4 The Insurer
4 The local Fire and Rescue Service
4 A specialist fire alarm system supplier
4
4
by Honeywell
L5
L4
L3
Category L5, designed for buildings
that have a particular risk identified
which warrants some special
attention. For example if there
is an area of high risk which is
considered worthy of having some
automatic detection but a manual
system is also needed, then this
will be termed as L5/M.
Category L4 provides detection
within the escape routes only,
whereas L3 not only covers these
areas but all rooms leading onto
the escape route. The reasoning
behind this is to alert people of
the danger prior to the corridor
becoming Smoke logged so
people can escape safely.
L2
L2 is a further enhancement
of protection with all the areas
covered by an L3 category as
well as all high risk areas such as
boiler rooms etc.
L1 provides protection throughout
the building.
L1
by Honeywell
Design Stage 2
Detection and Alarm Zones
Generally a building is broken down into smaller compartments to enable the fire fighters to
locate the fire as quickly as possible.
Even if the system is addressable it is still considered beneficial to have a separate at a
glance indication of the location of the fire.
These compartments of a building are called detection zones, which need to comply with
the following criteria.
Detection Zones
4 A detection zone should cover no more than 1 storey, unless total floor area is less than
300m2. Voids in the same fire compartment should be included in the same floor zone.
The maximum floor area of a zone should not be greater than 2,000m2, except for some
large open plan areas that incorporate manual call points only, which can be extended
to 10,000m2. The maximum search distance for the fire fighters to see the seat of the fire
within a zone should not exceed 60m assuming the route taken is the worst possible option.
Vertical structures like stairwells, liftwells etc should be considered as separate zones
4 A manual call point within a
staircase should be connected
to the zone associated with that
floor and ideally be mounted on
the accommodation side of the
corridor exit. Automatic sensors
on the stairwell remain as part of
the stairwell detection zone
ZONE 1
ZONE 5
ZONE 2
ZONE 3
ZONE 4
DETECTION
ZONE 2
DETECTION
ZONE 3
DETECTION
ZONE 4
DETECTION
ZONE 5
DETECTION
ZONE 6
DETECTION
ZONE 7
DETECTION
ZONE 8
DETECTION
ZONE 9
ALARM
ZONE 3
DETECTION
ZONE 10
DETECTION
ZONE 11
DETECTION
ZONE 12
ALARM
ZONE 2
DETECTION
ZONE 1
ALARM
ZONE 4
ALARM
ZONE 1
Alarm Zones
Design Stage 3
Siting of Manual Call Points
All manual call points, whatever the system, should comply to BS EN54-11 single action
Type A version only and should be located as follows:
On all storey exits and all exits to open air irrespective of whether they are designated fire
exits
4 Nobody should travel more than 45 metres to reach one, except if the exit routes are
undefined in which case the direct line distance should not exceed 30 metres
The above distances to be reduced to 25 and 16 metres respectively, if there are persons
In all areas with potential high fire risk such as kitchens etc
Where phased evacuation is planned, call points will need to be sited on all exits from
a particular zone
4
Call points fitted with protective hinged covers for whatever reason should be listed as
a variation
B
S
by Honeywell
FIRE
DETECTION
SYSTEMS
(defined)
(undefined)
H
Design Stage 4
Selection and siting of sensors
For further advice please refer to clauses 21 & 22 of BS 5839-1:2013
The objective is to select the correct sensor for the appropriate application, to provide the
earliest warning of fire without the risk of a false alarm.
It is therefore worth trying to visualise the type of fire that is likely to occur in a
particular room or area and also to familiarise oneself with the application and the risks
that could give rise to a false alarm.
It should also be remembered that a Vigilon system can incorporate a whole range
of different sensors using S-Quad multi-sensors. These can be set up for different
applications and can be switched from state to state should particular risks be present
for short periods of time. This is achieved by an internal programmable timer, key
switch or external input source. At the end of this booklet, a pull out section is attached
showing a full application guide for all sensors including the latest S-Quad multi-sensor
with a range of selectable states for every application and risk.
DETECTION
SYSTEMS
Grade
Rate of Fire
State 0
A1
59.5 +/ 5.5C
Normal sensitivity*
State 13
A2
62 +/ 8C
Less sensitivity
State 5
77 +/ 8C
Less sensitivity*
State 6
BS
77 +/ 8C
Disabled
OFF
Disabled
State 15
HEAT
5.3m
5.3m
7.5m
5.3m
10
by Honeywell
FIRE
DETECTION
SYSTEMS
STATE
11
12
A1 Heat Only*
15
STATE
O2Heat & CO
O2Heat & CO
O Heat & CO
O2Heat & CO
O2Heat & CO
O2Heat & CO
11
O Heat & CO
12
A1 Heat only*
O2Heat & CO
15
11
* Certified by LPCB.
SMOKE detector spacing (Under flat horizontal ceiling)
7.5m
7.5m
7.5m
SMOKE
10.6m
7.5m
HEAT detector spacing in corridors (category P only)
UP TO 2m WIDTH
7.5m
SMOKE
15m
5.3m
10.6m
HEAT
12
by Honeywell
OR TOP
125mm
OF VOID
OF VOID
13
OBSTACLE
500mm
500mm
MIN
MIN
OBSTACLE
D>250mm
D>250mm
2xD
MIN
OBSTACLE
IF>10%
OF CEILING
HEIGHT
CONSIDER
AS A WALL
14
by Honeywell
HALF M
L
15
CEILING HEIGHT
(H)
SMOKE SENSOR
SPACING (M)
HEAT SENSOR
SPACING (M)
6m or less
5m
3.8m
More than 6m
5m
3.8m
More than 6m
5m
3.8m
3m or less
2.3m
1.5m
4m
2.8m
2.0m
5m
3.0m
2.3m
6m or more
3.3m
2.5m
Obstructions
IF < 300mm
CONSIDER
AS
REACHING
THE CEILING
RACKING
Ceilings above racking
IF GAP BETWEEN
TOP OF RACK AND
CEILING IS LESS
THAN 300mm THEN
TREAT AS WALL
AND PROVIDE
DETECTION IN
EACH AISLE
16
by Honeywell
AT LEAST
1m FROM
AN AIR
HANDLING
UNIT
FREE 500mm
SPACE BELOW
DETECTOR
STORAGE
RACKS
ACCEPTABLE
NOT
ACCEPTABLE
One of the most common mistakes is to mount a smoke sensor adjacent to the air
conditioning intake or outlet grill. The minimum distance between the two should be at
least 1 metre and further if possible. This is due to the fact that smoke may have difficulty
penetrating the sensor when the air conditioning is switched on. Also there is a greater risk
of the sensor becoming contaminated and giving rise to false alarms.
17
Uniform
4 The Minimum
4 The Thickness Is
WHERE AIR IS
FORCED THROUGH A
PERFORATED CEILING,
THE DETECTOR
SHOULD BE MOUNTED
ON A SOLID BAFFLE
WITH A MINIMUM
DIAMETER OF 1200mm
18
by Honeywell
25
600mm
20m
1.25m
2.5m
17.5m
Additional units may be included in atria to detect at lower levels, to counter stratification
effect
Maximum (m)
Up to 10% (m)
9.0
10.5
7.5
10.5
10.5
12.5
10.5
12.5
25.0
28.0
10.5
12.5
15.0
18.0
25.0
28.0
NOTE 1 The use of supplemental detection is recommended [see 22.5d)] unless the risk (i.e. probability consequence) of
stratification is minimal.
NOTE 2 The use of multilevel sampling is recommended [see 22.7c)] unless the risk (i.e. probability consequence) of stratification is
minimal
19
Design Stage 5
Choice and siting of alarm sounders and visual alarms
Sounders and strobes are generally provided for systems designed to protect life. However,
on the rare occasion when only the property is being protected it is still essential to mount a
sounder adjacent to the fire control panel as well as immediately outside the main entrance
for the fire fighters.
Before deciding on the number and location of sounder/visual alarms, it is important to
establish what the Fire Plan or cause and effect will be.
If the building is not going to have a one out all out arrangement, the evacuation
procedures must be established. Once this is known, you can then establish the alarm zone
areas where different alarm messages may be given, for example an alert or an evacuation
tone.
20
by Honeywell
Audible alarm levels within buildings are generally accepted as 65dB(A) throughout.
However, the new standard does accept that in certain locations this can be as low as
60dB(A). This allows some degree of flexibility, although in general the majority of a site
must achieve 65dB(A) or greater to be compliant.
The drawing below illustrates the areas where 60dB(A) is permitted
ENCLOSURE OF
LESS THAN 60sqm
MINIMUM OF
60dB(A)
SPECIFIC POINT OF
LIMITED EXTENT
MAY BE 60dB(A)
65
60
65
65
65
AREAS OF LESS
THAN 1m2 OF
HABITABLE SPACE
NO MINIMUM
65
65
60
65
65
65
65
60
60
60
65
60
65
60
It is maintained that to rouse sleeping persons you need to achieve a minimum of 75dB(A)
at the bedhead.
LED
Position
79dB(A)
45
2m
79dB(A)
45
80dB(A)
80dB(A)
30
30
84dB(A)
84dB(A)
15 84d B(A) 15
0
75dB(A)
45
75dB(A)
15
75dB(A)
30
75dB(A)
30
75dB(A)
15
75dB(A)
0
0.6m
75dB(A)
45
21
1m
For areas with high ambient background noise levels, the Standard recommends a sound
level of 5dB(A) above the norm although it now goes on to say the maximum sound levels
should not exceed 120dB(A) for health & safety reasons. Finally it is essential that at least
one sounder is placed within each fire compartment and the sounder choice should be
common throughout the building. You should not mix bells and electronic sounders within
the same building although the Gent S-Cubed & S-Quad, both offer bell and electronic
sounders allowing a system upgrade or switch over from a bell tone to an electronic tone
when required.
Sound attenuation is affected by numerous physical structures within a room, including the
door, furniture, people and materials used for floor, walls etc.
General internal doors will attenuate at least 20dB(A), whilst heavier fire doors may well
attenuate by up 30dB(A). To ensure 75dB(A) is achieved within a bedroom it is accepted
that the sounder is mounted within the room rather than the corridor outside. Use of sensor
sounders ensures an even spread of sound throughout the building without the need for
separate louder sounders. Visual alarms are generally considered as supplementary rather
than the only means of providing an alarm, and are used in areas where the dB(A) level
exceeds 90dB(A) or where persons within the area have impaired hearing. The exception
could be where sound of any description is undesirable, for example operating theatres, TV
studios and places of entertainment where a discreet staff alarm system is the best option to
avoid panic.
Visual alarms are also included as a requirement of the Equality Act 2010 (formerly
the Disability Discrimination Act 1995) and Approved Document Part M of the Building
Regulations and should be included in all sleeping accommodation where people with a
hearing disability may be present.
22
by Honeywell
Design Stage 6
Control equipment & power supplies
The Control panel itself should comply to EN54-2 and any power supply used should comply
to EN54-4. Today all of the Gent fire control panels incorporate their own battery and charger
and as long as the guidelines for loading these systems are complied with, the batteries
should be sufficient to maintain the system for a period of at least 24 hours with half an hour
alarm load thereafter.
It is however recommended that a battery load calculation is carried out to verify the standby
period provided by the capacity of the battery supplied.
Irrespective of the size or type of system the control panel should be sited with the following
points in mind;
4
On the ground floor entrance which the fire fighters will use
In buildings of multiple occupancy, the panel should be sited within a communal area or if
this does not exist, a location which is accessible at all times
4
4
4 Fire
If there are several entrances to the building, consideration should be given to the provision
of repeat indicators.
23
un-sprinklered buildings where the Fire Plan involves the evacuation of occupants in
four or more phases
4 In
un-sprinklered buildings or large networked sites where a fire could affect the cables
critical path, particularly where people will remain in occupation during a fire elsewhere
on the site
4 Where
in part, a delayed evacuation may exist and the critical signal path may pass
through an area of high risk
Where a Risk Assessment has identified a particular need for Enhanced cable
24
by Honeywell
SIXTH
FLOOR
FIFTH
FLOOR
FOURTH
FLOOR
THIRD
FLOOR
SECOND
FLOOR
FIRST
FLOOR
GROUND
FLOOR
Example of a networked
fire alarm in a multistorey building, showing
standard cable grade
throughout provided that
there is diverse routing of
the network cable loop.
STANDARD FIRE
RESISTING CABLE
STANDARD FIRE
RESISTING CABLE
ENHANCED FIRE
RESISTING CABLE
Example of a
networked fire alarm
in a multi-storey
building, showing
standard cable grade
for local wiring and
enhanced grade for
network cable.
For the Vigilon system, Gent regularly updates the list of approved standard and enhanced
cables used for loops or networks. We would suggest you obtain the latest copy of our
installation manuals or contact your local System Integrator to obtain the latest approved
product.
4
Cable requirements
4
Core size not less than 1mm (for Gent products 1.5mm loop cables are required)
4
Where
4
The
25
avoid electro magnetic interference from extra low voltage (240v) circuits
4 The
Standard precludes the use of multicore cable where a single fault will cause
more than one circuit to fail. This is particularly true with loop wired systems where
communication from either end is required and the failure of a 4-core cable will mean that
all communication is lost
4 Cable
support should withstand the same temperature as the cable, which method
the use of plastic cable clips, cable ties or trunking, where this is the main means of
supporting the cable, should NOT be used
4 Mains
power supplies should also be wired back to the main circuit breaker in Standard
grade 3 fire resistant cable
26
by Honeywell
System Commissioning
Commissioning Engineers responsibilities:
4
Look for any incorrect positioning of sensors or other devices snag them
or list them as Variations
Design Certificate
Installation Certificate
27
It is important that the system is commissioned by a competent person who has attended
recognised training courses on the equipment as well as the British Standard.
At this stage the entire system should be inspected and tested, in particular;
4
4 Check
that all devices are correctly sited to cover the area they are intended to protect
see previous notes on siting of devices
Check that all devices are correctly labelled and display the correct information on the
control panels
4
The fire plan or cause and effect should be checked from every device
All alarm panels and printers display the correct information and are sited correctly
No changes to the building have affected the siting of equipment or effectiveness of the
system for example an additional partition requiring additional sensors
4 Mains
and standby power supplies are adequate and designed to support the system for
a specified period, for example 24, 48 or 72 hours
4 As
far as reasonable, ascertain that the installation complies with the standard and
certificates are provided by the installer
4 If
radio equipment is used, ensure all radio signals are of sufficient strength to ensure
reliability
4 Ensure
there are no obvious shortcomings with the system as a whole and that all the
documentation is correct
It is also recommended that the system is soak tested for up to a week, dependent on the
system size, so that any teething problems are identified without giving rise to any false
alarms.
28
by Honeywell
Installation Guide
The purpose of this section of the guide to fire detection and alarm systems is to look at the
simple guidelines an installer should follow when installing a Gent by Honeywell Vigilon or
Nano Analogue Addressable system.
A3 Mimic
Panel
S-Quad
Sensor
S-Quad Sensor
Sounder Strobe
Up to 200 Devices
per Loop
Loop
Length 1Km
S-Quad Sensor
Honeywell
Voice Alarm
Node
Secure
Fibre
Network
Mains Switching
Interface
Node
6 Loop
Vigilon Panel
Secure
Copper
Network
2 Loop
Vigilon Compact
Beam
Receiver
Beam
Transmitter
Sprinkler Activated
S-Quad Sensor
Sounder Strobe
Node
Secure
Fibre Optic
Domain
S-Quad
Sensor
Manual
Call Point
Interface
Unit
Please note that a Vigilon loop can accept upto 200 devices, the Nano single loop panel
29
Manual
S-Quad Sensor Call Point
Sounder
Strobe
4 Loop Vigilon Panel
T-breaker
WINMAG PC Based
Management System
Manned
Centre Link to
Fire Station
Manual
Call Point
Repeat
Panel
Loop Loadings
The Vigilon loop will support up to 200 devices (127 with the Nano panel) per loop. In
addition to the maximum number of devices each loop has a loading capacity of 1000 units
which associates to a load per device. The unit rate per device is detailed in the list below.
Whilst some items have low loop loadings there is a maximum constraint on the number that
can be connected to a detection loop.
If you have any concerns regarding loop loadings please contact the Gent by Honeywell
Sales Support Team.
Description
Loop load
Factor
Maximum
per loop
1
8
16
1
10
8
18
26
1
18
26
1
18
26
1
1
1
1
5
5
13
15
28
23
33
10
23
1
8
1
3
3
200
125
62
200
100
125
55
38
200
55
38
200
55
38
200
200
200
200
16*
200
70
60
30
40
30
100
40
200
8
200**
8***
8***
30
by Honeywell
Loop Connections
All devices that connect to a Gent Analogue Addressable fire detection system follow the
same loop connection methodology; please refer to the diagram below.
31
Loop Length
Using 1.5mm cable, the resistance equating to 1km in length is 13ohms. In practice there
will be additional resistance due to terminations at devices. It would not be unusual to
measure a resistance of 15 ohms for a 1km loop. However if a resistance higher than this is
measured this would indicate the loop may be longer than 1km or that there may be some
terminations that need attention. If the resistance is higher than 18 ohms there is potential
for performance issues during the life of the system. Loops with a resistance greater than
18 ohms will not be guaranteed to work without problems and actions should be taken to
reduce the loop length.
In summary, the resistance for loops should be a range up to 15 ohms. If the value is
between 15 and 18 ohms the loop integrity should be investigated, but provided the system
functions satisfactorily, no further action is necessary. If the loop resistance is greater than
18 ohms the loop length should be reduced, probably by the addition of an extra loop or an
additional panel.
32
by Honeywell
33
Mixing different types of cables on the same network is not supported, it will create
impedance imbalance and disruption to data communication.
34
by Honeywell
fitted drawings detailing all devices installed and the sequence they are connected on
each loop
4 Label
schedule per loop detailing address details for each device that have been agreed
with the building user and cross referenced to as fitted drawings
4 Cause
and effect schedule. The system will need to be set up to a predetermined cause
and effect, this needs to be confirmed in writing or in the form of cause and effect matrix
37
Project
Anywhere
Location
No Town
Device
Type of Device label (Description to be displayed on panel) N.B MCP automatically display
device
MCP using four characters
reference on
drawing
1
Panel
No
Panel
No
1
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
1/1
1/2
1/3
1/4
1/5
MCP M A I N
E N T R A N C E
SD
M A I N
HD
G R O U N D
F L O O R
P L A N T
R O O M
SND G R O U N D
F L O O R
P L A N T
R O O M
S N D
F L O O R
P L A N T
R O O M
I / F
I/F
E N T R A N C E
G R O U N D
1/5
CH - 1 L I F T
L O B B Y
C O N T R O L
1/5
CH - 2 A C C E S S
1/5
CH - 3 G A S
1/5
CH - 4 S P A R E
1/6
L I F T
C O N T R O L
V A L V E
MCP K I T C H E N
1/7
HD
1/8
HD
K I T C H E N
1/9
SD
K I T C H E N
E X I T
K I T C H E N
S T O R E
Labels can be up to 64 characters using token labels. A list of tokenaised labels can be found in the generic commissioning manual.
38
Project
x
or x
Panel
No
Location
Device
reference
on drawing
Type of
device
Panel
No
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 3031 32
Labels can be up to 64 characters using token labels. A list of tokenaised labels can be found in the generic commissioning manual.
39
Detection
in zone
1
2
3
4
5
6
7
8
9
Evacuate
Alert
Zoning
Second floor
First floor
Ground floor
40
by Honeywell
Make sure the installation wiring complies with the requirements of BS 5839-1:2013
and the latest edition of the IET Electrical Regulations
4
Make sure that the loop length is within the manufacturers recommendations
4 Check
Make sure that all field devices are connected as per installation manual
Make sure that all monitored input/output (interface) devices have the required end of line
units fitted.
4
If an insulation resistance test is carried out it must be done so without the field devices
being connected, make sure that the loop cables are grounded before field devices
connected
4
Once a detector is fitted please ensure the dust cap stays on until the system has been
commissioned
Donts
4
Do not carry out an insulation resistance test with the field devices connected
Do not exceed the manufacturers recommendations for loop length or loop resistance
Do not power up any mains powered field devices until starting the commissioning
process
4
41
Documentation
On completion of commissioning and user
training all documentation will have to be
collected and handed to the client or their
representative. This will include;
4
4 As
42
by Honeywell
Notes
45
by Honeywell
42
L i t e r a t u r e r e f: GEN 0 31