Eng052 20erw 002 PL Bod 0001 000 - 02
Eng052 20erw 002 PL Bod 0001 000 - 02
Eng052 20erw 002 PL Bod 0001 000 - 02
Singh
[email protected], c=AE
Date: 2022.02.11 15:47:15 Z
YOUSS Digitally
signed by
Moham Digitally signed
YF EFFRANG
YOUSSEF
IEH 15:58:02
+04'00'
This document is issued pursuant to an Agreement between Petrofac Facilities Management Limited and Zallaf Libya Exploration and Production Oil & Gas
Company which agreement sets forth the entire rights, obligations and liabilities of those parties with respect to the content and use of the report. Reliance by
any other party on the contents of the document shall be at its own risk. Petrofac makes no warranty or representation, expressed or implied, to any other party
with respect to the accuracy, completeness or usefulness of the information contained in this report and assumes no liabilities with respect to any other party’s
use of or damages resulting from such use of any information, conclusions or recommendations disclosed in this document.
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 2 of 42
HOLDS
Hold No. Section Description
ABBREVIATIONS
Abbreviation Description
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 3 of 42
CONTENTS
1.0 ABBREVIATIONS
2.0 INTRODUCTION
2.1 Project Background
Erawin Project consists of the development of NC-200 E, G and H oil accumulations. NC-200 E, G
and H fields lay in Murzuq basin southwest of Akakus Oil Operations El Sharara production
facilities. E field is around 100 km from NC-115 GOSP-B. These fields were discovered and
appraised by REMSA between 2003 and 2009 by drilling and testing 3 exploration and 4 appraisal
wells. NC-200 block was assigned to Zallaf Libya in September 2017 and the Field Development
Plans (FDP) for the 3 existing discoveries were approved by NOC in April 2018.
For the Surface Facilities, Zallaf adopted development strategy in a 2-phase approach during the
FEED preparation. An Early Production Facility (EPF) consisting of one train of 10,000 BOPD oil
and 9,000 BWPD produced water separation capacity and located by well E-01 was selected for
Phase 1. These rates exclude the 10% design margin. In addition, Phase 1 would entail the
construction of a 12-inch exportation pipeline of about 100 km to Akakus NC-115 GOSP-B and a
20,000 bbl/d capacity Produced Water Treatment and Injection/Disposal Plant.
During the Post-FEED studies, Zallaf deleted Produced water treatment, injection / disposal scope
for Phase-1 along with implementation of various value engineering points.
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 7 of 42
Permanent Facilities Phase 2 would involve the design and construction of one separation train of
10,000 BOPD oil and 9,000 BWPD produced water capacity and addition or expansion of water
handling facilities and other auxiliary infrastructure as necessary.
Expected hydrocarbon production plateau rates are 16,000 BOPD oil and associated gas. The
maximum forecasted produced water rate during NC-200 production life is 20,000 BWPD.
Export tie back pipeline to NC-115 GOSP-B should be suitable for batch and continuous operation.
At NC-115 GOSP-B receiving end and crude oil will be discharged to existing storage tank.
In April 2021, Company stated their intent to go for a rental early works processing facility EWT
(procured by Company) to fast-track oil production and this strategy had been named as Plan B.
EWT will be designed for 10,000 BOPD, associated gas and 3,000 BWPD as water cut.
Plan B broadly comprises of following systems:
i. Wellheads: 4 nos. of wells (E1, E4, E5 & E7) are considered as part of Plan B.
ii. Flowlines: 4 nos. of flowlines from wells E1, E4, E5 & E7 will be routed till EPF area along with
FO Cable
iii. EPF: EPF / Processing facilities shall be by COMPANY. Crude oil Export scraper launcher will
be provided by Contractor.
a. Pipeline from 4 nos. of flowlines from EPF area to EWT and Export oil pipeline routing
from EWT to oil export pipeline near Crude oil export scraper launcher will be carried out
by Contractor along with suitable Telecommunication radio system at Temporary Camp.
b. The temporary Inlet manifold along with a rental processing facility including all utilities,
Power and control system shall be procured, installed, commissioned, operated, and
maintained by Company.
v. Brownfield and Greenfield work in existing NC-115B facility with fiscal metering skid, Metering
control room, Containerized substation, DG set, Diesel tank with necessary
Telecommunication system.
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 8 of 42
COMPANY/ ZALLAF
or Zallaf Zallaf Libya Exploration and Production of Oil and Gas Company
VENDOR/
The party that manufactures or supplies equipment and services to the
SUPPLIER/ SUB-
PURCHASER.
CONTRACTOR
▪ American lifelines Allianz: Guidelines for the design of buried steel pipe
▪ OTC 6335 - Design of Submarine Pipelines Against Upheaval Buckling
4.1.4 Reference Documents
The following documents shall be referred when required:
Document No Description
ENG052-20ERW-000-PR-BOD-0001-000 Process Design Basis and Design Criteria
Document No Description
ENG052-20ERW-000-EL-BOD-0001-000 Electrical Design Basis
Topographical and Geotechnical survey NOT performed during FEED phase of the project
therefore, as part for works, CONTRACTOR shall perform a detailed Flowline route selection
survey to finalize the flowline routes. The survey shall include as a minimum:
• Topographic survey.
• Geotechnical investigation
• Determination of the number, type, depth (where applicable), length and location of all
crossings.
• The CONTRACTOR or CONTRACTOR’s Survey SUB-CONTRACTOR shall prepare a
detailed report for the finding/ assessments along the proposed route centreline and shall
submit to COMPANY for review, comment and acceptance.
COMPANY to refer to Flowlines route survey report, Doc.No. ENG052-20ERW-002-PL-REP-0025-
000 for the survey details of flowline route & associated facilities.
The approved route map for flowlines shall be the basis for the topographical survey. Detail
topographical survey will be conducted for the flowlines route and associated facilities during detail
engineering by qualified Third-Party SUB-CONTRACTOR, approved by COMPANY.
The approval of the Pipeline route from various authorities shall be part of the CONTRACTOR’s
scope of work.
Based on the topographical survey drawings provided by Survey SUB-CONTRACTOR, Pipeline
alignment sheets will be prepared and issued to COMPANY for review and approval.
For the details of flowlines route, refer to project Pipeline route map drawings, Dwg.No. ENG052-
20ERW-002-PL-MAP-0002-000
6.3 C). Co-ordinate System
All coordinates or grid positions for the pipeline network shall be as shown in below Table. The
datum shall be used for defining the coordinates of the pipeline network and any features within it.
The coordinate reference system for the on-Plot (EPF area, EWT, NC-115 GOSP-B area, BVS &
Tie-in locations) is same that used for the pipeline sections. The coordinate system within on-plot
area and its conversion details to Pipeline system shall be recorded on drawings and documents
as required.
Data Parameters
Projection TM-CM 12 E
Data Parameters
Topographical Sub-Contractor shall establish a horizontal and vertical control system based on this
coordinate system.
The A/G section of pipelines and flowlines shall be externally painted as per recommendation from
Project Painting specification document, Doc.No. ENG052-20ERW-000-ML-SPC0002-000.
As part of this project strategy, Client will free-issue the Line Pipes (CS, API 5L Gr. X42, PSL-2) for
Production flowlines and Oil Export Pipeline to the CONTRACTOR. The minimum ordered line pipe
thickness for Production Flowlines and Oil Export pipeline is 0.375” (9.525mm). For Oil Export
Pipeline, the wall thickness calculation shall be performed in accordance with ASME B31.4 and for
Production Flowlines, the wall thickness calculation shall be performed in accordance with ASME
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 20 of 42
B31.8. This is to verify the suitability of ordered thickness for bend thinning (elastic bend, cold bend
and Induction bend), Von Miss condition (equivalent stress) and Vacuum conditions.
The BVSs shall be designed, engineered and constructed mainly as per ASME B31.4 and other
COMPANY specifications. BVS arrangement shall be installed inside concrete pit for safety reasons.
The elevation of pipeline at BVS section shall be maintained and shall be aligned to match the
adjacent pipeline sections.
The details of work at each BVS station shall include the following as a minimum, but not limited to
the following:
• Design, Supply and installation of the mainline valve and By-pass arrangement
• Main line valve assembly shall be manual gear operation.
• Design, supply and installation of all By-pass valve assemblies, mechanical fittings, flanges,
valves and piping etc.
• Design, supply and installation of all valves as per P&ID.
• Mechanical fittings, flanges and piping.
• Design, supply and installation of all Instruments including pressure gauges, pig signaller,
etc.
• By-pass arrangement.
• Grading and compaction and all-around fence with suitable access graded road, main and
escape gates.
• Sign boards as per COMPANY specifications.
• Access barriers, crossovers, access platforms.
• Power supply as applicable.
• Design and Grading, excavation & backfilling, compaction/re-compaction, cleaning of soil
excess, etc.
• Design, supply, installation and Construction of concrete pits (see Civil design basis for more
details).
• Design, supply and installation Sign boards as per COMPANY specifications
• Design, supply and installation of Access barriers, crossovers, access platforms as per
operational practice, requirements and recommendations of the COMPANY
• Design, supply and installation of all Civil foundations as per Civil design basis in reference
at section 4.1.4.
Feasible sleeper/supports shall be provided to ensure that no stress is transferred to the BVS piping
while manual depressurization of the pipeline. CONTRACTOR shall submit the design calculation
with stress analysis report for COMPANY review and approval.
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 23 of 42
The use of Hot-Induction shall be avoided, , Induction bends can be used at the station plot entry/
exit locations and block valve stations to absorb thermal expansion when required. Minimum bending
radii for hot bends should be 5D. Induction Bends shall be procured as per Project Specification
prepared as part of this project. The wall thickness of induction bend after thinning shall not be less
than the corresponding calculated pipe thickness (required design thickness).
The use of mitre bends shall not be allowed.
8.4 Valves
All mainline valves (within ASME B31.4/ B31.8 code break-limit) shall be in accordance with API 6D
and as per approved project material specification documents. All mainline valves shall be ball valves
with full bore to facilitate the pigging operation.
The material for body shall be CS and trim shall be SS 316/316L.
All above ground Pipeline valves including BVS underground valves in pit shall have flanged ends;
tight shut-off (TSO), soft seats with double isolation and bleed (DIB-2 i.e., single valve with two
seating surfaces) arrangement.
Valves shall be operated by hand wheel. The actuation type for valves shall be as per relevant
valve data sheet.
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 26 of 42
Pipeline Valves shall be in accordance with the API 6D and applicable project specification for
Pipeline Ball Valves, Doc.No. ENG052-20ERW-002-PL-SPC-0003-000.
All Pipeline isolation ball valves of 4 inch and higher size shall be provided with sealant injection/
greasing, cavity and drain points for seat and stem along with necessary fittings and valves.
The pipeline valves of size 6” and larger shall be provided with cavity vent and drain piping with
isolation flanged ball valve with blind flange. The vent and drain connection piping shall be fully
welded into the body, threaded fittings shall not be allowed. The drain piping shall be sloped toward
the isolation valve to prevent liquid accumulation within the drain piping.
Specification. Insulating Gasket will be used for the Pipelines between EPF & EWT where required
to isolate the CP systems for Pipelines. All insulation gaskets shall be metallic reinforced type.
For Isolation Joints, the pup pieces shall be supplied by the CONTRACTOR for welding and testing
at vendor’s production facility in case Vendor finds difficulty in sourcing the pipes as per the
requirements of Project Line Pipe specification. The pup pieces shall be of the same grade, strength
and wall thickness as the line pipe material to which they will subsequently be welded.
Where, Vendor intent to purchase forging pup pieces instead of using pups from line pipe then, the
Isolating Joints and pup piece material, grade, strength, wall thickness and diameter shall be
equivalent as that of the main pipeline.
The overall length of the isolation joint & pup piece shall be optimized by vendor to avoid any
damages to the internals of isolation joint such as filler material, due to heat generated during field
welding to pipeline. Welding proximity to the non-metallic seals shall be avoided by providing
sufficient length. Final assembly of Isolating Joint including pup piece shall be tested with a gauging
plate of 95% of the nominal internal diameter of connecting line pipe
Isolating Joints shall be supplied in accordance with the specification for Monolithic Isolation Joint,
Doc.no. ENG052-20ERW-002-PL-SPC-0002-000.
8.10 Welding
The welding shall be carried out as per COMPANY Standards and applicable international standards
listed / nominated in ASME B31.4/B31.8. CONTRACTOR shall prepare a project specific Pipeline
Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) and approved
by COMPANY before start of any welding works.
CONTRACTOR shall ensure that all welders employed on welding of line pipe shall be qualified in
accordance with API STD 1104 as amended by CONTRACTOR’s specification approved by
COMPANY. Post weld heat treatment (PWHT) is not required for field girth weld joints.
Butt welds shall be radiographed for pipeline joints as per project welding and NDT procedures.
Radiographic examination may be substituted for ultrasonic examination only with the prior approval
of the CONTRACTOR as specification approved by COMPANY. Ultrasonic examination shall only
be used where Radiographic examination methods are not practical.
Refer QA/QC project specifications for further details on Pipeline welding and NDT procedures.
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 29 of 42
9 SUPPORTS
The sections of above ground pipeline and associated piping system within the plot fence shall be
designed with adequate supports.
The preferred measure to allow the thermal expansion of buried pipeline at ends is by the aid of
sliding supports at above ground section of pipeline system as practicable and the use of anchor
blocks on the buried Pipeline/ Flowlines are avoided as part of FEED works as per agreement with
COMPANY. However, during detail design based on design or COMPANY requirement, the use of
Anchor block may be reviewed and considered (if required) by CONTRACTOR.
Pipe supports shall be designed in accordance with project specification/ standard for Pipe supports.
Supports for Pig traps of oil export pipeline shall be designed to carry the weight of the pig trap
system filled with water (or other fluids if their density is greater than that of water) together with the
weight of intelligent pigs.
The sections of above ground pipeline including isolating joints, pig trap valves, tie-line valves, kicker
valves and associated piping system within the plot fence shall be designed with adequate supports.
Pipe Supports between the over bend and the Isolating joint shall be electrically isolated to
maintain electrical isolation for the design life of the pipeline system. Similarly, the pipe supports in
the sections of pipeline (before insulating gasket break) within ASME B31.4 design code limit at
BVS shall be electrically isolated.
Pipe supports shall not cause coating damage to the pipeline and shall be designed to prevent
water and dirt from being trapped between the pipe support and the pipe.
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 31 of 42
11 CONSTRUCTION
The project Pipelines and Flowlines shall be constructed as per Project routing alignment sheet
drawings and preliminary typical construction drawings prepared as part of the FEED. Further these
drawings shall be reviewed and updated as part of detail design to meet the COMPANY
requirements and site conditions to ensure the safe and successful installation of the Pipelines and
Flowlines.
Construction of pipeline shall also be in accordance with COMPANY approved Pipeline Construction
Specification and Pipeline construction drawings or as per EPC CONTRACTOR Construction
Specifications approved by COMPANY, Doc.No. ENG052-20ERW-002-PL-SPC-0008-000.
11.1 General
The project export Pipeline and Flowlines shall be constructed by Approved-For-Construction (AFC)
drawings, specifications and all applicable codes and standards.
The construction of carbon steel pipelines shall be in accordance with COMPANY Specifications
and Standards as amended by CONTRACTOR’s specification for Pipeline Construction, Doc.No.
ENG052-20ERW-002-PL-SPC-0008-000 approved by COMPANY.
13 ENVIRONMENTAL CONDITIONS
For environmental conditions, refer to Process Design Basis (Doc. No.: ENG052-20ERW-000-PR-
BOD-0001-000)
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 36 of 42
14 HSE PLAN
14.1 General
The HSE plan shall be customization of the COMPANY HSE Management System meeting
COMPANY’s proactive and reactive targets and reduced risks to ALARP (As Low As Reasonably
Practicable). Special attention given to: Safety and health risk assessment; and Hazard
identification, assessment and control.
14.3 Specifications
For engineering, procurement and construction, the HSE requirements given in International
Standards & COMPANY procedures shall be followed.
PROJECT: PROJECT NO: CLIENT: DOCUMENT NUMBER:
NC-200 ERAWIN FIELD EPF PHASE- I JI-2047 ZALLAF ENG052-20ERW-002-PL-
(PLAN B) BOD-0001-000
DOCUMENT TITLE: ORIGINATOR: REV: DATE: PAGE NO:
PIPELINE DESIGN BASIS PETROFAC 02 08/02/2022 37 of 42
15.1 Design Data Summary – 12 inch Oil export Pipeline NC-200 EPF to N115
Line Pipe Wall Thickness 9.525mm (0.375 Inch) [For both DF=0.6 & 0.72]
V. PIPELINE – Coatings/CP
Cathodic Protection system Impressed Current Method
Pipeline Internal Coating Nil
15.2 Design Data Summary –6 inch Production Flowlines from E Fields to EWT
V. PIPELINE – Coatings/CP
Cathodic Protection system Impressed Current Method
Pipeline Internal Coating Nil
0.6 for On-plot and road / wadi crossings (For Wadi Type B & C)
Design Factors (DF) 0.72 for Off-Plot (including Wadi Type A/ flood plains and
Livestock crossings)
Pipeline OD 219.1
V. PIPELINE – Coatings/CP
Cathodic Protection system Impressed Current Method
Pipeline Internal Coating Nil