Previous
Previous
Which of the following factors indicate most that detailed test conditions should be
specified for system testing? [K2]
a) Test basis is of low quality
b) Test basis is changing frequently
c) Domain experts are available for consultation during test design
d) Test conditions are used for management milestone presentations
e) Test design and test execution is outsourced
a,e
Q2. You are the Test Manager working on a project developing a tourist information
mobile
application. The project recently switched to an agile process and test driven
development. Each development cycle lasts 15 days, with daily builds beginning at day
7. After day 10, no new features are allowed to be added. The development team is
composed of very experienced team members, who are proud of their work, but not
tolerant of the testing team. The requirements are written down as coarse grained user
stories like the following one:
The software depends on existing web services, which are stubbed during
development. Unit testing is done by developers, while system and user acceptance
testing is the testing team's responsibility. System test in earlier development cycles
was often blocked due to severe failures of newly developed features. Analysis shows
that many of these failures could have been found during unit test. Analysis of issues
found during production show that 30% of performance problems were due to unreliable
web services delivered by 3rd party suppliers. Primary test objectives are to mitigate the
perceived performance risks and to increase the confidence that no failures with high
severity will occur in user stories with priority >= High. Moreover, upper management
demanded for closer cooperation of testers and developers.
Which of the following test activities and/or work products will achieve the test
objectives best? [K4]
a) Performance tests for user stories with priority = Very High done by developers
during unit
test before day no. 10
b) Metrics suite for unit testing defined by and reported to test management at day 7
c) Integration test level plan defined by test manager before each development cycle
and
handed over to developers on day 10
d) Automated performance testing of user stories with priority >= High done by testers
during
system test with test execution starting on day 10
e) Joint informal reviews of unit tests done by developers and testers before day 10
d,e
Previous
Play
Next
Rewind 10 seconds
Move forward 10 seconds
Unmute
0:00
/
0:15
Full screen
Brainpower
Read More
Q3. Which of the following metrics are best suited to be included in a test progress
report for unit test executive? [K2]
a) The test cases associated with this risk item must be run first in the test execution
period.
b) The test cases associated with this risk item must be run toward the middle of the
test
execution period.
c) A large number of test cases should be associated with this risk item, based on
impact.
d) This risk item should be assessed as a very high impact level risk.
d
Q9. Which of the followings are NOT a metrics related to a code?
a) Cyclomatic complexity
b) Component frequency
c) Number of function calls
d) Mean time failure arrival rate
e) Mean time between failures
b,d,e
Q10. Which of the following are proper ways to identify risks"' Choose all of possible
answer [K2]
a) Expert interviews
b) Independent assessments
c) Calling on future results
d) Use of risk templates
a,b,d
QI 1. Which of the following statements correctly reflects the way project management
work products affect testing? [K2]
a) The test manager should work with the project manager to develop the project
schedule
b) The tests should completely cover the requirements specification
c) Constraints in the project plan may constrain testing
d) The test manager should work with the technical support manager during test closure
c
Q12. Which of the following statements describes an appropriate approach to managing
nonfunctional testing? [K2]
a) Non-functional test implementation activities that take longer than a single iteration
should
be handled outside of the iterations
b) The test manager shall delegate the non-functional test planning to the technical test
analysts working on the project
c) Non-functional testing should be prioritized to follow functional testing and based on
perceived risks
d) Non-functional risks should be mitigated during early levels of testing or even during
development
a
Q13. Which of the following is a test document in which you would you expect to find
the precondition to start executing a level of testing? [1(1]
a) Project plan
b) Test log
c) Test result report
d) Test plan
e) Test design specification
d
Q14. You are the manager of a bank's quality assessment group, in charge of
independent testing for banking applications. You have just concluded a project to
implement an integrated system that will use three off-the-shelf systems to manage a
bank's accounts-receivable system. During the project, you found that one of the
vendor's systems, while comprising approximately the same amount of functionality and
of roughly the same complexity as the other two systems, had significantly more
defects. Making no assumption other than ones based on the information provided here,
which of the following is a reasonable improvement to the test process for subsequent
projects involving this
vendor? [1(.41
a) Impose retroactive financial penalties on this vendor for the number of bugs delivered
on
this project
b) Perform an acceptance test for all systems received, with particular rigor for this
vendor.
c) Cancel the contract with this vendor and put it on an industr∎ blacklist
d) Require the vendor's developers to attend training to improve their ability to write
quality
code.
b
Q15. Regarding of Business Value of Testing, there are quantifiable values and
Qualitative values. Which of the followings are categorized as Qualitative values? [1(3]
a) Smoothing releases
h) Find* deferrable defects
c) Increasing conlidetice
d) Reducing risk by running tests
e) Protecting from legal liability
a,c,e
Q16, In the !HEM test design specification. The test design specification describes a
collection of test cases and the test conditions they cover at a high level. Which of the
following sections is NOT included in the 1111:829 test design specification? [K2]
a) Features to he tested (in this suite, which should be a subset of the feature to he
tested from
test plan)
h) Approach refinements (where we elaborate on the approach described in the test
plan,
discussing the specific techniques, tools and so torth needed for this test suite)
c) Test identification (which traces to test cases in suite)
d) Feature pass/fail criteria (e.g,„ test oracle, test basic, legacy systems—)
e) Intercase dependencies (if needed to set up preconditions)
e
Q17. In the 1EEE829 test case specification which of the following sections is NOT
true? [K2]
a) Test case specification identifier
b) Test items (what is to be delivered and tested. which should be a subset of the test
items in
the test plan)
c) Input specification (user inputs, tiles, and so forth)
d) Actual results (including screens, files, timing and such)
e) Environmental (hardware, software, people. and props, again a subset of the test
plan's
environmental needs)
b
QI8. When doing Failure Mode and Effect Analysis, which of the following are NOT to
be a typical factors used to determine the risk priority number [K4]
a) Severity. This is an assessment of the impact of the failure mode on the system,
based on
the failure mode itself and the effects.
b) Priority. This is an assessment of the impact of the failure mode on users, customers,
the
business. stakeholders, the project, the product, and society, based on the effects,
c) Detection. This is an assessment of the likelihood of the problem existing in the
system and
escaping detection without any additional mitigation. This takes into consideration the
causes of the failure mode and the failure mode itself.
d) Urgency. This is an assessment of the impact of the timeline of the project.
e) Testability. This is an assessment of how the system is ready for testing
d,e
Q19. A critical element of test planning is the identification of test-to-project touch points
and hand-offs. In the following list are some examples of such touch points and hand-
offs. Which of
following is NOT correct? [K4]
a) Arranging for delivery of early, informal builds during test implementation to test the
test
cases, test procedures, test environments, and test tools
b) Coordinating the delivery of formal test releases, referred to in IEEE parlance as test
item
transmittal, In a regular, organized, reliable, efficient, and minimally disruptive fashion.
c) Ensuring that test releases have reliable, incrementally increasing, easily ascertained
revision numbering so that meaningful test results can be gathered and reported.
d) Analyze a target metrics and actual metrics by evaluating test result and adjust a
factors of
each metrics to meet the customer requirement.
e) Providing for reliable, timely, competent test environment support when the
complexity,
size, or criticality of the test environment is such that the test team should not support it
e
Q20. In test case Metrics, which of following aspect are NOT true statement? [K3]
a) Test Environment: Provides identifying information for the hardware, software, and
infrastructure used to run the test
b) Def RPN (or Defect Risk Priority Number): This is the defect risk rating, probably from
the
defect tracking system, analogous to the risk priority number in the quality risk analysis.
c) Test Effort: The number of person-hours planned for this test
d) Actual Effort: The number of person-hours ultimately expended on the test
e) Test Duration: The number of clock-hours required from start to end of test
b,e
Q21. Which of the following alternatives are typical project risks to be considered by the
test manager? [K2]
a) Delays and especially complex areas in the delivered product.
b) Low quality of requirements, design, code and tests, as well as failure-prone areas in
the
delivered product.
c) Potential failure areas in the software or system.
d) Supplier problems, organizational factors and the quality of design, code and tests
a,d
Q22. Which of the following alternatives are typical product risks to be considered by
the test manager? [K3]
a) Error-prone areas, the potential harm to the user, poor product characteristics
b) Low quality of requirements, design, code and tests as well as failure-prone areas
c) Political problems and delays in especially complex areas in the product.
d) Problem in defining the right requirements; potential failure areas in the software or
system.
a,d
Q23. Some proponents of session-based test management are use an acronym,
PROOF. Which of the followings are NOT true statement about PROOF? [K3]
a) Past: What happened during the session? What did you do, and what did you see?
b) Results: What was achieved during the session? What bugs did you find? What
worked?
c) Overviews: What still needs to be done? What subsequent test sessions should we
try?
d) Obstacles: What got in the way of good testing? What couldn't you do that you
wanted to?
e) Feelings: How do you feel about this test session?
c
Q24. As a test manager, you are participating in a meeting with other members of the
project management team. The agenda of the meeting is to discuss whether the project
can begin
acceptance testing based on the system test exit criteria, the acceptance test entry
criteria, and other business considerations. Which of the following statements is true?
There have been problems to keep up with the hardware development schedule.
Your manager thinks that the project might find some defects more efficiently by having
testers review the business requirements.
Which three of the following metrics would be used best to prove this point during
review trial?
You have written a first release of the system test plan based on the final requirements
specification. You receive an early draft of the design specification. Identify all of the
following statements that are true.
Which of the following interpretations of this chart provides a reason to not declare the
system integration testing complete? [K4]
a) The bug find rate has not leveled off.
b) Developers aren't fixing bugs fast enough.
c) The complete set of tests has not yet been run.
d) A number of unresolved bugs remain in the backlog
d
Q41, Which of the following represents a legal sequence of states for a defect report
that leads to a terminal state? Assume that "in progress" means one or more states
where developers or other project stakeholders are addressing the defect. [K2]