NReport On Layout Development Project at Jigni
NReport On Layout Development Project at Jigni
NReport On Layout Development Project at Jigni
Site Overview
Site is located 2.5 Kms from APC Circle near Jigni. Just 500 meters inside jigniAnekal Road. Jigani is located in Anekal Taluk in South Bangalore and is situated at a distance of 20 km from Bangalore city railway station. Site falls on the south end of Bangalore within 15 Kms from here Tamilnadu Border starts. Site has good connectivity to major places in Bangalore;
Electronic city falls within 13 Kms to the East and to Bannerghatta road is 10 kms to the west. Proposed site for Villas development falls within the jurisdiction of village Panchayat and BMRDA (Bangalore Metropolitan Region Development Authority) it is a cultivable land surrounded by other cultivable lands at 3 sides and one side by 30ft road. Total site for proposed project is 24 Acres having three different owners. Two sites are measuring 10 acres each and third site is 4 acres.
Development at Jigani
Some of the features of the place Jigani are that it has a well established Jigani industrial area and also very near to Electronics City Several such Government initiatives to improve development to this area in Bangalore has led to growth of population in this area starting 2004. There are three main access roads to Jigani from Bangalore. 1. The state highway Bannerghatta road from Bangalore via Bannerghatta via Jigani till Anekal was upgraded in early 2006. 2. As per the BMRDA's Radial Road development plan, the Road from Bommanahalli to Anekal via Jigani has been upgraded as of Dec 2009. 3. from Hosur List of Industries in Jigani Kumar Organic Products Ltd Kirloskar Toyoda Textile Machinery Private Ltd. (KTTM)
Accelerated Freeze Drying Company Limited Halgona Radiators Pvt, Ltd. Crompton Greaves Limited. American Power Conversion (I) Pvt. Ltd Imperial Constrafin Pvt. Ltd. Cauvery Electrodes (India) Southern Herbals Ltd.
Global Heat Treatment and Services Pvt. Ltd. Engineered Polymers Pvt. Ltd. Southern Rubber Products. Syngene International Ltd, Biocon Park.
Givaudan (India) Ltd. (Flavours & Fragrances production) Deccan Chronicle Holdings Limited Shoba interior division etc
Due to presence of many goods and service industries in the area, it became limelight for many IT and non-IT employees. Population in that area is increasing rapidly and as a result of that many Government facilities and other infrastructure development is coming up rapidly.
Similar Projects
With development of the area, many developers have already started many projects in that area including Township development, Layout and villas
development. Study conducted by square foot properties has shown that at least 10 layout development projects within the radius of 5 kms are already begun. (Most of the development includes only layout because of the affordability and comparatively slower population growth in the area). Besides that many developers are giving construction offer to customers. Most of the projects we came across have already 80-90% sold up within 1-2 years from commencement of project and many projects are available for resale.
require to get the loan easily for purchase of site; loan for construction will be available even for Panchayat approved sites. Very high demands for the sites measuring 2000 to 3000 Sq ft is observed in the area. Mostly sites are sold in dimensions of 40*50, 60*40 and 30*40; bigger layout has better scope as it will decrease marketing expenses and will be a good opportunity for investment for the customer. Many layouts have been sold out completely but no construction started yet, it shows that many people are looking for investing in land for long term growth.
Proposed-Agreement Terms
The Project will commence under a joint development agreement between the Land owner and Dreamz Infra. This agreement is the result of mutual understanding between the land owner and the Dreamz Infra. This agreement will remain intact unless the project reaches its closure.
24 Acres 1.35 cr
60 lacs at time of agreement; 75 lacs in three equal instalment of 25 lacs each, post dated check will be issue at the time if agreement. Payment Terms From the day of approval of layout payment will be release
in following manner At the end of 4th month At the end of 6th month At the end of 8th month At the end of 10th month At the end of 12th month At the end of 14th month At the end of 16th month At the end of 18th month At the end of 20th month At the end of 22th month At the end of 24th month At the end of 26th month and time of closing of agreement 1,00,00,000 2,00,00,000 2,00,00,000 2,00,00,000 2,00,00,000 2,00,00,000 2,00,00,000 2,00,00,000 2,00,00,000 2,00,00,000 2,00,00,000 3,50,00,000
Project will take 24-30 months to complete Total of 25.85 crores for 24 acres of land in 26 months.
25,85,00,000 5,45,00,000
Assumptions i) ii) iii) 30,000 Sft of land per acre is utilized for selling purpose; rest will be used for Road and other amenities development. Average Selling price is taken as Rs. 725 per Sft. All expenses are based on current prices plus additional 10% as a safety precaution to handle any expected cost overrun in future.
Components of Site development Site development includes: i) ii) iii) iv) v) vi) vii) Levelling of site Disposal of waste mud and other waste material (if any) Fencing of site Construction of security Kiosk Development of Road and Walkways Demarcation of individual sites Obtaining permission from electricity and water supply board facility ix) x) xi) xii) Making appropriate arrangement for electricity to individual sites and common area Provision of Sewerage Treatment Plant and Water Treatment Plant Solid Waste Management Gardening works and planting trees at appropriate place
Components of Advertisement & promotion Advertisement & promotion includes: i) ii) iii) iv) Bulk SMS Campaign Advertisement in Newspapers Flyers Boards/Hoardings, etc
Components of Administrative expenses Administrative expenses include: i) ii) Salaries to the employees directly involved in the project Legal services
Conclusion
The proposed project for layout development will be a profitable venture as the area is rapidly developing and have good scope in future.. The following conclusions are made; Attractive project for land owner and Dreamz Infra Very low degree of Associated risk, layouts development is on high demand in that area and no sign of marketing going down BMRDA approval is require it will increase the price of sites and will make the loan approval easy.
We can provide villa construction facility but it is recommended that we should go only with layout at initial stages, later if required villa can be constructed at 1200-1250 per sft.